Вы находитесь на странице: 1из 13

RATE ANALYSIS - BRICKWORK

Akhila Udayashankar A-1472


Mani Mathur A-1502
Suranjana Datta A-1536
1.CALCULATION OF MATERIALS PER 10 cu m. VOLUME OF BRICK

METRIC BRICKS
No. of metric brick having size with mortar 10 cm x 10 cm x 20 cm
= 10 = 5000 nos.
0.1 x 0.1 x 0.2

The size of one metric brick without mortar is 9 cm x 9 cm x 19 cm


Therefore mortar required per 10 c.m. = 10-(5000 x .09 x .09 x .19) = 2.3 cu m.
Due to frog filling, brick bonding courses and wastage, etc. increase this quantity by 15%
therefore, volume of wet mortar = 2.3 + 2 .3 x .15 = 2.64 cu m
when dry, increase this quantity by 1/3 = 2.64 + 2.64 x 1/3 = 3.5 cu m
In case of lime mortar, the above quantity., 3.5 cu m. reaches upto 4.0 cu m. .Such increase
may be justifies considering the void in surkhi is more, joints are generally thicker and
additionally, less care is observer towards wastage.
With second class bricks, the quantity of cement mortar of 4.0 cu m. and lime mortar of 4.2
cu m. are required according to the shape and size of second class bricks.
TRADITIONAL BRICKS

No. of traditional bricks having size with mortar 25.4 cm x 12.7 cm x 7.6 cm =
10 = 4079 nos. , say, 4100 nos.
0.254 x 0.127 x 0.076
With this traditional size of bricks, joints are less, and therefore lesser amount of mortar
should be required. But due to larger size of frog and wider area of a brick such variation
may be minimized.

TRADITIONAL BRICKS
No. of traditional bricks having size with mortar 22.9 cm x 11.4 cm x 7.6 cm =
10 = 5041 nos. , say, 5000 nos. (due to thi
0.229 x 0.114 x 0.076

The no. of bricks being same to that of metic brick and the quantity of mortar is also
same.

2. FIRST CLASS BRICKWORK IN LIME AND SURKHI MORTAR (1:3 FOUNDATION AND
PLINTH)

Consider first 10 c.m.


Calculation of materials: Lime = 4/4 = 1.0 c.m.
Surkhi = 1.0 x 3 = 3.0 c.m.
PARTICULARS QUANTITY RATE AMOUNT
Rs. P.
(a) Materials - Brick (kiln) 5000 nos. 8p per no. 4000
metric 20 x 10 x 10 cm
traditional 25.4 x 12.7 x 7.6 cm 4100 nos.
22.9 x 11.4 x 7.6 cm 5000 nos.
Surkhi 3.00 cu m 146.00 per cu m 438
Lime 1.00 cu m 398.00 per cu m 398
(b) Labour- Head mason 1/2 no. 38.00 per day 19
Mason 8 nos. 35 each per day 280
Mazdoor (2 nos. as bhisti) 10 nos. 20.00 per day 200
Mazdoor (female) 6 nos. 20.00 per day 120
Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 27.27 27.27
Total = 5482.27
(c) Water charges 1% of the total 54.82
Total = 5537.09
(d) Profit and overhead 10% 553.7
Rate per cu m. = Rs. 609.107 Grand total = 6090.79
3. FIRST CLASS BRICKWORK IN CEMENT MORTAR (1:4) IN SUPER STRUCTURE,
GROUND FLOOR

Consider first 10 c.m.


Calculation of materials: Cement = 3.5/5 = 0.7 cu m
Sand =0.7 x 4 = 2.8 cu m

PARTICULARS QUANTITY RATE AMOUNT


Rs. P.
(a) Materials -
Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000
Sand ( medium) 2.8 cu m 130 per cu m 364
Cement 0.70 cu m = 21 bags 2.1 bags 73 per bag 1533
Scaffolding L.S 20 20
(b) Labour-

Head mason 1/2 no. 38.00 each per day 19


Mason 8 nos. 35 each per day 280
Mazdoor (2 nos. as bhisti) 10 nos. 20.00 per day 200

Mazdoor (female) 7 nos. 20.00 per day 140

Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 32.78 32.78

Total = 6588.78

(c) Water charges 1% of the total 65.88

Total = 6554.66

(d) Profit and overhead 10% 655.46

Rate per cu m. = Rs.721.01 Grand total = 7210.12

BRICKWORK FOR ADDITIONAL STOREY:

Labour cost of 1 mason, 3 mazdoors, and a lump sum amount of Rs. 20 for scaffolding per 10
cu m. volume of work are to be added over the ground floor as illustrated in the next slide.
According to All India Standard Schedule of Rates an extra overrate of 1% shall be added per
floor of brickwork, taking each floor to be of average 3m height
4. FIRST CLASS BRICKWORK IN CEMENT MORTAR (1:6) IN SUPER STRUCTURE,
FIRST FLOOR

Consider first 10 c.m.


Calculation of materials: Cement = 3.5/7 = 0.5 cu m
Sand =0.5 x 6 = 3.0 cu m

PARTICULARS QUANTITY RATE AMOUNT


Rs. P.

