Site Visit Check List and Brief Report ( Ground Mounted)

Project Name 35MW Soalr Power Plant Chithradurga Karnataka


Project Client/Consultant -
Place (Village/Taluka/Dist/state) Torekolammanahall,Challakere,Chithradurga, Karnataka
Date of Site visit 05-04-17
Mr.Pawan Vyas (Land Aggregator)
Team members name/agency name involved during site visit Mr. Swapnil Kotwal (Sterling & Wilson)
Mr. Prakasha (Sterling & Wilson)
S. No. PARTICULARS DESCRIPTION
A Latitude / Longitude
1 Site 14.56450179 N, 76.53987992 E
2 Substation 14.519918 N, 76.435134 E
Distance Chart for SS SS is 16 km from site by road
B. APPROACH TO SITE
1 Nearest Town & Distance Challakere ,40 Kms
2 Nearest Highways & Distance Chithradurga to Hosapete,15 Kms
3 Nearest Railway Station & Distance Chithradurga,55 Kms
4 Railway type (BG / MG) BG
5 Nearest Airport & distance Bangalore,KIA,256Kms & Hubbali Airport 243Kms
Accessibility to site from existing road(existing road wide enough
6 to pass container/narrow road/WBM road/mud road/not exists to 3 mtr wide Asphalt road
be constructed by purchasing)
7 Load carrying capacity of the road/ culverts NA
8 Distance from nearest water way & the port. NA
General site features, previous history of use if any, information The site is undulated with Bushes & No information of existing
9
regarding any failure of existing structures or foundations. structures failure is present

C. LAND AVAILABILITY
1 Area of the plot 170 Acres
2 Shape of Land Irregular
3 Type of Land Revenue/ Private/Forest Private
4 Earlier use of Site (Waste/Agricultural/Barren etc.) Barren
5 Existing Structures/ shrines, wells, ponds etc. No

6 Requirement of site clearing for making it ready for construction. Clearing & cutting required & 3m to 4m Leveling required

7 Time required to acquire complete land earmarked for the Project NA

Area/land available in single parcel or multiple patches(if so how


8 Single Parcel (Single owners)
many parcels)?
D. SOIL CONDITION
1 Nature of soil Presence of black cotton & red soil with small boulders.
2 Earth Resistivity NA
3 Termite problem, if any NA
4 Nature of strata at shallow depth (Soil or Rock ) NA
5 Presence of any wells (opens / tube). Not Present
6 Natural Vegetation and presence of big trees Extensively Present
7 Earthquake Zone, history any examples of local damage. NA
Terrain of the Land (flat/rocky/Huge undulated/occupied with Undulated land cutting & leveling around 3 to 4 mtrs with 70% to
8
tree/vegetations)? 80% Shurbs
Tree cutting required,levelling required & Clearing of Bushes
9 Site development required?(Cutting/levelling/tree cutting)
required

Surrounding site Conditions/near/adjacent area(near by


10 NA
hill/mountain/forest/power line/Wind turbine/no obstacles)

Shading object details if fouls within/surrounding the site boundry.


(a) Wind turbine height/dia & etc)
(b) Line tower height/width & etc.
11 No
(c) Building height/width & etc.
(d) Hill height and distance from site boundry
S. No. PARTICULARS DESCRIPTION
E. SITE DATA
1 Altitude above MSL ( Mean Sea Level) 588 meters
2 HFL ( High Flood Level) NA
3 Flash flood condition NA
4 Area drainage outflow available NA
5 Max and Min Temperature 16 degrees/34 degrees
6 Humidity )
7 Rain fall (Daily/Annual) Maximum, Minimum, Average Average rainfall is 499.2 mm (min) 971 mm (max) per annual
8 Wind velocity for past 10-15 years and wind directions NA
9 Any mining activity in the area. No
Radiation data(from available from nearby meteo station/plant
10 NA
name)
11 Site level w.r.t. (a) Road (b) Nearby site .5 meter below the Existing road level
Area drainage system possibility(natural drain / required to be
12 No
designed)
G. WATER
1 Source of Construction and Drinking Water Near by village
2 Physical and Chemical analysis of water if done NA
Water source available?(Borewell exits/well exists/no
3 No
borewell/nearby lake/river/no waterbody)
4 Maximum and minimum level of the Groundwater Table. NA
5 River/ Canal/Municipal water availability and quality NA
6 Features of Dam/ Barrage existing/ to be constructed. NA
7 Physical and Chemical analysis of water along with temperature NA

