I. HSE Matters
Based on marine inspection on 20 February 2011, found any findings at LCT. Teluk
Bontang which needs to be complied before IRC or MOP can be issued. No activity
since 21 February 2011.
Item. 10752C
Installation of goose neck and 3 drain line at T-922
Status:
- Modification of 6 goose neck line already completed.
- Stringing material and double joint of 3 drain line from T-922 to disposal tube area
Remaining
- Install line from 6 goose neck to flame arrestor
- Install pipe support and operating access for 3 drain line, must be done by cold job.
- Replace corroded level glass of T-922, waiting material from CPA/MNT.
III. Main Events on the Period.
Item. 11075C
Replace 12 valve SDV 5083
Status:
Completed
Item. 10599C
Replace corroded plate and nozzle at T-922
Status:
In progress.
Item. 10752C
Installation of goose neck and 3 drain line T-922
Status:
In progress
Item. 11002C
Replacement of corroded reducer and sprinkler FW line at API
Item. 10807C
Repair corroded section of jetty structure API area
Item. 10563C
Install scaffolding at V-9200 to assist CPA/INS
NIL