Академический Документы
Профессиональный Документы
Культура Документы
AND
MAINTENANCE MANUAL
FOR THE
RANGE OF PUMPS
Issue B 20/06/03
Installation, Operation & Maintenance Manual
For The Classic Range Of Rotary Lobe Pumps
1.1 RISK ASSESSMENT RELATING TO THE USE OF JOHNSON PUMP (UK) LTD. CLASSIC
ROTARY LOBE PUMPS AND PUMP UNITS IN POTENTIALLY EXPLOSIVE ATMOSPHERES. 7
2.0 INTRODUCTION. 8
2.1 GENERAL. 8
2.2 JOHNSON PUMP (UK) DISTRIBUTORS. 8
2.3 RECEIPTS AND STORAGE. 8
2.4 CLEANING. 9
2.5 PUMP MODEL DESIGNATION. 9
2.5.1 ATEX IDENTIFICATION PLATE 10
2.5.3 EQUIPMENT GROUPS & CATERGORIES 10
2.6 PUMP MODEL AND SERIAL NUMBER. 11
2.7 STANDARD PUMP COMPONENT TERMS. 12
3.0 GENERAL. 13
Page : 1
4.2.3 GEARBOX DISASSEMBLY 44
4.2.4 GEARBOX ASSEMBLY 47
4.2.5 ROTORCASE, ROTOR AND FRONT COVER ASSEMBLY 51
4.3 IC40 SERIES PUMPS - DISASSEMBLY AND ASSEMBLY 53
4.3.1 FRONT COVER AND ROTOR REMOVAL 53
4.3.2 ROTORCASE REMOVAL 54
4.3.3 GEARBOX DISASSEMBLY 57
4.3.4 GEARBOX ASSEMBLY 59
4.3.5 ROTORCASE, ROTOR AND FRONT COVER ASSEMBLY 62
4.4 IC50 SERIES PUMPS - DISASSEMBLY AND ASSEMBLY 63
4.4.1 FRONT COVER AND ROTOR REMOVAL 63
4.4.2 ROTORCASE REMOVAL 65
4.4.3 GEARBOX DISASSEMBLY 68
4.4.4 GEARBOX ASSEMBLY 70
4.4.5 ROTORCASE, ROTOR AND FRONT COVER ASSEMBLY 72
Page : 2
6.2.4 FLUSHED PACKED GLAND SEAL REPLACEMENT 97
6.3 PACKED GLAND SEALS - IC50 SERIES PUMPS. 98
6.3.1 PACKED GLAND SEAL REMOVAL 98
6.3.2 PACKED GLAND SEAL REPLACEMENT 98
6.3.3 FLUSHED PACKED GLAND SEAL REMOVAL 99
6.3.4 FLUSHED PACKED GLAND SEAL REPLACEMENT 100
6.3.5 SEAL CONVERSION TO PACKED GLAND (WITH SHAFT SLEEVE) 100
6.3.6 SEAL CONVERSION TO FLUSHED PACKED GLAND (WITH SHAFT SLEEVE) 101
Page : 3
1.0 Saftey Information
DANGER
DO NOT place fingers, etc. into the pumping chamber or its connection ports
or into any part of the gearbox if there is ANY possibility of the pump shafts
being rotated. Severe injury will occur.
Installation and operation of the pump must always comply with health and
safety regulations.
A device must be incorporated into the pump, system, or drive to prevent the
pump exceeding its stated duty pressure. It must be suitable for both
directions of pump rotation where applicable. Do not allow pump to operate
WARNING with a closed/blocked discharge unless a pressure relief device is
incorporated. If an integral relief valve is incorporated into the pump, do not
allow re-circulation through the relief valve for extended periods (refer to
section 3.8).
Page : 4
The mounting of the pump or pump unit should be solid and stable.
Pump orientation must be considered in relation to drainage/cavity
ventilation requirements. Once mounted, shaft drive elements must be
checked for correct alignment. Rotate pump shaft by at least one full
revolution to ensure smoothness of operation. Incorrect alignment will
produce excessive loading and will create high temperatures and
increased noise emissions. Do not use any drive arrangements that
cause side loading of the drive shaft. It may also be necessary to earth
the pump head to avoid the build up of a potential charge difference
that could cause a spark.
The installation must allow safe routine maintenance and inspection (to
replenish lubricants, check for leakage, monitor pressures, etc) and provide
adequate ventilation necessary to prevent overheating.
Fill all gearboxes with the recommended grades and quantities of lubricant
WARNING
(refer to section 3.4). Beware of over/under filling the gearbox as this could
cause the pump to overheat and mechanical damage to occur.
Before operating the pump, be sure that it and all parts of the system to which
WARNING
it is connected are clean and free from debris and that all valves in the suction
and discharge pipelines are fully opened. Ensure that all piping connecting to
the pump is fully supported and correctly aligned with its relevant connections.
Misalignment and/or excess loads will cause severe pump damage. This
could result in unexpected mechanical contact in the pump head and has the
potential to be an ignition source.
Be sure that pump rotation is correct for the desired direction of flow (refer to
WARNING
section 3.4).
Do not install the pump into a system where it will run dry (i.e. without a supply
WARNING
of pumped media) unless it is equipped with a flushed shaft seal arrangement
complete with a fully operational flushing system. Mechanical seals require a
thin fluid film to lubricate the seal faces. Dry running can cause excessive heat
and seal failure.
WARNING
Pressure gauges/sensors are recommended, next to the pump suction and
discharge connections to monitor pressures.
Caution must be taken when lifting the pump. Suitable lifting devices should
be used as appropriate. Lifting eyes installed on the pump must only be used
to lift the pump, not pump with drive and/or baseplate. If pump is baseplate
mounted, the base plate must be used for all lifting purposes. If slings are
used for lifting, they must be safely and securely attached. For weights of bare
shaft pumps refer to section 8.6.
Page : 5
- The pump is fully isolated from the power source (electric, hydraulic,
pneumatic).
- The pumping chamber, pneumatic relief valve and any shaft seal
support system are depressurised and purged.
DO NOT loosen or undo the front cover, any connections to the pump, shaft
seal housings, temperature control devices, or other components, until sure
that such action will not allow the unsafe escape of any pressurised media.
Pumps and/or drives can produce sound power levels exceeding 85-dB (A)
under certain operating conditions. When necessary, personal protection
against noise must be taken. Typical noise emission data can be found in
section 8.7.
Avoid any contact with hot parts of pumps and/or drives that may cause injury.
Certain operating conditions, temperature control devices (jackets, heat-
tracing, etc.), bad installation, or poor maintenance can all promote high
temperatures on pumps and/or drives.
When cleaning, either manually or by CIP method, the operator must ensure
that a suitable procedure is used in accordance with the system requirements.
WARNING
During a CIP cleaning cycle, a pump differential pressure of between 2 and 3
bar (30 and 45 psi) is recommended to ensure suitable velocities are reached
within the pump head. The exterior of the pump should be cleaned
periodically.
Page : 6
1.1 Risk assessment relating to the use of Johnson Pump (UK) Ltd. Classic rotary
lobe pumps and pump units in potentially explosive atmospheres.
Note:- For a feature to be suitable for an application, The feature must be fit for its
designated purpose and also suitable for the environment where it is to be installed.
Frequency Of
Source Of Hazards Potential Hazards Recommended Measures
Hazards
Ensure that pump is totally filled.
Unvented cavities Build up of explosive gas Very Rare Consider mounting ports vertically.
See Chapter 1.0
Ensure that operating pressures are
Rotorcase / Rotors / Front Unintended mechanical not exceeded. Ensure that suffcient
Cover contact
Rare NPSH to prevent cavitation. See
Chapter 1.0/3.3.1 Service plan.
User must ensure temperature limits.
Do not overfill gearboxes with
excess temperature.
Pump external surfaces
Electrostatic charging
Rare lubricant. Provide a ground contact
for pump. See Chapter 1.0 / Service
plan.
Check selection of elastomers are
Pump liquid leakage. Build
Cover 'O' ring
up of explosive gas.
Very Rare suitable for application. Ensure cover
retaining nuts are tight. Service plan.
Pump liquid leakage. Build
Pump casing / cover
up of explosive gas.
Very Rare Stainless steel, Corrosion resistant.
excess temperature.
Selection of seal system must be
Unintended mechanical
suitable for application. See Chapter
Shaft seals contact. Rare 5.0. Service plan. Seals must never
Leakage.
run dry.
Build up of explosive gas.
Selection of auxiliary seal system
Auxiliary system for shaft Pump liquid leakage. Build
sealing up of explosive gas.
Rare must be suitable for application.
Seals must never run dry.
If flushed seals are installed ensure
that flush is applied to seal
Rotation direction test Excess temperature Very Rare assemblys. Only allow pump to run
for minimum period - just a few
seconds.
Excess Temperature. Can cause excessive pressue, heat
Closed valve condition Excess Pressure. Rare and mechanical contact. See
Mechanical contact. Chapter 1.0
Provide a ground contact for pump.
Shaft Random induced current Very Rare See Chapter 1.0.
Temperature from friction
Mechanical shaft coupling Sparks from break up of Coupling selection must suit
(Torque Protection) shear pins.
Rare application. See Chapter 1.0.
Electrostatic charging
Break up of spider.
Coupling selection must suit
Mechanical shaft coupling Unintended mechanical
(standard) contact.
Rare application. Service plan. See
Chapter 1.0.
Electrostatic charging
Page : 7
2.0 Introduction.
2.1 General.
This manual includes all the necessary information for Classic pumps
and should be read prior to beginning installation, operation, or
maintenance.
When asking for assistance please provide the pump model and serial
number. This information can be obtained from the pump nameplate
which is located on the side of the pump gearbox cover, refer to section
2.6.
Page : 8
If the pump is not required for immediate installation then it should be stored
in a clean, dry environment. It is recommended that storage temperature
should be between 10? and 40?C (14F and 105F).
2.4 Cleaning.
The Classic pump series is suitable for both manual cleaning and CIP
(Cleaning In Place), refer to section 3.3.2.
IC 30 / 0069 / 12
Page : 9
2.5.1 Atex Identification Plate
Temperature Class.
Page : 10
2.6 Pump Model and Serial Number.
Should you require any information regarding your Classic rotary lobe
pump contact Johnson Pump (UK) or your Johnson Pump (UK)
distributor, providing the pump model and serial number as stated on
the pump nameplate, see Fig 2, which is fixed to the pump gearbox
cover.
