Академический Документы
Профессиональный Документы
Культура Документы
Area-to-Area Interchange
INTA
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Zone Based Reports] dialog (Figure 16-1 Area/Zone Based Reports Dialog, Area) provides options for interchang
reports and tie line loading reports, of all subsystems or selected subsystems, by area or zone.
Click [Go] to produce the report (Figure 16-2 Example of Area Interchange Report), which is displayed in the Report tab b
default.
Zone-to-Zone Interchange
INTZ
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Zone Based Reports] dialog (Figure 16-3 Area/Zone Based Reports Dialog, Zone) provides options for interchang
reports and tie line loading reports, of all subsystems or selected subsystems, by area or zone.
Click [Go] to produce the report (Figure 16-4 Example of Zone Interchange Report), which is displayed in the Report tab b
default.
Example of Zone Interchange Report
Additional Information
PSSE Program Operation Manual,
Section 10.12, Summarizing Zone-to-Zone Interchange
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Zone Based Reports] dialog (Figure 16-5 Area/Zone Based Reports Dialog, Area Tie Line Loadings) provide
options for interchange reports and tie line loading reports, of all subsystems or selected subsystems, by area or zone.
Click [Go] to produce the report (Figure 16-9 Area/Owner/Zone Totals Dialog, Area), which is displayed in the Report tab b
default.
Example of Area Tie Line Loadings Report
Additional Information
PSSE Program Operation Manual,
Section 10.13, Summarizing Loadings on Ties from Interchange Areas
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Zone Based Reports] dialog (Figure 16-5 Area/Zone Based Reports Dialog, Area Tie Line Loadings) provide
options for interchange reports and tie line loading reports, of all subsystems or selected subsystems, by area or zone.
Click [Go] to produce the report (Figure 16-9 Area/Owner/Zone Totals Dialog, Area), which is displayed in the Report tab b
default.
Example of Zone Tie Line Loadings Report
Additional Information
PSSE Program Operation Manual,
Section 10.14, Summarizing Loadings on Ties from Zones
Area/Owner/Zone Totals
Area Totals
AREA
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Owner/Zone Totals] dialog (Figure 16-9 Area/Owner/Zone Totals Dialog, Area) provides options for subsystem totals
of all subsystems or selected subsystems, by area, owner, or zone. The area report may also include zone subtotals.
Click [Go] to produce the report (Figure 16-10 Example of Area Totals Report with Zone Subtotals), which is displayed in th
Report tab by default.
Example of Area Totals Report with Zone Subtotals
Additional Information
PSSE Program Operation Manual,
Section 10.7, Summarizing Area Totals
Owner Totals
OWNR
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Owner/Zone Totals] dialog (Figure 16-11 Area/Owner/Zone Totals Dialog, Owner) provides options for subsystem
totals, of all subsystems or selected subsystems, by area, owner, or zone:
Area/Owner/Zone Totals Dialog, Owner
Click [Go] to produce the report (Figure 16-12 Example of Owner Totals Report), which is displayed in the Report tab b
default.
Additional Information
PSSE Program Operation Manual,
Section 10.8, Summarizing Owner Totals
Zone Totals
ZONE
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
The [Area/Owner/Zone Totals] dialog (Figure 16-11 Area/Owner/Zone Totals Dialog, Owner) provides options for subsystem
totals, of all subsystems or selected subsystems, by area, owner, or zone. The zone report may also include area subtotals.
Area/Owner/Zone Totals Dialog, Zone
Click [Go] to produce the report (Figure 16-12 Example of Owner Totals Report), which is displayed in the Report tab b
default.
Additional Information
PSSE Program Operation Manual,
Section 10.9, Summarizing Zone Totals
Bus-Based Reports
Through the [Bus Based Reports] dialog (Figure 16-15 Bus Based Reports Dialog, Standard Format), several power flow
solution reports may be obtained.
The [Bus Based Reports] dialog enables the user to designate for processing either the entire working case or a specifie
bus subsystem (refer to Section 4.8, Subsystem Selection of the PSSE Program Operation Manual). A bus subsystem may b
Reports] dialog.
Click [Go] to produce the report . The report is written to the Report device.
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
In the [Bus Based Reports] dialog (Figure 16-15 Bus Based Reports Dialog, Standard Format), select Powerflow output wit
the Wide format output check box unchecked. Click [Go] to produce the report (Figure 16-16 Example of Standard Forma
Power Flow Solution Report).
Additional Information
PSSE Program Operation Manual,
Section 10.2, Producing a Standard Power Flow Solution Report
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
In the [Bus Based Reports] dialog (Figure 16-17 Bus Based Reports Dialog, Wide Format), select Powerflow output with th
Wide format output check box checked and the Output with amps check box unchecked. Click [Go] to produce the repo
(Figure 16-18 Example of Wide Format Power Flow Solution Report).
