Академический Документы
Профессиональный Документы
Культура Документы
LT Switchgear:
Highlights of technical specifications
Degree of Protection- All indoor panels should have IP52 class of protection. First
digit stands for protection against dust ingress & second digit stands for protection
against water ingress. All outdoor panels should have IP 55 degree of protection.
Chapter 5
Safety aspects- All switchboards shall necessarily have earth bus bar throughout
the length, which shall be welded/bolted with each panel. Earth bus of switchboard at
both ends shall be finally welded/ bolted with main horizontal earth bus of substation.
All hinged doors shall be earthed with flexible earthing wire braids.
Clearances- The minimum clearances in air between phases and between phase
and earth shall be 25 mm for the entire run of horizontal and vertical bus bars. For all
other components this shall be minimum 10 mm throughout.
Verification of continuity of protective circuit- All circuits are verified during this
test to ensure the continuity.
AC LT System
LT Transformer
Incomer 1 supply fails Incomer 2 will supply all loads through Bus coupler and
vice versa. Both the incomer fails means DG set will automatically switched on
for supplying power to essential loads.
LT Transformers:
630 KVA & 800 KVA transformers are required to meet auxiliary power
demand in substations. 800 KVA Transformer is connected with tertiary of
autotransformer in substation, however 630 kVA Transformer is fed by SEB
supply.
DG SETS:
250 KVA capacity DG sets for Arasur (400/230 kV) substation. DG sets
are silent type in weather proof enclosure. In addition to this the
enclosure provided with acoustic enclosure to meet the noise level limit
requirements.
Input:
Incomer-1 & 2.
Bus Coupler.
Output:
HVW Pump.
Colony.
Incomer 1 supply fails Incomer 2 will supply all loads through Bus coupler and vice
versa.
Input:
DG Set.
Bus Coupler.
Chapter 5
Output:
BMK.
ICT MBs.
Battery chargers
Incomer 1 supply fails Incomer 2 will supply all loads through Bus coupler and
vice versa.
Both the incomer fails means DG set automatically switched on for supplying
power to essential loads.
Input:
Bus Coupler.
Output:
Switchyard Lighting
Supply from incomer 1 & 2 meet the lighting loads via lighting transformer 1&
2 respectively. If any one of the supply fails, supply extends to lighting loads
through bus coupler.
Input:
ACDB
Output:
Supply from incomer 1 & 2 meet the lighting loads via lighting transformer
1& 2 respectively. If any one of the supply fails, supply extends to lighting
loads through bus coupler. Both supplies fail means DG set will automatically
switched on for supplying emergency lighting loads through emergency
lighting transformer.
Chapter 5
Main Switch Board Receives Both 415V Supply from Transformer with auto changeover
Incomer-1 Incomer-2
1 2 Incomer & 1 Buscoupler
Supply to Oil Filtartion Unit of Transformer Supply to Oil Filtartion Unit of Transformer scheme is there if 1st I/C fails
Supply to Main System Supply distribution Supply to Main System Supply distribution then Bus coupler Transfers the
2
Board Board Supply of 2nd I/C Bus to 1st I/c
Bus & Viseversa with automatic
3 Interlocking. System Voltage,
Supply to Main Lighting distribution Board Supply to Main Lighting distribution Board
4 Current , Main Breaker Status to
Supply to Colony Supply to Colony
SCADA through Transducers &
5 Supply to High velocity Water Spray System Potential Free Contacts
AC Distribution Board Receives Both 415V Supply from Main Switch Board with auto
changeover
1 No. 415V Supply for Main System Supply 1 No. 415V Supply for Main System Supply
distribution Board Receives from Main distribution Board Receives from Main
Switch Board & 1 no. Supply from DG with Switch Board
Automatic changeover 3 Incomer & 1 Buscoupler
Supply for 48V & 220V DC Charger from Supply for 48V & 220V DC Charger from scheme is there if 1st I/C fails
1 both Supply both Supply then Bus coupler Transfers the
Emergency Ltg Suply to Emergency Lighting Supply of 2nd I/C Bus to 1st I/c
2 Board. Supply to Bay ( Qty as per S/s Requirement) Bus & Viseversa. And when
Supply to Bus Reactors ( Qty as per S/s both Supply fails the DG will
3 Supply to Bay ( Qty as per S/s Requirement) Requirement) Start & in that condition Both
Supply to Bus Reactors ( Qty as per S/s Supply to Line Reactors ( Qty as per S/s Incomer cannot be operated
4 Requirement) Requirement) ,DG System Voltage, Current ,
Supply to Line Reactors ( Qty as per S/s Supply to Auto Transformers ( Qty as per Main Breaker Status to SCADA
through Transducers & Potential
5 Requirement) S/s Requirement)
Free Contacts
Supply to Auto Transformers ( Qty as per
6 S/s Requirement) Supply to AC Systems
Supply to Jocky Pump, Sump Pump , Fire
7 Fighting Panel & AC Systems
Main Lighting Distribution Board Receives Both 415V Supply from Main Switch Board 2 Incomer & 1 Bus coupler