Fig 2
Fig 3
12345/A/67
Page : 11
2.7 Standard Pump Component Terms.
Fig 4
Page : 12
3.0 General.
The pumping action of the rotary lobe pump principle is generated by the
contra rotation of two pumping elements (rotors) within a chamber (rotorcase),
see Fig 5. The rotors are located on shafts which in turn are mounted within
an external gearbox and supported by bearings, the timing gears are also
located on the shafts. The timing gears transfer the energy from the drive
shaft to the driven shaft, synchronizing the rotors such that they rotate without
contact with each other.
As the rotors pass the suction port, see Fig 5a, the cavity generated increases
creating a pressure decrease, which induces the pumped medium to flow into
the rotorcase.
The pumped medium is carried around the rotorcase by the rotors, see Fig 5b
and 5c, to the discharge side of the pump, Fig 5d. Here the cavity decreases
and the pumped medium is discharged from the rotorcase, Fig 5e.
Page : 13
3.2 Classic Range Operating Parameters.
The maximum pressure and speed operating parameters are given in Fig 6. In
practice these may be limited due to the nature of the product to be pumped
and/or design of the system in which the pump is to be installed. Consult
JPUK or your JPUK distributor for assistance.
Page : 14
Fig 6 Operating Parameters
Max
Nominal Max Diff.
Max Diff. Max. Speed @
Pump Series Theoretical Displacement Connection Pressure @
Pressure Speed Max Diff.
Size Max Speed
Pressure
Imp.gal US gal
ltr/rev mm inches bar psi rev/min rev/min bar psi
/100 rev /100 rev
IC20/0020/12 0.202 4.44 5.34 38 1.5 12 175 1000 750 8.5 120
IC50/0351/12 3.514 77.31 92.84 101 4 12 175 650 420 8.5 120
Note: For pumps with packed gland product seals, maximum operating speed should
WARNING never exceed the maximum speed at maximum differential pressure, as stated
above.
Page : 15
3.3 System Design.
a) Access to the pump and drive for routine inspection and maintenance,
i.e. to replenish pump or drive lubricant or to remove pump front cover
and rotors.
ii) The pump must not be used to support piping. All piping to and from the
pump unit must be independently supported. Failure to observe this may
WARNING
distort the pump head components or assembly and cause serious
consequential damage to the pump.
iii) Valves should be provided adjacent to the pump suction and discharge
connections to allow the pump to be isolated from the system for routine
inspection and maintenance.
iv) Rotary lobe pumps are of the positive displacement type and therefore an
overload protection device must be provided. This can take the form of:
a) A pressure relief valve integral with the pump where available and
suited to the application, refer to section 3.8.
v) It is recommended that all piping and associated equipment from the tank
to the discharge point be thoroughly cleaned before installation of the
WARNING pump to avoid the possibility of debris entering the pump and causing
damage.
Page : 16
vi) Pressure gauges should be installed adjacent to the pump suction and
discharge connections such that system pressures can be monitored.
WARNING These gauges will provide a clear indication of changes in operating
conditions and where a relief valve is incorporated in the system, will be
necessary for setting and checking the functioning of the valve.
vii) It is imperative that the suction condition at the pump inlet meets the Net
Positive Suction Head Required (NPSHr) by the pump. Failure to observe
WARNING this could cause cavitation, resulting in noisy operation, reduction in flow
rate and mechanical damage to the pump and associated equipment.
The Net Positive Suction Head Available (NPSHa) from the system must
WARNING always exceed the Net Positive Suction Head Required (NPSHr) by the
pump. Observing the following general guidelines should ensure the best
possible suction condition is created.
- The minimum number of bends, tees and pipework restrictions are used.
- That calculations to determine system NPSHa are carried out for the
worst condition, see Fig 7.
Fig 7
Page : 17
(viii) When installing a pump complete with baseplate, motor and drive, the
following guidelines must be observed:
a) The preferred drive arrangement for any rotary lobe pump is in-line
direct coupled. If an alternative is required please contact JPUK or
your JPUK distributor.
f) When using electric motor drives, ensure that the electrical supply is
compatible with the drive and controls and that the method of wiring is
correct for the type of starting required by the motor i.e. Direct On
Line, or other similar method. Ensure all components are correctly
grounded.
The Classic pump has been designed to be effectively cleaned by the CIP
procedures recommended for in place cleaning of process plant. It is
recommended that a differential pressure of 2 to 3 Bar (30 to 45 psi) be
developed across the pump head during cleaning in order to develop the
necessary fluid velocities required for thorough cleaning.
Page : 18
3.4 Start Up Procedure.
WARNING - Check that all piping and associated equipment are clean and free from
debris and that all pipe connections are secure and leak free.
WARNING - For pumps fitted with flushed product seals check all auxiliary services
are in place and connected and provide sufficient flow and pressure for
flushing purposes, refer to section 7.0.
- Ensure lubrication is provided for both pump and drive. Classic pumps
WARNING are shipped without oil and should be filled to the level of the oil sight
glass which must be installed in the upper tapped hole in the side of the
gearbox cover, refer to section 8.3 for pump oil capacities and grades.
- Ensure both suction and discharge valves are fully opened and that
WARNING pipework is free from all obstructions. Classic pumps are of the positive
displacement type and should therefore never be operated against a
closed valve as this would result in pressure overload, resulting in
damage to the pump and possibly the system.
WARNING - Ensure rotation of the drive shaft is correct for the direction of flow
required, see Fig 8.
Page : 19
Fig 8
When shutting the pump down, stop pump, close both the suction and
discharge valves and ensure that the necessary safety precautions are taken:
Page : 20
3.6 Routine Maintenance.
- Change the oil every 12 months or 3000 operating hours, whichever is the
sooner.
All Classic pumps can be supplied with a jacketed front cover and rotorcase
for circulation of a heating/cooling media.
The front cover and rotorcase jacket ports are strategically positioned such
that the required thermal effect acts on the pumping chamber.
The pressure rating of the Classic series jacketed front cover and rotorcase is
3 Bar (50 psi) and this should not be exceeded without consulting JPUK or
your local JPUK distributor.
Page : 21
Fig 9 Dimensions of Front Cover Jacket for Heating/Cooling.
Millimeters Inches
Model A6 M1 A6 M1 Y4
IC10/0005/12 50.0 52.0 1.97 2.05
IC10/0008/08 50.0 61.0 1.97 2.40
IC10/0011/05 50.0 61.0 1.97 2.40
IC20/0020/12 64.0 71.0 2.52 2.80
IC20/0031/07 64.0 81.0 2.52 3.19
IC30/0069/12 92.5 81.0 3.64 3.19
IC30/0113/07 92.5 96.0 3.64 3.78
IC40/0180/12 130.0 108.0 5.12 4.25
IC40/0250/07 130.0 123.0 5.12 4.84
IC50/0351/12 175.0 115.0 6.89 4.53
IC50/0525/08 175.0 138.0 6.89 5.43
Page : 22
Fig 10 Dimensions of Rotorcase Jacket for Heating/Cooling.
Millimeters Inches
Model A7 BJ D1 M2 A7 BJ D1 M2 Y5
IC10/0005/12 70.0 56.0 156.0 3.0 2.76 2.20 6.14 0.12
IC10/0008/08 70.0 56.0 156.0 2.0 2.76 2.20 6.14 0.08
IC10/0011/05 70.0 56.0 156.0 7.5 2.76 2.20 6.14 0.30
IC20/0020/12 80.0 64.0 216.0 0.0 3.15 2.52 8.50 0.00
IC20/0031/07 80.0 64.0 216.0 1.0 3.15 2.52 8.50 0.04
IC30/0069/12 118.0 93.0 280.0 1.0 4.65 3.66 11.02 0.04
IC30/0113/07 118.0 93.0 280.0 3.5 4.65 3.66 11.02 0.14
IC40/0180/12 156.0 125.0 352.0 2.5 6.14 4.92 13.86 0.10
IC40/0250/07 156.0 125.0 352.0 3.5 6.14 4.92 13.86 0.14
IC50/0351/12 191.0 155.0 430.0 8.0 7.52 6.10 16.93 0.31
IC50/0525/08 191.0 155.0 430.0 10.0 7.52 6.10 16.93 0.39
Page : 23
3.8 Integral Pressure Relief Valves
- see Fig 11, 12, 13 and 14.
All models in the Classic IC10, IC20, IC30 and IC40 series of pumps can be
supplied with integral pressure relief valves. For the IC10, IC20 and IC30
series both spring and air loaded versions are available, for the IC40 series
only air-loaded valves can be supplied. The function of the valves can be
further enhanced with the option of manual or airlift override, offering particular
benefits where CIP or SIP procedures are employed. Valves incorporating this
option can be opened to regulate the flow of the cleaning media through the
pump chamber, thereby avoiding the need for manual cleaning or external
bypass.
Where the pump is mounted onto a portable cart baseplate, complete with
motor and drive to be used as a mobile set, an integral pressure relief valve
should be installed.
- Valve can be set to the required pressure relief setting. Manual lift
override can be used to open valve without disturbing pressure relief
setting.
- Valve can be set to the required pressure relief setting. Airlift override,
which operates on an air supply of up to 7 Bar (102 psi) depending on
pressure relief setting, can be used to open valve without disturbing
pressure relief setting.
Air actuated relief valves can be operated remotely and interfaced with other
elements of the system or process control.
Integral pressure relief valves are normally used to protect the pump from the
effects of increases in system pressure caused, for example, by a restricted or
Page : 24
closed discharge line. In response to a pressure increase, the valve opens
and internally circulates the pumped media within the pump chamber. When
the valve opens, because the volume of liquid circulating is relatively small,
WARNING the temperature of the liquid in the pump chamber may rise if the pump
continues to operate for an extended period. In severe cases, this may result
in temperatures in excess of the pumps operating limits, or vaporization of the
liquid, both of which should be avoided. For these reasons when the valve is
activated the cause of the system pressure increase should be eliminated as
continuous operation of the pump with the valve open is not recommended
and may cause severe damage to the pump.
For setting and operating Classic integral relief valves refer to sections 3.8.1
and 3.8.2. Before beginning the relief valve setting procedure the pump should
be installed, refer to section 3.3.1, paragraph (vi), with a pressure gauge in the
discharge line adjacent to the pump discharge port.
- Remove cover (108). For integral relief valve with manual lift, see Fig 12;
first remove nut (129) and handwheel (111).
- Unscrew nut (107) using pry bar in holes provided to relieve spring
compression. For integral relief valve with airlift, see Fig 13, the air
cylinder must be exhausted prior to unscrewing the nut (107).
- Screw in nut (107) using pry bar in holes provided until the required
pressure relief setting is reached.
Note: Care should be taken not to exceed the lower of either the pump's
WARNING maximum pressure rating or the system design pressure.
