Академический Документы
Профессиональный Документы
Культура Документы
Post-Tensioned Concrete
Box Girder Bridges and
Retrofit Procedures
O
n the premise that "Those who ig- these factors.
nore history will be condemned to Cracking in post-tensioned concrete
relive it," this paper attempts to docu- box girders generally results, in a broad
ment those types of problems that lead sense, for the following reasons: inade-
to cracking in post-tensioned concrete quate flexural and shear capacity, non-
box girder bridges and have been en- consideration of thermal stresses, insuf-
countered in both Europe and the ficient attention to stresses developed
United States. by curvature of tendons, improper or in-
These problems are not limited to appropriate construction techniques,
those of prestressed box girder bridges, lack of quality workmanship to meet the
but may occur in other types of struc- tolerances necessary for problem free
tures with similar conditions and de- structures, and understrength materials.
tails. Problems are generally attributed It should also be noted that cracks are
to poor quality control, inadequate de- not totally avoidable in post-tensioned
sign details, inferior workmanship, or concrete box girder bridges, since not all
lack of understanding as to how the portions of the structure are precom-
structure will behave, either through ig- pressed in three directions and local
norance or because a particular concrete shrinkage is not always con-
phenomenon is unknown to the current trollable. Certain cracks may not be
state-of-the-art, or a combination of all structurally serious, while others are. It
82
is, therefore, important for the structural
engineer to determine the structural
Synopsis
significance of a crack and its effect on
the serviceability of the structure. The appearance of distress in
In general, in today's technology it is the form of cracking in any con-
very rare that the triggering mechanism crete structure is one of concern
can be traced to a single source, Each of and consternation to all parties in-
the sources cited above, when taken in- volved. It is evidence of an unf a-
dividually, usually produce stresses or vorable stress condition and if seri-
cverstresses that are minor and within ous enough could affect the struc-
allowable limits. However, if one or a ture's integrity. Cracking may occur
number of the sources is ignored or in- for a number of reasons but usually
advertently overlooked, a superposition is the result of the interaction of
of stress can occur such that the capacity several causative factors. These
cf the concrete is exceeded and the only factors taken individually may be
relief the structure has from this over- minor but when superimposed can
stress is to crack. result in distress.
Therefore, it can be seen that it is very This paper presents documenta-
difficult to diagnose a specific triggering tion of problems that have led to
mechanism. It generally requires an cracking in post-tensioned con-
extensive investigative effort, usually by crete box girder bridges in Europe
a. process of elimination, to determine a as well as in the United States. 1t
single or small group of probable causa- discusses cracking resulting from
tive factors. inadequate flexural and shear
When serious and/or extensive capacity, thermal stress cracking,
cracking distress occurs in a project, and cracking resulting from tendon
there may he a concern for the integrity curvature and tendon misalign-
of the structure. This usually results in ment. Also discussed are possible
delay of the project, investigation, ret- retrofit measures.
rofit measures, determination of liabil- The intent of this paper is to
ity and legal involvements, which be- bring these problems to the atten-
comes costly in terms of both time and tion of the engineering and con-
money. It is hoped that the data pre- struction professions with the hope
sented in this paper will help to dissipate of precluding their recurrence.
the occurrence of these problems to the
benefit of both the engineering and con-
struction professions.
inflection
points
MOMENT DIAGRAM
+M
Flexural cracks can he small (mi- quate flexural capacity, cracking behind
crocracks) and the structure may appear anchorage blisters or a combination of
to be intact. However, the width of these both.
flexural cracks can vary and become Causes of inadequate flexural capacity
quite large, 1 to % in. (3 to 10 mm), are varied in origin and it is seldom that
under the effects of external loading, a single cause will produce significant
such as dynamic traffic load or thermal cracking. More generally, there are a
gradient. number of causes which by themselves
In areas near the support the effect of are insignificant, but when acting in
shear will be superimposed upon the concert with other causes produce sub-
flexural stresses producing, after initial sequent cracking.
vertical cracking, cracks that are in- The more prevalent causes are as fol-
clined and become more and more diag- lows:
onal in the webs, which may indicate
insufficient shear strength (Fig. 3).
(a) During Design
This type of cracking will be accom-
panied by deformation in the structure, 1. Inadequate consideration of, or un-
visible and measurable deflection. derestimation of, stresses resulting from
Cracks of this type pose a risk to the moment redistribution,
reinforcement, prestress or conven- 2. Underestimation of thermal stresses
tional, that traverse the crack from corro- (expansion or contraction),
sion or from fatigue damage under large 3. Lack of consideration of, or under-
and frequent stress variation. estimation of, thermal gradient.
Considerable care must be exercised 4. Overestimation of initial prestress
in diagnosing the cause of cracks in this resulting from optimistic coefficients of
pattern. Inadequate flexural capacity friction and wobble.
may or may not necessarily be the 5. Underestimating relaxation loss in
causative factor. Excess tension and prestressing.
subsequent cracking behind blister an- 6. Selection of a tendon profile
chorages can produce similar cracking whereby a large variation of prestress
(this effect will be discussed in a sub- eccentricity occurs (Fig. 4), and not
sequent section). Therefore, cracking of checking the stresses at critical loca-
this type may have its origin in inade- tions.n
84
Fig. 2. Flexural cracks.
combined
vertical bending-shear
bending Cracks
cracks near support
f '
continuity tendons
cantilever tendons
joint(i) joint(i*I)
sections at right sections at right
and left checked and left chocked
unchecked zone
where cracking
develops
la!