H. ENVIRONMENTAL CONSIDERATIONS
Industries in neighbouring areas, any toxic effluents or
1 No
atmospheric emission from these industries.
2 Any major river/ canal passing in the vicinity No
3 Community and social factors : Rural or Urban Rural
For disposal of effluent, what is the arrangement? Any regulations
and laws prevailing? In absence of any regulations whether this
4 NA
can be disposed along with sewage into any industrial drainage or
nallah?
5 Existence of any corals for coastal plants. NA
Present industrial concentration and future expansion in the
6 NA
neighbourhood
7 Rehabilitation & Resettlement of persons required. NA
I. GENERAL
1 Source of start-up power. Near by Villages / DG
Availability of communication/internet facilities e.g. A hotel in the
2 Near town.
nearest town may have telex, telephone or fax facility.

Existing high voltage power supply lines crossing the plot which
3 No
requires shifting before Construction start up.

4 Contour survey map in AutoCAD if available. NA


Any other Solar Farm visible nearby within 10-20 km area ;- Name
5 NA
& rating of machine , size of Wind farm , distance
Do we need boundary wall/fencing for security(possibility of theft
6 Yes
risk if any)
7 Availability of courier service NA
Proximity of infrastructure facilities (Hospitals, schools, post office,
8 Near by town
etc.)
J. ELECTRICAL Detail SS-1
Nearest Grid substation and its rating KPTCL SS Hiremallanahole- 66/11kV MUSS 2x8MVA

KPTCL SS Hiremallanahole- (400/220kV upcoming ss) 2x100 MVA


1
2 No of 8MVA Transformer
No. of Transformers
2 No of 100MVA Transformer (Upcoming SS)
2 Proximity of the substation No
1) Is the sub-station is same as proposed by the
3 -
developer
2) Any other prospective /existing SS near to offered site No
S. No. PARTICULARS DESCRIPTION

3) Whether space is available within the sub-station for


yes in upcoming 400/220kv
bay extension of our proposed evacuation.
4) Total connecting;-
a) incoming lines and outgoing lines to this SS, NA

b) Any other power generating station i.e. Wind


YES Solar & Wind Farm exist
farm / Solar/ Hydro is connected to this SS
c) Nature of load connected to the SS- i.e.
Agricultural/domestic
Agricultural/ Industrial/Commercial/domestic
4 Space availability in control room for extra panel No
Other developers nearby looking to connect to the same
5 Not in 400/220kV
line/substation
6 Fault Level of SS BUS NA
Bay availability at the substation for the capacity or to be
7 -
constructed newly
Voltage variation/fluctuation record of the substation(min & max-
8 NA
previous record)
9 X/ R ratio at the connecting bus of the terminating Substation NA
10 Space available for new bays No
11 SLD Of the substation(photos) No
12 GA and MRC room layout(photos) No
13 Power Transformer name plate details(photos) No
14 Substation configuration(single bus/double bus) & ratings -
SLDC interconnection with substation(exists/not exists/type of
15 NA
SLDC communication- PLCC/OLTE)
RoW Issues expected ( e.g. pass trough pvt
16 NA
land/forest/river/power line/telephone crossings & etc.)

Total available land is 170 acres as informed by Land aggregator.


Land is divided into two plots separated by a 15m to 20m wide & 1.5
K Other Observations to 2m depth seasonal streams passing in between. 60 to 70% of the
land is covered with Bushes & shurbs.80% of land is heavily
undulated around 3 to 4 mtrs cutting is required.

https://www.dropbox.com/sh/ggs605f3el8aghy/AADPumIDMquQuP
L For Site Pics
dSAencxylsa?dl=0
Report Prepared By Prakasha & Swapnil Kotwal
Report reviewed by Ravi kumar & Shivakumar kinni
Date 06-04-17
Issued/Circulated to -Tendering/BD/Design