- Reinstall cover (108). For integral relief valve with manual lift, see Fig 12;
reinstall handwheel (111) and nut (129).
Page : 25
- The relief valve is now set.
For Integral Relief Valve with Manual Lift - see Fig 12.
- To operate the manual lift, turn the handwheel (111) clockwise, which will
lift the valve head (102/128). To resume normal relief valve operation,
turn the handwheel (111) counter-clockwise.
For Integral Relief Valve with Air Lift - see Fig 13.
- To actuate the airlift, connect an air supply not exceeding 7 Bar (102 psi)
to the cylinder (123), connection 'B', which will lift the valve head (112).
To resume normal relief valve operation, exhaust the cylinder (123).
3.8.2 Setting and Operating Air Loaded Integral Pressure Relief Valves
- Fig 14.
- Connect an air supply, not exceeding 7 Bar (102 psi), via a regulating
valve to the relief valve connection 'A' in the cylinder (114). Do not turn on
the air supply.
- Using the regulating valve, gradually increase the air pressure until
required pressure relief setting is reached. The air pressure must not
exceed 7 Bar (102 psi).
Note: Care should be taken not to exceed the lower of either the pump's
WARNING maximum pressure rating or the system design pressure.
- To use the air lift system, the regulated air supply must be routed through
a change-over valve in order to transfer air from the relief valve load air
chamber, connection 'A', to the lift air chamber, connection 'B', while
depressurizing the load chamber and vice versa. The change-over valve
will actuate the air lift which will lift when the air supply is diverted to
connection 'B', and will close, restoring normal relief valve operation, when
the air supply is diverted back to connection 'A'.
DANGER
Under no circumstances should any attempt be made to disassemble a
pressure relief valve which has not had the spring pressure relieved, is
still connected to a pressurized air supply or is mounted on a pump
that is operating. Serious personal injury or pump damage may occur.
Fig 11 Spring Loaded Integral Pressure Relief Valve IC10, IC20, IC30 Typical.
Page : 26
Fig 12 Spring Loaded Integral Pressure Relief Valve with Manual Lift
IC10, IC20, IC30 Typical.
Fig 13 Spring Loaded Integral Pressure Relief Valve with Air Lift
Page : 27
IC10, IC20, IC30 Typical.
Fig 14 Air Loaded Integral Pressure Relief Valve with Air Lift
IC10, IC20, IC30, IC40 Typical.
Page : 28
4.0 Classic Pump Disassembly and Assembly.
Before starting any work on the pump the recommended Shutdown Procedure
should be followed, refer to section 3.5.
The position of all parts should be identified as they are removed to ensure
they are reinstalled in the same position.
Lipseals and o-rings are incorporated within the gearbox assembly to contain
the lubricant for the bearings and timing gears. Regular inspection and correct
maintenance of these items will ensure that the lubrication is sustained and
the pump maximum working life is achieved. To ensure this, it is extremely
important that care is taken when removing and replacing new o-rings and
lipseals. When removing and replacing lipseals ensure that the location bore
for the outside diameter and the seat for the back of the lipseal is not
damaged as this may create a leak path for the lubricant.
All o-rings and sealing lips of lipseals should be lightly lubricated with a
suitable lubricant (silicon grease etc.) before installing.
When installing lipseals do not allow the rear face to come into contact with
bearings or other rotating parts.
Prior to beginning assembly, ensure all parts are clean and free from burrs or
damage. Where a vice is to be used then this should be installed with
protective jaws to avoid damage to components. Do not hammer or apply
undue force to install or position components.
WARNING All fasteners are required to be tightened to the required torque setting during
assembly, refer to section 8.2.
Page : 29
The preferred method of installing bearing cones is that they are heated to
approximately 125C (250F) prior to installation. During this operation
protective gloves should be used. Once bearing cones are installed in correct
position they should be allowed to cool before proceeding with assembly. As
an alternative, bearing cones may be pressed into position providing the
proper equipment is employed and the necessary procedures are used to
prevent component damage.
For torque settings for fasteners and shaft rolling torque settings refer to
section 8.2.
Fig 15
Page : 30
- Follow recommended shutdown procedure, refer to section 3.5.
- Gradually loosen front cover retaining dome nuts (36). Care should be
taken as there may still be residual product and pressure in the pump
head and as the dome nuts are loosened, this will vent to atmosphere.
Note: Do not rotate shafts at this stage as the rotorcase is held in place
WARNING
by the front cover retaining dome nuts (36).
- Remove front cover (38) using lever slots where necessary and the front
cover o-ring (39) or gasket (88).
Note: The socket (58) should always be used, the use of other tools may
WARNING damage the retainer.
- For Single Unflushed Mechanical Seals - see Fig 15 and Fig 16.
Slide rotorcase (40) from bearing housing (20), noting it is located on dowels
(57), keep arch shims (15) in appropriate sets if they are to be reused.
For Single Flushed and Double Mechanical Seals - see Fig 15, Fig 17 & Fig 18.
Page : 31
Fig 16 Single Unflushed
Mechanical Seal.
Page : 32
Fig 18 Double Flushed Mechanical Seal.
Page : 33
4.1.3 Gearbox Disassembly
(after completing 4.1.1 and 4.1.2) - see Fig 20
Page : 34
The following procedure describes complete disassembly of the gearbox.
- Remove oil drain plug (5) and breather (21), drain oil into suitable
container and retain if later inspection is required.
- Remove screws (7) and separate gearbox cover (16) from bearing
housing (20). The gearbox cover (16) is located on dowels (60) and is
sealed to the bearing housing (20) with a gasket (3).
- Remove oil seal (11) and blanking cap (70) from gearbox cover (16).
- Remove retaining rings (18) from gearbox cover (16) and press out
Bearing outer rings (19).
- Remove shims (22) and spacers (2), keep shims and spacers in sets
and identify position.
- Remove screws (23) and retainers (1) from bearing housing (20).
- Remove shafts (9 and 10) from bearing housing (20). Shafts (9 and 10)
will be complete with bearings (24) and shims (73), keep shims in sets
and identify position.
- Remove bearing cups (24) and any associated shims (73) from bearing
housing (20), keep bearing cups (24) and shims (73) in sets and
identify position.
Page : 35
4.1.4 Gearbox Assembly
- see Fig 20
- Install bearing cones (24) to shafts (9 and 10) ensuring they locate against
shaft shoulder. The cones are installed as shown in Fig 21.
Fig 21
- Install shafts (9 and 10) in bearing housing (20). Install remaining bearing
cups (24), shims (73) to nominal value of 0.60mm(0.024"), retainers (1) and
secure with screws (23) tightened to correct torque refer to section 8.2.
- Using a torque wrench check rolling torque of each shaft assembly, refer to
section 8.2. If necessary, adjust amount of shim (73), either by adding
shim (73) to increase rolling torque or removing shim (73) to decrease
rolling torque, until correct rolling torque has been achieved. If shim (73) is
adjusted ensure screws (23) are tightened to correct torque before final
check of rolling torque.
- Install rotors (41) on to shafts (9 and 10) with rotor retainers (35).
WARNING Note: The socket (58) should always be used, the use of other tools may
damage the retainer.
Page : 36
Fig 22
Fig 23
- Install rotors (41) and rotor retainers (35). Check mesh clearance (N)
against the Clearance Chart, refer to section 8.1. To adjust mesh
clearance shims (22) will need to be inserted between the spacer (2) and
the gear (14). As a guide for a mesh clearance change of one unit (say
0.1mm or 0.004"), shims (22) of four units thickness (say 0.4mm or
0.016") need to be inserted. Further, for clockwise movement of the rotor
(when viewed from the rotor end) insert shim (22) in between the spacer
(2) and the gear (14) having a right hand helix, and vice versa, see Fig 24.
Having installed shim (22) ensure lock nuts (12) are tightened to correct
torque, refer to section 8.2, before checking mesh clearance (N). Having
achieved optimum mesh clearances the tab washers (13) can be
secured.
Page : 37
Fig 24
- Install bearing (19) inner races to shafts (9 and 10), positioning against
shoulder on shaft.
- Install inner retaining rings (18), bearing (19) outers, outer retaining rings
(18), lipseal (11), blanking cap (70), filler plug (21), sight glass (6) and
drain plug (5) to cover (16).
- Install cover (16) to bearing housing (20) with gasket (3), locating on
dowels (60), and secure with screws (7) tightened to correct torque, refer
to section 8.2.
Page : 38
4.1.5 Rotorcase, Rotor and Front Cover Assembly
- see Fig 20.
- To adjust front clearance (J), remove rotors (41) and rotorcase (40) and
insert arch shims (15) between the rotorcase (40) and bearing housing
(20).
Note: It is essential that the thickness of arch shim (15) inserted is the
WARNING same at both the top and bottom of the rotorcase (40).
- Install rotors (41) with o-rings (25 and 34) and retainers (35) tightened to
correct torque, refer to section 8.2, using socket (58).
- Check all rotor clearances, front (J), rear (K), top/bottom (L), sides (M)
and mesh (N), refer to section 8.1, Clearance Chart.
- Remove temporary spacers retaining rotorcase (40) and install front cover
(38) with o-ring (39) or gasket (88) and secure with nuts (36) tightened to
correct torque, refer to section 8.2.
Page : 39
4.2 IC20 and IC30 Series Pumps - Disassembly and Assembly.
Fig 25
- Gradually loosen front cover retaining dome nuts (36). Care should be
taken as there may still be residual product and pressure in the pump
head and as the dome nuts are loosened, this will vent to atmosphere.
Page : 40
- Remove front cover (38) using lever slots where necessary and the front
cover o-ring (39).
- For Single Unflushed Mechanical Seals - see Fig 25 and Fig 26.
Fig 26
- Slide rotorcase (40) from gearbox (16), noting it is located on dowels (57),
keep arch shims (15) in appropriate sets if they are to be reused.
Page : 41
- For Single Flushed and
Double Mechanical
Seals - see Fig 25, 27 &
28
Fig 27
Fig 28
Page : 42
Fig 29
- Slide rotorcase (40) from gearbox (16), noting it is located on dowels (57),
keep arch shims (15) in appropriate sets if they are to be reused.
Page : 43
4.2.3 Gearbox Disassembly
(after completing 4.2.1 and 4.2.2) - see Fig 30 & 31.
Page : 44
Fig 31 IC30 Component Parts
Page : 45
The following procedure describes complete disassembly of the gearbox.
- Remove oil drain plug (5) and breather (21), drain oil into suitable
container and retain if later inspection is required.
- Remove screws (7) from bearing housing (20). Separate bearing housing
(20), which is located on dowels (60), from gearbox (16). The bearing
housing (20) is provided with two jacking holes (tapped M10 on IC20, M12
on IC30) which can be used to break the joint.
