Вы находитесь на странице: 1из 58

The Cause of Cracking in

Post-Tensioned Concrete
Box Girder Bridges and
Retrofit Procedures

Walter Podolny, Jr.


Bridge Division
Office of Engineering
Federal Highway Administration
Washington, D.C.

O
n the premise that "Those who ig- these factors.
nore history will be condemned to Cracking in post-tensioned concrete
relive it," this paper attempts to docu- box girders generally results, in a broad
ment those types of problems that lead sense, for the following reasons: inade-
to cracking in post-tensioned concrete quate flexural and shear capacity, non-
box girder bridges and have been en- consideration of thermal stresses, insuf-
countered in both Europe and the ficient attention to stresses developed
United States. by curvature of tendons, improper or in-
These problems are not limited to appropriate construction techniques,
those of prestressed box girder bridges, lack of quality workmanship to meet the
but may occur in other types of struc- tolerances necessary for problem free
tures with similar conditions and de- structures, and understrength materials.
tails. Problems are generally attributed It should also be noted that cracks are
to poor quality control, inadequate de- not totally avoidable in post-tensioned
sign details, inferior workmanship, or concrete box girder bridges, since not all
lack of understanding as to how the portions of the structure are precom-
structure will behave, either through ig- pressed in three directions and local
norance or because a particular concrete shrinkage is not always con-
phenomenon is unknown to the current trollable. Certain cracks may not be
state-of-the-art, or a combination of all structurally serious, while others are. It

82
is, therefore, important for the structural
engineer to determine the structural
Synopsis
significance of a crack and its effect on
the serviceability of the structure. The appearance of distress in
In general, in today's technology it is the form of cracking in any con-
very rare that the triggering mechanism crete structure is one of concern
can be traced to a single source, Each of and consternation to all parties in-
the sources cited above, when taken in- volved. It is evidence of an unf a-
dividually, usually produce stresses or vorable stress condition and if seri-
cverstresses that are minor and within ous enough could affect the struc-
allowable limits. However, if one or a ture's integrity. Cracking may occur
number of the sources is ignored or in- for a number of reasons but usually
advertently overlooked, a superposition is the result of the interaction of
of stress can occur such that the capacity several causative factors. These
cf the concrete is exceeded and the only factors taken individually may be
relief the structure has from this over- minor but when superimposed can
stress is to crack. result in distress.
Therefore, it can be seen that it is very This paper presents documenta-
difficult to diagnose a specific triggering tion of problems that have led to
mechanism. It generally requires an cracking in post-tensioned con-
extensive investigative effort, usually by crete box girder bridges in Europe
a. process of elimination, to determine a as well as in the United States. 1t
single or small group of probable causa- discusses cracking resulting from
tive factors. inadequate flexural and shear
When serious and/or extensive capacity, thermal stress cracking,
cracking distress occurs in a project, and cracking resulting from tendon
there may he a concern for the integrity curvature and tendon misalign-
of the structure. This usually results in ment. Also discussed are possible
delay of the project, investigation, ret- retrofit measures.
rofit measures, determination of liabil- The intent of this paper is to
ity and legal involvements, which be- bring these problems to the atten-
comes costly in terms of both time and tion of the engineering and con-
money. It is hoped that the data pre- struction professions with the hope
sented in this paper will help to dissipate of precluding their recurrence.
the occurrence of these problems to the
benefit of both the engineering and con-
struction professions.

gate in the webs. Flexure cracks in the


FLEXURAL CRACKING top of the section, in the negative mo-
ment area, occur less often since there is
Flexural cracking is associated with generally a moment redistribution that
tensile stresses that exceed the tensile occurs which reduces the tensile stress-
capacity of concrete. They are generally es in this area.
found, in continuous girders, at the bot- In segmental box girders, flexure
tom of the girder in positive moment cracks will generally occur in or near the
areas and at the top of the girder in segment joints (Fig. 2). The crack width
negative moment areas (Fig. 1). In box at the bottom can be on the order of
girders, positive moment flexure cracks 0.004 to 0.008 in, (0.1 to 0.2 mm). As the
will traverse the bottom flange (soffit) cracks propagate up to the top flange,
width and if severe enough will propa- they will become fine microcracks.

PCI JOURNAL/March-April 1985 83


^^K^PATTERN

inflection
points
MOMENT DIAGRAM
+M

Fig. 1. Flexural cracking zones.

Flexural cracks can he small (mi- quate flexural capacity, cracking behind
crocracks) and the structure may appear anchorage blisters or a combination of
to be intact. However, the width of these both.
flexural cracks can vary and become Causes of inadequate flexural capacity
quite large, 1 to % in. (3 to 10 mm), are varied in origin and it is seldom that
under the effects of external loading, a single cause will produce significant
such as dynamic traffic load or thermal cracking. More generally, there are a
gradient. number of causes which by themselves
In areas near the support the effect of are insignificant, but when acting in
shear will be superimposed upon the concert with other causes produce sub-
flexural stresses producing, after initial sequent cracking.
vertical cracking, cracks that are in- The more prevalent causes are as fol-
clined and become more and more diag- lows:
onal in the webs, which may indicate
insufficient shear strength (Fig. 3).
(a) During Design
This type of cracking will be accom-
panied by deformation in the structure, 1. Inadequate consideration of, or un-
visible and measurable deflection. derestimation of, stresses resulting from
Cracks of this type pose a risk to the moment redistribution,
reinforcement, prestress or conven- 2. Underestimation of thermal stresses
tional, that traverse the crack from corro- (expansion or contraction),
sion or from fatigue damage under large 3. Lack of consideration of, or under-
and frequent stress variation. estimation of, thermal gradient.
Considerable care must be exercised 4. Overestimation of initial prestress
in diagnosing the cause of cracks in this resulting from optimistic coefficients of
pattern. Inadequate flexural capacity friction and wobble.
may or may not necessarily be the 5. Underestimating relaxation loss in
causative factor. Excess tension and prestressing.
subsequent cracking behind blister an- 6. Selection of a tendon profile
chorages can produce similar cracking whereby a large variation of prestress
(this effect will be discussed in a sub- eccentricity occurs (Fig. 4), and not
sequent section). Therefore, cracking of checking the stresses at critical loca-
this type may have its origin in inade- tions.n

84
Fig. 2. Flexural cracks.

combined
vertical bending-shear
bending Cracks
cracks near support

f '

Fig. 3. Flexural cracks.

continuity tendons
cantilever tendons

joint(i) joint(i*I)
sections at right sections at right
and left checked and left chocked
unchecked zone
where cracking
develops

Fig. 4. Unverified zone of cracking.

PCI JOURNALIMarch-April 1985 85


point of
infI -tinn

la!

faulting

(b)

Fig, 5. Shear cracking.

(b) During Construction occur whereby the thickness is reduced


resulting in decreased concrete area to
1. Losses as a result of excessive fric- accommodate stress.
tion resulting from crushed tendon 3. Underestimation of the voiuminal
ducts. mass of concrete, especially where
2. Displacement of poorly secured dense aggregates such as those of basal-
tendon ducts which then alters the ec- tic origin are used.
centricity and also produces additional
friction.
(d) Secondary Stresses and
3. Lack of isolation from the concrete
of tendon couplers. If the coupler is po- Overloads
sitioned such that it cannot freely move These are stresses experienced during
as the tendon elongates under stressing, construction and service life for which it
the prestress force distribution is al- may not have been designed.
tered. 1. Differential settlement of supports
4. Failure of strands or wires in a ten- or movements of pier foundations which
don. modify stresses and/or deformations.
2. Cracks caused in the concrete dur-
ing or after setting that result from
(c) Excess Permanent Loads
moving construction loads or shifting of
1. Underestimating the weight of con- formwork.
struction equipment and permanent 3. Faulty concreting sequence that
nonstructural loads (roadway thickness, can cause cracking as a result of differ-
overlay, utility lines not originally ential shrinkage.
planned, etc.). 4. Overload from heavy truck traffic
2. Accidental displacement of forms and accompanying dynamic effects.
before or during concrete placement re- 5. Failure to recognize local effects
sulting in a greater thickness and such as, for example, curvature of ten-
heavier deck. The opposite can also dons or stresses behind anchorages.

86
draped cantilever tendons

t fX

longitudinal
stresses

Fig. 6. Shear forces.

SHEAR CRACKING 1. Lack of recognition of shear dis-


tribution in the webs of multicell gird-
Shear cracks occur in the webs and are ers. The transverse design of the sec-
perceptibly inclined at approximately a tion does not take into account the true
45 deg angle. They normally manifest flexibility of the cross section. (This ef-
themselves in a zone between the sup- fect will be discussed in a subsequent
port and an inflection point (Fig. 5a). section.)
The web reinforcement traversing these 2. Lack of double checking to the right
cracks is subject to stress variations and left of a section where a tendon ter-
which can cause bond failure and minates.
fatigue damage. In addition, at the limit, 3. Failure to recognize the effect of in-
the reinforcement can yield. This may clination of continuity tendons in vari-
result in the faulting of the intrados able depth girders. Although the vertical
which is usually not visible to the eye component of a single tendon may be
(Fig. 5b), but can be instrumentally small, if there are a large number of ten-
measured. dons they can create a significant shear
Most of the causes of flexural cracks force.
are also responsible for shear cracks The total net shear force, V, is the
since a change in bending moment au- sum of the following terms (Fig. 6):3
tomatically changes shear stress:' 1. Shear force due to applied loads
1. Insufficient prestressing equals V,
2. Excess permanent loads 2. Reduction due to verticaI compo-
3. Secondary stresses nent of draped tendons, where used
4. Thermal effects equals E P sin a.
Shear cracks can also be initiated by 3. Increase due to inclination of con-
bending cracks or high tensile stresses tinuity tendons in the bottom flange for
behind tendon anchorages. The fol- variable depth girders equals +1 P sin
lowing design oversights may also con- Is.
tribute to the formation of shear cracks: 4. Reduction due to the inclined prin-

PCI JOURNALJMarch-April 1985 87


typical diagonal cracks
IT-max. oper+ing 0.02" (0.6 mm)

intermediate diaphragm

PARTIAL ELEVATION

Fig, 7. Web cracking of center web.

cipal compressive stresses in the bottom vertically curved tendons in the bottom
flange (usually called the Resat effect flange. Vertical prestress was applied in
after the engineer who first studied the webs to control shear stresses. Diag-
members of variable depth) equals onal cracking was observed in the center
ff tB tany. web, only near the intermediate dia-
Thus: phragms, with a maximum crack opening
of 0.02 in. (0.6 mm). In addition there
Vo V YEP sin a+IPsing f. tB tan y
was cracking in the bottom flange,
A complete investigation of the prob-
Cracking Produced by Incorrect lems encountered revealed that crack-
ing was the result of the superposition of
Distribution of Forces
several adverse effects, any of which
This example 3.4 is one of a two-cell, might have been harmless if considered
variable depth, box girder bridge con- separately:
structed by the balanced cantilever 1. The computation of shear stresses
method and consisting of five spans of failed to take into account the adverse
210, 370, 370, 390, and 230 ft (64, 113, effect (usually neglected) of the vertical
113, 119, and 70 m). External webs are component of continuity prestress in the
13 in. (340 mm) thick and the center web bottom flange of a girder with variable
is 12 in. (300 mm) thick. Because the depth. The curvature of continuity ten-
bridge was subsequently intended to dons distributed in the bottom flange is
carry monorail pylons, two intermediate such that a downward reaction is pro-
diaphragms were provided at the third duced at the webs that is additive to the
points of each span, as indicated in Fig. shear in the web (see above).
7. 2. The distribution of shear stresses
Longitudinal prestress was applied by was made under the conventional
straight tendons in the top flange and structural analysis assumption that the

88
(a) conventional assumption
of transverse rigidity

(b) transverse deformability

Fig. B. Transverse stiffness of a two-cell box.

