Вы находитесь на странице: 1из 1

PERHITUNGAN WATER DELUGE FOUNDATION TRANSFORMER

No Description WorkProject Location : ADDITIONAL MAIN TRANSFORMER 230 MVA INALUM KSP-CE-03-04-2017

1 TRANSFORMER

EXCAVATION :
: 2,5 M X 2,5 M X 1,7 M X 10 SET = 106,25 M3

SAND URUG :
: 1,6 M X 1,6 M X 0,1 M X 10 SET = 2,56 M3

LEAN CONCRETE :
: 1,6 M X 1,6 M X 0,075 M X 10 SET = 1,92 M3

REBAR :
D16-200 : 1,8 M X 1,58 KG/M X 7 PC X 2 sideX 10 SET REBAR Arah x = 397,8455 KG
D16-200 : 1,9 M X 1,58 KG/M X 7 PC X 2 sideX 10 SET REBAR Arah y = 419,94803 KG
D16-200 : 1,45 M X 1,58 KG/M X 12 PC X 1 sideX 10 SET REBAR PEDESTAL = 274,70285 KG
D13-150 : 0,8 M X 1,04 KG/M X 8 PC X 1 sideX 10 SET REBAR TOP = 66,702272 KG
D10-200 : 2,7 M X 0,62 KG/M X 5 PC X 1 sideX 10 SET BEUGLE = 83,2545 KG
KAWAT BETON : 0,54 X 11,26 = 6,0804 KG
= 1.248,534 KG
FORMWORK :
CAP: 0,25 M X 0,25 M X 40 SET = 2,5 M2
PEDESTAL
: 0,7 M X 1,15 M X 40 SET = 32,2 M2
= 34,7 M2
CONCRETE K-225 :
CAP : 1,5 M X 1,5 M X 0,25 M X 10 SET = 5,625 M3
PEDESTAL : 0,7 M X 0,7 M X 1,15 M X 10 SET = 5,635 M3
= 11,26 M3

ANCHOR BOLT : 4 PC X 10 SET = 40 PC

BACKFILL :
: 106,25 - 13,18 M3 = 93,07 M3

DISPOSAL :
: 13,18 M3 = 13,18 M3

GROUTING : 0,7 M X 0,7 M X 0,05 M X 10 SET = 0,245 M3

Note Book :

PT.GRID SOLUTIONS INDONESIA PT.INDOPRIMA SURYA KHARISMA PT. KARYA SATRIA PUTRA

Name : Syahrial Situmorang Name : Yopi Isworo Name : Affan Mawardi


Site Manager Project Manager Site Engineer

Вам также может понравиться