Bus Based Reports Dialog, Wide Format
Additional Information
PSSE Program Operation Manual,
Section 10.3, Producing a Wide-Format Power Flow Solution Report
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Bus based reports
In the [Bus Based Reports] dialog (Figure 16-19 Bus Based Reports Dialog, Wide Format, with Branch Current Loadings
select Powerflow output with the Wide format output and Output with amps check boxes both checked. Click [Go] to produc
the report (Figure 16-20 Example of Wide Format Power Flow Solution Report with Branch Current Loadings).
Bus Based Reports Dialog, Wide Format, with Branch Current Loadings
Example of Wide Format Power Flow Solution Report with Branch Current Loadings
Additional Information
PSSE Program Operation Manual,
Section 10.4, Producing a Wide-Format Power Flow Solution Report in Amps
Summary of Subsystem Conditions
SUBS
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
In the [Bus Based Reports] dialog (Figure 16-21 Bus Based Reports Dialog, Subsystem Summary), select Subsystem
summary / totals. Click [Go] to produce the report (Figure 16-22 Example of Subsystem Summary Report).
Additional Information
PSSE Program Operation Manual,
Section 10.5, Summarizing Subsystem Conditions
Requirements / Prerequisites
The working case must contain a validly specified power flow case solved to an
acceptable mismatch tolerance.
The load reduction reporting activity LODR summarizes the reduction in:
Nominal constant MVA load caused when voltage at a load bus falls below PQBRAK.
Nominal constant current load caused when voltage at a load bus falls below 0.5 pu.
In the [Bus Based Reports] dialog (Figure 16-23 Bus Based Reports Dialog, Load Reduction Output), select Load reductio
output. If subsystem selection by area, owner and/or zone had been specified, select the desired option for defining subsystem
loads. Click [Go] to produce the report.
Bus Based Reports Dialog, Load Reduction Output
Additional Information
PSSE Program Operation Manual, Section 10.6, Summarizing Load Reduction
Section 11.1.1, Boundary Conditions
The [Limit Checking Reports] dialog provides tabs to produce all PSSE limit checking reports:
Requirements / Prerequisites
Validly specified power flow case.
Machine Capability Data File (*.gcp)
Power Flow > Reports > Limit checking reports
Clicking the Reactive capability tab in [Limit Checking Reports] will generate a report that tabulates machine loading and lim
data. There is a checkbox option to update the machine reactive power limits in the power flow case. The PSSE Program
Operation Manual (Section 10.21.1) provides details of the data records for the required Machine Capability Data file (*.gcp).
Additional Information
PSSE Program Operation Manual,
Section 10.21, Producing a Machine Reactive Capability Report
Section 10.21.1, Machine Capability Curve Data File Contents
Requirements / Prerequisites
Validly specified power flow case.
Plant outputs and voltages are valid only if the working case is solved to an
acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Generator bus tab in [Limit Checking Reports] will generate a report that tabulates the loading and voltag
conditions at generator buses. The following reports can be selected:
Additional Information
PSSE Program Operation Manual,
Section 10.22, Producing a Generator Bus Limits Report
Requirements / Prerequisites
Validly specified power flow case.
Machine outputs and voltages are valid only if the working case is solved to an
acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Machine terminal tab in [Limit Checking Reports] will generate a report that tabulates machine loading an
voltage conditions at the generator terminals of on-line machines at type two and three buses in the working case. The repo
may include all on-line machines or only those that are overloaded.
Branch Overloads
RAT3
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Branches tab in [Limit Checking Reports] and then selecting the both transformer and non-transforme
branches option from the pull-down list will generate a report that tabulates branch overloads. Options are available to specify th
Rating Set and Percent Loading limit.
Additional Information
PSSE Program Operation Manual,
Section 10.16, Producing a Branch Overload Checking Report
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Branches tab in [Limit Checking Reports] and then selecting the only non-transformer branches option from th
pull-down list will generate a report that tabulates transmission line overloads. Options are available to specify the Rating Set an
Percent Loading limit.
Example of Transmission Line Overload Report, Rate C
Additional Information
PSSE Program Operation Manual,
Section 10.18, Producing a Transmission Line Overload Checking Report
Transformer Overloads
OLTR
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Branches tab in [Limit Checking Reports] and then selecting the only transformers option from the pull-down lis
will generate a report that tabulates transformer overloads. Options are available to specify the Rating Set and Percent Loading limit.
Additional Information
PSSE Program Operation Manual,
Section 10.17, Producing a Transformer Overload Checking Report
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Branches tab in [Limit Checking Reports] provides options to include any of the following network components i
the output:
Selecting all three network component options with the all ratings option will generate a report that tabulates branch curren
ratings.
Additional Information
PSSE Program Operation Manual,
Section 10.19, Producing a Branch Current Ratings Report
Requirements / Prerequisites
Validly specified power flow case.
Bus voltages are valid only if the working case is solved to an acceptable mismatch
tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Regulated buses tab in [Limit Checking Reports] will generate a report that tabulates those buses where voltage
are controlled by generation, switched shunts, voltage controlling transformers, FACTS devices, and/or VSC dc line converters.