cross section was rigid and transversely with short bar tendons and even if
undeformable (Fig. 8a). However, de- equipped with a fine thread they are not
pending upon the stiffness of compo- completely reliable unless special pre-
nent parts of the cross section this as- cautions are taken under close supervi-
sumption may be erroneous (Fig. 8b). sion. Even a small anchor set signifi-
Conventional analysis, assuming a rigid cantly reduces the prestress force, and it
undeformable cross section, assumes is not unlikely that the actual prestress
that a centered loading is evenly dis- force is only three-fourths or even
tributed among the webs. In fact, a two-thirds of the theoretical prestress.
center loading induces a transverse de-
formation in the top and bottom flanges Cracking as a Result of Indirect
with a displacement of the center web
larger than that of the external webs. Support
Fig. 9 indicates influence lines for shear The ideal position of bearings at a pier
in the center web and the external web. is directly tinder the webs of a box gir-
The transverse behavior appears very der. The shear from the web is trans-
different from that of a transversely un- ferred directly from the web to the
deformable section and may produce bearings, and there is need only for a
cracking in the bottom flange as indi- simple inside diaphragm designed to
cated in Fig. 10. For any particular cross transfer the shear stress, due to possible
section, a more rigorous analysis is indi- torsion moments, to the substructure.
cated than that usually conducted. However, to avoid spalling the bottom
3. The vertical web prestress was par- outside comer of the soffit, the edge of
tially lost into the intermediate dia- the bearing should be a minimum of 2
phragms, and the actual vertical compres- in. (50 mm) clear of the corner. If a
sive stress was lower than assumed. chamfer exists at the corner, the clear
4. Vertical prestress is usually applied distance should he measured from the

PCI JOURNALJMarch-April 1985 89


edge of the chamfer (Fig. Ila). tion immediately above the pier to ac-
A more complicated situation arises commodate the following:3
when the bearings are offset with re- 1. Suspend all shear stresses carried
spect to the webs (Fig. lib). Mild steel by the web under Point A, where a 45
reinforcement and possibly prestressing deg line starting at the bearing edge in-
steel must be provided in the cross see- tersects the web centerline (hatched
area in the shear diagram).
2. Balance the moment (V x d) in-
duced by the hearing effect.
Obviously the most severe situation is
that where a single bearing is used, or a
60 pair ofbearings is sufficiently offset, and
that the 45 deg line from the bearing
40 does not intersect the web centerline
(Figs. lie and lid).
20
An approach to the determination of
the forces involved is by means of a truss
analogy,' using trusses with compres-
sion struts formed in the plane of the
webs and diaphragms. Fig. 12 shows the
truss analogy for the case of a single
(a) INTERNAL WEB bearing at the centerline of the cross
section. Where the web trusses and the
diaphragm truss intersect, the web is
actual stressed in the same manner as if a load
conventional analysis were suspended from the bottom at the
100
position of the diaphragm.
89 Reinforcement requirements should
80 he based upon an ultimate load condi-
40 4HH tion. Suspension reinforcement is re-
quired to transfer the ultimate load in
the web to the diaphragm. The resisting
suspension reinforcement in the web
should be in addition to the normal
shear reinforcement.
This suspension reinforcement
(b) EXTERNAL WEB should, in addition, be distributed in the

Fig. 9. Shear influence lines.

Fig. 10. Cracking pattern in bottom flange.

90
web

distribution of
shear stress
in web

I R \v
1 I )

( V ^ (b)

I
(c) (d)

Fig. 11. Position of bearings.

hatched area of the intersection zone perature rise and fall of a concrete
(Fig. 12d), such that 70 percent of it is structure about an assumed temperature
located in the web.' It should he the full at time of construction is as follows:
depth of the girder and adequately an-
chored. Temperature
In many instances, provisions are
made (or should be made) for future Type of climate Rise Fall
jacking up of the superstructure in the Moderate climate 30F 40F
event the bearings require replacement. (16.7C) (22.2C)
The design drawings should indicate Cold climate 35F 45F
the intended position of the jacks and (19.4C) (25.0C)
the consequences of this temporary re-
positioning of reactions should be ac- The thermal coefficient for normal
commodated in the design. weight concrete is taken as 6 x I0- 11 per
deg F (10.8 x 101 per deg C). Thus, by
using the equation:
THERMAL STRESS
CRACKING e=aIAt (1)

The current AASHTO Specifications where


recognize thermal expansion and con- e = total change in length I
traction in the design of bridge struc- a = thermal coefficient of
tures. The rise and fall of temperature expansion (or contraction)
should be determined for the site of the l = length of a member from a
structure under consideration. In gen- reference point
eral, AASHTO requirements for tern- A t = change in temperature of an

PCI JOURNALI March-April 1985 91


unrestrained member From Eq. (1) the strain in the member
The change in length of an unre- is determined as:
strained member can be determined.
Where a member is restrained (fixity of E= ell=a At (2)
supports or friction in bearings) the
thermal expansion or contraction is pre- The change in length of the member
vented by reactions at the supports per unit of length accompanying the
which then cause stresses in the mem- unit stress "s" caused by the restraint is:
ber. This stress is calculated by assum-
e = s/E (3)
ing that the thermal expansion or con-
traction first occurs and then forces where E is the compressive or tensile
(reactions) are applied at the restraints modulus of elasticity. Thus:
to bring the member hack to its original
length. e=s1E=aAt ors =EaAt (4)

@ webs

girder depth

support
reaction 2V it
(a) CROSS SECTION d

`4 t

aphrag g e

compressi(
tension
(b) CRACK PATTERN

reaction 2Vult //I jdiaphragm

(c) ANALOGUS TRUSSES ^ N

web

d/2 T whichever
produces
the largest area
L
(d) PLAN OF DIAPHRAGM/ WEB REGION

Fig. 12. Indirect bearing support.

92
ambient temperature sun

---`-wind speed A.
re-radiation doorio ^/ asphalt
} } 7 qi

\]/
cate:iai
properties

--+- wind speed

ambient temperature

Fig. 13. Thermal response parameters.

From the above, expected movements increase in temperature of the upper


or stresses can he determined for sup- surface with respect to the lower sur-
port conditions and expansion joints and face. Since the structure is restrained
bearings as appropriate can be provided. from cambering freely, restraint mo-
However, occasionally distress is still ments and shears are produced (Fig.
evident from displaced bearings and/or 14)-' 'Z
damaged expansion joints. Presumably, In prestressed concrete structures
this distress occurs from unanticipated there may be zones, under dead load
temperature rise or fall. plus prestress, where there is a low
Although the above consideration has compressive stress reserve and the
been a traditional approach to thermal stresses due to restraint forces can easily
stresses in bridge structures, bridge en- reach values that exceed the tensile
gineers have relatively recently become strength of the concrete. This usually
aware of another thermal phenomenon, leads to vertical cracks very close to in-
namely, thermal gradient. As a result of termediate supports. Cracking as a re-
the poor thermal conductivity of con- sult of thermal gradients have been re-
crete, a temperature gradient will occur ported 13 and is considered to he one of
through the depth of a concrete mem- four prime causes of cracking in pre-
ber. The gradient is a function of a stressed concrete bridges.-' In some
number of variables (Fig. 13) such as cases the thermal gradient stresses can
solar radiation, ambient temperature, be larger than the live load stresses.
wind speed fluctuations, material prop- These cracks can be further enhanced or
erties, surface characteristics, and see- aggravated by stresses resulting from
tion shape. bearing pressure at the supports or ra-
This type of thermal gradient will dial tendon stresses from curved ten-
cause external restraint forces in stat- dons in the support area.12
ically indeterminate structures such as The magnitude of the restraining
continuous girders. If in a continuous forces is a function of the thermal gra-
bridge the interior supports (points of dient assumed and can be linear or non-
fixity) are released, the structure will linear. Several countries recognize the
attempt to camber upward, assuming an existence of thermal gradient and make

PCI JOURNAL/March-April 19B5 93


curves assume a thickness of surfacing
of 40 mm (1.6 in.) for Groups 1 and 2
loading and 100 mm (4 in.) for Groups 3
and 4. For other thicknesses of surfac-
FREE DEFORMATION ing, the values of (T) are adjusted ac-
cording to prescribed tables that are
presented in the British Code of Prac-
tice.
tP ^ In Australia' the thermal gradient
P_ = PL1 curve takes the shape indicated in Fig.
15c. In France' (Fig. 15d) a linear varia-
RESTRAINT FORCES AND MOMENTS tion is used with a 10C gradient used in
combination with dead load, shrinkage,
and creep. A 5C gradient is used with
Fig. 14. Moment caused by thermal
all loads (including live load and im-
gradient.
pact).
Currently in the United States there
are no general criteria for thermal gra-
recommendations for their considera- dient, although a recommendation is
tion in design. Most of these recom- presented in Ref. 16. However, the Na-
mendations require different shaped tional Cooperative Highway Research
gradients and intensities to be evaluated Program (NCHRP) has a current Project
(Fig. 15). However, it should be noted 12-22 titled "Thermal Effects in Con-
that they are influenced by local crete Bridge Superstructures" that will
meteorology and construction practices. hopefully result in recommendations to
The New Zealand gradient" (Fig. be used for United States practice.
15a) is a fifth power parabola for a depth The effects of thermal gradient are
of 1200 mm (48 in.) with the tempera- usually computed by assuming the gra-
ture (T) at the concrete surface related to dient to be constant throughout the
an asphalt thickness (d) in mm. This bridge superstructure length, which is
curve is used for webs and that portion not necessarily the case. Fig. 16 indi-
of the deck not above an enclosed cell, cates the results for the case of a typical
i.e., deck flange cantilevers. span fixed at both ends (the case of a
For decks above an enclosed cell a long structure with many identical
linear curve is used of 5 0.054C per spans). The stress at the bottom fiber
100 nun (4 in.) thickness with the temper- depends upon the following two factors:
ature (1') at the top surface. A linear 1. Variation of height between span
temperature increase from 0C to 1.5C center and support (ratio ]k 11,, ).
is used over the bottom 200 mm (8 in.) 2. Position of the center of gravity
thickness of the section. within the section (ratio c2/h),
For structures shallower than 1400 The stress increases rapidly when the
mm (56 in.) the two parts of the solid variation in depth is more pronounced.
curve are to be superimposed. For box For normal proportions the effect of gra-
girders the transverse effects are ob- dient is increased by 50 percent in vari-
tained by using the dotted curve. On a able depth girders compared to constant
bridge which is to be surfaced, the tem- depth girders.'
porary unsurfaced condition is to be Another source of thermal stress
checked by using a value for(T) of27C. (strain) related cracking is that associ-
Thermal gradient curves used in En- ated with heat of hydration, subsequent
gland 15 are indicated in Fig. 15b for deck cooling and shrinkage. Heat of hydra-
warming and deck cooling. These tion is a chemical process that is a func-

94
T

concrete deck surface 1


iy 100 mm
''' tY
' (deck above
webs , enclo sad Cell
deck nol above
enclosed cell
ii
ty T(y3 1200)5
} E Yy - 5-0,05d0C
(a) NEW ZEALAND
0

T- 32-0.2d*C
v .Drat
d=capful thickness (mm)
1.5 C

Tt Tt
hi hi
T2 72
__I
h
h2
h1.0.3hz6 0.15 m
h2.0.3h 8 0.10 m h1 4 02h0.25 m
- u1
h2

h 2 `h3 -0.25h^0 .2 m h
50.25 m
h '. 0.3h^ (0.1 mtsurlacinp h3
depth In meters) T3
(tor thin slabs. h 3 hmlled
1e
h4
13 by h-hl-h27 T4

h T1 T2 T h T T2 T T
Ill oC m
(b) ENGLAND zz 0.2 e.5 3.5 05 0.2 2.0 0.5 0.5 1.5
0.4 12.0 3.0 1.5 4.5 1.4 1.0 3.5
0.6 13.0 3.0 2.0
0.4
0.6 6.5 1,8 1.5 5.0
ar 0.8 13.6 3.0 2.5 0.8 7.6 1.7 1.5 6.0
1.0 8.0 1.5 1.3 6.3
(deck warming) 1.5 6.4 0.5 1.0 6.5
(deck cooling)

10G ar Soc
^ ^Il
24 C

n_
c
0
goC
h

(c) AUSTRALIA v (d) FRANCE

Fig. 15. Thermal gradient diagrams of various countries.

