MRP on POM-QM for Windows

MRP Example 2: Starship Problem

P r o d u c t S tr u c tu r e T r e e

S t a r s h ip ( 1 )

W a r p E n g in e ( 3 ) I m p u ls e E n g in e ( 4 )

D ilit h iu m C r y s t a l ( 1 0 ) P la t in u m ( 7 ) A n t im a t t e r P o d ( 3 ) A n it m a t t e r P o d ( 2 ) P la t in u m ( 4 )

MRP Example 2: Indented Bill of Materials

Item Level Lead Time # Per Parent On Hand Lot Size

Starship 0 2 1 0 1
WE 1 3 3 0 1
DC 2 2 10 0 1
PL 2 2 7 0 1
AM 2 1 3 0 1
IE 1 1 4 0 1
AM 2 1 2 0 1
PL 2 2 4 0 1
MRP Example 3

P r o d u c t S tr u c tu r e T r e e fo r Ite m A P r o d u c t S tr u c tu r e T r e e fo r Ite m R

A (1 ) R (1 )

D (3 ) B (2 ) E (4 ) B (4 )

C (2 ) E (3 ) C (2 ) E (3 )

MRP Example 3: Indented Bill of Materials

Item Level Lead Time # Per Parent On Hand Lot Size

A 0 3 1 10 1
D 1 3 3 200 500
B 1 2 2 0 400
C 2 1 2 0 1
E 2 1 3 0 1
E 1 1 4 0 1
R 0 3 1 20 1
B 1 2 4 0 400
C 2 1 2 0 1
E 2 1 3 0 1
C* 0 1 1 0 1

* C as spare part.