Example of Regulated Buses Report
Additional Information
PSSE Program Operation Manual,
Section 10.24, Producing a Regulated Bus Report
Controlling Transformers
TLST
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Power Flow > Reports > Limit checking reports
Clicking the Controlling transformer tab in [Limit Checking Reports] will generate a report that tabulates those transformers i
the power flow case where off-nominal turns ratio or phase-shift angle may be adjusted by power flow solution activities.
The user has the option of listing All controlling transformers or of restricting the report to Controlling transformer violations
those transformers where the controlled quantity is outside of its specified band. The Output with voltage reversed optio
produces a report reversing the voltage option specified (pu or kV) in the Program Settings Dialog.
Additional Information
PSSE Program Operation Manual,
Section 10.25, Producing a Controlling Transformer Report
Requirements / Prerequisites
Power Flow > Reports > Limit checking reports
Clicking the Out-of-limit bus voltage tab in [Limit Checking Reports] will generate a report that tabulates those buses wher
voltage magnitude is outside the specified range. The example (Figure 16-34 Example of Out-of-Limit Bus Voltage Report) i
based on the default limits, which can be changed by the user in .01 pu increments.
Additional Information
PSSE Program Operation Manual,
Section 10.20, Producing an Out-of-Limits Bus Voltage Report
AC Contingency Reports
Power Flow > Reports > AC Contingency reports
The [AC Contingency Reports] dialog (Figure 16-35 AC Contingency Reports Dialog) allows the user to configure a variety o
reports from the results of an ac contingency analysis. These formats include:
Click [ ] to open a selection window for the required Contingency solution output file (*.acc).
Click [Go] to produce the report, which is displayed in the Report tab by default (Figure 16-36 Example of Available Capacit
Table).
AC Contingency Reports Dialog
Example of Available Capacity Table
Additional Information
PSSE Program Operation Manual,
Section 6.10.10, Single Run Report Formats
Refer to Refer to Additional Resources for PSSE, AcccBrwsGrid, for a description of ACCC post-processor data format.
This activity preserves the output system conditions of a contingency case solution when a contingency case exceeds th
capability of the ac contingency solution. The [Append to AC Contingency Solution Output File] dialog is used to specify:
Additional Information
PSSE Program Operation Manual,
Section 6.10.8, Appending Data to a Contingency Solution Output File
The [Multiple AC Contingency Run Report] dialog (Figure 16-38 Multiple AC Contingency Run Report Dialog) allows the use
to configure a variety of reports from the results of multiple ac contingency analyses. These formats include:
Click [ ] to open a selection window for the required Contingency Solution Output file (*.acc). As many as nine Contingenc
Solution Output files may be specified.
Click [Go] to produce the report, which is displayed in the Report tab by default.
Additional Information
PSSE Program Operation Manual,
Section 6.10.12, Multiple Run Output Report Formats
Requirements / Prerequisites
Validly specified power flow case solved to an acceptable mismatch tolerance.
Unblocked multi-terminal dc lines must be present in the working case.
Power Flow > Reports > Multi-terminal DC line solution output (MTDC)
The multi-terminal dc line power flow output activity MTDC prints power flow solution results at all dc buses of all unblocke
multi-terminal dc lines in the working case.
Activity MTDC displays a popup message No unblocked multi-terminal dc lines in this case and terminates if these networ
conditions are not found. Click [OK] to remove the message.
There are no user-defined options. The report is displayed in the Report tab by default (Figure 16-39 Example of DC Networ
Conditions Report).
Example of DC Network Conditions Report
Additional Information
PSSE Program Operation Manual,
Section 10.30, Reporting DC Network Conditions
By Area
Subsystem > Area
The [Area Subsystem Selector] dialog is similar to the area tab in the [Bus Subsystem Selector] (see Figure 2-9 Bu
Subsystem Selector Dialog). The buttons respond the same way, but the Memorize and Recall options are not available. Thi
dialog is used to limit report output and does not affect the [Spreadsheet] display.
Area Subsystem Selector Dialog
By Owner
Subsystem > Owner
The [Owner Subsystem Selector] dialog is similar to the owner tab in the [Bus Subsystem Selector] (see Figure 2-9 Bu
Subsystem Selector Dialog). The buttons respond the same way, but the Memorize and Recall options are not available. Thi
dialog is used to limit report output and does not affect the [Spreadsheet] display.
By Zone
The [Zone Subsystem Selector] dialog is similar to the zone tab in the [Bus Subsystem Selector] (see Figure 2-9 Bu
Subsystem Selector Dialog). The buttons respond the same way, but the Memorize and Recall options are not available. Thi
dialog is used to limit report output and does not affect the [Spreadsheet] display.
Power Flow > Reports > Export ACCC, PV/QV results to Excel
OR
The [Export PSSE Data/Result to Excel] dialog (Figure 16-44 Export Data/Result to Excel Dialog) requires specification o
the Contingency for export:
Click [OK] to return to [Export PSSE Data/Result to Excel]. Click [ ] to open selection windows for the file to b
exported and the Excel output file, which can be a new file with the default name of the *.acc file, a designated filename, o
a previously-built file to be over-written.
Checkboxes are provided to select the desired Quantities to Export and contingencies.
Click [Export] to complete the action. The Excel Workbook will open in a new window.