Академический Документы
Профессиональный Документы
Культура Документы
Abstract
This paper presents a method for buffering critical resources in make-to-order shop floor control in manufacturing
complex products. The research was done in Marine Diesel Engines Factory, HCP S.A. Poznan conditions. HCP
S.A. Poznan is the biggest producer of high- power marine engines in Europe. These methods of buffering critical
resources include procedures of buffers management, (buffers configuration and optimization), a system of
disruptions compensation and feedback protecting from destructive influence of wandering bottlenecks. The flow
simulations show that this method is more effective than classical drum-buffer-rope production solution, according
to TOC, using FIFO rule. Finally, the lead-time and the level of work-in-process were about 20% lower than the
solution recommended to TOC.
Keywords:
TOC (Theory of Constraints), Make-to-order company, A-plant (V-A-T analysis)
production batch
mechanism (Drum-Buffer-Rope) [figure 3]. The planning
and breaking
algorithms assume the creating critical resource work
The area of effective
cycle
self-control of FIFO
Statistical process fluctuation will always be the type The studied parameters were: the length of lead-times, the
belonging to group A as this is the idea of TOC concept number of set-ups of production resources, resources
that it is the integral part of the production process. utilization and financial parameters such as net profit and
Group B includes disruptions compensated by the capacity and the level of works-in-process. The results
production system (exactly speaking the resources- were better by about 20% for the developed buffering
compensators existing in the system) and the system of method (Simulation 1) than for the reference TOC
procurement logistics. Group B comprises such (Simulation 2).
disruptions as:
long-lasting breakdowns of machines and Diagram 1. The results of simulation for the method of
appliances, buffering (Simulation 1) and the reference model TOC
employees absences, (Simulation 2).
deviations from the scheduled deliveries of materials
and subassemblies, The length of lead-time
temporary shortages of universal tools.
40
The third category of disruptions (group C) includes non- 35
Simulation
compensated disruptions. No system of compensation can 30
"1"
cover all possible kinds of disruptions. In the case of the 25
least frequent disruptions and the biggest ones as far as 20 Simulation
their length is concerned, any protection against their "2"
15
influence would be highly inefficient and unprofitable. In
10
this case the activities should be aimed at the limitation of
number their occurrences. 5
0
The last but not the least element of the method is the A D F
procedure of buffer reconfiguration. The assumed size of
the buffer in the process of its reconfiguration and There is also a very visible tendency to improve the results
calibration is the base for further planning of the flow of for the buffering method along with the level of flow
materials. The materials issues for production taking place complexity and the growth of disruptions level in the
ahead of time are not of permanent character and have to production system.
undergo changes. The implementation of buffer
reconfiguration should limit the possibility of wandering
bottlenecks that have a strong and destructive influence Initial capacity
Sales balancing for
on the constraint buffer. plan critical resources
The change of buffer size for new orders should take place
always when:
the average load of a post has increased, especially Final products Capacity
when the emergency level of particular non-critical schedule balancing
resources has been reached,
the disruption of flow has taken place (e.g. a
Production Final
breakdown) and it wasnt fully compensated by the Framework
schedule products
reserve resources (which means that the time Schedule of level
constraint buffer requires reconstruction) engine
the dynamic of production system has been changed building.
due to unknown in the particular moment reasons. Coope-
The analysis of buffer penetration trend for individual Strategic machines Components ration
orders showed the increasing trend. schedule schedule
Parts
The last element of buffer reconfiguration procedure is the level
Scheduling production
global feedback between the configuration loop of DBR
flow according to TOC.
and the loop of flow balancing. It is the feedback
procedure taking into consideration breakdowns, changes Operation
of dynamic due to the change of average load of positions Critical level
or the change of the trend which determines the size of resources
buffer penetration. The purpose of the feedback is creating
the possibility of the reconstruction of constraint buffer in
subsequent planning cycles and preventing the Work stations
occurrence of wandering bottlenecks. Suppliers Customers
4 VERIFICATION OF THE METHOD AND PLACING IT Figure 5: The planning system of HCP SA Marine Diesel
IN THE PRODUCTION SYSTEM Engines Factory (W2) and the position of the suggested
The method was verified within the area of planning for method of buffering critical resources.
data acquired in the company. The second verification was
carried out in order to compare the effectiveness of the The next step in the studies is placing the developed
developed model of planning to the reference model TOC method in the system of production planning and
Drum-Buffer-Rope Solution, The simulations were done managing. The suggested method of buffering the critical
with the use of Goldratt Simulator Version 1.0 Copyright resources fills the existing gap in the planning system
(C) 2002 application. (figure 5) On the level of elements it combines information
about the critical resources load with the planning level
according to operation. It is a combination of data from two
key documents in the planning system of the company: the
plan of engine building (framework schedule) and the
schedule of critical resources load.
Such a way of positioning the method in the planning
system enables solving the problem of the sequence of
tasks for non-critical resources and at the same time
ensuring the bottleneck work continuity. Therefore the
buffering method is a practical application of the step of
exploitation (step 2) and the step of subordination (step 3)
belonging to the 5 focusing steps. Since the existing
planning system of the company is the system of MRPII
class after positioning the buffering method in it a hybrid
MRP/TOC system was created.
5 CONCLUSIONS
For the make-to-order manufacturing complex products
the best system of planning and managing the production
flow is the hybrid system MRP/TOC. Developing of such a
system requires creating and implementation of buffering
method which is a sufficient tool of scheduling the
production flow and assuring the continuity of critical
resources flow. Such a method must include developed
methodics of constraint buffer configuration and an
appropriate system of disruption compensation which
allows keeping global buffers of correct size as well as
effective balancing the flow aiming at critical resource.
6 REFERENCES
[1] Encyclopedia of Production and Manufacturing
Management, Kluwer Academic Publisher,
Boston/Dordrecht/London 2000, 742-746.
[2] Hadas L., Domanski R., Identification of the
production-management problems in the production
enterprise of a long-cycle produce, Poznan University
of Technology Institute of Engineering Management,
Poznan 2005, 52-57.
[3] Hadas L., Global buffering in production systems
according to TOC, Poznan University of Technology
Institute of Engineering Management, Poznan 2006,
267-273.
[4] Goldratt E., Cox J., The Goal. Excellence in
production, WERBEL, Warsaw 2000, 216-218.
[5] Goldratt E., Critical Chain, WERBEL, Warsaw 2000,
102-112.
[6] Umble M., Analyzing Manufacturing Problems using
V-A-T Analysis, Production and Inventory
Management Journal; Second Quarter 1992, Vol. 33,
Issue 2, 55-60.
[7] Umble M., Srikanth M. L., Synchronous
manufacturing: principles for world-class excellence,
Spectrum Publishing, Connecticut 1995, 211-255.