PCI JOURNALMarch-April 1985 95


300
^^` range C2 /h=0.65

E 'y-
oa
250
i
C2/h0=0.60

220 50 psi for constant


^
n 200 depth and inertia
a f2 Ec (t T)C2Jh0
rn 150
W 160 Si a -coefficient of
.. a cons ant de rth thermal expansion
tl7 N
100 oT+tamp erature
gradient
NOTE: For other modulii
c of elasticity mutttply
Ec = 5,000,000 psi stress by E/5,000,000

1.0 1.5 2.0 2.5 3.0 h11h0

h1 h1 T" 18F f

^' r0LEi f2
ELEVATION OF SPAN SECTION AT CENTER

Fig. 16. Effect of thermal gradient on box girder decks.

Lion of the type and amount of cement, the bottom thin flange will cool faster
thickness of concrete members and and attempt to shrink at a faster rate than
temperature of aggregate, mixing water the webs and is therefore being re-
and surrounding atmosphere. As a result strained. To relieve tensile strains, pro-
of heat of hydration and shrinkage, duced by restraint of the webs, the thin
especially between thick and thin por- bottom flange has no other alternative
tions of a cross section, large residual but to crack (Fig. 17a). In a transverse
stresses can be produced which exceed section, large differences in thickness
the tensile strength of"green" concrete. can produce restraining moments which
Thin parts of the cross section will can produce horizontal cracks in the
cool faster than adjoining thick parts webs (Fig. 17b).
producing residual tensile stress and A similar thermal stress (strain) in-
cracking, There is always a potential of duced cracking can occur in staged con-
cracking when a thin member is at- struction whereby the cross section is
tached to a relatively larger member. constructed in two or more pours re-
The thinner member will always he quiring construction joints. When fresh
subjected to a faster rate of temperature young concrete is placed against hard-
change (cooling), larger creep and ened older concrete there is a danger of
shrinkage than the larger member and cracking. Initially, the fresh concrete
thus the thinner member will crack,112 will have an increase in temperature re-
In box girders with thick webs rela- sulting from heat of hydration, then
tive to the thickness of the bottom flange, when cooling occurs the new concrete is

96
crack

crack

b!2

/ n
N
cracks

Plan

(a) CRACKS IN THIN BOTTOM FLANGE (b) HORIZONTAL CRACKS IN WEBS

Fig. 17. Thermal shrinkage cracking.

top flange
3rd stage casting

web
2nd stage casting
forms still in place

bottom flange
1st stage casting ELEVATION

SECTION

Fig. 18. Web shrinkage cracks.

restrained from shrinking by the older straint to shrinkage produced by the


concrete. older concrete and cracking of the
Usually, because of insufficient lon- younger concrete will occur. If the forms
gitudinal reinforcement and/or lack of are left in place too long, they will pre-
sufficient bond development between sent a large surface area of friction that
the reinforcement and the young con- will also hamper the shrinkage of the
crete, there is insufficient capacity for new concrete and thus cause cracking
the younger concrete to resist the re- (Fig. 18).'

PCI JOURNAL/March -April 1985 97


segment A segment B

(a) ELEVATION

cons,

(6) CONSTRUCTION STAGES

Fig. 19. Klement Gottwald Bridge.

As an example of temperature varia- placing was approximately 35C. Blown


tion in a box girder bridge, data extract- hot air was used as a protection against
ed from Ref. 17 is presented here to freezing; however, the distribution was
illustrate the point. The research effort uneven.
involved the instrumentation and tem- These conditions are far from normal
perature data collection in two adjacent and the results have to he considered as
segments near the midspan of an inter- extreme, nevertheless, the results are
ior span (Fig. 19a) during construction of indicative of thermal distribution in this
the Klement Gottwald Bridge over the type of cross section.
Nusle Valley in Prague, Czechoslovakia. Temperature distribution during con-
Segment A had been previously cast and struction of Segment B is indicated in
Segment B is the segment being con- Fig. 20. Fig. 20a shows the temperature
structed, Segment length is 11.5 ft (3.5 distribution 10 hours after casting Stage
m) and is cast in three stages as indi- 1. Note that the bottom flange has a
cated in Fig. 19h. thickness of 11.8 in. (300 mm). Fig. 20b
Concrete temperature data obtained shows the temperature distribution 20
in December 1969 was influenced by hours after casting Stage 2 (44 hours
the following factors: after casting Stage 1). The web thickness
1. Extremely cold ambient tempera- is 23.6 in. (600 nim).
ture. The temperature was below 0C At this point in time the temperature
and in the final phases of data collection at Point "a" was 38.6C. Fig. 20c indi-
the temperature was often below 20C. cates the temperature distribution 24
2. Preheating of the concrete mix, be- hours after casting Stage 3 (7 days after
cause of the low ambient temperature. casting Stage 2). The temperature at
Hot water was used in preparing the mix Point "b" was 51.1C and the tempera-
such that the average mix temperature at ture immediately above this point, Point

98
7 1 I (a) STAGE 1
y 5
1 1
20
0 1 1^

10
20 30

^.
10
20 - 15
30 25
point
35 (b) STAGE 2
10
30 ----------
25 ..
2015

point "c"
10 20 1 30 20

30_ipoint "b"
40 - 50

i0'/\
20
0 ,.
(c) STAGE 3
-7.5
-10
all values are in 0C

Fig. 20. Temperature distribution.

on the surface of the deck, is ap- casting Stage 3 as 32.2C for a vertical
proximately 20C and the temperature in distance of 28,7 in. (730 mm) between
the bottom portion of the web and the the two points.
bottom flange is below 0C. Time-temperature distribution along
The temperature distribution with the centerline of the web in the lon-
time for Points "b" and "c" with respect gitudinal direction is shown in Fig. 22.
to placing Stage 3 is shown in Fig. 21. The heavy dashed line indicates the
These curves indicate, as would be ex- joint between the previously cast Seg-
pected, a heat dissipation at the surface ments A and B. The curves show, be-
(Point "c") as compared with the heat tween the points ofO.5to1.2rn(1.6to4ft)
dissipation at an internal position (Point from the end of the segment, the influ-
"h"). A comparison of the two curves in- ence of the locally effective hot air
dicates a maximum gradient between heating of the segment and also its poor
Points "b" and "c" at 15 hours after heat distribution.

PC[ JOURNAUMarch-April 1985 99


T oC
60 .56.0 c
50 b r

40

30 X28-0 temperature of concrete at point 'b'


20
temperature of concrete at point
10
20 40 60 0 10 20 140 t (hours)
-- _ - 8.4
-1 0
-16.6_
-20
air temperature inside box
external
heating

Fig. 21. Temperature distribution with time (Points b and c).

These curves are also noticeably in- of contiguous members and proper cur-
fluenced by the low temperature of the ing procedures.12
previously cast Segment A and the cool There are basically two methods of
ambient temperature. The maximum heat curing concrete: (1) preheating the
temperature gradient decreases gradu- fresh concrete before placement in the
ally after the first few hours of hydration forms and (2) heat curing the concrete
heat development. This gradual de- after consolidation in the forms.'
crease in gradient is due initially to the In the first case the concrete is pre-
heating up of the adjacent segment and heated to about 85 to 90F (30 to 35C).
later on to decrease in heat of hydration This operation is achieved in several
and cooling of the web of the segment. ways:
Thin members cool at a faster rate 1. Steam heating the aggregates a
than thicker members which, therefore, simple solution that presents the disad-
create considerable tensile stress. When vantage of changing the aggregate water
fresh concrete is cast against old con- content.
crete there is a potential for cracking in 2. Heating the water a solution that
the younger concrete which, when sub- has limited efficiency, because of the
sequent cooling occurs, is hampered small proportion of water in comparison
from shortening by the older concrete. with the other components (water at
This usually occurs during the first few 140F raises the concrete temperature
cool evenings when the strength of con- by approximately 20F).
crete is low and low tensile stresses can 3. Direct heating of the concrete mix
cause cracking. At this point, because by injecting steam into the mixer itself
bond is not sufficiently developed, the best solution and the one most
reinforcement cannot prevent opening easily controlled.
of the cracks. Restraint forces due to To avoid heat loss, the forms are gen-
temperature differences must be erally insulated and some source of
minimized to the extent possible by radiant heat is installed inside the seg-
avoiding large differences in thickness ment.

ie
segment A segment B

T C

60
joint
50 l time in hours
from placing
40 of concrete
24
30 --12
49
20 67
10 91
115
0
0.5 1.0 20 m
I
external
heating

Fig. 22. Longitudinal temperature distribution in web (Stage 2).

In the second case, the concrete is these cracks, which can cause a devia-
heated in its form inside a thermal con- tion of the isostatic lines of compression
tainer in which low pressure steam is toward the uncracked zones, altering the
circulated. The heat curing cycle should prestressing distribution in the section
include (Fig. 23):3 under consideration resulting in insuffi-
1. An initial curing period of 2 or 3 cient bearing strength.
hours, during which the concrete is kept To avoid this situation the members
at the ambient temperature. being joined must be rigidly held in po-
2. An increase in temperature at a low sition. Normally, in cast-in-place bal-
rate of less than 36F (20C) per hour. anced cantilever construction a form
3. A period, depending on the con- traveler is used to clamp the two can-
crete strength to be achieved, during tilever tips rigidly in place. For precast
which the temperature is held constant segments or for longitudinal closure
and below 150F (65C). pours between flange tips an external
4. A period during which the concrete rigid clamping device must he
is cooled at a rate similar to that used for employed (strongbacks). In addition,
the temperature increase. proper curing procedures must be
A similar form of cracking occurs at a employed to control shrinkage stresses.
closure pour either at midspan in bal- Another difficulty during curing is
anced cantilever construction or lon- that resulting from large temperature
gitudinal closure pours between the tips differences between the curing envi-
of adjacent box girder flanges (Fig. 24).' ronment of the segment being cast and
As the closure pour concrete hardens, the outside environment of the cast-
the units being connected may undergo against segment (Fig. 25). If a tempera-
deformations (solar heat) as discussed ture gradient exists across the east-
previously or by transient moving con- against segment, its shape will change.
struction loads and/or as a result of The segment will return to its original
thermal shrinking as discussed previ- shape when the temperature gradient
ously. The prestressing may not close falls back to zero,

PCI JOURNAL/March-April 1985 101


T o f Ow

uj z rt
212 W 0Gr1
cca ^o^^ZG max. temp. <150F(65C)
^ G3
65 FORM STRIPPING
65
time in hours
2 to 3hI

ut
zp F
w : -J
~)W << 0
?Ud aw Z 0
w w
2i OM
w w
I

Fig. 23. Heat treatment cycle.

cracks

detachments

PLAN
closure pour

flange movements

SECTION

closure segment

movements

Fig. 24. Closure pour cracks.

102
-il" fit` ft1fr
<h "

segment conjugate
tr t
end form

gradient in
conjugat
y
curingAT F
tempera re
1f
` ambient
y' ' temperature

%"^^' mot'

en t
L

Fig. 25. Effect of improper curing of segments in short -line casting.

