VALORIZACIN A PRECIOS UNITARIOS

ESTRUCTURAS
VALORIZACIN N 01 (periodo 15 al 30/Nov./2014)

Obra : CONSTRUCCIN DE POSTA MDICA

Ingeniero LEONARDO GARCIA Modalidad de Ejecucin: A PRECIOS UNITARIOS


Ubicac. : PIURA
FECHA DE INICIO DE OBRA: 15/11/2014

Presupuesto 01: Estructuras


VAL. ACTUAL
PRESUPUESTO CONTRACTUAL VAL ANTERIOR VAL ACUMULADO
ITEM DESCRIPCION (15-30/Nov/2014)
UND. CANT. P.U. PARCIAL MET PARCIAL MET PARCIAL MET PARCIAL

1.00 OBRAS DE CONCRETO SIMPLE


CONCRETO PARA CIMIENTOS CORRIDOS
1.01 m3 200.00 130.00 26,000.00 0.00 0.00 45.00 5,850.00 45.00 5,850.00
C:H-1:10 + 30% P.G.
CONCRETO PARA SOBRECIMIENTOS C:H-
1.02 m3 60.00 200.00 12,000.00 0.00 0.00 20.00 4,000.00 20.00 4,000.00
1:8 + 25% P.M.
ENCOFRADO Y DESENCOFRADO DE
1.03 m2 200.00 30.00 6,000.00 0.00 0.00 40.00 1,200.00 40.00 1,200.00
SOBRECIMIENTOS H=45cm.

1.04 FALSO PISO DE CONCRETO 1:12 DE E=4" m2 550.00 40.00 22,000.00 0.00 0.00 120.00 4,800.00 120.00 4,800.00

COSTO DIRECTO 66,000.00 15,850.00 15,850.00


GASTOS GENERALES (10%) 6,600.00 1,585.00 1,585.00
UTILIDAD (5%) 3,300.00 792.50 792.50
SUB-TOTAL OFERTADO 75,900.00 18,227.50 18,227.50
I.G.V. (18.00%) 13,662.00 3,280.95 3,280.95
PRESUPUESTO TOTAL OFERTADO 89,562.00 21,508.45 21,508.45
% AVANCE 24.02% 24.02%

NOTA:

- LA VAL. A PRECIOS UNITARIOS SE REALIZA CON LOS METRADOS EJECUTADOS Y LOS PRECIOS UNITARIOS OFERTADOS POR EL CONTRATISTA.
SALDO

MET PARCIAL

155.00 20,150.00

40.00 8,000.00

160.00 4,800.00

430.00 17,200.00

50,150.00
5,015.00
2,507.50
57,672.50
10,381.05
68,053.55
75.98%

RATISTA.
VALORIZACIN A SUMA ALZADA

ESTRUCTURAS
VALORIZACIN N 01 (periodo 10 al 31/Oct./2014)

Obra : CONSTRUCCIN DE POSTA MDICA

Ingeniero LEONARDO GARCIA Modalidad de Ejecucin: A SUMA ALZADA


Ubicac. : PIURA
FECHA DE INICIO DE OBRA: 10/10/2014

Presupuesto 01: Estructuras


VAL. ACTUAL
PRESUPUESTO CONTRACTUAL VAL ANTERIOR VAL ACUMULADO
ITEM DESCRIPCION (10-31/Oct/2014)
UND. CANT. P.U. PARCIAL MET PARCIAL MET PARCIAL MET PARCIAL

1.00 OBRAS DE CONCRETO SIMPLE


CONCRETO PARA CIMIENTOS CORRIDOS
1.01 m3 200.00 130.00 26,000.00 0.00 0.00 45.00 5,850.00 45.00 5,850.00
C:H-1:10 + 30% P.G.
CONCRETO PARA SOBRECIMIENTOS C:H-
1.02 m3 60.00 200.00 12,000.00 0.00 0.00 20.00 4,000.00 20.00 4,000.00
1:8 + 25% P.M.
ENCOFRADO Y DESENCOFRADO DE
1.03 m2 200.00 30.00 6,000.00 0.00 0.00 40.00 1,200.00 40.00 1,200.00
SOBRECIMIENTOS H=45cm.