- Remove oil seal (11) and blanking plug (70) from gearbox (16).
- Remove retaining rings (18) from gearbox (16) and press out bearing (19)
outer rings.
- IC20 Series Pumps Only - Remove lock nuts (12) and tab washers (13).
- IC30 Series Pumps Only - Remove locking screws (13) and lock nuts (12).
- Remove screws (23) and retainers (1) from bearing housing (20).
- Remove shafts (9 and 10) from bearing housing (20). Shafts (9 and 10)
will be complete with bearings (24) and shims (73), keep shims in sets and
identify position.
- Remove bearing cups (24) and any associated shims (73) from bearing
housing (20), keep bearing cups (24) and shims (73) in sets and identify
position.
Page : 46
4.2.4 Gearbox Assembly
- see Fig 30 and Fig 31
- Install bearing cones (24) to shafts (9 and 10) ensuring they locate against
shaft shoulder. The cones are installed as shown in Fig 32.
Fig 32
- Install shafts (9 and 10) to bearing housing (20). Install remaining bearing
cups (24), shims (22) to nominal value of 0.6mm (0.024") retainer (1) and
secure with screws (23) tightened to correct torque, refer to section 8.2.
- Using a torque wrench check rolling torque of each shaft assembly, refer
to section 8.2, if necessary adjust amount of shim (73), either by adding
shim (73) to increase rolling torque or removing shim (73) to decrease
rolling torque until correct rolling torque has been achieved. If shim (73) is
adjusted ensure screws (23) are tightened to correct torque before final
check of rolling torque.
- Install rotors (41) on to shafts (9 and 10) with rotor retainers (35).
Note: The socket (58) should always be used, the use of other tools may
WARNING damage the retainer.
Page : 47
Fig 33
X
Add Remove
Shim X Shim X
- After adjusting shim (73) check rotor front face alignment and rolling
torque.
- Install gear keys (61) to shafts (9 and 10). Install gears (14) to shafts (9
and 10) (note that gear marked 'D' should be installed to the drive shaft (9)
and gear marked 'L' should be installed to lay shaft (10). Also, that
shoulder on gear faces towards bearing (24), see Fig 35) ensuring correct
alignment of timing marks, see Fig 34.
- IC20 Series Pumps Only - Install tab washers (13) and lock nuts (12)
tightened to correct torque, refer to section 8.2. Do not secure tab
washers (13).
- IC30 Series Pumps Only - Install lock nuts (12) tightened to correct torque
refer to section 8.2. Install, but do not tighten lock screws (13).
- Install rotors (41) and rotor retainers (35). Check mesh clearance (N)
against the Clearance Chart, refer to section 8.1. To adjust mesh
clearance shims (22) will need to be inserted between the bearing cone
(24) and the gear (14) shoulder. As a guide for a mesh clearance change
of one unit (say 0.1mm or 0.004") shims (22) of four units thickness (say
0.4mm or 0.016") need to be inserted. Further, for clockwise movement
of the rotor (when viewed from the rotor end) insert shim (22) in between
the bearing cone (24) and the gear (14) having a right hand helix and vice
versa, see Fig 35. Having achieved optimum mesh clearances, the tab
washers (13) (IC20) can be secured, or the lock screws (13) (IC30) can
be tightened to the correct torque, refer to section 8.2.
Page : 48
Note: If shims (22) are to be added to alter rotor timing on an existing
cartridge assembly, it is permissible to cut the shims (22) to allow
them to be inserted without the necessity to remove the bearing
(19) inner race and gear (14) from shaft (9 or 10). Access can be
gained by loosening the lock nut (12) and pulling the gear (14)
along to shaft (9 or 10). If more then one cut shim is to be
installed, then the cuts must be spaced 180 or 120 degrees apart.
If more than three shims (22) need to be added, then full
disassembly is necessary to allow shims (22) to be installed uncut.
Fig 34
Fig 35
Page : 49
- Remove rotor retainers (35) and rotors (41).
- Install bearing (19) inner races to shafts (9 and 10), positioning against
shoulder on shaft.
- Install dowels (57) to gearbox (16) using a liquid retainer (Loctite 640 or
similar). When installed dowels should protrude 3/16" - 1/4" above
gearbox face.
- Install bearing housing (20) to gearbox (16) and secure with screws (7)
tightened to correct torque, refer to section 8.2.
- Install rotorcase (40) to gearbox (16) locating on dowels (57) and secure
with dome nuts (87) tightened to correct torque, refer to section 8.2.
- Check rotor top/bottom clearance (L) and side clearances (M); refer to
section 8.1, Clearance Chart. If adjustment is required loosen screws (7)
fully, then lightly tighten screws (7). Reposition the bearing housing (20) in
relation to gearbox (16) and rotorcase (40) using a suitable drift and
mallet. Once optimum top/bottom (L) and side (M) clearances have been
achieved, tighten screws (7) to correct torque, refer to section 8.2.
- Remove retainers (35), rotors (41), dome nuts (87) and rotorcase (40).
Page : 50
4.2.5 Rotorcase, Rotor and Front Cover Assembly
- see Fig 36
Fig 36
Page : 51
- Install rotorcase (40) to gearbox (16) locating on dowels (57) and secure
with dome nuts (87) tightened to correct torque, refer to section 8.2.
- To adjust front clearance (J), remove rotors (41), nuts (87) and rotorcase
(40) and insert arch shims (15) between rotorcase (40) and gearbox (16).
Note: It is essential that the thickness of arch shim (15) inserted is the
WARNING same at both the top and bottom of the rotorcase.
- Install rotorcase (40) to gearbox (16) securing with dome nuts (87), noting
it locates on dowels (57).
- Install rotors (41) with o-rings (25 and 34) and retainers (35) tightened to
correct torque, refer to section 8.2, using socket (58).
- Check all rotor clearances, front (J), rear (K), top/bottom (L), sides (M)
and mesh (N) refer to Clearance Chart, section 8.1.
- Install front cover (38) with o-ring (39) and secure with nuts (36) tightened
to correct torque, refer to section 8.2.
Page : 52
4.3 IC40 Series Pumps - Disassembly and Assembly
Fig 37
- Gradually loosen front cover retaining dome nuts (36). Care should be
taken as there may still be residual product and pressure in the pump
head and as the dome nuts are loosened, this will vent to atmosphere.
Page : 53
- Remove rotor retainers (35) with socket (58).
Note: The socket (58) should always be used, the use of other tools may
damage the retainer.
- Slide rotorcase (40) from gearbox (16) noting it is located on dowels (57),
keep arch shims (15) in appropriate sets if they are to be reused.
- For Single Flushed and Double Mechanical Seals - see Fig 15, 39 & 40
Page : 54
Fig 39
Fig 40
Page : 55
Fig 41
- Slide rotorcase (40) from gearbox (16), noting it is located on dowels (57),
keep arch shims (15) in appropriate sets if they are to be reused.
Page : 56
4.3.3 Gearbox Disassembly
(after completing 4.3.1 and 4.3.2) - see Fig 42
Page : 57
Before proceeding with disassembly of the gearbox remove product seals; refer
to sections 5.0 for Mechanical Seals or 6.0 for Packed Glands.
- Remove drive key (8), oil drain (5) and breather plugs (21), drain oil into
suitable container and retain if later inspection is required.
- Remove screws (74) and gearbox cover (70). The gearbox cover (70) is
located on dowels (60) and sealed with suitable liquid sealer.
- Loosen by 2 full turns all screws in retainer (82). Once this is done, the
retainer may release its grip. If it does not become free, remove the two
screws which differ in color (these may also have a washer under the
head). Once these screws are removed, tapped holes will be revealed.
Insert two jacking M8 x 40 setscrews into the tapped holes and tighten
until the retainer's grip is broken. Remove the retainer.
- Remove timing gears (14), gear key (61), o-ring (85), spacer (86) and
lipseal (83).
- Support pump with shafts in the vertical position with rotor end up.
- Remove bearing retainers (20), o-rings (3) and shims (73), keep shims
(73) in sets and identify position.
- Remove shafts (9 and 10) from gearbox (16). Shafts (9 and 10) will be
complete with bearings (24), spacers (84), lock nuts (1), lock washers (23)
and bearing inner races (19).
- Remove bearing cups (24) from gearbox (16), keep any further shims (73)
in sets and identify position.
- Remove lock nuts (1), lock washers (23), spacers (84) and bearing cones
(24) from shafts (9 and 10).
- Remove retaining rings (18) and bearing outers (19) from gearbox (16).
Page : 58
4.3.4 Gearbox Assembly
- see Fig 42
- Install bearing cones (24) to shafts (9 and 10) ensuring they locate against
the shaft shoulder. The cones are installed as shown in Fig 43.
Fig 43
- Install spacers (84), tab washers (23) and lock nuts (1) to shafts (9 and
10) tightening to correct torque, refer to section 8.2. Secure tab washers.
- Install bearing (19) inner races to shafts (9 and 10) positioning against
shoulder on shaft.
- Install bearing (19) outer races and retaining rings (18) to gearbox (16).
- Support gearbox (16) in a vertical position and install shafts (9 and 10) to
gearbox (16).
- Install remaining bearing cups (24), shims (73) to nominal value of 0.6mm
(0.024"), o-rings (3), retainers (20) and secure with screws (7) tightening
to correct torque, refer to section 8.2.
- Using a torque wrench, check rolling torque of each shaft assembly, refer
to section 8.2, if necessary adjust amount of shim (73) either by adding
shim (73) to increase rolling torque or removing shim (73) to decrease
rolling torque until correct rolling torque has been achieved. If shim is
adjusted ensure screws (23) are tightened to correct torque before final
check of rolling torque.
- Install rotors (41) onto shafts (9 and 10) with rotor retainers (35).
WARNING Note: The socket (58) should always be used, the use of other tools may
damage the retainer.
Page : 59
(73) of thickness equal to the difference (X) from beneath the lower rotors
bearing retainer (20) and reposition under the front bearing (24) cup.
Fig 44
- After adjusting shim (73) check rotor front face alignment and rolling torque.
- Install lipseal (83) to gearbox (16). Install spacer (86) and o-ring (85) to drive
shaft (9). Install gear key (61) to drive shaft (9).
- Install tab washer (13) and lock nut (12) tightening to correct torque, refer to
section 8.2. Secure tab washer (13).
- Rotate shafts (9 and 10) so as to position the gaps made by the missing
splines in the vertically uppermost positions, see Fig 45.
Page : 60
- Lubricate retainer (82) with oil and mount to timing gear (14). Do not tighten.