This will result in match cast surfaces dients being set up which could lead to
that are not necessarily parallel full horizontal curvature of segments and
length. This condition is evidenced in consequent lack of matching in the
the top slab joints; the joints will be structure. This effect is particularly sig-
tight at the curbs and a small gap may nificant for segments with high width to
be noticed at the center. The problem length ratios (in excess of 6).2 3
becomes cumulative if this condition
exists for subsequent castings. With the
tremendous prestressing force, the seg- CRACKING AT OR NEAR
ments develop longitudinal cracks as ANCHORAGES
the segments are seated against each
other. Certain anchorage positions, such as
This also results in an unaccounted an anchorage blister on a thin flange as
variable when evaluating the bridge shown in Fig. 26, should be avoided.
camber. For match-cast segments, it is Wherever possible, anchorage blisters
important to enclose both the cast for continuity tendons should be placed
against segment and the segment being in a fillet between the web and flange
cast in an isothermal enclosure. This where the transverse section has the
will prevent longitudinal thermal gra- largest rigidity. If this type of detail can-

PCI JOURNAL/March-April 1985 103


anchorage

Fig. 26. Anchorage blister position to be avoided.

segment joint
web

anchorage >tendons
blister
-i

cracks vweb

Fig. 27. Cracking at anchorages.

cracking
in joint,
iF J anchorage
'blister web

segmen
tendons

-web

joints

Fig. 28. Cracking in joint behind anchorage.

104
not be avoided, then particular attention capacity of the webs will he reduced
must he paid in design and construction and failure of the structure may he im-
to the zone concerned.3.L8 minent.2 It should be noted that this
Cracking will originate in the bottom type of cracking is not symptomatic with
flange behind continuity anchorage anchorage blisters; the same cracking
blisters and propagate forward toward pattern has been observed with anchor-
the webs, along a line forming a 30 to 45 ages embedded in the flange, i.e., no
deg angle with the longitudinal axis of blisters.
the girder (Fig. 27). If the rear face of the It is possible that this type of cracking
blister is located in close proximity to a from continuity tendon anchorages
segment joint, cracking may develop in in the bottom flange may join with simi-
the joint (Fig. 28). In some situations the lar cracks originating from cantilever
diagonal or herringbone cracks in the tendon anchorages in the top flange
bottom flange continue to propagate to (Fig. 30). In this situation, the center
the webs forming a 30 to 45 deg angle portion of the span may become an in-
with a horizontal axis (Fig. 29)..2 verse "key-stone" (Fig. 31) and im-
If the crack reaches a segment joint ,n mediate measures are required to pre-
the web it may cross the joint, but usu- vent collapse of the structure.'
ally travels vertically up the joint to a This situation occurred in a box girder
point below the top flange where it may constructed by incremental launching'
continue vertically in the joint, resume a (Fig. 32..). Permanent prestress was
diagonal path in the web proper, or achieves. by straight tendons placed in
cease to propagate. Obviously, the shear the top and bottom flanges, as required

so^

Fig. 29. Anchorage cracking propagating to web.

PCI JOURNAL/March-April 1985 105


by the distribution of moments. During webs of the box section were subjected
launching an additional uniform pre- to additional tensile stresses due to the
stress was applied to the constant depth distribution of the large concentrated
single box section, which produced an forces of the top and bottom prestress.
average compressive stress of 520 psi The truss analogy shown in Fig. 32 indi-
(3.6 MN/ins). Near each pier there was a cates clearly that such tensile stresses
vertical prestress designed to reduce are superimposed on the normal shear
web diagonal stresses to allowable val- and diagonal stress due to the applied
ues. dead load and may therefore produce
During launching a diagonal crack cracking. This could have been pre-
appeared through both webs between vented by extending the vertical pre-
the blisters provided in the box for an- stress in the webs further out toward
chorage of top and bottom tendons. The midspan.
corresponding shear stress was 380 psi The cause of this type of cracking is
(2.67 MN/m 2), and there was no vertical the application of a tendon force to a
prestress in that zone. small area of slab, in its plane, compress-
The principal tensile stress at the ing the slab forward of the force in a
centroid of the section was 200 psi (1.4 zone of radial compression stresses that
MN/ms), which is far below the cracking cause tensile stresses behind the point
strength of plain concrete. In fact, the of application of the tendon force (Fig.

top tendon
ack

riange crack bottom tendon

Fig. 30. Insufficient lap between anchorages.

flanne cranks

Fig. 31. Symmetrical cracking causing inverted "key-stone."

106
initial load 1
490 k/tendon iq no vertical prestress in this zone top tendon pier

average -^ ' I I ' I II


compression throwg h crack in I
t i
520 psi both webs I ' I
stress i i
380 psi
initial load 490 kltendon 7 i I F I

141a 1 1 i 4

bottom J

tendon '
PARTIAL LONGITUDINAL SECTION

diagonal tension
due to prestress
distribution in web
II ,
diagonal crack II ,

I
TRUSS ANALOGY

SECTION A-A

Fig. 32. Web cracking under high prestress force.

33). 1,2 Among the parameters that can tendon forces. In a recent failure of this
produce this type of cracking are the type, after epoxy injection of the cracks,
following:' additional external post-tensioning was
1. Termination of numerous con- provided to close-up and induce com-
tinuity tendons in a single section, par- pression in open segment joints and
ticularly when the joint behind the an- cracks.
chorages is not compressed by other
tendons and when passive longitudinal
reinforcement does not traverse the CRACKS RESULTING FROM
joints between segments or is inade- VERTICAL CURVATURE OF
quate. SOFFIT TENDONS
2. Insufficient horizontal offset be-
tween tendon anchorages in the top and This type of distress is associated with
bottom flanges (Fig. 30). variable depth girders and occurs in the
If this type of cracking andlor failure is positive moment area. It is manifested
to be inhibited, the design, detailing, by longitudinal cracks occurring in the
and placement of reinforcement in these bottom flange, at the juncture of the
highly stressed zones must be carefully bottom flange and web, and possibly in
considered. Location of blisters must be the web (Fig. 34).'
considered and there must he sufficient Tendons for continuity or positive
longitudinal reinforcement behind the moment prestress may not, or even
blister or anchorage and sufficient should not, always be located in the fil-
transverse reinforcement abreast of the let between web and bottom flange.
anchorage to accommodate the initial They may be located in the bottom

PCI JOURNAL/March-April 1985 107


possibly failure. Practically, this situa-
tion may be aggravated by tendon cusps
associated with tendon profile devia-
tions which will be subsequently dis-
t^
'\l l l^^
tension cussed (see Fig. 57).
As a numerical example (Fig. 36) of
secondary stresses due to vertically
I\\tension
curved prestressing tendons, assume the
following:'
compression Longitudinal radius of curvature
= 1000 ft (304.8 m)
Fig. 33. Stress pattern at anchorage. Weight of bottom slab
= 100 psf (4.8 kN/m2)
Compressive stress:
Unloaded bridge = 2000 psi
(13.8 kN/m2)
flange proper. When a variable depth Loaded bridge = 0
girder is used, the bottom flange has a Tendon capacity = 280 kips at 10 in.
curvature in the vertical plane, which spacing (1.25 MN
must be followed by the prestressing at 0.254 m)
tendons (Fig. 35),
The radial load resulting from pre-
Unless careful consideration is given
stress compression is then determined
to that fact at the concept and detailed
as:
design stages, difficulties are likely to
NIB f. t/R = (2000) (8) (12)/1000
develop. This is indicated in Fig. 35,
= 200 psf (9.6 kNlmz)
which shows the free-body diagrams of
The tendon radial load is:
stresses in the bottom flange due to the
FIR = 280,0001(10/12) (1000)
curvature, Curvature of a tendon in-
340 psf (16.3 kN /m2)
duces a downward radial force, which
The total loads on the bottom flange
must be resisted by transverse bend-
are:
ing of the bottom flange between the
webs? (1) During construction (dead load)
= 100 psf (4.8 kN/mg)
Longitudinal compressive stresses in (2) Unloaded bridge
the bottom flange similarly induce an = 100 200 + .340
upward radial reaction in the flange, = 240 psf (11.5 kNlm')
counteracting at least in part the effect of
(3) Loaded bridge
the tendons. Unfortunately, when the = 100 + 340
full live load and variable effects, such
= 440 psf (21 kN/m2)
as thermal gradients, are applied to the Bending moment
superstructure, the longitudinal stresses
= w12/12
vanish and consequently the partial ne- = 9 ft-kips/f} (40,000 N -m/m)
gation of the effect of tendon curvature
Stress in the bottom flange
is lost.
f== (9000)
(uncracked section):
Therefore, the effect of tendon cur-
MIS
vature adds fully to the dead load stress-
(12)1(12 x 8216)
es of the concrete flange. The corre-
= 840 psi (5.8 MN /m2)
sponding flexural stresses may be four to
five times greater than the effect due to At this stress level the tensile strength
dead load only, and if sufficient rein- of the concrete would be exceeded, pro-
forcement is not provided for this effect, ducing the longitudinal cracks depicted
heavy cracking is to be expected and in Fig. 34.

108
possible web cracks
C

n 0
corner crack

1 0 t 1 0) Q / 0 Oj 0

bottom flange cracks- L longitudinal tendons

Fig. 34. Cracking from curved soffit tendons.

f4^;E 1i i.^.
PARTIAL CROSS-SECTION

unit load N/R


t ^ N F

/ ^^r Pt

effect of unit load FIR


compressive
Stresses effect of
prestressing
tendons
FREE BODY DIAGRAM

Fig. 35. Vertically curved tendon.

PCI JOURNAUMarch-April 1985 109


Assumed Longitudinal Radius 1,000 ft.

Fig, 36. Numerical example.

PULLOUT OF 9 ft (2.74 m). The top flange varies in


HORIZONTALLY CURVED thickness transversely froth 8% to 12 in.
(0.22 to 0.305 m). The bottom flange
TENDONS varies in thickness longitudinally from
71/2 in. (0.19 m) at midspan to 14 in.
A problem has occurred relatively re- (0.356 m) at the piers.
cently with small radius horizontally The bridge was post-tensioned with
curved, post-tensioned box girder 12 draped tendons, which are continu-
bridges. The problem has occurred at ous throughout the entire length of the
two known sites during construction. It structure. Four bundled tendons were
concerns the lateral force produced in placed in each web and all tendons were
the webs by the tensioning of horizon- jacked from both ends at the abutments.
tally curved longitudinal tendons. The first failure (Fig. 39) occurred
The first example* is a continuous, during prestressing operations when the
cast-in-place, post-tensioned concrete twelfth and last tendon, located in the
box girder bridge, with three spans of north web along the inside of the curve,
176, 234, and 176 ft (53.6, 71.3, and 53.6 was near its full prestress. A loud noise,
m) with slightly over half of the eastern described as a "bang," was heard and all
176 ft (53.6 m) span aligned on a hori- four tendons in that web broke away
zontal curve with a 250 ft (76 m) radius from the web for almost the entire
(Fig. 37). This 176 ft (53.6 m) curved length of the curved east span, tearing
span has three 12 in. (0.305 in) thick in- the curved reinforced web along the
termediate diaphragms, located at each profile of the tendons. Two days later,
quarter point of the span. the east quarter-span length of tendons
In cross section (Fig. 38) the in the south web, along the outside of
superstructure is a two-cell box with top the curve, suddenly broke out of the
flange width of 34 ft (10.4 m), a bottom concrete web, again making a loud
flange width of 23 ft (7 m), and a depth of noise.
An immediate inspection of the
structure indicated that the horizontally
"Las Lomas Bridge Causes of Structural Fail-
ure," Report to Department of the Anny, San
curved tendons, exerting a radial hori-
Francisco District Corps of Engineers, T. Y. Lin zontal pressure, had overloaded the
International, August 1979 (Unpublished). reinforced concrete webs. This overload
t
N

176' 234' _ 176`

Lam;

Fig. 37. Bridge elevation and plan.

r^

14 1
23'

Fig. 38. Typical cross section.

PCI JOURNALIMarch-April 1985 111


Fig. 39. Horizontal pullout of curved tendons (courtesy of T. Y. Lin).

Abt. 1

Pier 2 tI
N11

Pulled out tendon ^urv'^d Span

====ice =s=y r^ ^V ^'^^`

1- L --_- JL -. -
pulled out tendons

Partial Plan

location of failures

section

Fig. 40. Zones of web failure.