faulting
(b)
86
draped cantilever tendons
t fX
longitudinal
stresses
intermediate diaphragm
PARTIAL ELEVATION
cipal compressive stresses in the bottom vertically curved tendons in the bottom
flange (usually called the Resat effect flange. Vertical prestress was applied in
after the engineer who first studied the webs to control shear stresses. Diag-
members of variable depth) equals onal cracking was observed in the center
ff tB tany. web, only near the intermediate dia-
Thus: phragms, with a maximum crack opening
of 0.02 in. (0.6 mm). In addition there
Vo V YEP sin a+IPsing f. tB tan y
was cracking in the bottom flange,
A complete investigation of the prob-
Cracking Produced by Incorrect lems encountered revealed that crack-
ing was the result of the superposition of
Distribution of Forces
several adverse effects, any of which
This example 3.4 is one of a two-cell, might have been harmless if considered
variable depth, box girder bridge con- separately:
structed by the balanced cantilever 1. The computation of shear stresses
method and consisting of five spans of failed to take into account the adverse
210, 370, 370, 390, and 230 ft (64, 113, effect (usually neglected) of the vertical
113, 119, and 70 m). External webs are component of continuity prestress in the
13 in. (340 mm) thick and the center web bottom flange of a girder with variable
is 12 in. (300 mm) thick. Because the depth. The curvature of continuity ten-
bridge was subsequently intended to dons distributed in the bottom flange is
carry monorail pylons, two intermediate such that a downward reaction is pro-
diaphragms were provided at the third duced at the webs that is additive to the
points of each span, as indicated in Fig. shear in the web (see above).
7. 2. The distribution of shear stresses
Longitudinal prestress was applied by was made under the conventional
straight tendons in the top flange and structural analysis assumption that the
88
(a) conventional assumption
of transverse rigidity
cross section was rigid and transversely with short bar tendons and even if
undeformable (Fig. 8a). However, de- equipped with a fine thread they are not
pending upon the stiffness of compo- completely reliable unless special pre-
nent parts of the cross section this as- cautions are taken under close supervi-
sumption may be erroneous (Fig. 8b). sion. Even a small anchor set signifi-
Conventional analysis, assuming a rigid cantly reduces the prestress force, and it
undeformable cross section, assumes is not unlikely that the actual prestress
that a centered loading is evenly dis- force is only three-fourths or even
tributed among the webs. In fact, a two-thirds of the theoretical prestress.
center loading induces a transverse de-
formation in the top and bottom flanges Cracking as a Result of Indirect
with a displacement of the center web
larger than that of the external webs. Support
Fig. 9 indicates influence lines for shear The ideal position of bearings at a pier
in the center web and the external web. is directly tinder the webs of a box gir-
The transverse behavior appears very der. The shear from the web is trans-
different from that of a transversely un- ferred directly from the web to the
deformable section and may produce bearings, and there is need only for a
cracking in the bottom flange as indi- simple inside diaphragm designed to
cated in Fig. 10. For any particular cross transfer the shear stress, due to possible
section, a more rigorous analysis is indi- torsion moments, to the substructure.
cated than that usually conducted. However, to avoid spalling the bottom
3. The vertical web prestress was par- outside comer of the soffit, the edge of
tially lost into the intermediate dia- the bearing should be a minimum of 2
phragms, and the actual vertical compres- in. (50 mm) clear of the corner. If a
sive stress was lower than assumed. chamfer exists at the corner, the clear
4. Vertical prestress is usually applied distance should he measured from the
90
web
distribution of
shear stress
in web
I R \v
1 I )
( V ^ (b)
I
(c) (d)
hatched area of the intersection zone perature rise and fall of a concrete
(Fig. 12d), such that 70 percent of it is structure about an assumed temperature
located in the web.' It should he the full at time of construction is as follows:
depth of the girder and adequately an-
chored. Temperature
In many instances, provisions are
made (or should be made) for future Type of climate Rise Fall
jacking up of the superstructure in the Moderate climate 30F 40F
event the bearings require replacement. (16.7C) (22.2C)
The design drawings should indicate Cold climate 35F 45F
the intended position of the jacks and (19.4C) (25.0C)
the consequences of this temporary re-
positioning of reactions should be ac- The thermal coefficient for normal
commodated in the design. weight concrete is taken as 6 x I0- 11 per
deg F (10.8 x 101 per deg C). Thus, by
using the equation:
THERMAL STRESS
CRACKING e=aIAt (1)
@ webs
girder depth
support
reaction 2V it
(a) CROSS SECTION d
`4 t
aphrag g e
compressi(
tension
(b) CRACK PATTERN
web
d/2 T whichever
produces
the largest area
L
(d) PLAN OF DIAPHRAGM/ WEB REGION
92
ambient temperature sun
---`-wind speed A.
re-radiation doorio ^/ asphalt
} } 7 qi
\]/
cate:iai
properties
ambient temperature
94
T
T- 32-0.2d*C
v .Drat
d=capful thickness (mm)
1.5 C
Tt Tt
hi hi
T2 72
__I
h
h2
h1.0.3hz6 0.15 m
h2.0.3h 8 0.10 m h1 4 02h0.25 m
- u1
h2
h 2 `h3 -0.25h^0 .2 m h
50.25 m
h '. 0.3h^ (0.1 mtsurlacinp h3
depth In meters) T3
(tor thin slabs. h 3 hmlled
1e
h4
13 by h-hl-h27 T4
h T1 T2 T h T T2 T T
Ill oC m
(b) ENGLAND zz 0.2 e.5 3.5 05 0.2 2.0 0.5 0.5 1.5
0.4 12.0 3.0 1.5 4.5 1.4 1.0 3.5
0.6 13.0 3.0 2.0
0.4
0.6 6.5 1,8 1.5 5.0
ar 0.8 13.6 3.0 2.5 0.8 7.6 1.7 1.5 6.0
1.0 8.0 1.5 1.3 6.3
(deck warming) 1.5 6.4 0.5 1.0 6.5
(deck cooling)
10G ar Soc
^ ^Il
24 C
n_
c
0
goC
h
E 'y-
oa
250
i
C2/h0=0.60
h1 h1 T" 18F f
^' r0LEi f2
ELEVATION OF SPAN SECTION AT CENTER
Lion of the type and amount of cement, the bottom thin flange will cool faster
thickness of concrete members and and attempt to shrink at a faster rate than
temperature of aggregate, mixing water the webs and is therefore being re-
and surrounding atmosphere. As a result strained. To relieve tensile strains, pro-
of heat of hydration and shrinkage, duced by restraint of the webs, the thin
especially between thick and thin por- bottom flange has no other alternative
tions of a cross section, large residual but to crack (Fig. 17a). In a transverse
stresses can be produced which exceed section, large differences in thickness
the tensile strength of"green" concrete. can produce restraining moments which
Thin parts of the cross section will can produce horizontal cracks in the
cool faster than adjoining thick parts webs (Fig. 17b).