(a) Materials -
Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000
(For 25.4 cm x 12.7 cm x 7.6 cm) 41000 nos.
(For 22.9 cm x 11.4 cm x 7.6 cm) 5000 nos.
Sand ( medium) 3 cu m 130 per cu m 390
Cement 0.50 cu m = 15 bags 15 bags 73 per bag 1095
Scaffolding L.S 30 30
(b) Labour-
38.00 each per
Head mason 1/2 no. day 19
35 each per
Mason 9 nos. day 315
Mazdoor (2 nos. as bhisti) 13 nos. 20.00 per day 260
Mazdoor (female) 7 nos. 20.00 per day 140
L.S 1/2 %(a +
Contingencies, T and P, risk etc. b) 31.24 31.24
Total = 6280.24
(c) Water charges 1% of the total 62.8
Total = 6343.04
(d) Profit and overhead 10% 634.3
Rate per cu m. = Rs.697.73 Grand total = 6977.34

5.FIRST CLASS BRICKWORK IN PLAIN ARCHES IN SUPERSTRUCTURE SPAN NOT


EXCEEDING 6M IN CEMENT MORTAR 1:4 INCLUDING CENTERING AND
SHUTTERING COMPLETE

PARTICULARS QUANTITY RATE AMOUNT


Rs. P.
(a) Materials -
First class brick (metric) 5000 8p per no. 4000
Sand ( medium) 2.80 cu m 130 per cu m 364
Cement 0.70cu m = 21 bags 21 bags 73 per bag 1533
Centring and shuttering -
Considering a semi circular arch 3.6
m
clear span 3.0 m long and .40 m thk.
area of centring = 3.142 x 1.8 x 3.0
16.97 sq m
Brickwork in arch = 3.142 x 2 x .4 x
3.0
= 7.54 cu m
area/ 10 cu m =16.97/ 7.54x10 =22.5
sqm 22.5 sq m 30.00 per sq m 675
Scaffolding L.S 25 25
(b) Labour-
Head mason 1 no. 38.00 each per day 38
Mason 10 nos. 35 each per day 350
Mazdoor (2 nos. as bhisti) 22 nos. 20.00 per day 440
Contingencies, T and P, risk etc. L.S 1/2 %(a + b) 37.12 37.12
Total = 7462.12
(c) Water charges 1% of the total 74.62
Total = 7536.74
(d) Profit and overhead 10% 753.67
Rate per cu m. = Rs.829.04 Grand total = 8290.41

Extra rate for brickwork (1:4) in plain arches = Rs.527.35 Rs.452.76 = Rs.74.59 cu m
Extra labour rate for brickwork only = Rs.464.00 Rs.358 = Rs.106 per 10 cu m
According to IS-1200, the brickwork rate for arches of span not exceeding 6m, hire and
labour charges for centering and shuttering shall be included in the item and for spans
exceeding 6m centering and shuttering shall be measured separately.
6.HALF BRICK i.e10 CM BRICK WALL IN CEMENT MORTAR (1:3)WITH PLAIN ARCHES
WITH H.B NETTING IN EVERY THIRD LAYER(GROUND FLOOR)

Consider first 10 c.m.


Calculation of materials: Bricks(metric) = 100 = 5000 nos.
.10 x .20
Volume of mortar35% to the volume of work = 100 x .10 x .35 = 3.5 cu m. Due to half
brickwork, volume of mortar becomes 10% less than 3.5 cu m. = 3.5 0.35 = 3.15 cu m.
Therefore, cement = 3.15 / 4 = 0.79 cu m
sand = .79 x 3 = 2.37 cu m.
Wire netting for every third layer i.e, 30 cm intervals (considering a wall 10m length x
10m height) = 10 x 10 / .30 = 334 rm, with 10 cm wide area of netting =
334 x .10 = 33.4 sq m.

PARTICULARS QUANTITY RATE AMOUNT


Rs. P.
(a) Materials -
Brick (kiln) - 20cm x 10cm x 10cm 5000 8p per no. 4000
(For 25.4 cm x 12.7 cm x 7.6 cm) 41000 nos.
(For 22.9 cm x 11.4 cm x 7.6 cm) 5000 nos.
Sand ( medium) 2.37 cu m 130 per cu m 308.1
Cement (0.79 cu m = 23 bags) 23 bags 73 per bag 1679
Wire netting 33.4 sq m 30 per sq m 1002
Scaffolding L.S 25 25
(b) Labour-
38.00 each per
Head mason 1/2 no. day 19
Mason 14 nos. 35 each per day 490
Mazdoor (2 nos. as bhisti) 21 nos. 20.00 per day 420
L.S 1/2 %(a +
Contingencies, T and P, risk etc. b) 39.71 39.71
Total = 7982.81
(c) Water charges 1% of the total 79.83
Total = 8062.64
(d) Profit and overhead 10% 806.26
Rate per cu m. = Rs.88.69 Grand total = 8868.90

7. HALF BRICKWORK FOR EACH HIGHER STOREY:


Labour costs of 3 mazdoors (beldars) is to be added to lift the materials over and above
the above costs
8.SECOND CLASS BRICKWORK IN MUD MORTAR IN SUPER STRUCTURE,
GROUND FLOOR

PARTICULARS QUANTITY RATE AMOUNT


Rs. P.
(a) Materials -
Brick second class ( metric) 5000 8p per no. 4000
Clay ( selected loamy soil) 4.00 cu m 12.50 per cu m 50
Scaffolding L.S 25 25
38.00 each per
(b) Labour- Head mason 1/2 no. day 19
Mason 8 nos. 35 each per day 280
Mazdoor (1 nos. as bhisti) 12 nos. 20.00 per day 240
L.S 1/2 %(a +
Contingencies, T and P, risk etc. b) 28.02 28.02
Total = 5632.52
(c) Water charges 1% of the total 56.32
Total = 5688.84
(d) Profit and overhead 10% 568.88
Rate per cu m. = Rs. 625.77 Grand total = 6257.72

Вам также может понравиться