112
original curved tendon path
sharp
angle
change pulled out portion

tension } 1 { { r tension
large radial / l
tearing force L/
distributed
radial
force

Fig. 41. Progressive failure along tendon.

had caused the concrete to fail, allowing After that, most of the tendons were re-
the tendons to straighten out and pull leased except two tendons along the
away from the webs (Fig. 40). The fail- north web and one tendon along the
ure was particularly evident in the inner center web which were not released.
(north) web, where the tendons had It should be pointed out that a review
pulled well clear of the concrete. In the of the construction documents and the
outer (south) web the failure (inside the construction method for both structure;
box) had not progressed past the first revealed no serious discrepancies be-
quarter-span diaphragm. The center tween the construction method as com-
web was undamaged. Additional obser- pared to the construction documents
vations indicated that the tendons were and specifications. Further, the
continuing to pull away from the webs, AASHTO Standard Specifications for
and that failure had progressed several Highway Bridges' does not provide
more feet towards the abutment and the guidance for the design of curved
pier (Fig. 41). post-tensioned box girders.
The second example* occurred on an In both these structures, there was a
interchange ramp (Fig. 42). This struc- combination of relatively sharp curva-
ture is a post-tensioned, cast-in-place, ture, thin concrete cover over the ten-
continuous, two-cell concrete box gir- dons and the bundling of a number of
der, constructed essentially on a curve large sized tendons close together.
with a radius of 540 ft (164.6 m). The These failures are somewhat unique in
structure, between expansion hinges, that the problem would not have sur-
experienced concrete spilling and faced in the case of a flatter curvature,
cracking during construction oh the thicker concrete cover over the tendons,
south web of the box along the curve as or adequate spreading of the tendons
indicated in Figs. 43 and 44. into individual ducts as compared to
During the first post-tensioning oper- bundled ducts.
ations, four tendons out of six in each The analysis of the failure of these
web were fully post-tensioned, then structures can be divided into three
noise was heard and cracking and spall- separate actions (Fig. 45) which need to
ing were observed along the south web. he considered in design:
1. The global or overall girder action
`'Kapiolani Interchange On-Ramp Project No.
1-H1-(157):24," Design Review: Interim Report to of the bridge together with its support-
Department of Transportation, State of Hawaii, ing piers and abutments.
T. Y. Lin International, April 1982 (Unpublished). 2. Regional beam action of each web

PCI JOURNAL,1March-April 1985 113


la
-I!
\ rio., W) ^m /^
/4

N
DC

a^
C C I CD
o D Cr

0 ^ li Cal EA ICA
ID

36'IO C

23'

Fig. 42. Plan, elevation and section.

supported at the top and bottom flanges stresses are not a major factor. Thus, it is
as a beam. believed that the global action for both
3. Local slab action of the concrete of these structures had only minor ef-
cover over the tendons. fects on the failures experienced, and
It is important from both the analysis were not quantitatively considered.
and the design viewpoint to look into all Regional action considers each web as
three of these actions and their effect on a beam supported at the top and bottom
both the concrete and the reinforcement flanges. This beam (Fig. 46) is acted
in the webs of the boxes. upon by the radial force from the ten-
One point concerning global action of dons. The radial tendon force produces
the girder is the restraining effect of the shear and bending in the web, as it
piers and the bridge hearings. A curved spans vertically, The bending moment
bridge tends to shrink along certain di- and shear in the web are also influenced
rections, depending on the flexibility of by the fact that the web concrete is
the piers, while the movement of the under longitudinal compression from
bearings maybe restrained to take place tendon prestress.
along a different direction. Thus, sec- This precompression has an arching
ondary moments in the horizontal di- effect which partly counteracts the ra-
rection are produced in the girder of dial force from the tendons, thus reduc-
these two structures. ing the bending moment produced by
It has been determined that such the tendon force. In other words, the

114
yv

LI
4. B! _c1
^
^% J

g. y^^4 111 _

5 11 I,

hairline cracks
large cracks
Spa us

Fig. 43. Failure of south web.

tendency to push radially inward by the schematically in Fig. 47.


curved tendons is counteracted to some This condition of equilibrium is often
degree by the tendency to push radially taken for granted so that the local and
outward by the concrete. This is shown regional effects of these forces are not
normally calculated, in spite of the fact
that they may be far from being bal-
anced, depending on the degree of cur-
vature and amount of prestress tendon
pressure occuring locally or regionally.
The inward pressure from the tendons is
often much higher than the outward ra-
dial arch pressure from the concrete.
Such a force imbalance has been re-
sisted without failure in thousands of
structures constructed, although some of
them may be on the verge of failure and
not detected.
The stirrups in the beams are de-
signed, as usual, to resist the vertical
web shear at the ultimate range. Gener-
ally, the webs of the box do not crack
under normal loadings and the stirrups
are seldom called into action. On the
other hand, at ultimate load, where the
beam webs do crack, then the stirrups
are called into full action. At that time
the stirrups may or may not have excess
capacity to serve as the beam flexure
reinforcement for the web in the vertical
Fig. 44. Web spalling (courtesy of direction.
Clarence R. Yamamoto). It appears that the stirrups should be

PCI JOURNAllMarch-April 1985 115


provided to take ultimate web shear first practice to design plain concrete to take
and to resist the web-beam action in ad- tension, this analysis has very little
dition. In the second failure example, meaning.
where #5 stirrups at 12 in. (0.305 m) The second analysis, shown to the
centers were provided, they were over- right in Fig. 48, assumes that the con-
stressed in beam action alone, even crete has cracked and is unable to sup-
without their service as shear stirrups. ply tension for the support area between
Local slab action is probably the most the bundled tendons. If this is the case,
important item that actually caused the the slab will act as a single span fixed at
failure in both of these structures. The the ends; however, the reinforcement is
local slab action can be studied in dif- in one plane on the inside face only.
ferent ways. First, consider the cover as This can offer very little resistance to
a slab 2 in. (50 mm) thick (reinforced the radial force from the tendons, both
with #5 bars along the inside face only) in bending and in shear. The stresses
acting as a two-span continuous beam are exceedingly high.
with a central support furnished by the An extraordinarily high percentage of
concrete between the two sets of bun- reinforcing steel would be required to
dled tendons, as shown on the left of resist such moments. Unfortunately, the
Fig. 48. tendons were tied to the stirrups on the
This can be analyzed as a plain con- inside of the curvature; thus the stirrup
crete beam acting in shear and in flex- reinforcement is in position next to the
ure. However, there is a tendency for tendon ducts such that it does not func-
concrete to shrink against the more rigid tion to resist positive moment produced
ducts. As a result, the tensile strength of by the radial forces. Therefore, the con-
the concrete can be entirely lost, both in crete cover essentially is a plain con-
the support area between bundled ten- crete slab and its resistance is nil.
dons and maybe in the 2 in. (50 mm) slab The order of magnitude of the stress
itself. Since it is not considered good produced by the three causes discussed,

Girder Action

GLOBAL

1
REGIONAL ^ 1

1 LOCAL
Beam Action 1 1
1 1 ^^/
Slab Action
1 1

Fig. 45. Box girder actions due to horizontally curved tendons.

116
Top Flange /\

ttom Flange
Web Spanning
Vertically

distributed
radial
force
from
arch
radial r action
force
from --
tendons

Fig. 46. Vertical span of web.

distributed force
from arch
compression

concentrated force
from tendons

System tendon force arch total


action

Fig. 47. Moments in vertical span of web.

PCI JOURNAL/March-April 1985 117


32^ 12

fZ "/Ar ^_ 3.39
hL

O.f7 %T.

_3K o0 o.ra4

a.)1K/sr

a^'yFr 32^Fr
^ r.la9 K i
^3,3gK

2 span loading 1 span loading

Fig. 48_ Slab action.

-I
IuIuiii!iIflhuuII
-=
9

uiuiiuiiriuiiu
8

IIUI!iUii!!1
6

n
v

3 1

2 4 6 8 1 12 14 16 18 20

F Q/R (k/ft per web)

Fig. 49. Chart for determining web reinforcement (#5 stirrups).

118
2 4 6 8 10 12 14 16 18 20

F = j I
R
(kilt per web)

Fig. 50. Chart for determining web reinforcement (#6 stirrups).

d^
ide of curve

dl

standard detail

Fig. 51. Tendon placement details.

PCI JOURNAL/March-April 1985 119


when compared to the allowable stress- the jacking force (Ps) by the radius (R), a
es in concrete or its reinforcement is lateral prestress force (F) of 9.67 kips per
approximately as follows:* ft (14 kN/m) is obtained.
1. For global secondary horizontal The first step is to enter the chart (Fig.
stress ......... 1 to 10 percent 49) with this value (F) on the horizontal
2. For regional bending axis of the graph and travel vertically
stress ......... 5 to 50 percent upward until the ordinate (he.) of web
3. For local slab bending height is reached. The chart then indi-
stresses ....... 10 to 300 percent cates that a web thickness of 12 in.
Of course, every case is different and (0.305 m), #5 stirrups at 9 in. (228 mm)
could fall outside of these ranges. But spacing, and tendon placement detail
the percentages cited present some rea- "A" as opposed to a "standard detail" is
sonable order of magnitude. required.
Another important factor in the above A similar set of curves (Fig. 50) has
is the bundling of the large tendons. It been prepared for #6 stirrups. In cases
appears that bundled tendons should that specify final prestress force (P1)
not be used for horizontally curved rather than jacking prestress force (P3), it
bridges with a radius under 700 ft (213 may be assumed that PP is equal to 1.25
m), unless proper design considerations P. Up to a lateral prestress force pres-
are implemented. sure (F) of 7.2 kips per ft (10.5 kN/m),
It therefore appears that, for both shown by the vertical dashed line, the
these structures, the local slab action chart indicates a "standard" tendon
was the primary cause of failure, but the placement. Above this value, Detail "A"
regional beam action could have been a is required.
contributory cause, and could by itself The "standard detail" indicated at the
have overstressed some of the stirrups, left of Fig. 51, as the name implies is a
even if not to the point of failure. The standard detail for bundled tendons.
global action had a relatively small ef- Detail "A", at the right of Fig. 51, indi-
fect upon these failures. cates that the tendons are stacked verti-
In the design of curved post-ten- cally and placed against the outside stir-
sioned concrete box girders the designer rup with respect to curvature. This is
must consider the lateral prestress force. done to provide a greater thickness for
In recognition of this problem the Cali- local slab action and to put the inside
fornia Department of Transportation stirrup in a position to participate as ac-
(CALTRANS) has prepared and imple- tive reinforcement in the slab action.
mented design guidelines. f They have Further, Tendon Detail "A" requires
prepared charts and details to he used as #4 ties between the stirrups and adja-
a check of girder webs for containment cent to the bundled tendons, and a hoop
of tendons and adequate stirrup rein- around the bundled tendon hooked to
forcement to resist flexural bending. the outside stirrup (Fig. 52). This then
As an example, assume that the design mobilizes the outboard stirrup and the
of the girder requires a prestress jacking central concrete area behind the inboard
force (P1) of 2900 kips (12.9 MN) per stirrup in participating to resist the pull-
web, a radius of curvature (R) of 300 ft out of the tendons.
(91.4 m), and a vertical inside height of The application of the California
web (he) of 6.83 ft (2.08 m). By dividing guidelines is based upon the following
assumptions:
1. The girder web is assumed to be a
*Private correspondence with Dr. T. Y. Lin. beam with a length equal to the clear
tMeino to Designers, "Curved Post-Tensioned
Bridges," 11.31, California Department of Tranx- distance between top and bottom
portation, November l982. flanges.

120
B "lolls
* 4 'L_^c /35 bend
of each stirrup. Hook around stirrup
^ 24mox. Place duct against le g s AI rernole sides for 135 hook.

C
*4
and hook tie around stirrup leg on Place one above top duct and one
Inside
oufsrds of curve. below bottom duct.
of curve

Prestress
Duct --

Stirrup
Legs---

Bottom slob reinforcement


2''clr !o stirrup leg on inside of curve

Fig. 52. Tendon placement Detail "A".