producing residual tensile stress and A similar thermal stress (strain) in-
cracking, There is always a potential of duced cracking can occur in staged con-
cracking when a thin member is at- struction whereby the cross section is
tached to a relatively larger member. constructed in two or more pours re-
The thinner member will always he quiring construction joints. When fresh
subjected to a faster rate of temperature young concrete is placed against hard-
change (cooling), larger creep and ened older concrete there is a danger of
shrinkage than the larger member and cracking. Initially, the fresh concrete
thus the thinner member will crack,112 will have an increase in temperature re-
In box girders with thick webs rela- sulting from heat of hydration, then
tive to the thickness of the bottom flange, when cooling occurs the new concrete is
96
crack
crack
b!2
/ n
N
cracks
Plan
top flange
3rd stage casting
web
2nd stage casting
forms still in place
bottom flange
1st stage casting ELEVATION
SECTION
(a) ELEVATION
cons,
98
7 1 I (a) STAGE 1
y 5
1 1
20
0 1 1^
10
20 30
^.
10
20 - 15
30 25
point
35 (b) STAGE 2
10
30 ----------
25 ..
2015
point "c"
10 20 1 30 20
30_ipoint "b"
40 - 50
i0'/\
20
0 ,.
(c) STAGE 3
-7.5
-10
all values are in 0C
on the surface of the deck, is ap- casting Stage 3 as 32.2C for a vertical
proximately 20C and the temperature in distance of 28,7 in. (730 mm) between
the bottom portion of the web and the the two points.
bottom flange is below 0C. Time-temperature distribution along
The temperature distribution with the centerline of the web in the lon-
time for Points "b" and "c" with respect gitudinal direction is shown in Fig. 22.
to placing Stage 3 is shown in Fig. 21. The heavy dashed line indicates the
These curves indicate, as would be ex- joint between the previously cast Seg-
pected, a heat dissipation at the surface ments A and B. The curves show, be-
(Point "c") as compared with the heat tween the points ofO.5to1.2rn(1.6to4ft)
dissipation at an internal position (Point from the end of the segment, the influ-
"h"). A comparison of the two curves in- ence of the locally effective hot air
dicates a maximum gradient between heating of the segment and also its poor
Points "b" and "c" at 15 hours after heat distribution.
40
These curves are also noticeably in- of contiguous members and proper cur-
fluenced by the low temperature of the ing procedures.12
previously cast Segment A and the cool There are basically two methods of
ambient temperature. The maximum heat curing concrete: (1) preheating the
temperature gradient decreases gradu- fresh concrete before placement in the
ally after the first few hours of hydration forms and (2) heat curing the concrete
heat development. This gradual de- after consolidation in the forms.'
crease in gradient is due initially to the In the first case the concrete is pre-
heating up of the adjacent segment and heated to about 85 to 90F (30 to 35C).
later on to decrease in heat of hydration This operation is achieved in several
and cooling of the web of the segment. ways:
Thin members cool at a faster rate 1. Steam heating the aggregates a
than thicker members which, therefore, simple solution that presents the disad-
create considerable tensile stress. When vantage of changing the aggregate water
fresh concrete is cast against old con- content.
crete there is a potential for cracking in 2. Heating the water a solution that
the younger concrete which, when sub- has limited efficiency, because of the
sequent cooling occurs, is hampered small proportion of water in comparison
from shortening by the older concrete. with the other components (water at
This usually occurs during the first few 140F raises the concrete temperature
cool evenings when the strength of con- by approximately 20F).
crete is low and low tensile stresses can 3. Direct heating of the concrete mix
cause cracking. At this point, because by injecting steam into the mixer itself
bond is not sufficiently developed, the best solution and the one most
reinforcement cannot prevent opening easily controlled.
of the cracks. Restraint forces due to To avoid heat loss, the forms are gen-
temperature differences must be erally insulated and some source of
minimized to the extent possible by radiant heat is installed inside the seg-
avoiding large differences in thickness ment.
ie
segment A segment B
T C
60
joint
50 l time in hours
from placing
40 of concrete
24
30 --12
49
20 67
10 91
115
0
0.5 1.0 20 m
I
external
heating
In the second case, the concrete is these cracks, which can cause a devia-
heated in its form inside a thermal con- tion of the isostatic lines of compression
tainer in which low pressure steam is toward the uncracked zones, altering the
circulated. The heat curing cycle should prestressing distribution in the section
include (Fig. 23):3 under consideration resulting in insuffi-
1. An initial curing period of 2 or 3 cient bearing strength.
hours, during which the concrete is kept To avoid this situation the members
at the ambient temperature. being joined must be rigidly held in po-
2. An increase in temperature at a low sition. Normally, in cast-in-place bal-
rate of less than 36F (20C) per hour. anced cantilever construction a form
3. A period, depending on the con- traveler is used to clamp the two can-
crete strength to be achieved, during tilever tips rigidly in place. For precast
which the temperature is held constant segments or for longitudinal closure
and below 150F (65C). pours between flange tips an external
4. A period during which the concrete rigid clamping device must he
is cooled at a rate similar to that used for employed (strongbacks). In addition,
the temperature increase. proper curing procedures must be
A similar form of cracking occurs at a employed to control shrinkage stresses.
closure pour either at midspan in bal- Another difficulty during curing is
anced cantilever construction or lon- that resulting from large temperature
gitudinal closure pours between the tips differences between the curing envi-
of adjacent box girder flanges (Fig. 24).' ronment of the segment being cast and
As the closure pour concrete hardens, the outside environment of the cast-
the units being connected may undergo against segment (Fig. 25). If a tempera-
deformations (solar heat) as discussed ture gradient exists across the east-
previously or by transient moving con- against segment, its shape will change.