Fig 45
- Install rotors (41) and rotor retainers (35) to shafts (9 and 10).
- Check rotor mesh clearance (N) against Clearance Chart, refer to section
8.1. Adjustment of mesh clearance is made by rotating the shafts (9 and
10). Having achieved optimum mesh clearance (N), retainer (82) can be
tightened to correct torque, refer to section 8.2, taking note of typical
tightening sequence, see Fig 46.
Fig 46
- After tightening of retainer (82) check mesh clearance (N) refer to section
8.1, Clearance Chart.
Page : 61
- Apply liquid sealant (Loctite 573 or similar) to sealing area of gearbox
cover (70) and install to gearbox (16), locating on dowels (60) and
securing with screws (74), tightened to correct torque, refer to section 8.2.
Fig 47
- To adjust front clearance (J) remove rotor retainers (35), rotors (41), nuts
(87) and rotorcase (40) and insert arch shims (15) between the rotorcase
(40) and gearbox (16).
Note: It is essential that the thickness of arch shims (15) inserted is the
same at both the top and bottom of the rotorcase.
Page : 62
4.4 IC50 Series Pumps - Disassembly and Assembly
Page : 63
- Follow recommended shutdown procedure, refer to section 3.5.
- Gradually loosen front cover retaining dome nuts (36). Care should be
taken as there may still be residual product and pressure in the pump
head and as the dome nuts are loosened, this will vent to atmosphere.
- Remove front cover (38), using lever slots where necessary, and the front
cover o-ring (39).
Note: The tool (58) should always be used, the use of other tools may
WARNING damage the rotor cap.
- Loosen by 2 full turns all screws in rotor retainer (53). Once this is done
the retainer may release its grip. If it does not, loosen further the screws
until the assembly become free to remove.
(On some brands of locking device there are two screws that are different
in color (these may also have a washer under the head). Once these
screws are removed tapped holes will be revealed. By inserting two
jackscrews (M8 x 40 setscrews), into the tapped holes and tightening, the
retainer's grip is broken. Remove the retainers (53)).
Page : 64
4.4.2 Rotorcase Removal
(after completing 4.4.1) - see Fig 48
Fig 49
- Slide rotorcase (40) from gearbox (16), noting it is located on dowels (57).
For Single Flushed and Double Mechanical Seals - see Fig 48, 50 & 51
Page : 65
Fig 50
Fig 51
Page : 66
Fig 52
- Slide rotorcase (40) from gearbox (16), noting it is located on dowels (57).
Page : 67
4.4.3 Gearbox Disassembly
(after completing 4.4.1 and 4.4.2) - see Fig 53.
Page : 68
The following procedure describes complete disassembly of the gearbox.
- Remove oil drain (5) and breather plugs (21), drain oil into suitable
container and retain (inspection may later be required).
- Remove screws (74) and gearbox cover (70). The gearbox cover (70) is
located on dowels (60) and sealed with suitable liquid sealant.
- Loosen by two full turns all screws in retainer (82) on the lay shaft (10).
Once this is done the retainer may release its grip. If it does not become
free identify and remove the three screws which differ in color (these may
also have a washer under the head). Once these screws are removed
tapped holes will be revealed. Insert three jackscrews (M10 x 40
setscrews), into the tapped holes and tighten until the retainer's grip is
broken. Remove the retainer.
- Remove timing gears (14), gear key (61), spacer (86), o-ring (85) and
lipseal (83).
- Support pump with shafts in the vertical position with rotor end up.
- Remove shafts (9 and 10) from gearbox (16). Shafts (9 and 10) will be
complete with pins (76), spacers (15), bearings (24), spacers (18 and 84),
tab washers (23), lock nuts (1), bearings (19) and spacers (22 and 73).
- Remove bearings (19) complete with spacers (22 and 73) from shafts (9
and 10) keep them in matched sets and identify position.
- Remove bearings (24) complete with spacers (18 and 84) from shafts (9
and 10), keep them in matched sets and identify position.
- Remove shaft sleeve drive pins (76) from shafts (9 and 10), remove
spacers (15), note fitting position.
Page : 69
4.4.4 Gearbox Assembly
- see Fig 53
- Install bearings (24) complete with spacers (18 and 84) to shafts (9 and 10)
ensuring correct positioning of all components as either removed in 4.4.3.
above or supplied as new replacement set, see Fig 54.
- Install spacers (15), product seal sleeves (28 or 66), rotor keys (78) and
rotors (41) to shafts (9 and 10) and secure with rotor retainers (35) using tool
(58).
Fig 54
Fig 55
Page : 70
- Install tab washers (23) and lock nuts (1) tightening to correct
torque, refer to section 8.2. Secure tab washers.
Note: Ensure that the cups of the rear most bearings (24) are in position
on inner races before proceeding.
- Install bearings (19) complete with spacers (22 and 73) to shafts (9 and 10)
ensuring correct positioning of all components as either removed in 4.4.3
above or as supplied as new replacement set, see Fig 55.
- Support gearbox (16) in a vertical position and install shafts (9 and 10) to
gearbox (16).
- Install retainers (20) and o-rings (3) and secure with screws (7) tightening to
correct torque, refer to section 8.2.
- Install lipseal (83) to gearbox (16). Install o-ring (85), spacer (86) and key
(61) to drive shaft (9).
- Install tab washer (13) and lock nut (12) tightening to correct torque, refer to
section 8.2. Secure tab washer (13).
- Rotate shafts (9 and 10) such that keyways for rotor keys are vertically
upwards.
- Lubricate retainer (82) with oil and install to timing gear (14). Do not tighten.
- Clamp gear (14) to shaft (10) using tool (58) and associated stud and nut,
ensuring that two screws in retainer (82) are visible through holes in tool (58).
- Check rotor mesh clearance (N) against Clearance Chart, refer to section 8.1.
Adjustment of mesh clearance is made by rotating the shafts (9 and 10).
Having achieved optimum mesh clearance (N), partially tighten visible screws
in retainer (82), to clamp gear in place. Remove tool (58) with associated stud
and nut. Fully tighten screws in retainer (82) to correct torque, refer to section
8.2, taking note of typical tightening sequence, see Fig 56.
- After tightening of retainer (82) check rotor mesh clearance (N); refer to
section 8.1 (Clearance Chart).
Page : 71
Fig 56
- Apply liquid sealant (Loctite 573 or similar) to sealing area of gearbox cover
(70) and install to gearbox (16), locating on dowels (60) and securing with
screws (74), tightened to correct torque, refer to section 8.2.
- Remove rotor retainers (35) using tool (58), rotors (41) and spacers (15)
- Install spacers (15) and product seal sleeves (28 or 66) to shafts (9 and 10).
- Install rotorcase (40) to gearbox (16) locating on dowels (57) and secure
with dome nuts (87) tightened to correct torque, refer to section 8.2.
- Clamp one rotor (41) to shaft (9 or 10) using tool (58) and associated stud
and nut see Fig 57.
Page : 72
Fig 57
- Using a depth
micrometer or similar device, measure front clearance (J); refer to section
8.1, Clearance Chart, between the rotorcase and clamped rotors front face
and check that this corresponds to the appropriate clearance as indicated
on the Clearance Chart. Note any discrepancy in front clearance (J).
- Repeat clamping and front clearance (J) measurement for other rotor
(again note any discrepancy in front clearance (J).
- Remove rotors (41), rotorcase (40) and product seal sleeves (28 or 66).
- If any discrepancies were noted in front clearances (J), between rotors and
front face of rotorcase, then spacers (15) will require machining to shorten
them to achieve the correct front clearance (J), refer to section 8.1.
Note: If it is found that the measured front clearance (J) is greater than
that shown in the Clearance Chart, refer to section 8.1, then new
spacers (15) will need to be obtained and machined to the correct
lengths to achieve correct front clearance (J).
- After any machining of spacers (15), check front clearances (J) for both
rotors, refer to section 8.1, Clearance Chart.
- Install spacers (15) to shafts (9 and 10) ensuring they are correctly located.
- Install pins (76) to shafts (9 and 10) using a liquid retainer (Loctite 640 or
similar).
Page : 73
- Install rotorcase (40) to gearbox (16) locating onto dowels (57) and securing
with dome nuts (87) tightened to correct torque, refer to section 8.2.
- Lubricate retainers (53) with oil and install to shafts (9 and 10).
- Clamp one rotor (41) to shaft (9 or 10) using tool (58) and associated stud
and nut, see Fig 57, ensuring that two of the screws in retainer (53) are
visible through holes in tool (58).
- Repeat clamping and retainer (53) tightening procedure for other rotor.
- Install o-rings (34) and retainers (35) tightening to correct torque refer to
section 8.2, using tool (58).
- Check all rotor clearances, front (J), rear (K), top/bottom (L), sides (M)
and mesh (N), refer to section 8.1, Clearance Chart.
- Install front cover (38) with o-ring (39) and secure with nuts (36) tightened
to correct torque, refer to section 8.2.
Page : 74
5.0 Classic Mechanical Seal Removal & Replacement.
- Remove any sharp corners and burrs that may damage any elastomers
such as o-rings or lipseals.
- Ensure that all seal component fitting bores and housings are thoroughly
cleaned before installation.
- The seal faces and seats must be handled with care and cleaned
thoroughly before installation.
- Ensure that seal faces are undamaged and the o-rings are not cut,
swollen or cracked.
- Ensure when installing seals with brittle faces and seats such as silicon
carbide that extra care is taken.
Page : 75
5.2 Mechanical Seals IC10, IC20, IC30 and IC40 Series Pumps
Fig 58
Fig 59
Page : 76
5.2.2 Single Mechanical Seal Replacement
See Fig 58 for IC10 and Fig 59 for IC20, IC30 and IC40
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
Note: On IC10 models the stationary seal seat (31) has a location recess
which fits over the anti-rotation washer (74).
On IC20, IC30 and IC40 models the stationary seal seat (31) has a triangular
shape, which must locate fully into the rotorcase (40) bore.
- Install rotary seal cartridges (27, 28, 29, 33) with o-ring (32) to shafts (9
and 10) positioning to correct setting distance, see Fig 60 and tighten
screws (27) to correct torque, refer to section 8.2.
Fig 60
- Install rotorcase (40), o-rings (25), rotors (41), o-rings (34), rotor retainers
(35) and front cover (38), refer to sections 4.1.5 (IC10) or 4.2.5
(IC20/IC30) or 4.3.5 (IC40).
Page : 77
5.2.3 Single Flushed Mechanical Seal Removal
See Fig 61 for IC10 and Fig 62 for IC20, IC30 and IC40
Fig 61
Page : 78
Fig 62
Page : 79
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25) and rotorcase (40), refer to sections 4.1.1 and 4.1.2 (IC10) or
4.2.1 and 4.2.2 (IC20/IC30) or 4.3.1 and 4.3.2 (IC40).