2. The lateral prestress force is as- It appears that these guidelines


sumed acting at midheight of the web. should be incorporated in the design of
2. The moment is calculated by sim- horizontally curved post-tensioned
ple beam formula reduced 20 percent girders which have a radius of approxi-
for continuity between web and flanges mately 700 ft (213 m) or less.
with a 1.0 load factor applied.
4. The shear and bending stresses in
the web stirrups are additive. However, OTHER CRACKING MODES
for the purpose of these design aids the ASSOCIATED WITH
stirrups are considered capable of han-
dling these stresses independently for CURVED TENDONS
the following reasons:
Cracks have occurred in thin webs
(a) The ultimate moment is cal- following the profile of curved tendons
culated for the maximum con- at some distance from the anchorage.
dition of the lateral prestress This type of cracking appears in con-
force (F) acting at midheight of struction, during tendon stressing, and
the web span. This occurs at later stabilizes. Nevertheless, these
only two points in a span due cracks can lead to corrosion of the ducts
to tendon drape. and eventually the tendon. If moisture
(h) The jacking force, Pj , is used in penetrates these cracks and suhse-
the calculations of ultimate yuently freezes, spalling can occur. Al-
moment, and at the time Pj is though this type of cracking occurs in
applied, the structure is sup- thin webs, it can occur in thin flanges
ported on falsework. When the where there is horizontal curvature of
falsework is removed and ver- the tendons.
tical shear forces act, the pre- This type of crack usually occurs
stressing force has been re- where there is significant tendon cur-
duced by losses. vature and multi-strand tendons. Where

PCI JOURNALMarch-April 1985 121


there is tendon curvature, a uniform Iat- To preclude this type of cracking or
eral pressure is set-up that is normal to failure, confinement reinforcing is re-
the tendon axis and in the plane of cur- quired in the area of tendon curvature. A
vature. This laterally distributed pres- very excellent research program was
sure may cause cracking along the ten- conducted at the University of Texas at
don profile at a prestress force lower Austin concerning this phenomenon,
than that required to initiate cracking at along with cracking at the anchorage
the anchorage zone. zone proper, and is presented in Refs. 19
The strands in a multi-strand tendon, through 23. An empirical design method
as it is being tensioned, tend to flatten to control cracking along the tendon
out toward the inside of the tendon cur- profile is given in Ref. 23.
vature. This action then creates large Another type of cracking is associated
lateral forces on the duct and side cover with the anchorage of external tendons
resulting in cracking and/or spalIing. in a diaphragm. The general arrange-
The failure mechanism is illustrated in ment of external tendons in a segmental
Fig. 53.21.23 box girder bridge is illustrated in Fig.

` P r a

p a

,OOO
pQ I
(a) UNSTRESSED TENDON
O

. P a I. P I

6 ,

.
"$edge"

(b) TENDON AT STRESSING LOAD

y large radial forces due to


a r 'flattening out" of tendon
9 , , ' bundle Initiate cracking In
vicinity of sharpest curvature

ne w p (c) FAILURE

side face rupture at


point of sharpest
curvature

Fig. 53. Multistrand failure in a curved tendon.

122
post - tensioned tendons
in nolvethvlene ducts

Fig. 54. External tendon configuration.

P i

(a)

Q a laminar crack

(b)

Fig. 55. Diaphragm cracking from tendon curvature.

54. The external tendons pass through In addition, a splitting crack may de-
the diaphragm along a vertically curved velop as a result of multi-strand com-
profile and are anchored in the dia- paction in the zone of curvature as dis-
phragm face which produces a radial cussed above. It appears that the lami-
pressure as indicated in Fig. 55a. As a nar crack either by itself or in conjunc-
result, a tensile stress field is set-up tion with the splitting crack, over a pe-
above the tendons (Fig. 55b) similar to riod of time will propagate to the surface
the tension stress field behind an an- and produce spalling. Spalled areas of
chorage blister. This tension field may the deck have been as large as 3 x 3 ft (1
then cause a laminar crack above the x 1 m). The spalled surface in two proj-
tendons. ects were located generally over the

PCI JOURNALJMarch -April 1985 123


access opening

- ` longitudinal'tendons

cracks

web

Fig. 56. Cracking at an access opening.

tensile zone B in Fig. 55 b. position, being held in position by the


This is probably associated with the bulkhead form or by the position of
fact that there is less cover over the ten- ducts in the segment cast against. How-
dons in Zone B and that Zone B repre- ever, if flexible tubing is used with an
sents the jacking end of the tendons and insufficient number of supporting chairs
thus a larger prestress force. Zone A is or ties, or if they are deflected down-
associated with the dead-end anchor- ward by the weight of the wet concrete
ages. It appears that tie reinforcement being placed, or by workmen walking in
should be provided to not only confine the fresh concrete, the duct profile will
the splitting crack but also to provide have an angle break or cusp at each
reinforcement to resist the tension gen- joint. In addition to the increased fric-
erated above the tendons. tion losses, there is a potential danger of
Diaphragms can be elements of a local spalling and bursting of the intra-
bridge that have a highly complex stress dos of the bottom flange (Fig. 57a).'2.'2;
field. This is particularly true if, in ad- Cracking may also appear in the top of
dition to vertically curved longitudinal the flange midway between the segment
tendons, there exist transverse tendons joints. Depending on the spacing be-
in the top flange and straight or curved tween adjacent tendons and therefore
tendons in its plane to accommodate tor- the area of concrete between tendons to
sion. A finite element method of analy- resist the tension developed, a laminar
sis should be utilized to evaluate the crack may develop (Fig. 57b).
state of stress in these members. Laminar cracking may then propagate
Where longitudinal tendons are flared to a spalling failure during further ten-
or deflected around access openings in a sioning of the tendon (Fig. 57c) which
bottom flange, there is a potential for se- will produce a deformation in the rein-
vere cracking to occur as illustrated in forcing steel and displacement of the
Fig, 56. The flange in front of the open- tendon. In some instances, spalling has
ing is literally being torn or ripped apart occurred during water pressurization
as a result of the tension created by the tests or during grouting, especially
tendon curvature.' when all tendons in a group are tested or
grouted simultaneously (Fig_ 57d).
Occasionally, because of the wrong
CRACKING AND SPALLING height chairs or mislocation, the profile
FROM TENDON will he inadvertently placed in an in-
MISALIGNMENT verted profile as shown in Fig. 57e. Ob-
viously, the cracking and/or spalling
Longitudinal ducts at the segment pattern will he inverted from that shown
joints are usually placed at their proper in Fig. 57a.

124

cracks

L ioint crack or spalling^ S., r

(a)

laminar cra k
C_ original
imprint of to on
of tendon
(b) of duct

deformed /
reinforcement
N position
of tendon
after failure
delamination (c)

(d)

joint cracks or spalling

cracks

(e)

Fig. 57. Effects of misalignment of tendon ducts.

This problem can be avoided by the problem indicated that during construc-
use of rigid ducts properly positioned tion the longitudinal tendons had been
and securely tied to the reinforcing deflected downward because of an in-
cage, use of a rigid mandrel placed in- terference with the deflected profile of
side of the duct during casting, and pro- the transverse tendons.
viding work bridges for workmen so that The result of the upward components
they do not walk in the wet concrete. of the two curved tendon systems prob-
In a recently reported example 2425 of ably created a laminar crack upon ten-
this type, a 16 x 32 ft (5 x 10 m) area of sioning of the tendons. Air pressure
the upper portion of a deck slab lami- used to blow out the remaining un-
nated and spalled. Investigation of the stressed tendon ducts probably propa-

PCI JOURNALMarch-April 1985 125


To avoid the problem of duct crush-
ing, a number of alternatives are avail-
able to restrain the duct being tensioned
from displacing into and crushing an
t adjacent ungrouted duct, namely,
OCR_ 00 maintaining a clearance of one duct di-
ameter between ducts, use of prebent
steel tubes of adequate thickness in the
zone of curvature, or providing adequate
tie reinforcement.
Fig. 58. Lateral duct crushing. Close spacing of longitudinal ducts
combined with transverse ducts and
longitudinal and transverse reinforcing
steel in the top and bottom of the flange
gated the laminar crack initiated during makes it very difficult to effectively
stressing and precipitated the spalling. place concrete, Concrete does not al-
A factor closely associated with this fail- ways work around and under the ducts
ure was the numerous closely spaced and reinforcement. Workmen often
longitudinal ducts. stand or walk in the fresh concrete. This
It may have been possible to substi- pushes the ducts and reinforcement
tute 24-0.6 in. (15.4 mm) strand tendons down and when the men have moved, it
for the 19-0.5 in. (12.7 mm) strand ten- springs back up, which may cause a
dons specified thus reducing the num- laminar separation in the concrete.
ber of tendons by 40 percent and in- Apparently, vibration does not always
creasing the horizontal (in-plane) area of extend deep enough to force concrete
concrete at mid-depth of the flange by up between closely spaced ducts and
70 percent.24 In effect, numerous very knit the top and bottom layers together.
closely spaced ducts produce a Bleed water may collect under flat ducts
"built-in" lamination. and in the "V" formed by two adjoining
Subsequent to the failure described longitudinal ducts. Much of the problem
above, #3 C-shaped vertical ties at 24 in. can be alleviated by selection of tendon
(610 mm) centers were installed be- size and duct spacing to maximize the
tween tightly spaced tendons to tie to- concrete area at mid-depth of the flange,
gether the top and bottom portions of as discussed above.
the flange. These ties cannot prevent Another form of cracking, spalling and
cracking but do function as crack propa- failure is associated with misplacement
gation arresters." of a curved tendon in a blister anchor-
There are several other interacting age. The design assumes that the tendon
causes that may have contributed to profile as it leaves the flange (or web)
other laminar spalling. Although the de- and enters the anchorage blister is a
sign had the ducts spaced apart, in smooth curve (Fig. 59a) with a uniform
reality in many instances they touched, pressure along the curve. In reality, this
especially where there was a horizontal is seldom accomplished in construction.
curvature of the ducts. In some in- The duct usually has an angular "kink"
stances where there was a horizontal instead of a smooth curve transition,
curvature and there were closely ad- which produces a concentrated force at
joining ducts, stressing of the tendon on the toe of the blister (Fig. 59b).
the outer side of the curve caused the This then leads to a spalling or "pop-
duct to crush into the inner duct, dis- out" failure (Fig. 59c). The concrete area
torting it vertically and causing spalling in the slab forward of the blister is then
(Fig. 58).24 reduced, leading to a compression f'ail-

126
dSa^ Pre5sre
,yn;tosmt ra 1 t ` t ^
..
itt

(a) DESIGN ASSUMPTION

concentrated force

^} I^nuA

(b) ACTUAL CONDITION

pop_out or Spa

tension failure
1j

"\ compression failure zone


(c) FAILURE ZONES

Fig. 59. Anchorage blister failure.

ure at that location, tension failure be- sile forces behind the blister, and ade-
hind the blister and shearing along the quate transverse reinforcement should
longitudinal sides of the blister. be used to cater to shear forces along-
To avoid the "kink" in the duct, a side of the blister.
heavier gauge duct or prebent tube The design of blisters requires, in ad-
should be used, tie confining reinforce- dition to reinforcement for anchorage
ment around the tendon should be ex- bursting stresses, adequate reinforce-
tended well forward of the blister, ade- ment for shear and bending between the
quate reinforcement extending from the blister and the flange or web interface.
blister into the flange (or web) behind it Consideration should be given to Sea
should be employed to cater to the ten- tions 11.7 and 11.9 of the ACI Building