struction loads and/or as a result of The segment will return to its original
thermal shrinking as discussed previ- shape when the temperature gradient
ously. The prestressing may not close falls back to zero,
uj z rt
212 W 0Gr1
cca ^o^^ZG max. temp. <150F(65C)
^ G3
65 FORM STRIPPING
65
time in hours
2 to 3hI
ut
zp F
w : -J
~)W << 0
?Ud aw Z 0
w w
2i OM
w w
I
cracks
detachments
PLAN
closure pour
flange movements
SECTION
closure segment
movements
102
-il" fit` ft1fr
<h "
segment conjugate
tr t
end form
gradient in
conjugat
y
curingAT F
tempera re
1f
` ambient
y' ' temperature
%"^^' mot'
en t
L
This will result in match cast surfaces dients being set up which could lead to
that are not necessarily parallel full horizontal curvature of segments and
length. This condition is evidenced in consequent lack of matching in the
the top slab joints; the joints will be structure. This effect is particularly sig-
tight at the curbs and a small gap may nificant for segments with high width to
be noticed at the center. The problem length ratios (in excess of 6).2 3
becomes cumulative if this condition
exists for subsequent castings. With the
tremendous prestressing force, the seg- CRACKING AT OR NEAR
ments develop longitudinal cracks as ANCHORAGES
the segments are seated against each
other. Certain anchorage positions, such as
This also results in an unaccounted an anchorage blister on a thin flange as
variable when evaluating the bridge shown in Fig. 26, should be avoided.
camber. For match-cast segments, it is Wherever possible, anchorage blisters
important to enclose both the cast for continuity tendons should be placed
against segment and the segment being in a fillet between the web and flange
cast in an isothermal enclosure. This where the transverse section has the
will prevent longitudinal thermal gra- largest rigidity. If this type of detail can-
segment joint
web
anchorage >tendons
blister
-i
cracks vweb
cracking
in joint,
iF J anchorage
'blister web
segmen
tendons
-web
joints
104
not be avoided, then particular attention capacity of the webs will he reduced
must he paid in design and construction and failure of the structure may he im-
to the zone concerned.3.L8 minent.2 It should be noted that this
Cracking will originate in the bottom type of cracking is not symptomatic with
flange behind continuity anchorage anchorage blisters; the same cracking
blisters and propagate forward toward pattern has been observed with anchor-
the webs, along a line forming a 30 to 45 ages embedded in the flange, i.e., no
deg angle with the longitudinal axis of blisters.
the girder (Fig. 27). If the rear face of the It is possible that this type of cracking
blister is located in close proximity to a from continuity tendon anchorages
segment joint, cracking may develop in in the bottom flange may join with simi-
the joint (Fig. 28). In some situations the lar cracks originating from cantilever
diagonal or herringbone cracks in the tendon anchorages in the top flange
bottom flange continue to propagate to (Fig. 30). In this situation, the center
the webs forming a 30 to 45 deg angle portion of the span may become an in-
with a horizontal axis (Fig. 29)..2 verse "key-stone" (Fig. 31) and im-
If the crack reaches a segment joint ,n mediate measures are required to pre-
the web it may cross the joint, but usu- vent collapse of the structure.'
ally travels vertically up the joint to a This situation occurred in a box girder
point below the top flange where it may constructed by incremental launching'
continue vertically in the joint, resume a (Fig. 32..). Permanent prestress was
diagonal path in the web proper, or achieves. by straight tendons placed in
cease to propagate. Obviously, the shear the top and bottom flanges, as required
so^
top tendon
ack
flanne cranks
106
initial load 1
490 k/tendon iq no vertical prestress in this zone top tendon pier
141a 1 1 i 4
bottom J
tendon '
PARTIAL LONGITUDINAL SECTION
diagonal tension
due to prestress
distribution in web
II ,
diagonal crack II ,
I
TRUSS ANALOGY
SECTION A-A
33). 1,2 Among the parameters that can tendon forces. In a recent failure of this
produce this type of cracking are the type, after epoxy injection of the cracks,
following:' additional external post-tensioning was
1. Termination of numerous con- provided to close-up and induce com-
tinuity tendons in a single section, par- pression in open segment joints and
ticularly when the joint behind the an- cracks.
chorages is not compressed by other
tendons and when passive longitudinal
reinforcement does not traverse the CRACKS RESULTING FROM
joints between segments or is inade- VERTICAL CURVATURE OF
quate. SOFFIT TENDONS
2. Insufficient horizontal offset be-
tween tendon anchorages in the top and This type of distress is associated with
bottom flanges (Fig. 30). variable depth girders and occurs in the
If this type of cracking andlor failure is positive moment area. It is manifested
to be inhibited, the design, detailing, by longitudinal cracks occurring in the
and placement of reinforcement in these bottom flange, at the juncture of the
highly stressed zones must be carefully bottom flange and web, and possibly in
considered. Location of blisters must be the web (Fig. 34).'
considered and there must he sufficient Tendons for continuity or positive
longitudinal reinforcement behind the moment prestress may not, or even
blister or anchorage and sufficient should not, always be located in the fil-
transverse reinforcement abreast of the let between web and bottom flange.
anchorage to accommodate the initial They may be located in the bottom
108
possible web cracks
C
n 0
corner crack
1 0 t 1 0) Q / 0 Oj 0
f4^;E 1i i.^.
PARTIAL CROSS-SECTION
/ ^^r Pt
Lam;
r^
14 1
23'
Abt. 1
Pier 2 tI
N11
1- L --_- JL -. -
pulled out tendons
Partial Plan
location of failures
section
112
original curved tendon path
sharp
angle
change pulled out portion
tension } 1 { { r tension
large radial / l
tearing force L/
distributed
radial
force
had caused the concrete to fail, allowing After that, most of the tendons were re-
the tendons to straighten out and pull leased except two tendons along the
away from the webs (Fig. 40). The fail- north web and one tendon along the
ure was particularly evident in the inner center web which were not released.