- Loosen but do not remove screws (27), which secure rotary seal
cartridges (27, 28, 29, 33) to shafts (9 and 10).
Note: Access to screws (27) is through the flush pipe connections of housing (44).
- Remove rotary seal cartridges (27, 28, 29, and 33) with o-ring (32) from
shafts (9 and 10).
- Remove housing(s) (44) complete with lipseals (43) and o-ring(s) (42)
from shafts (9 and 10).
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
WARNING Note: On IC10 models the stationary seal seat (31) has a location recess which
fits over the anti-rotation washer (74).
On IC20, IC30 and IC40 models the stationary seal seat (31) has a triangular
shape, which must locate fully into the rotorcase (40) bore.
- Install rotary seal cartridges (27, 28, 29, 33) to shafts (9 and 10)
positioning to correct setting distance, see Fig 61 and tightening screws
(27) to correct torque, refer to section 8.2.
Note: Access to screws (27) is through the flush pipe connections of housing (44).
- Install rotorcase (40), o-rings (25), rotors (41), o-rings (34), rotor retainers
(35) and front cover (38) refer to sections 4.1.5 (IC10) or 4.2.5 (IC20/IC30)
or 4.3.5 (IC40).
- Secure housing(s) (44) to rotorcase (40) with screws (36) ensuring correct
location onto dowels (54).
Page : 80
5.2.5 Double Flushed Mechanical Seal Removal - IC10
See Fig 63.
Fig 63
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25) and rotorcase (40), refer to sections 4.1.1 and 4.1.2.
- Loosen but do not remove screws (27), which secure rotary seal
cartridges (27, 46, 51, 52, 53) to shafts (9 and 10).
Note: Access to screws (27) is through the flush pipe connections of housing (47).
- Remove rotary seal cartridges (27, 46, 51, 52, and 53) with o-rings (49)
from shafts (9 and 10).
- Remove housing (47) complete with o-ring (42), stationary seal seats (48)
and o-rings (45) from shafts (9 and 10).
- Remove stationary seal seats (48), o-rings (45) and o-ring (42) from
housing (47).
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
Page : 81
5.2.6 Double Flushed Mechanical Seal Replacement - IC10
See Fig 63
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
Note: The stationary seal seat (31) has a location recess which fits over the
WARNING
anti-rotation washer (74).
- Install stationary seal seats (48) to housing (47) ensuring correct location
of o-ring (45).
- Clean faces of outboard seal (46 and 48) use a soft tissue and suitable
solvent based cleaner for best results.
- Install rotary seal cartridges (27, 46, 51, 52, and 53) with o-ring (49) to
shafts (9 and 10).
Note: For pumps installed with flange type rotorcase (40) connections, it may
be easier to set the position of the rotary seal cartridge (27, 46, 51, 52, 53)
onto the shafts (9 and 10) using the setting distance, see fig 60, before
installing the rotorcase (40). Screws (27) must be tightened to the correct
torque refer to section 8.2.
- Install rotorcase (40), o-rings (25), rotors (41), o-rings (34), rotor retainers
(35) and front cover (38), refer to section 4.1.5.
- Secure housing (47) to rotorcase (40) with screws (26) ensuring correct
location onto dowels (54).
Note: Access to screws (27) is through the flush pipe connections of housing (47).
Page : 82
5.2.7 Double Flushed Mechanical Seal Removal IC20, IC30 and IC40
See Fig 64.
Fig 64
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25) and rotorcase (40), refer to sections 4.2.1 and 4.2.2 (IC20/IC30)
or 4.3.1 and 4.3.2 (IC40).
- Loosen but do not remove screws (75), which secure rotary seal
cartridges (29, 46, 51, 52, 75) to shafts (9 and 10).
Note: Access to screws (79) is through the flush connections of housings (44).
- Remove rotary seal cartridges (29, 46, 51, 52, and 75) with o-ring (32)
from shafts (9 and 10).
- Remove housings (44) from shafts (9 and 10) complete with stationary
seal seats (48), o-rings (45) and o-rings (42).
- Remove stationary seal seats (48), o-rings (45) and o-rings (42) from
housings (44).
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
Page : 83
5.2.8 Double Flushed Mechanical Seal Replacement - IC20, IC30 & IC40
See Fig 64
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
Note: The stationary seal seats (31) have a triangular shape which must locate
WARNING
fully into the rotorcase (40) bore.
- Install stationary seal seats (48) to housings (44) ensuring both correct
location of o-ring (45) and of drive slots in stationary seal seats (48) over
pins in housings (44).
- Clean faces of outboard seal (46 and 48) use a soft tissue and a suitable
solvent based cleaner for best results.
- Install rotary seal cartridges (29, 32, 46, 51, 52, 75) to shafts (9 and 10).
Note: For pumps installed with flange type rotorcase (40) connections, it may
be easier to set the position of the rotary seal cartridge (29, 32, 46,51,
52, 75) onto the shafts (9 and 10) using the setting distance, see Fig 61,
before installing the rotorcase (40). Screws (27) must be tightened to the
correct torque refer to section 8.2.
- Install rotorcase (40), o-rings (25), rotors (41), o-rings (34), rotor retainers
(35) and front cover (38) refer to sections 4.2.5 (IC20/IC30) or 4.3.5
(IC40).
- Secure housings (44) to rotorcase (40) with screws (26) ensuring correct
location onto dowels (54).
Note: Access to screws (75) is through the flush connections of housings (44).
Page : 84
5.3 Mechanical Seals - IC50 Series Pumps.
Fig 65
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25) and rotorcase (40), refer to sections 4.4.1 and
4.4.2.
- Remove rotary seal cartridges (27, 28, 29, and 33) with o-ring (32) from
shafts (9 and 10) by simply sliding off. Do not loosen screws (27).
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
Page : 85
5.3.2 Single Mechanical Seal Replacement
See Fig 66
Fig 66
Page : 86
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25) and rotorcase (40) refer to sections 4.4.1 and
4.4.2.
- Remove rotary seal cartridges (27, 28, 29, and 33) with o-ring (32) from
shafts (9 and 10) by simply sliding off. Do not loosen screws (27).
- Remove housings (44) complete with lipseals (43) and o-rings (42) from
shafts (9 and 10).
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
Note: The stationary seal seat (31) has a triangular shape, which must locate
WARNING fully into the rotorcase (40), bore.
- Install rotary seal cartridges (27, 28, 29, and 33) with o-ring (32) to shafts
(9 and 10) ensuring engagement of drive slots with pins (76) in shafts (9
and 10).
- Install rotorcase (40), o-rings (25), rotors (41), retainers (53), o-rings (34),
rotor caps (35) and front cover (38), refer to section 4.4.5.
Page : 87
5.3.5 Double Flushed Mechanical Seal Removal
See Fig 67
Fig 67
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25) and rotorcase (40), refer to sections 4.4.1 & 4.4.2.
- Remove rotary seal cartridges (28, 29, 33, 46, 75) with o-rings (32) and
(45) from shafts (9 and 10) by simply sliding off. Do not loosen screws
(75).
- Remove housings (47) from shafts (9 and 10) complete with stationary
seal seats (48), o-rings (49) and o-rings (42).
- Remove stationary seal seats (48), o-rings (45) and o-rings (42) from
housings (47).
Page : 88
- Remove stationary seal seats (31) and o-rings (30) from rotorcase (40).
- Install stationary seal seats (31) to rotorcase (40) ensuring correct location
of o-rings (30).
Note: The stationary seal seat (31) has a triangular shape, which must locate
WARNING
fully into the rotorcase (40), bore.
- Install stationary seal seats (48) to housings (47) ensuring both correct
location of o-rings (49) and of drive slots in rotary seal cartridges (28, 29,
33, 43, 46, 76) over pins in housings (47).
- Clean faces of outboard seal (46 and 48) use a soft tissue and a suitable
solvent based cleaner for best results.
- Install rotary seal cartridges (28, 29, 33, 46, 76) with o-ring (32) and (45)
to shafts (9 and 10) ensuring engagement of drive slots with pins (76) in
shafts (9 and 10).
- Install rotorcase (40), o-rings (25), rotors (41), retainers (53), o-rings (34),
rotor caps (35) and front cover (38), refer to sections 4.4.5.
Page : 89
5.4 Fitting of DIN24 960 form KU Seals
Fig 68
Note: Fitting of DIN24 960 form KU mechanical seals to IC20 or IC30 series
pumps will necessitate rotorcase modification. Contact Viking Pump for
specific details.
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25), nuts (87) and rotorcase (40), (which is located on dowels (57)),
refer to sections 4.2.1 and 4.2.2 (IC20/IC30) or 4.3.1 and 4.3.2 (IC40).
- Remove all parts of the existing shaft seal arrangement including any
stationary and rotary parts, housings, o-rings etc.
Page : 90
Note: If the seal manufacturer has produced the seal to a shorter length than
the dimension specified in DIN24 960 and given in the following table,
then dimension A must be increased accordingly.
Fig 69
- Install assembled seal stationary parts and housing (44) onto shafts (9
and 10) pushing assemblies as far as possible along shafts (9 and 10).
- Install rotorcase (40), (which locates on dowels (57)), nuts (87), o-rings
(25), rotors (41), o-rings (34), rotor retainers (35), and front cover (38),
refer to section 4.2.5, (IC20/IC30) or 4.3.5, (IC40).
- Move assembled stationary seal parts and housings (44 or 47) forward
along shafts (9 and 10) to install against rotorcase (40), locating onto
dowels (54) and securing with screws (26).
Page : 91
5.4.2 Conversion of Shaft Seal Arrangement to DIN24 960 Form KU Internally
Mounted Single Mechanical Seal - IC50 Series Pumps
See Fig 69 & Fig 70
Fig 70
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25), dome nuts (87) and rotorcase (40) (which is
located on dowels (57)), refer to sections 4.4.1 and 4.4.2.
- Remove all parts of the existing shaft seal arrangement including any
stationary and rotary parts, housings, sleeves, o-rings etc.
- Apply liquid retainer (Loctite 270 or similar) to studs (26) and install studs
(26) to rotorcase (40).
Note: If the seal manufacturer has produced the seal to a shorter length than
the dimension specified in DIN24 960 then dimension A must be
increased accordingly.
Page : 92
- Following the manufacturers instructions, install stationary parts of DIN
seals into housings (47).
- Install assembled seal stationary parts and housings (47) onto shafts (9
and 10) pushing assemblies as far as possible along shafts (9 and 10).