with Manual changeover scheme is there if 1st I/C fails
1 Switch Yard Supply ( As per Requirement) Switch Yard Supply ( As per Requirement) then Bus coupler Transfers the
Control room Supply ( As per Supply of 2nd I/C Bus to 1st I/c
2 Control room Supply ( As per Requirement) Requirement) Bus & Viseversa with
3 Receptacles Receptacles Mechanical Interlocking.
Emergency Lighting Distribution Board Receives Both 415V Supply from AC Dis. Board
from DG Side
1 Switch Yard Supply ( As per Requirement) Switch Yard Supply ( As per Requirement)
Control room Supply ( As per
2 Control room Supply ( As per Requirement) Requirement)
220V DC Distribution Board Receives Both 415V Supply from 415V AC Distribution Board
from (DG Side, I/C-1) & I/C-2
1 Line & Bus Reactor Panels Line & Bus Reactor Panels
2 Control Relay Panels ( As per Requirement) Control Relay Panels
System Voltage, Current to
3 Bus Bar Protection Panel Bus Bar Protection Panel
SCADA through Transducers &
48V DC Distribution Board Receives Both 415V Supply from 415V AC Distribution Board Potential Free Contacts.
from (DG Side, I/C-1) & I/C-2
1 PLCC Panels ( As per Requirement) PLCC Panels ( As per Requirement)
Phase Comparision Panels ( As per
2 Requirement) Control Relay Panels
Feeders shall be multiplied for different Voltage Label i.e.
33kV/66kV/132kV/220kV/400kV/765kV
Chapter 5
5. Interlock logic:
Electrical & Mechanical interlocking arrangement with Trip logic between the
air circuit breakers are to be provided.
1. under normal condition (i.e. when supply is available through both the incomers),
incomers I & II of 400V switch board shall be in closed condition, Closing of Bus
Coupler breaker shall be prohibited.
2. In case of failure of either of the sources, the incomer of that source shall trip
through Under-Voltage relay and Bus coupler shall be allowed to close. After
restoration, the respective incomer shall be allowed to close only after opening of
Bus coupler breaker.
3. The above electrical interlock should be done through Breaker auxiliary contact
switch.
1. under normal condition (i.e. when supply is available through both the incomers),
incomers I & II of 400V switch board shall be in closed condition, Closing of DG-
Incomer breaker shall be prohibited.
2. In case of failure of either of the sources, the incomer of that source shall trip
through Under-Voltage relay and Bus coupler shall be allowed to close, but Closing
of DG-Incomer breaker shall be prohibited.
3. In case of failure of supply of both the incomers, both the incomer shall trip
through Under Voltage relay and DG set breaker shall be allowed to switch on. After
restoration, the incomer breakers shall be allowed to close only after opening of DG
set breaker.
4. The above electrical interlock should be done through Breaker auxiliary contact
switches.
Chapter 5
Aluminum Conductor, XLPE insulated, armoured power cables are used for
main supply purposes.
Aluminum conductor, PVC insulated armoured power cables are used for all
other distribution applications.
Copper Conductor, PVC insulated armoured control cables are used for all
control & protection applications.
Voltage Drop
Technical Requirements-
All XLPE insulated power cables used in main power supply purposes shall be able
to withstand 3 phase fault level of 45 kA for 0.12 sec for 3-Phase with an initial peak
of 105kA in any one phase at rated conductor temperature i.e. 70C for PVC
insulated and 90C for XLPE insulated.
2. All cables shall be of FR type for fire retardant property. Under this
category oxygen index of outer sheath shall not be less than 29 and
temperature index shall not be less than 250 deg C.
Battery bank:
Stationary batteries:
Maintenance free
Safety measures
Economy
Safety valve
Discharge depth
Overcharge quantity
BATTERY CHARGERS:
Ramp Generator:
This will ensure a gradual rose of o/p voltage, even if the reference is set
at full value. Its o/p is fed to voltage regulator.
Voltage Regulator:
Chapter 5
Firing Circuit:
The o/p of current regulator is fed to the firing circuit, which is then fed to
the thyristors. The firing circuits consist of identical UJTs controlled
oscillator circuits which will be used for the triggering of thyristors in the right
sequence.
Suitably designed L-C filter circuit has been incorporated to bring down
the ripple at the o/p.
Both charger 1 & 2 are of Float/ Boost charger type while charger 3 is of Float
type.