(north) web, where the tendons had It should be pointed out that a review
pulled well clear of the concrete. In the of the construction documents and the
outer (south) web the failure (inside the construction method for both structure;
box) had not progressed past the first revealed no serious discrepancies be-
quarter-span diaphragm. The center tween the construction method as com-
web was undamaged. Additional obser- pared to the construction documents
vations indicated that the tendons were and specifications. Further, the
continuing to pull away from the webs, AASHTO Standard Specifications for
and that failure had progressed several Highway Bridges' does not provide
more feet towards the abutment and the guidance for the design of curved
pier (Fig. 41). post-tensioned box girders.
The second example* occurred on an In both these structures, there was a
interchange ramp (Fig. 42). This struc- combination of relatively sharp curva-
ture is a post-tensioned, cast-in-place, ture, thin concrete cover over the ten-
continuous, two-cell concrete box gir- dons and the bundling of a number of
der, constructed essentially on a curve large sized tendons close together.
with a radius of 540 ft (164.6 m). The These failures are somewhat unique in
structure, between expansion hinges, that the problem would not have sur-
experienced concrete spilling and faced in the case of a flatter curvature,
cracking during construction oh the thicker concrete cover over the tendons,
south web of the box along the curve as or adequate spreading of the tendons
indicated in Figs. 43 and 44. into individual ducts as compared to
During the first post-tensioning oper- bundled ducts.
ations, four tendons out of six in each The analysis of the failure of these
web were fully post-tensioned, then structures can be divided into three
noise was heard and cracking and spall- separate actions (Fig. 45) which need to
ing were observed along the south web. he considered in design:
1. The global or overall girder action
`'Kapiolani Interchange On-Ramp Project No.
1-H1-(157):24," Design Review: Interim Report to of the bridge together with its support-
Department of Transportation, State of Hawaii, ing piers and abutments.
T. Y. Lin International, April 1982 (Unpublished). 2. Regional beam action of each web
N
DC
a^
C C I CD
o D Cr
0 ^ li Cal EA ICA
ID
36'IO C
23'
supported at the top and bottom flanges stresses are not a major factor. Thus, it is
as a beam. believed that the global action for both
3. Local slab action of the concrete of these structures had only minor ef-
cover over the tendons. fects on the failures experienced, and
It is important from both the analysis were not quantitatively considered.
and the design viewpoint to look into all Regional action considers each web as
three of these actions and their effect on a beam supported at the top and bottom
both the concrete and the reinforcement flanges. This beam (Fig. 46) is acted
in the webs of the boxes. upon by the radial force from the ten-
One point concerning global action of dons. The radial tendon force produces
the girder is the restraining effect of the shear and bending in the web, as it
piers and the bridge hearings. A curved spans vertically, The bending moment
bridge tends to shrink along certain di- and shear in the web are also influenced
rections, depending on the flexibility of by the fact that the web concrete is
the piers, while the movement of the under longitudinal compression from
bearings maybe restrained to take place tendon prestress.
along a different direction. Thus, sec- This precompression has an arching
ondary moments in the horizontal di- effect which partly counteracts the ra-
rection are produced in the girder of dial force from the tendons, thus reduc-
these two structures. ing the bending moment produced by
It has been determined that such the tendon force. In other words, the
114
yv
LI
4. B! _c1
^
^% J
g. y^^4 111 _
5 11 I,
hairline cracks
large cracks
Spa us
Girder Action
GLOBAL
1
REGIONAL ^ 1
1 LOCAL
Beam Action 1 1
1 1 ^^/
Slab Action
1 1
116
Top Flange /\
ttom Flange
Web Spanning
Vertically
distributed
radial
force
from
arch
radial r action
force
from --
tendons
distributed force
from arch
compression
concentrated force
from tendons
fZ "/Ar ^_ 3.39
hL
O.f7 %T.
_3K o0 o.ra4
a.)1K/sr
a^'yFr 32^Fr
^ r.la9 K i
^3,3gK
-I
IuIuiii!iIflhuuII
-=
9
uiuiiuiiriuiiu
8
IIUI!iUii!!1
6
n
v
3 1
2 4 6 8 1 12 14 16 18 20
118
2 4 6 8 10 12 14 16 18 20
F = j I
R
(kilt per web)
d^
ide of curve
dl
standard detail
120
B "lolls
* 4 'L_^c /35 bend
of each stirrup. Hook around stirrup
^ 24mox. Place duct against le g s AI rernole sides for 135 hook.
C
*4
and hook tie around stirrup leg on Place one above top duct and one
Inside
oufsrds of curve. below bottom duct.
of curve
Prestress
Duct --
Stirrup
Legs---
` P r a
p a
,OOO
pQ I
(a) UNSTRESSED TENDON
O
. P a I. P I
6 ,
.
"$edge"
ne w p (c) FAILURE
122
post - tensioned tendons
in nolvethvlene ducts
P i
(a)
Q a laminar crack
(b)
54. The external tendons pass through In addition, a splitting crack may de-
the diaphragm along a vertically curved velop as a result of multi-strand com-
profile and are anchored in the dia- paction in the zone of curvature as dis-
phragm face which produces a radial cussed above. It appears that the lami-
pressure as indicated in Fig. 55a. As a nar crack either by itself or in conjunc-
result, a tensile stress field is set-up tion with the splitting crack, over a pe-
above the tendons (Fig. 55b) similar to riod of time will propagate to the surface
the tension stress field behind an an- and produce spalling. Spalled areas of
chorage blister. This tension field may the deck have been as large as 3 x 3 ft (1
then cause a laminar crack above the x 1 m). The spalled surface in two proj-
tendons. ects were located generally over the
- ` longitudinal'tendons
cracks
web
124
cracks
(a)
laminar cra k
C_ original
imprint of to on
of tendon
(b) of duct
deformed /
reinforcement
N position
of tendon
after failure
delamination (c)
(d)
cracks
(e)
This problem can be avoided by the problem indicated that during construc-
use of rigid ducts properly positioned tion the longitudinal tendons had been
and securely tied to the reinforcing deflected downward because of an in-
cage, use of a rigid mandrel placed in- terference with the deflected profile of
side of the duct during casting, and pro- the transverse tendons.