Note: It is very important that the position of the o-ring groove located on the
inside diameter of the rotary seal part is investigated to ensure that the o-ring
position does not conflict with the drive pin and for shaft (9 and 10) to sleeve
(66) interface. For minimum dimension see Fig 71.
- Install rotorcase (40), (which locates on dowels (57)), dome nuts (87), o-
rings (25), rotors (41), retainers (53), o-rings (34), rotor caps (35), and
front cover (38), refer to section 4.4.5.
- Move assembled stationary seal parts and housings (47) forward along
sleeves (66) to fit against rotorcase (40), and secure with nuts (54).
Page : 93
6.0 Classic Packed Gland Seals
- Packed gland seals are a simple but effective means of shaft sealing.
They will provide optimum performance only if installed carefully and
according to instructions.
- Remove any sharp corners and burrs that may damage packing rings or
any elastomers such as o-rings or lipseals.
- Always inspect shaft sleeves for wear when the packed gland seal is
dismantled or serviced.
- Ensure that all seal component fitting bores, housings, followers, sleeves
etc. are thoroughly cleaned before installation.
- When inserting packing rings ensure that they are installed neatly to the
rotorcase bores without loose strands.
- Ensure that ring joint gaps are set at approximately 120 to each other
around the rotorcase bores so as not to create a leakage path.
Page : 94
6.2 Packed Gland Seals - IC10, IC20, IC30 and IC40 Series Pumps
Fig 71
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25), dome nuts (87) and rotorcase (40) refer to sections 4.1.1 and
4.1.2 (IC10) or 4.2.1 and 4.2.2 (IC20/IC30) or 4.3.1 and 4.3.2 (IC40).
Note: It is not recommended that gland tubes (64) are removed unless
replacement is necessary. They may be damaged during removal.
- Remove sleeves (60) and slingers (62) from shafts (9 and 10).
Page : 95
6.2.2 Packed Gland Seal Replacement
See Fig 71
Note: If gland tubes (64) have been removed from rotorcase (40) they should
be installed at this point. Apply liquid retainer (Loctite 640 or similar) to
one end of tubes (64) on outside diameters to a width of approximately
5mm (3/16"), and similarly apply to inside diameters of rotorcase (40)
bores. Press tubes (64) into rotorcase (40) bores. Remove any excess
liquid retainer. Allow sufficient time for liquid retainer to fully cure.
- Install packing rings (65) and followers (67) to gland tubes (64).
- Install rotorcase (40), dome nuts (87), o-rings (25), rotors (41), o-rings
(34), rotor retainers (35) and front cover (38), refer to section 4.1.5 (IC10)
4.2.5 (IC20/IC30) or 4.3.5 (IC40).
- Once pump is installed and started adjust packed gland seals by a slow
and even tightening of nuts (81).
Page : 96
- Remove front cover (38), rotor retainers (35), o-rings (34), rotors (41), o-
rings (25), dome nuts (87) and rotorcase (40), (which is located on dowels
(57)), refer to sections 4.1.1 and 4.1.2, (IC10) or 4.2.1 and 4.2.2,
(IC20/IC30) or 4.3.1 and 4.3.2, (IC40).
- Remove packing rings (65) and lantern ring (88) from housing (94) bores,
carefully noting location of lantern rings (88).
- Remove sleeves (66) and slingers (62) from shafts (9 and 10).
Note: If housings (94) have been removed from rotorcase (40) they should be
installed at this point. Apply liquid retainer (Loctite 640 or similar) to
outside diameter of location spigots of housings (94), and similarly apply
to inside diameters of rotorcase (40) bores. Install housings (94) over
studs (80) and press into rotorcase (40) bores. Remove any excess liquid
retainer. For models IC30, install nuts (81) to studs (80).
- Install packing rings (65) and lantern rings (88) to housing (94) bores,
ensuring correct location of lantern rings such that they align with the
liquid supply connection holes in housings (94).
- Install rotorcase (40), (which locates onto dowels (57)), dome nuts (87), o-
rings (25), rotors (41), o-rings (34), rotor retainers (35) and front cover
(38), refer to section 4.1.5 (IC10), 4.2.5, (IC20/IC30) or 4.3.5 (IC40).
Page : 97
6.3 Packed Gland Seals - IC50 Series Pumps.
Fig 73
-
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25), dome nuts (87) and rotorcase (40), refer to
sections 4.4.1 and 4.4.2.
- Remove followers (67), sleeves (66), slingers (62), packing rings (65) and
sleeves (63).
- Install slingers (62) and sleeves (66) to shafts (9 and 10) ensuring
engagement of drive slots with pins (76) in shafts (9 and 10).
- Install sleeves (63), packing rings (65) and followers (67) to gland tubes
(64).
- Install nuts (81) to studs (80) but do not tighten.
- Install rotorcase (40); dome nuts (87), o-rings (25), rotors (41), retainers
(53), o-rings (34), rotor caps (35) and front cover (38) refer to section 4.4.5.
- Once pump is installed and started adjust packed gland seals by slow and
even tightening of nuts (81).
Page : 98
6.3.3 Flushed Packed Gland Seal Removal
See Fig 74.
Fig 74
- Remove front cover (38), rotor caps (35), o-rings (34), rotors (41), o-rings
(25), dome nuts (87) and rotorcase (40) (which is located on dowels (57)),
refer to sections 4.4.1 and 4.4.2.
- Remove packing rings (65) and lantern rings (88) from tube (94) bores,
carefully noting location of lantern rings (88).
- Remove sleeves (66) and slingers (62) from shafts (9 and 10).
Page : 99
6.3.4 Flushed Packed Gland Seal Replacement
See Fig 74
- Install slingers (62) and sleeves (66) to shafts (9 and 10) ensuring
engagement of drive slots over pins (76) in shafts (9 and 10).
- Install packing rings (65) and lantern rings (88) to gland tube (94) bores,
ensuring correct location of lantern rings such that they align with the
liquid supply connection holes in tubes (94).
- Install rotorcase (40), (which locates onto dowels (57)), dome nuts (87), o-
rings (25), rotors (41), retainers (53), o-rings (34), rotor caps (35) and front
cover (38), refer to section 4.4.5.
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25), dome nuts (87) and rotorcase (40) (which is
located on dowels 57)), refer to sections 4.4.1 and 4.4.
- Remove all parts of the existing shaft seal arrangement including any
stationary and rotary parts, housings, sleeves, o-rings etc.
- Apply liquid retainer (Loctite 640 or similar) to outer end of tubes (64) on
outside diameters to a width of approximately 5mm (3/16"), see Fig 75.
Fig 75
- Press tubes (64) into rotorcase (40) bores. Remove any excess liquid retainer.
- Apply liquid retainer (Loctite 270 or similar) to studs (80) and install studs (80)
to rotorcase (40).
- Follow instructions for packed gland replacement, refer to section 6.3.2.
Page : 100
6.3.6 Seal Conversion to Flushed Packed Gland (With Shaft Sleeve)
See Fig 75
- Remove front cover (38), rotor caps (35), o-rings (34), retainers (53),
rotors (41), o-rings (25), dome nuts (87) and rotorcase (40) (which is
located on dowels (57)), refer to sections 4.4.1 and 4.4.2.
- Remove all parts of the existing shaft seal assembly including any
stationary and rotary parts, housings, sleeves o-rings etc.
Fig 77
- Install tubes (94) to rotorcase (40) bores. Remove any excess liquid
retainer.
Note: The tubes (94) have a triangular shape which must locate fully into the
rotorcase (40) bores.
- The tubes (94) have two sets of drillings for the flush/quench liquid to pass
through. Ensure that one set of drillings aligns with the liquid supply
connection holes in rotorcase (40) bores.
- Apply liquid retainer (Loctite 270 or similar) to studs (80) and install studs
(80) to rotorcase (40).
Page : 101
7.0 Flushed Product Seals Auxiliary Services
i) Terminology.
a) "Quench"
- To provide a liquid barrier that is not induced to flow through the
seal area by any external means.
b) "Flush"
- To provide a liquid barrier that is induced to flow through the seal
area by an external means.
The media used for quenching or flushing a seal area must be fully compatible
WARNING with the pumped media, and the relevant materials of construction of the
pump.
This seal arrangement requires a supply of media to the outboard side of the
mechanical seal to quench or flush the seal area. The nature of the pumped
media and the specific duty conditions will determine whether a quench or a
flush is required.
For a suitable flush, the media must be supplied at a flowrate of one gallon
per minute per shaft seal.
WARNING Note: The limiting flush or quench pressure in any application is 10 psig.
Page : 102
7.2 Double Mechanical Seal (For High Pressure Flush)
- See Fig 18 (IC10) and Fig 28 (IC20, IC30, IC40) and Fig 51 (IC50)
The flush media must be supplied at a flowrate of one gallon per minute per
shaft seal assembly.
The flush pressure must be a minimum of 15 psi greater than the maximum
discharge pressure created by, or the maximum suction pressure applied to,
the pump, whichever is the greater.
WARNING Note: The limiting flush pressure in any application is 188 psig.
Note: The liquid supply connections to flushed seals are made by threaded ports
on the sides of the seal housings (two per seal, except IC10 & IC20
models, which have common seal housings encompassing both shaft
seals). For models IC30 to IC50 inclusive, one port on each housing
should be used for flush 'in' and the other for flush 'out'. The pipework
should be arranged to provide an independent flush to each seal.