PCI JOURNALJMarch-April 1985 127


straight tendon other location in the structure. Without
the benefit of previous experience and
behavioral data over time (perhaps as
much as 10 years) no judgment can be
made relative to a particular retrofit
measure. Therefore, the retrofit mea-
sures discussed below must not be con-
draped tendon
sidered as absolute or automatically ap-
plicable to typical problem solutions,
nor should they be attempted without
rigorous analysis and application of en-
deviation blocks
gineering judgment.`
Fig. 60. Tendon profiles.
Epoxy or Mortar Injection
Epoxy and mortar injection of cracks
Code requirements for shear friction is well known and the mechanics of im-
and corbels. 2e A check should be made plementation will not be expounded
of the localized bending induced into upon in this paper. Rather, two precau-
the flange or web away from the anchor- tions are presented which if not consid-
age and reinforcement provided ac- ered may inhibit the repair.
cordingly. A minimum radius of tendons Effective repair by injection requires
of 15 ft (4.5 m) is recommended with an a stable crack. If the crack width con-
absolute minimum of 10 ft (3 m). A tinues to widen while polymerization of
minimum clear tangent length of 1 ft (0.3 epoxy or curing of grout is taking place,
m) is recommended from the anchorage the effectiveness of the repair is jeopar-
cone or trumpet. dized. The crack may be "working" as a
result of traffic loads or as a result of
RETROFIT MEASURES thermal gradient. On a particular proj-
ect, it was possible to measure signifi-
The purpose of retrofitting is to correct cant crack opening from the cool of the
a deficiency in a structure the result of morning through late afternoon heating
which has been manifested b y formation and subsequent closing when the
of cracks. Thus, in order to propose a. structure cooled down during the eve-
corrective measure, the source(s) of the ning. Obviously the structure should he
problem must be determined. As previ- closed to traffic. To minimize or pre-
ously pointed out, cracking rarely re- clude the effects of thermal gradient the
sults from a single cause but more likely deck surface should be kept cool by fre-
from a combination and interaction from quent water spraying.
several sources. The analysis and inves- The second precaution is one con-
tigation of the problem are frequently cerning pressure injection of laminar
difficult. Some of the phenomena ex- cracks. The problem here is one of frac-
hibited are not well understood either in ture mechanics, i.e., driving the crack by
qualitative or quantitative terms. pressure injection, further complicated
Therefore, the repair method can rarely by the fact that there usually is no cross
be presented in simple terms. reinforcement to arrest crack propaga-
To further compound the problem, a tiion."4 Either a low pressure injection
proposed repair must he analyzed with procedure or some external means of
respect to the structure as a whole to in- applying a pressure transverse to the
sure that a detrimental effect or adverse crack, clamping the two portions of the
stress condition is not produced at some member together, will be required.

128
new distribution beam
ttrcionai external tendons

new backw^

(a) DISTRIBUTION BEAM

prestress tendon pins

box girder web


additional external tendon

attached concrete boss

(b) BOSS

Fig. 61. Tendon anchorage.

Flexural Cracks where it was observed that the moment


developed was decreased by 20 percent
In this situation the intent of the ret- sifter 16 months and that less than half
rofit is to restore the integrity of the would remain after 3 years. It is a suit-
girder by recompressing it where it has able measure to be used as a temporary
decompressed and subsequently basis until a permanent retrofit can be
cracked. There are two retrofit measures devised or as a means of creating com-
that can be considered: support Ievel pression after grouting of the cracks and
adjustment or additional prestressing.' before permanent prestress is applied.
Support level adjustment is simply a Additional permanent prestressing
method of prestressing whereby sup- can be obtained by tensioning added
ports are jacked in such a manner as to longitudinal external tendons, To the
produce a moment that induces com- extent possible, this method should be
pressive stresses at the point where the preceded by grouting of the cracks so
member has been decompressed. This that the compression being applied can
method is attractive because of its rela- be transferred.
tive ease of implementation and low The external tendon profile can be
cost. However, because the method is either straight or polygonal (Fig. 60) de-
one of forced displacement its effective- pending upon the problem. The straight
ness is short term as a result of subse- tendon profile presents few problems
quent moment redistribution. with regard to installation, however, it is
As an example,' this method was used not very efficient and has only a minor
on a 15 year old structure in France effect in improving shear strength. The

PCI JOURNAL'March-April 1985 129


polygonal profile is a more satisfactory manner concentrated local stresses are
solution but requires construction of de- not imparted to the original girder or
viation blocks or saddles which increase diaphragm, i.e., stresses behind the ten-
friction loss. In both methods the tendon don anchorage bearing plate are distrib-
should be rigidly attached to the super- uted to the new transverse member.
structure at sufficiently close intervals to In all probability the existing dia-
preclude elastic instability (buckling) of phragm is not properly reinforced to ac-
the girder and to prevent resonance in cept these stresses. Therefore, high ca-
the tendons if the period of the structure pacity tendons can be utilized. The dis-
is near that of the tendons.27 advantage is that this construction re-
The installation of external tendons quires removal of the existing abutment
generally requires three elements for backwaIl, reconstruction of a new back-
transfer of prestress: a transverse distri- wall, and the construction of the trains-
bution member or diaphragm at the verse distribution member, all of which
abutments, deviation blocks anchored to require that the bridge be shut-down to
the web or flange or both, and a support traffic (Fig. 61a).'-"
at existing diaphragms. An alternative is to anchor the longi-
The transverse distribution member tudinal prestress tendons in a boss, of
at the abutments is simply a massive either concrete or steel, attached by pre-
reinforced or prestressed beam con- stressing to the existing structure (Fig.
structed across the end of the girder for 61h). This method is effective in trans-
the purpose of transferring the external rnilting prestress to the cross section but
prestress force to the girder. In this has the disadvantage of inducing high

clamshell
web 11
deviation block fastening pins

polyethylene tubeI
steel
tube fastening pins steel deflector

bottom flange
(b) STEEL
(a) CONCRETE

Fig. 62. Deviation saddle.

structural
c,nnl Frnw.._
bored hole

anchorage

anchorage additional
5 1 external
tendon

existing
diaphragm external
tendons
Fig. 63. Anchorage at diaphragms.

130
deviation buttress 1_ match-line
transverse distribution beam

addonal tendons anchorage buttress

match-line

deviation buttress /

Fig. 64. Additional prestressing retrofit.

local stresses (bending, shear, and ten- used, deviation blocks or saddles have
sion in the web behind the boss) which to be provided to achieve the profile.
the existing structure may be incapable These devices can be either concrete or
of accepting. Another disadvantage is steel (Fig. 62). They are attached to the
the very short tendons used to pin the existing web or flange by prestressing
boss to the web. These short tendons are pins.1 ' They are subject to the same
very sensitive to losses and could result difficulties as bosses discussed above.
in the boss sliding which would, of At existing diaphragms the tendons
course, lead to unanticipated losses in can pass through or be anchored (Fig.
the longitudinal tendons. Therefore, 63a) provided they have sufficient
particular attention must be given to strength and are adequately attached to
the:' the girder cross section to transfer the
1. Methodology to be followed to re- resulting longitudinal shear. Depending
duce losses through the improper fas- upon the diaphragm detail it may be
tening of anchorages during tensioning necessary to provide a structural steel
operations. frame to transfer the longitudinal pre-
2. Distribution of the anchoring force stress force (Fig. 63b), With existing
along the entire length of the boss diamond coring technology 3 in. (80
(transfer of prestressing from the boss to mm) diameter holes can be drilled to
the structure). depths of approximately 6.5 to 10 ft (2 to
3. Treatment of the surface of the 3m), with a longitudinal tolerance of s/ie
joint between the anchoring boss and to % in. (5 to 10 mm).
the structure, and the resulting coeffi- A recent application of this system in
cient of friction. the United States (Fig. 64) used the
4. Value of the coefficient of friction transverse distribution member at the
between the fastening mortar and the abutments and a concrete buttress for a
boss, if it is made of steel, and deviation saddle that was keyed and
5. Ratio between the fastening force doweled into the existing flange and
and force created by the anchored ten- web (Fig. 65). Where tendons were an-
dons. chored to existing diaphragms, the dia-
Where a polygonal tendon profile is phragm was locally reinforced by a sim-

PCI JOURNALIMarch-April 1985 131


J

B
PARTIAL PLAN

SI

web

flange

SECTION A-A

Fig. 65. Retrofit deviation buttress.

ilar buttress arrangement (Fig. 66). section in question or at some other lo-
A potential repair method for the type cation in the structure.
of cracking shown in Fig. 34 is illus- Another possible repair method is that
trated in Fig. 67 and consists of sup- indicated in Fig. 69, whereby the flange
porting the bottom flange by a suspen- thickness is increased or transverse ribs
sion system.' If the crack width is less are added to assist in resisting the flex-
than 0.008 in. (0.2 mm), the cracks are ural stresses.' However, some means of
harmless with regard to environmental providing external support to the origi-
effects; if the crack width exceeds this nal bottom flange to resist the added wet
dimension it should be epoxy injected. concrete weight, so as not to aggravate
In some cases the crack width may reach the already overstressed original flange,
% in. (1 mm). In this case consideration must be provided. In addition, or con-
might be given to applying external currently, a method of external loading
forces to the section so as to return it to, is required to return as near as possible
or near to, an undeformed state. the original flange to its undeformed po-
This can be accomplished (in Fig. 67) sition, otherwise the stress condition in
by jacking the suspension rods at the the bottom flange is not alleviated and
deck level producing the external loads the effectiveness of the procedure is
indicated in Fig. 68. However, this questionable.
method or any other method (tried or
untried previously) should not be at- Shear Cracks
tempted without careful evaluation and Repair of shear cracks in the web of
analysis to determine that adverse ef- the structure illustrated in Fig. 7 was ac-
fects are not being introduced at the complished by adding vertical prestress

132
Fig. 66. Retrofit anchorage buttress at diaphragm.

suspension rod

uni.

suspender
LL.
Section 1-1

Fig. 67. Repair system.

in the center web after injecting the upper layer of reinforcement and lon-
cracks. Two series of Dywidag vertical gitudinal tendon ducts were exposed.
prestress tendons were utilized to ac- 4. Since at some locations the longi-
complish the retrofit in the following tudinal cantilever tendons in the top
operations:4 flange terminate, it was possible to bore
1. The overlay and membrane was a 2' in. (56 mm) hole through the web
removed in such a manner as to allow to within 10 in. (250 mm) of the bottom
restoration. of the box. At this point a gamma ray
2. The theoretical location of vertical source was placed in the hole and at the
tendons was marked with chalk on the same time a sensitive plate was placed
concrete. underneath the box. If the exposure in-
3. Anchorage pockets were chipped dicated that there was no interfering
out with a lightweight pneumatic ham- longitudinal bottom flange tendon, the
mer; this had to he accomplished very drilling was continued and a 1 1/4 in. (32
carefully because in the process the mm) diameter vertical Dywidag bar

PCI JOURNAL^March-April 1985 133


tendon was placed (Fig, 70a). Where ceptible to deicing chemicals.
there was interference from either a 2. Because of anchorage slip and or
longitudinal top or bottom tendon, the anchor set losses associated with short
single tendon was replaced by two I in. tendons, it is difficult to obtain a theoret-
(26.5 mm) diameter Dywidag bars on ical prestress force.
either side of the web (Fig. 70b). 3. Boring is always a sensitive opera-
Placement of retrofit shear tendons as tion and often impossible, especially
indicated above is very satisfactory in when boring the full depth of the web.
theoretical terms but has the following In the case depicted by Fig. 70b, the
disadvantages:'27 boring problem is significantly mini-
In the case depicted by Fig. 70a: mized; however, the problem of anchor-
1. An anchorage is located near the age location with respect to the roadway
roadway surface and therefore is sus- surface and losses in short tendons are

Fig. 68. Counteracting external loading.

thickened flange or rib


^^ L

-w--

roug ened surface

thickened flange_...,rib

Section 1-1

Fig. 69. Repair system.