viding work bridges for workmen so that The result of the upward components
they do not walk in the wet concrete. of the two curved tendon systems prob-
In a recently reported example 2425 of ably created a laminar crack upon ten-
this type, a 16 x 32 ft (5 x 10 m) area of sioning of the tendons. Air pressure
the upper portion of a deck slab lami- used to blow out the remaining un-
nated and spalled. Investigation of the stressed tendon ducts probably propa-
126
dSa^ Pre5sre
,yn;tosmt ra 1 t ` t ^
..
itt
concentrated force
^} I^nuA
pop_out or Spa
tension failure
1j
ure at that location, tension failure be- sile forces behind the blister, and ade-
hind the blister and shearing along the quate transverse reinforcement should
longitudinal sides of the blister. be used to cater to shear forces along-
To avoid the "kink" in the duct, a side of the blister.
heavier gauge duct or prebent tube The design of blisters requires, in ad-
should be used, tie confining reinforce- dition to reinforcement for anchorage
ment around the tendon should be ex- bursting stresses, adequate reinforce-
tended well forward of the blister, ade- ment for shear and bending between the
quate reinforcement extending from the blister and the flange or web interface.
blister into the flange (or web) behind it Consideration should be given to Sea
should be employed to cater to the ten- tions 11.7 and 11.9 of the ACI Building
128
new distribution beam
ttrcionai external tendons
new backw^
(b) BOSS
clamshell
web 11
deviation block fastening pins
polyethylene tubeI
steel
tube fastening pins steel deflector
bottom flange
(b) STEEL
(a) CONCRETE
structural
c,nnl Frnw.._
bored hole
anchorage
anchorage additional
5 1 external
tendon
existing
diaphragm external
tendons
Fig. 63. Anchorage at diaphragms.
130
deviation buttress 1_ match-line
transverse distribution beam
match-line
deviation buttress /
local stresses (bending, shear, and ten- used, deviation blocks or saddles have
sion in the web behind the boss) which to be provided to achieve the profile.
the existing structure may be incapable These devices can be either concrete or
of accepting. Another disadvantage is steel (Fig. 62). They are attached to the
the very short tendons used to pin the existing web or flange by prestressing
boss to the web. These short tendons are pins.1 ' They are subject to the same
very sensitive to losses and could result difficulties as bosses discussed above.
in the boss sliding which would, of At existing diaphragms the tendons
course, lead to unanticipated losses in can pass through or be anchored (Fig.
the longitudinal tendons. Therefore, 63a) provided they have sufficient
particular attention must be given to strength and are adequately attached to
the:' the girder cross section to transfer the
1. Methodology to be followed to re- resulting longitudinal shear. Depending
duce losses through the improper fas- upon the diaphragm detail it may be
tening of anchorages during tensioning necessary to provide a structural steel
operations. frame to transfer the longitudinal pre-
2. Distribution of the anchoring force stress force (Fig. 63b), With existing
along the entire length of the boss diamond coring technology 3 in. (80
(transfer of prestressing from the boss to mm) diameter holes can be drilled to
the structure). depths of approximately 6.5 to 10 ft (2 to
3. Treatment of the surface of the 3m), with a longitudinal tolerance of s/ie
joint between the anchoring boss and to % in. (5 to 10 mm).
the structure, and the resulting coeffi- A recent application of this system in
cient of friction. the United States (Fig. 64) used the
4. Value of the coefficient of friction transverse distribution member at the
between the fastening mortar and the abutments and a concrete buttress for a
boss, if it is made of steel, and deviation saddle that was keyed and
5. Ratio between the fastening force doweled into the existing flange and
and force created by the anchored ten- web (Fig. 65). Where tendons were an-
dons. chored to existing diaphragms, the dia-
Where a polygonal tendon profile is phragm was locally reinforced by a sim-
B
PARTIAL PLAN
SI
web
flange
SECTION A-A
ilar buttress arrangement (Fig. 66). section in question or at some other lo-
A potential repair method for the type cation in the structure.
of cracking shown in Fig. 34 is illus- Another possible repair method is that
trated in Fig. 67 and consists of sup- indicated in Fig. 69, whereby the flange
porting the bottom flange by a suspen- thickness is increased or transverse ribs
sion system.' If the crack width is less are added to assist in resisting the flex-
than 0.008 in. (0.2 mm), the cracks are ural stresses.' However, some means of
harmless with regard to environmental providing external support to the origi-
effects; if the crack width exceeds this nal bottom flange to resist the added wet
dimension it should be epoxy injected. concrete weight, so as not to aggravate
In some cases the crack width may reach the already overstressed original flange,
% in. (1 mm). In this case consideration must be provided. In addition, or con-
might be given to applying external currently, a method of external loading
forces to the section so as to return it to, is required to return as near as possible
or near to, an undeformed state. the original flange to its undeformed po-
This can be accomplished (in Fig. 67) sition, otherwise the stress condition in
by jacking the suspension rods at the the bottom flange is not alleviated and
deck level producing the external loads the effectiveness of the procedure is
indicated in Fig. 68. However, this questionable.
method or any other method (tried or
untried previously) should not be at- Shear Cracks
tempted without careful evaluation and Repair of shear cracks in the web of
analysis to determine that adverse ef- the structure illustrated in Fig. 7 was ac-
fects are not being introduced at the complished by adding vertical prestress
132
Fig. 66. Retrofit anchorage buttress at diaphragm.
suspension rod
uni.
suspender
LL.