The selector switches 1 & 2 determine the mode of working of the chargers,
while the selector switch 3 determines the DB to which the S/B charger has to
feed.
15 Nos of spare batteries are also provided for backup. 20V/20A cell booster
used as spare cell charger to chare the spare batteries.
Chapter 5
Hydrant System
High velocity water (H.V.W) Spray System (2 Nos of 315 MVA ICT).
Fire water storage and pumping system.
Fire Detection and alarm System.
Hydrant System
Dedicated fire water pumping system ids provided for the fire hydrant system
of HVWS system.
Fire Water storage tank of RCC construction with two compartments with a
common sump has been provided .The total capacity of two compartments is 634
m3. One no 410 m3 /hr MWC motor driven horizontal centrifugal pump set and one
no 410 m3 /hr MWC Diesel engine driven horizontal pump set have been installed.
Control Cum annunciation panel is provided with the necessary control
And annunciation for the fire water pumps.
The Fire fighting pumping house is having four types of pumps namely
The main problematic area in the pump is NRVS, diesel engine battery, spray pump.
These non return valves are provided in the discharge line to avoid the
pressurized water coming back to the impeller (Water Hammering).During the old
days, flap type valves were installed. These valves give heavy noise when pump
stops due to hammering effect. The failure of the pump impeller and the flap of the
NRV are imminent very frequently which in turn increase the outage time and
maintenance cost. To solve this issue rubber ball valve type NRVs are used which
gives noiseless operation and no water hammering effect on the impeller.
DE Pump Battery:
The diesel engine driven pump was provided with auto mobile type 24 volts
battery for starting. These batteries require regular maintenance and also charger
are of inferior monitoring mechanism to have controlled charging current. In recent
market trends, the sealed maintenance free starting system for the diesel engines is
available from the reputed manufactures like Cummins.
The spray pump is huge pump in the FF system of capacity 125 KW. The full
load current of the motor is 201 A. This pump is vital for the fire fighting system since
it starts only in case of emergency when all motors could not cope with the low water
pressure in case of fire. At the time of commissioning this pump was provided with
DOL (Direct online) starter due to which it takes six times the full load current (1204
A).
Recent times most efficient and flexible current control starters named soft starters
are available in the market.
Hydro-pneumatic tank
discharge pumps connected to Diesel engine or Electric driven pump will come into
picture. However for small pressure drop occurring in the system pressure owing to
minor leakages, Jockey pumps only shall run.
To avoid frequent cycling of the jockey pump and also reduce the water hammer and
pressure rise phenomenon in fire fighting system, Hydro-pneumatic tanks as
temporary energy storage devices are provided in the system. The size of the Hydro-
pneumatic tank is arrived based upon the above mentioned considerations. In power
grid 3 m3 the Hydro-pneumatic tank capacity in all substations.
The Hydro-pneumatic tank uses captive air compressed with water pump operation
for storing the energy. In Older Hydro-pneumatic systems for fire fighting system, Air
compressor was used to pump air into the system whenever air pressure in the
system dropped below threshold. In present day systems these compressors are
avoided. But in the absence fresh air into the system, the existing air column may
deplete due to air molecules getting absorbed in the water. This may result in water
logging in Hydro-pneumatic tank and eventually result in frequent pump cycling
occurring because of insufficient energy storage in the tank. The draining of Hydro-
pneumatic tank unable to resolve the problem, as no opening was available in the
top of the tank to inject the fresh air. For Drain out of tank, piping arrangement was
provided at top of the tank.
The valve was located at a convenient position, to facilitate the operator to carry out
the draining of the system, while simultaneously opening of air intake valve. After
completing the above modification the pump cycling successfully reduced.
Substation lighting:
For achieving the above specified lux levels in the switchyard, sodium or mercury
vapour luminaries of 400W/ 250W are used as per requirement. Indoor illumination is
generally achieved by various types of fluorescent / CFL & incandescent type of
lamps depending on applications.
In addition to above following items are generally required for illumination system:
AC Normal Lighting-
415 V Main Lighting distribution board located in MCC room feeds all normal AC
lighting requirement of substation.
AC Emergency Lighting-
415V Emergency lighting distribution board located in MCC room feeds all
emergency lighting requirements in strategic locations like control room, fire fighting
pump house, DG room & in switchyard area. Under normal circumstances this
distribution board is fed from main supply through auxiliary transformers, however in
case of emergency the board is fed by DG set of substation.
DC Emergency Lighting
AIR-CONDITIONING SYSTEM:
-Control room
-Conference room.
-DGMs room.
-Battery Room
Air-Conditioning units for control room building shall be set to maintain the following
inside conditions 24C 2 C.
Chapter 5