FINISHING SEQUENCE

PRELIMINARIES:
Shop drawing
Method statement

Trade: PLASTERING
Safety
Working conditions

CHECK MATERIAL (IITP-HT-02)

APPROVAL M&E SYSTEM

Wall: check against form Use plumb bob Check outlet of sanitary ware wire mesh between concrete &
Show wall centerline, thickness, IITP_HT_01 Check horizontally, diagonally, Approve wall-embedded M&E brick wall
finishing coats Check r.c member: Straightness, Check corners, wall lines. system wire mesh at cut wall
Details of wall types flatness Finishing thickness in Openings for technical system wire mesh at wall edge
Location of door and opening Door frame: as IITP-HT-09 accordance with shop drawings.
(agreed with door
subcontractor)

Check door wedging (as 2-layer plastering: thickness Brick wall: dampen by water
IITP-HT-09). gaining layer & flattening layer Concrete: Roughen surface,
Plastering to door side: attention Plastering to corner: use trowel ( dampen & paint cement grout.
to space for sealant filling (for can use angle trowel) to
aluminum door) smoothen corners
Note: the verticality of wall side
wire mesh

Clean wall surface by brush Watering to wall surface after Check flatness, straightness,
clean working area plastering mortar course, level and corner
Location of door opening and
technical opening.