Section 1-1
in the center web after injecting the upper layer of reinforcement and lon-
cracks. Two series of Dywidag vertical gitudinal tendon ducts were exposed.
prestress tendons were utilized to ac- 4. Since at some locations the longi-
complish the retrofit in the following tudinal cantilever tendons in the top
operations:4 flange terminate, it was possible to bore
1. The overlay and membrane was a 2' in. (56 mm) hole through the web
removed in such a manner as to allow to within 10 in. (250 mm) of the bottom
restoration. of the box. At this point a gamma ray
2. The theoretical location of vertical source was placed in the hole and at the
tendons was marked with chalk on the same time a sensitive plate was placed
concrete. underneath the box. If the exposure in-
3. Anchorage pockets were chipped dicated that there was no interfering
out with a lightweight pneumatic ham- longitudinal bottom flange tendon, the
mer; this had to he accomplished very drilling was continued and a 1 1/4 in. (32
carefully because in the process the mm) diameter vertical Dywidag bar
-w--
thickened flange_...,rib
Section 1-1
134
(a) SINGLE TENDON (b) DUAL TENDON
retained and the following additional weakening of the top and bottom flanges
disadvantages are introduced: by the 2 in. (51 mm) diameter holes re-
I. Punching shear through the quired, the tendons were staggered in a
flanges. vertical and inclined orientation as
2. Secondary bending stresses in the shown in Fig. 7Ia. The shearing force
flanges and webs. The bending in the produced at the interface of the existing
webs is particularly true of thin webs web and the web thickening is largely
and where an external web is con- resisted by bond. To prevent shearing at
cerned, where vertical tendons would the interface, mechanical doweling was
only be located at the inside of the box. provided by % in. (16 mm) diameter
The retrofit measures used for the re- bolts drilled into the web which sup-
pairs of cracked webs for a structure in ported a grid of conventional reinforce-
Canada" utilized a similar technique for ment (Fig. 71b).
the vertical internal webs as described
above. However, the inclined exterior
webs were more difficult to retrofit DESIGN/CONSTRUCTION
since no bar tendons could be used at RECOMMENDATIONS
the outside face of the web.
Boring through the external web was In the previous sections the author
impossible because of the two side-by- has attempted to delineate the causes of
side upper longitudinal tendons (Fig. cracking in post-tensioned concrete
71a). Preliminary calculations indicated bridges. To minimize the occurrence of
that placing tendons along the inside cracking during construction, or at some
face of the web only would produce un- future time in the life of the structure,
desirable large tensile stresses in the the designer should re-evaluate the fol-
outside surface of the web. Therefore, a lowing major considerations upon con-
decision was made to thicken the out- clusion of the design:
side webs as shown in Fig. 71a. 1. Has the effect of tendon curvature
To produce the required prestress in been accommodated?
the thickened web, tendons had to be (a) Horizontal pullout.
spaced at 71/2 in. (19(1 mm). To preclude (I)) Vertical curvature of soffit ten-
web thickening
epoxy
Injected
crack +^5 re-bar
tendons
caulking
material
(a)
web
2"x4"x 1" steel plate
washer
5/8" bolt
horizontal bar
.
\ 2-#5 re-bar
welded to plates
welds anchor
for bolts
view A-A
(b)
136
It is recommended that provisions for 3. Verify that adequate spacing is
future prestressing (say 10 percent of the provided between ducts at points of
design longitudinal prestress force) be horizontal curvature to prevent crushing
provided for in the initial design. Pro- of ducts, i.e., spread the ducts as much
viding anchorage bearing plates and as possible.E"
trumpets in the diaphragms and inter- 4. Be aware of and check construction
mediate deviation saddles for future loads to preclude overstressing and
placement of external tendons is a very cracking i.e., stock piling of material on
minor cost during initial construction. the deck.
To provide this capability after initial 5. Immediately bring to the attention
construction can he a very expensive of the Engineer any interferences be-
and difficult task. tween ducts or ducts and reinforcement
During construction a number of sim- and carefully evaluate the consequences
ple precautions can preclude costly time of duct relocation or cutting or rein-
delays and repairs. forcement
1. Use of stiff pipe mandrels and wo , 'c 6. Careful adherence to and moni-
bridges to preclude displacement or o:f- toring of concrete curing methods.
setting of tendons from segment to seg- Avoid temperature gradients between
ment during fabrication or casting. segments during match-casting opera-
2. Verify that ducts are not being tions. Avoid accelerated curing."
"kinked" at tendon curvature locations. 7. Minimize or eliminate any warping
Use prebent heavy gauge ducts or steel or distor -ion of segments during stor-
tubes when curving of tendons is neces- age when the concrete is still at an early
sary. age.
CONCLUDING REMARKS
An attempt has been made in this itive and negative experiences. How-
paper to document the current state-of- ever, there exists in our society a can-
knowledge with regard to reasons for toes attitude toward dealing with unfa-
cracking in post-tensioned concrete box vorable developments, errors, and dam-
girder bridges. However, the reasons for ages which inhibits technological prog-
cracking are so varied, complex and in- ress. Unfortunately, when a problem oc-
teractive that it is impossible to present curs the initial reaction is to seek out the
a document that is all inclusive and au- guilty. This then leads to the situation
thoritative. As with any type of con- whereby, under direction from the legal
struction with any material, problems profession, all parties concerned are ad-
arise that require the attention of not vised not to discuss the problem be-
only the designer, but contractors and cause of potential liability and litigation.
subcontractors as well. No matter how This is to some extent understandable
good the design, if the structure is not since none of the parties involved desire
properly constructed, there will be to jepoardize their rights or to incrimi-
problems. Conversely, no matter how nate themselves. The disadvantage is
dilligent the contractor, if the design that it may take years before the case is
details are poor, problems will result. resolved in the courts and in the mean-
Obviously, if both the design and the time the public safety at large may be
construction are poor, problems are jeopardized because the same errors or
compounded. problems are perpetuated in possibly
Technological progress is only of hundreds of additional projects. This
value if it is measured against both pos- impasse requires resolution and cooper-
ACKNOWLEDGMENTS
The data presented in this paper has Professor T. Y. Lin, T. Y. Lin Interna-
been gathered from personal experience tional; Mr. Robert C. Cassano, Califor-
and from numerous and varied nia Department of Transportation; and
documented sources. Much of the mate- Mr. Clarence R. Yamamoto, Hawaii De-
rial presented is not original. Although partrnent of Transportation, for material
acknowledgment of all the many sources presented on the "Pullout of Horizon-
is not possible, full credit is given wher- tally Curved Tendons." In addition, the
ever the specific source can be identi- assistance of Professor Ben C. Lerwick,
fied. Jr. in obtaining several FIP documents
The author is particularly indebted to is appreciated.