1.04 FALSO PISO DE CONCRETO 1:12 DE E=4" m2 550.00 40.00 22,000.00 0.00 0.00 120.00 4,800.00 120.00 4,800.00

COSTO DIRECTO 66,000.00 15,850.00 15,850.00


GASTOS GENERALES (10%) 6,600.00 1,585.00 1,585.00
UTILIDAD (5%) 3,300.00 792.50 792.50
SUB-TOTAL BASE 75,900.00 18,227.50 18,227.50
Factor de Relacin 0.95834 0.95834 0.95834

SUB-TOTAL OFERTADO (SUB TOT. BASE x FR) 72,738.01 17,468.14 17,468.14


I.G.V. (18.00%) 13,662.00 3,280.95 3,280.95
PRESUPUESTO TOTAL 86,400.01 20,749.09 20,749.09
% AVANCE 24.02% 24.02%

NOTA:

- LA VAL. A SUMA ALZADA SE REALIZA CON LOS METRADOS EJECUTADOS CONTRATADOS Y LOS PRECIOS UNITARIOS DEL VALOR REFERENCIAL AFECTADO POR EL
FACTOR DE RELACIN
- EL FACTOR DE RELACIN DEBE SER CALCULADO HASTA LA QUINTA CIFRA DECIMAL
SALDO

MET PARCIAL

155.00 20,150.00

40.00 8,000.00

160.00 4,800.00

430.00 17,200.00

50,150.00
5,015.00
2,507.50
57,672.50
0.95834

55,269.87

10,381.05
65,650.92
75.98%

RENCIAL AFECTADO POR EL


EJEMPLO

OBRA A SUMA ALZADA

MAYORES GASTOS GENERALES POR AMPLIACION DE PLAZO

MONTO CONTRACTUAL (Costo Directo): S/. 5,000,000.00 (PRESUPUESTO REFERENCIAL)

(1) GASTOS GENERALES VARIABLES S/. 490,000.00 9.800%


GASTOS GENERALES FIJOS S/. 10,000.00 0.200%
TOTAL GASTOS GENERALES 10% S/. 500,000.00

(2) PLAZO DE EJECUCION CONTRACTUAL 240 d/c


(3) GASTO GENERAL DIARIO (1) / (2) = (3) S/. 2,041.67 (S/. 490,000.00 / 240 das)
(Gasto General Variable / Plazo)
(4) FACTOR DE RELACION 0.95876

(5) GASTO GENERAL VARIABLE DIARIO ( 3 ) * ( 4 ) = ( 5 ) 1,957.47

IU 39 - MES BASE IU 39 - MES DE CAUSAL


AMP. MAYORES
AMPLIACION GAST. GEN. VAR. FACTOR DE REAJUSTES DE TOTAL MGG
ITEM PLAZO MES Io MES Ip GASTOS
N DIARIO REAJUSTE MGG (sin IGV)
(Das) GENERALES
REAJ=D x GGVD
D GGVD R=Ip/Io MGG=D x GGVD
x (R-1)

1 01 1 S/. 1,957.47 Nov-13 346.35 Jan-14 354.04 1.022 1,957.47 43.46 2,000.93

2 02 1 S/. 1,957.47 Nov-13 346.35 Apr-14 362.38 1.046 1,957.47 90.60 2,048.07

3 07 21 S/. 1,957.47 Nov-13 346.35 Jul-14 362.65 1.047 41,106.84 1,934.58 43,041.41

4 11 24 S/. 1,957.47 Nov-13 346.35 Aug-14 366.50 1.058 46,979.24 2,733.16 49,712.40

TOTALES S/. 92,001.01 S/. 4,801.80 S/. 96,802.81

NOTA:

1.- OBRA A PRECIOS UNITARIOS: EL GASTO GENERAL DIARIO SE CALCULAR DIVIDIENDO LOS GASTOS GENERALES VARIABLES OFERTADOS POR
EL CONTRATISTA

2.- OBRA A SUMA ALZADA: EL GASTO GENERAL DIARIO SE CALCULAR DIVIDIENDO LOS GASTOS GENERALES VARIABLES DEL PRESUPUESTO
REFERENCIAL

3.- El IU=39 ES EL NDICE GENERAL DE PRECIOS AL CONSUMIDOR