134
(a) SINGLE TENDON (b) DUAL TENDON

Fig. 70. Retrofit shear tendons.

retained and the following additional weakening of the top and bottom flanges
disadvantages are introduced: by the 2 in. (51 mm) diameter holes re-
I. Punching shear through the quired, the tendons were staggered in a
flanges. vertical and inclined orientation as
2. Secondary bending stresses in the shown in Fig. 7Ia. The shearing force
flanges and webs. The bending in the produced at the interface of the existing
webs is particularly true of thin webs web and the web thickening is largely
and where an external web is con- resisted by bond. To prevent shearing at
cerned, where vertical tendons would the interface, mechanical doweling was
only be located at the inside of the box. provided by % in. (16 mm) diameter
The retrofit measures used for the re- bolts drilled into the web which sup-
pairs of cracked webs for a structure in ported a grid of conventional reinforce-
Canada" utilized a similar technique for ment (Fig. 71b).
the vertical internal webs as described
above. However, the inclined exterior
webs were more difficult to retrofit DESIGN/CONSTRUCTION
since no bar tendons could be used at RECOMMENDATIONS
the outside face of the web.
Boring through the external web was In the previous sections the author
impossible because of the two side-by- has attempted to delineate the causes of
side upper longitudinal tendons (Fig. cracking in post-tensioned concrete
71a). Preliminary calculations indicated bridges. To minimize the occurrence of
that placing tendons along the inside cracking during construction, or at some
face of the web only would produce un- future time in the life of the structure,
desirable large tensile stresses in the the designer should re-evaluate the fol-
outside surface of the web. Therefore, a lowing major considerations upon con-
decision was made to thicken the out- clusion of the design:
side webs as shown in Fig. 71a. 1. Has the effect of tendon curvature
To produce the required prestress in been accommodated?
the thickened web, tendons had to be (a) Horizontal pullout.
spaced at 71/2 in. (19(1 mm). To preclude (I)) Vertical curvature of soffit ten-

PCI JOURNALIMarch-April 1985 135


bar tendon axis

web thickening
epoxy
Injected
crack +^5 re-bar
tendons

caulking
material

(a)

web
2"x4"x 1" steel plate
washer
5/8" bolt

horizontal bar
.
\ 2-#5 re-bar
welded to plates

welds anchor
for bolts

view A-A

(b)

Fig. 71. Retrofit of inclined external web.

dons. sions been made in design for future


(c) Curvature near anchorage jacking in the event of bearing replace-
zones in thin webs. ment?
(d) Diaphragm cracking and deck 4. Have thermal stresses and thermal
lamination over diaphragms. gradients been addressed?
(e) Adequate spacing between 5. Are there locations in the structure
horizontally curved ducts to where large variations of prestress ec-
prevent crushing. centricity occur and have critical sec-
2. Have blisters or embedded dead tions to either side of these locations
end anchorages been designed to ade- been checked?
quately accommodate stresses at these 6. Has the transverse design of the
locations? section taken into account the true flex-
3. Have stresses at bearings been ibility of the cross section (shear distri-
adequately addressed and have provi- bution in rnulticell girders)?

136
It is recommended that provisions for 3. Verify that adequate spacing is
future prestressing (say 10 percent of the provided between ducts at points of
design longitudinal prestress force) be horizontal curvature to prevent crushing
provided for in the initial design. Pro- of ducts, i.e., spread the ducts as much
viding anchorage bearing plates and as possible.E"
trumpets in the diaphragms and inter- 4. Be aware of and check construction
mediate deviation saddles for future loads to preclude overstressing and
placement of external tendons is a very cracking i.e., stock piling of material on
minor cost during initial construction. the deck.
To provide this capability after initial 5. Immediately bring to the attention
construction can he a very expensive of the Engineer any interferences be-
and difficult task. tween ducts or ducts and reinforcement
During construction a number of sim- and carefully evaluate the consequences
ple precautions can preclude costly time of duct relocation or cutting or rein-
delays and repairs. forcement
1. Use of stiff pipe mandrels and wo , 'c 6. Careful adherence to and moni-
bridges to preclude displacement or o:f- toring of concrete curing methods.
setting of tendons from segment to seg- Avoid temperature gradients between
ment during fabrication or casting. segments during match-casting opera-
2. Verify that ducts are not being tions. Avoid accelerated curing."
"kinked" at tendon curvature locations. 7. Minimize or eliminate any warping
Use prebent heavy gauge ducts or steel or distor -ion of segments during stor-
tubes when curving of tendons is neces- age when the concrete is still at an early
sary. age.

CONCLUDING REMARKS

An attempt has been made in this itive and negative experiences. How-
paper to document the current state-of- ever, there exists in our society a can-
knowledge with regard to reasons for toes attitude toward dealing with unfa-
cracking in post-tensioned concrete box vorable developments, errors, and dam-
girder bridges. However, the reasons for ages which inhibits technological prog-
cracking are so varied, complex and in- ress. Unfortunately, when a problem oc-
teractive that it is impossible to present curs the initial reaction is to seek out the
a document that is all inclusive and au- guilty. This then leads to the situation
thoritative. As with any type of con- whereby, under direction from the legal
struction with any material, problems profession, all parties concerned are ad-
arise that require the attention of not vised not to discuss the problem be-
only the designer, but contractors and cause of potential liability and litigation.
subcontractors as well. No matter how This is to some extent understandable
good the design, if the structure is not since none of the parties involved desire
properly constructed, there will be to jepoardize their rights or to incrimi-
problems. Conversely, no matter how nate themselves. The disadvantage is
dilligent the contractor, if the design that it may take years before the case is
details are poor, problems will result. resolved in the courts and in the mean-
Obviously, if both the design and the time the public safety at large may be
construction are poor, problems are jeopardized because the same errors or
compounded. problems are perpetuated in possibly
Technological progress is only of hundreds of additional projects. This
value if it is measured against both pos- impasse requires resolution and cooper-

PCI JOURNAIJMarch-April 1985 137


ation from both the legal and engineer- Education by dissemination of informa-
ing professions. tion is the only viable methodology
The only way our technology can ad- available to minimize the recurrence of
vance is if problems are openly and the problem. If this is not done, we run
frankly discussed, resolved and infor- the risk of losing credibility with deci-
mation disseminated to the profession. sion makers and society in general.

ACKNOWLEDGMENTS
The data presented in this paper has Professor T. Y. Lin, T. Y. Lin Interna-
been gathered from personal experience tional; Mr. Robert C. Cassano, Califor-
and from numerous and varied nia Department of Transportation; and
documented sources. Much of the mate- Mr. Clarence R. Yamamoto, Hawaii De-
rial presented is not original. Although partrnent of Transportation, for material
acknowledgment of all the many sources presented on the "Pullout of Horizon-
is not possible, full credit is given wher- tally Curved Tendons." In addition, the
ever the specific source can be identi- assistance of Professor Ben C. Lerwick,
fied. Jr. in obtaining several FIP documents
The author is particularly indebted to is appreciated.

REFERENCES
1. Technical Instructions for the Inspection 7. National Association of Australian State
and Maintenance of Highway Structures, Road Authorities, NAASRA Bridge De-
Interim Document 32, Sub-document 2, sign Specifications, 5th Edition, 1976,
"Box Girder or Ribbed Panel Bridges, 8. American Association of State Highway
and Similar Prestressed Concrete Struc- and Transportation Officials, "Standard
tures," Department of Highways and Specifications for Highway Bridges,"
Highway Traffic, Ministry of Transpor- 13th Edition, 1983.
tation (France), October 19, 1979. 9. Ontario Ministry of Transportation and
2. Bouvy, J. J . , and Foxier, J., "Problems Communication, "Ontario Highway
Encountered in Segmental Bridges In- Bridge Design Code and Commentary,"
fluencing Precast Segmental Construc- 1979.
tion," FIP Proceedings, V. 3, 1982. 10. Priestley, M. J. N., and Buckle, 1. C.,
3. Podolny, W., Jr., and Muller, J. M., Con- "Ambient Thermal Response of Con-
struction and Design of Prestressed crete Bridges, Bulletin 42, Road Re-
Concrete Segmental Bridges, John Wiley & search Unit, National Roads Board,
Sons, New York, N.Y., 1982. Wellington, New Zealand, 1979.
4. Moreau, P., and Virlogeux, M., "Lessons 11. Priestley, M. J. N., "Design of Concrete
From a Shear-Cracked Bridge," Elev- Bridges for Temperature Gradients,"
enth Congress of the International Asso- ACI Journal, V. 75, No. 5, May 1978.
ciation for Bridge and Structural Engi- 12. Leonhardt, F., "Prevention of Damages
neering, Vienna, September 1-5, 1980. in Bridges," FIP Proceedings, V. 1, 1982,
5. Leonhardt, F., and Lippoth, W., "Les- 13. Leonhardt, F., Kolbe, C., and Peter, J.,
sons From Damage to Prestressed Con- "Temperature Differences Endanger
crete Bridges," Beton- und Stahlbeton- Prestressed Concrete Bridges," Beton-
bau (Berlin), No- 10, October 1970. und Stahlbetonbau (Berlin), No. 7, July
6. Leonhardt, F., Koch, R., and Rostasy, 1965.
F. S., "Suspension Reinforcement for 14. New Zealand Ministry of Works and De-
Indirect Loading of Prestressed Con- velopment, "Highway Bridge Design
crete Beams: Test Report and Recom- Brief," CDP 701/D, Civil Division Pub-
mendations," Beton- and Stahlbeton- lication, Wellington, New Zealand,
bau (Berlin), No. 10, October 1971. September 1978_

138
15. British Standard BS 5400, Steel, Con- 22. Stone, W. C., and Breen, J. E-, "Behavior
crete and Composite Bridges, Part 1 of Post-Tensioned Girder Anchorage
General Statement, 1978. Zones," PCI JOURNAL, V. 29, No. 1.,
16. Precast Segmental Box Girder Manual, January-February 1984, pp. 64-109.
Published jointly by the Prestressed 23. Stone, W. C., and Breen, J. E., "Design
Concrete Institute and Post-Tensioning of Post-Tensioned Girder Anchorage
Institute, 1978. Zones," PCI JOURNAL, V. 29, No. 2,
17. Hejnic, Jiri, "Effects of Temperature March-April 1984, pp. 28-61.
Changes on Prestressed Concrete 24. Gerwick, Ben C., Jr., "Causes and Pre-
Bridge," Presented at FIP Seventh Con- vention of Problems in Large-Scale Pre-
gress, New York, May 26June 1, 1974. stressed Construction," PCI JOURNAL,
18. "Proposed Recommendations for Seg- V. 27, No. 3, May-June 1982, pp. 58-75.
mental Construction in Prestressed Con- 25. Harwood, Allan C., "1-205 Columbia
crete," FIP CommissionPrefabrica- River BridgeDesign and Construction
tion, 3rd Draft, September 1977. Highlights," PCI JOURNAL, V. 27, No.
19. Stone, W. C., and Breen, J. E., "Analysis 2, March-April 1982, pp. 56-77.
of Post-Tensioned Girder Anchorage 26, ACI Committee 318, "Building Code Re-
Zones," Research Report 208-1, Center quirements for Reinforced Concrete (ACI
for Transportation Research, The Uni- 318-83)," American Concrete Institute,
versity of Texas at Austin, August 1980. Detroit, Michigan, 1983.
20. Stone, W. C., Paes-Filho, W., and Breen, 27. Lecroq, P., and Poineau, D., "Rein-
J. E., "Behavior of Post-Tensioned forcement of Bridges by Prestressing,"
Girder Anchorage Zones," Research Re- Eleventh Congress of the International
port 208-2, Center for Transportation Re- Association for Bridge and Structural
search, The University of Texas at Aus- Engineering, Vienna, September 1-5,
tin, August 1980. 1980.
21. Stone, W. C., and Breen, J, E., "Design 28. Dilger, W. H., and Ghali, A., "Remedial
of Post-Tensioned Girder Anchorage Measures for Cracked Webs of Pre-
Zones," Research Report 208-3F, Center stressed Concrete Bridges," PCI JOUR-
for Transportation Research, The Uni- NAL, V. 19, No. 4, July-August 1974, pp.
versity of Texas at Austin, June 1981. 76-85.

NOTE: Discussion of this paper is invited. Please submit


your comments to PCI Headquarters by November 1, 1985.
PCI JOURNALiMarch-April 1985 139

Вам также может понравиться