Page : 103
8.0 Specifications
Page : 104
Millimeters x 0.01 Inches x 0.001
A B C D A B C D
Rotor Temp Rotor Temp
Model (Front) (Rear) (Top/Bottom) (Side) E (Mesh) Model (Front) (Rear) (Top/Bottom) (Side) E (Mesh)
Class Max (C) Class Max (F)
Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max
A 70 7 9 3 10 5 13 13 19 18 A 150 2.8 3.5 1.2 3.9 2 5.1 5.1 7.5 7.1
IC10/0005 B 100 9 11 5 12 7 14 15 21 18 IC10/0005 B 210 3.5 4.3 2 4.7 2.8 5.5 5.9 8.3 7.1
C 150 11 13 7 14 9 16 17 23 18 C 300 4.3 5.1 2.8 5.5 3.5 6.3 6.7 9.1 7.1
A 70 10 12 6 13 8 15 17 22 18 A 150 3.9 4.7 2.4 5.1 3.1 5.9 6.7 8.7 7.1
IC10/0008 B 100 12 14 9 16 10 17 18 24 18 IC10/0008 B 210 4.7 5.5 3.5 6.3 3.9 6.7 7.1 9.4 7.1
C 150 15 17 11 18 13 20 21 27 18 C 300 5.9 6.7 4.3 7.1 5.1 7.9 8.3 10.6 7.1
A 70 13 15 9 16 11 18 19 25 18 A 150 5.1 5.9 3.5 6.3 4.3 7.1 7.5 9.8 7.9
IC10/0011 B 100 16 18 13 20 13 20 21 27 20 IC10/0011 B 210 6.3 7.1 5.1 7.9 5.1 7.9 8.3 10.6 7.9
C 150 20 22 17 24 16 24 24 30 20 C 300 7.9 8.7 6.7 9.4 6.3 9.4 9.4 11.8 7.9
A 70 14 16 10 17 15 25 23 31 20 A 150 5.5 6.3 3.9 6.7 5.9 9.8 9.1 12.2 9.8
IC20/0020 B 100 16 18 13 20 18 28 25 33 25 IC20/0020 B 210 6.3 7.1 5.1 7.9 7.1 11 9.8 13 9.8
C 150 18 20 14 21 20 30 28 36 25 C 300 7.1 7.9 5.5 8.3 7.9 11.8 11 14.2 9.8
A 70 15 17 16 23 23 33 30 38 25 A 150 5.9 6.7 6.3 9.1 9.1 13 11.8 15 11
IC20/0031 B 100 19 21 19 26 29 39 37 45 28 IC20/0031 B 210 7.5 8.3 7.5 10.2 11.4 15.4 14.6 17.7 11
C 150 21 23 22 29 32 42 39 47 28 C 300 8.3 9.1 8.7 11.4 12.6 16.5 15.4 18.5 11
A 70 18 20 17 24 22 35 30 40 28 A 150 7.1 7.9 6.7 9.4 8.7 13.8 11.8 15.7 13.8
IC30/0069 B 100 22 24 21 28 27 40 35 46 35 IC30/0069 B 210 8.7 9.4 8.3 11 10.6 15.7 13.8 18.1 13.8
C 150 24 26 24 31 33 46 40 51 35 C 300 9.4 10.2 9.4 12.2 13 18.1 15.7 20.1 13.8
A 70 24 26 25 32 44 58 51 63 35 A 150 9.4 10.2 9.8 12.6 17.3 22.8 20.1 24.8 15
IC30/0113 B 100 29 31 30 37 47 61 54 66 38 IC30/0113 B 210 11.4 12.2 11.8 14.6 18.5 24 21.3 26 15
C 150 33 35 33 40 53 67 60 72 38 C 300 13 13.8 13 15.7 20.9 26.4 23.6 28.3 15
A 70 32 37 28 39 30 45 46 57 38 A 150 12.6 14.6 11 15.4 11.8 17.7 18.1 22.4 15.7
IC40/0180 B 100 35 40 32 43 35 51 51 63 40 IC40/0180 B 210 13.8 15.7 12.6 16.9 13.8 20.1 20.1 24.8 15.7
C 150 40 45 38 49 42 57 57 69 40 C 300 15.7 17.7 15 19.3 16.5 22.4 22.4 27.2 15.7
A 70 40 45 40 53 45 55 61 68 40 A 150 15.7 17.7 15.7 20.9 17.7 21.7 24 26.8 17.7
IC40/0250 B 100 49 54 46 59 50 65 66 78 45 IC40/0250 B 210 19.3 21.3 18.1 23.2 19.7 25.6 26 30.7 17.7
C 150 55 60 53 66 59 74 75 86 45 C 300 21.7 23.6 20.9 26 23.2 29.1 29.5 33.9 17.7
B 100 43 46 41 54 41 64 66 86 45 B 210 16.9 18.1 16.1 21.3 16.1 25.2 26 33.9 21.7
IC50/0351 IC50/0351
D 180 58 61 56 69 41 64 66 86 55 D 350 22.8 24 22 27.2 16.1 25.2 26 33.9 21.7
B 100 50 53 48 62 51 74 76 86 55 B 210 19.7 20.9 18.9 24.4 20.1 29.1 29.9 37.8 21.7
IC50/0525 IC50/0525
D 180 65 68 63 77 51 74 76 86 55 D 350 25.6 26.8 24.8 30.3 20.1 29.1 29.9 37.8 21.7
Page : 105
8.2 Fasteners & Torque Settings.
Page : 106
8.3 Lubricants.
EP150 -2 0C (0 32F)
EP220 0 30C (32 - 85F)
EP320 30C (85F) and higher
* Note: The IC50 has two gearbox cavities that should be subject to the same
maintenance program.
Page : 107
8.4 Material Specifications.
Page : 108
8.5 Trouble Shooting.
Page : 109
8.6 Foundation Dimensions and Weights.
Page : 110
Millimeters
Weight
MODEL A B1 B2 B3 B4 B5 C D E K (mm) G HB HT J K (mm) L M N P Q R S T U
(KGs)
IC10/0005 25 89 89 103 103 103 74 157 16 18 j6 32 48 100 28 6 249 35 129 45 11 67 144 126 8.5 13
IC10/0008 40 89 111 103 103 103 74 157 16 18 j6 32 48 100 28 6 264 42 129 45 11 67 144 126 8.5 14
IC10/0011 40 89 111 103 103 103 74 157 16 18 j6 32 48 100 28 6 277 53 129 45 11 67 144 126 8.5 15
IC20/0020 30 98 120 112 112 112 109 223 16 24j6 66 78 140 61 8 349 72 80 140 11 196 124 95 12 28
IC20/0031 50 98 120 112 112 120 109 223 16 24 j6 66 78 140 61 8 369 83 80 140 11 196 124 95 12 31
IC30/0069 50 124 146 138 138 146 144 280 20 38 k6 74 97 190 70 10 449 90 100 183 15 250 175 146 13 71
IC30/0113 80 124 156 138 146 151 144 280 20 38 k6 74 97 190 70 10 485 110 100 183 15 250 175 146 13 77
IC40/0180 80 159 191 173 181 186 177 347 35 48 k6 113 114 240 110 14 647 164 263 120 28 175 220 184 18 150
IC40/0250 100 163 206 173 181 186 177 347 35 48 k6 113 114 240 110 14 679 181 263 120 28 175 220 184 18 162
IC50/0351 100 188 235 202 210 215 216 423 40 60 m6 104 136 296 104 18 757 213 286 150 20 190 260 220 21 252
IC50/0525 150 N/A N/A 182 182 N/A 216 423 40 60 m6 104 136 296 104 18 826 240 286 150 20 190 260 220 21 274
Inches
Weight
MODEL A B1 B2 B3 B4 B5 C D E F (mm) G HB HT J K (mm) L M N P Q R S T U
(lbs.)
IC10/0005 1 3.5 3.5 4.1 4.1 4.1 2.9 6.2 0.6 18 j6 1.3 1.9 3.9 1.1 6 9.8 1.4 5.1 1.8 0.4 2.6 5.7 5 0.3 28.6
IC10/0008 1.5 3.5 4.4 4.1 4.1 4.1 2.9 6.2 0.6 18 j6 1.3 1.9 3.9 1.1 6 10 1.7 5.1 1.8 0.4 2.6 5.7 5 0.3 30.8
IC10/0011 1.5 3.5 4.4 4.1 4.1 4.1 2.9 6.2 0.6 18 j6 1.3 1.9 3.9 1.1 6 11 2.1 5.1 1.8 0.4 2.6 5.7 5 0.3 33
IC20/0020 1.5 3.9 4.7 4.4 4.4 4.4 4.3 8.8 0.6 24 j6 2.6 3.1 5.5 2.4 8 14 2.8 0 5.5 0.4 7.7 4.9 3.7 0.5 61.6
IC20/0031 2 3.9 4.7 4.4 4.4 4.7 4.3 8.8 0.6 24 j6 2.6 3.1 5.5 2.4 8 15 0 0 5.5 0.4 7.7 4.9 3.7 0.5 68.2
IC30/0069 2 4.9 5.8 5.4 5.4 5.8 5.7 11 0.8 38 k6 2.9 3.8 7.5 2.8 10 18 3.5 3.9 7.2 0.6 9.8 6.9 5.8 0.5 156.2
IC30/0113 3 4.9 6.1 5.4 5.8 5.9 5.7 11 0.8 38 k6 2.9 3.8 7.5 2.8 10 19 4.3 3.9 7.2 0.6 9.8 6.9 5.8 0.5 169.4
IC40/0180 3 6.3 7.5 6.8 7.1 7.3 7 14 1.4 48 k6 4.5 4.5 9.5 4.3 14 25 6.5 10 4.7 1.1 6.9 8.7 7.2 0.7 330
IC40/0250 4 6.4 8.1 6.8 7.1 7.3 7 14 1.4 48 k6 4.5 4.5 9.5 4.3 14 27 7.1 10 4.7 1.1 6.9 8.7 7.2 0.7 356.4
IC50/0351 4 7.4 9.3 8 8.3 8.5 8.5 17 1.6 60 m6 4.1 5.4 12 4.1 18 30 8.4 11 5.9 0.8 7.5 10 8.7 0.8 554.4
IC50/0525 5 0 0 7.2 7.2 0 8.5 17 1.6 60 m6 4.1 5.4 12 4.1 18 33 9.5 11 5.9 0.8 7.5 10 8.7 0.8 602.8
Notes: Dimensions given are for guidance only and should not B1 applies for all threaded connections except BSPT and NPT
be used for installation purposes. B2 applies for BSPT and NPT thread connections
Certified dimensions will be supplied on request. B3 applies for all flange connections except ASA150, BS4504 & ASA300
B4 applies for ASA150 and BS4504 flange connections
B5 applies for ASA300 flange connections
Page : 111
8.7 Typical Noise Emission Data - IC10, IC20 and IC30 Series.
Page : 112
8.8 Typical Noise Emission Data IC40 and IC50 Series.
Page : 113
8.9 Service History.
Date Comments
Page :114
8.9.1 Tool List.
Listed below are tools required for the maintenance of the Classic pump range.
Page :115
TYPE SIZE OR RANGE IC10 IC20 IC30 IC40 IC50
ADJUSTABLE TO MIN. 39 NM
TORQUE W RENCH v
(28.76 ft-lb.)
ADJUSTABLE TO MIN. 107 NM
TORQUE W RENCH v
(78.91 ft-lb.)
ADJUSTABLE TO MIN. 135 NM
TORQUE W RENCH v
(99.56 ft-lb.)
ADJUSTABLE TO MIN. 130 NM
TORQUE W RENCH v
(95.87 ft-lb.)
ADJUSTABLE TO MIN. 160 NM
TORQUE W RENCH v
(117.99 ft-lb.)
Page :116
9.0 Notes.
The information contained in this document is correct at time of print, but may
be subject to change without prior notice.
Page :117