REFERENCES
1. Technical Instructions for the Inspection 7. National Association of Australian State
and Maintenance of Highway Structures, Road Authorities, NAASRA Bridge De-
Interim Document 32, Sub-document 2, sign Specifications, 5th Edition, 1976,
"Box Girder or Ribbed Panel Bridges, 8. American Association of State Highway
and Similar Prestressed Concrete Struc- and Transportation Officials, "Standard
tures," Department of Highways and Specifications for Highway Bridges,"
Highway Traffic, Ministry of Transpor- 13th Edition, 1983.
tation (France), October 19, 1979. 9. Ontario Ministry of Transportation and
2. Bouvy, J. J . , and Foxier, J., "Problems Communication, "Ontario Highway
Encountered in Segmental Bridges In- Bridge Design Code and Commentary,"
fluencing Precast Segmental Construc- 1979.
tion," FIP Proceedings, V. 3, 1982. 10. Priestley, M. J. N., and Buckle, 1. C.,
3. Podolny, W., Jr., and Muller, J. M., Con- "Ambient Thermal Response of Con-
struction and Design of Prestressed crete Bridges, Bulletin 42, Road Re-
Concrete Segmental Bridges, John Wiley & search Unit, National Roads Board,
Sons, New York, N.Y., 1982. Wellington, New Zealand, 1979.
4. Moreau, P., and Virlogeux, M., "Lessons 11. Priestley, M. J. N., "Design of Concrete
From a Shear-Cracked Bridge," Elev- Bridges for Temperature Gradients,"
enth Congress of the International Asso- ACI Journal, V. 75, No. 5, May 1978.
ciation for Bridge and Structural Engi- 12. Leonhardt, F., "Prevention of Damages
neering, Vienna, September 1-5, 1980. in Bridges," FIP Proceedings, V. 1, 1982,
5. Leonhardt, F., and Lippoth, W., "Les- 13. Leonhardt, F., Kolbe, C., and Peter, J.,
sons From Damage to Prestressed Con- "Temperature Differences Endanger
crete Bridges," Beton- und Stahlbeton- Prestressed Concrete Bridges," Beton-
bau (Berlin), No- 10, October 1970. und Stahlbetonbau (Berlin), No. 7, July
6. Leonhardt, F., Koch, R., and Rostasy, 1965.
F. S., "Suspension Reinforcement for 14. New Zealand Ministry of Works and De-
Indirect Loading of Prestressed Con- velopment, "Highway Bridge Design
crete Beams: Test Report and Recom- Brief," CDP 701/D, Civil Division Pub-
mendations," Beton- and Stahlbeton- lication, Wellington, New Zealand,
bau (Berlin), No. 10, October 1971. September 1978_
138
15. British Standard BS 5400, Steel, Con- 22. Stone, W. C., and Breen, J. E-, "Behavior
crete and Composite Bridges, Part 1 of Post-Tensioned Girder Anchorage
General Statement, 1978. Zones," PCI JOURNAL, V. 29, No. 1.,
16. Precast Segmental Box Girder Manual, January-February 1984, pp. 64-109.
Published jointly by the Prestressed 23. Stone, W. C., and Breen, J. E., "Design
Concrete Institute and Post-Tensioning of Post-Tensioned Girder Anchorage
Institute, 1978. Zones," PCI JOURNAL, V. 29, No. 2,
17. Hejnic, Jiri, "Effects of Temperature March-April 1984, pp. 28-61.
Changes on Prestressed Concrete 24. Gerwick, Ben C., Jr., "Causes and Pre-
Bridge," Presented at FIP Seventh Con- vention of Problems in Large-Scale Pre-
gress, New York, May 26June 1, 1974. stressed Construction," PCI JOURNAL,
18. "Proposed Recommendations for Seg- V. 27, No. 3, May-June 1982, pp. 58-75.
mental Construction in Prestressed Con- 25. Harwood, Allan C., "1-205 Columbia
crete," FIP CommissionPrefabrica- River BridgeDesign and Construction
tion, 3rd Draft, September 1977. Highlights," PCI JOURNAL, V. 27, No.
19. Stone, W. C., and Breen, J. E., "Analysis 2, March-April 1982, pp. 56-77.
of Post-Tensioned Girder Anchorage 26, ACI Committee 318, "Building Code Re-
Zones," Research Report 208-1, Center quirements for Reinforced Concrete (ACI
for Transportation Research, The Uni- 318-83)," American Concrete Institute,
versity of Texas at Austin, August 1980. Detroit, Michigan, 1983.
20. Stone, W. C., Paes-Filho, W., and Breen, 27. Lecroq, P., and Poineau, D., "Rein-
J. E., "Behavior of Post-Tensioned forcement of Bridges by Prestressing,"
Girder Anchorage Zones," Research Re- Eleventh Congress of the International
port 208-2, Center for Transportation Re- Association for Bridge and Structural
search, The University of Texas at Aus- Engineering, Vienna, September 1-5,
tin, August 1980. 1980.
21. Stone, W. C., and Breen, J, E., "Design 28. Dilger, W. H., and Ghali, A., "Remedial
of Post-Tensioned Girder Anchorage Measures for Cracked Webs of Pre-
Zones," Research Report 208-3F, Center stressed Concrete Bridges," PCI JOUR-
for Transportation Research, The Uni- NAL, V. 19, No. 4, July-August 1974, pp.
versity of Texas at Austin, June 1981. 76-85.