Вы находитесь на странице: 1из 6

Optimal Location of Distribution Generation Source

in Power System Network


Vivek Kumar Shrivastava1 O.P.Rahi2 Vaibhav Kumar Gupta3 and Sameer Kumar Singh4
Department of Electrical Engineering, NIT Hamirpur, Himachal Pradesh, India
1
viveknit.paper@gmail.com
2
oprahi2k@gmail.com
3
vaibhavele.nith@gmail.com
4
samtridev@yahoo.ie

Abstract Distributed Generation (DG) is growing rapidly more costly grid electricity. DG can meet all or part of a
in power systems due to their potential solution for issues, like customers power needs. If connected to a distribution or
the deregulation in power system, to meet the power demand transmission system, power can be sold to the utility or a
and the shortage of transmission capacities. Optimal third party. The main reasons for the increasingly
placement of DG assumes significance that improper widespread use of DG can be summed up as follows [1]:
allocation of DG sources in power system would not only lead
to increased power or energy losses, but can also jeopardize It may be more economic than running a power
the system operation. Also optimal placement of DG is line to remote locations.
necessary for the maximization of reliability and stability in It provides primary power, with the utility
power system. In this paper classical grid search algorithm providing backup and supplemental power.
based on successive load flows has been employed to obtain
optimal location and size of multiple DG units in radial power It can provide backup power during utility system
system network in order to minimize total active power losses outages, for facilities requiring uninterrupted
and to improve voltage profile of the system. The proposed service.
method is the extension of single DG placement to the It can provide higher power quality for electronic
placement of multiple DG units. It is significant because of the equipment.
fact that with the integration of DG units at various locations, For reactive supply and voltage control of
there is more reduction in total power losses and maximum generation by injecting and absorbing reactive
voltage drop in the system is also decreased. The proposed
power to control grid voltage.
method is tested on 12-bus radial distribution feeder with
different sizes of DG source. The obtained results are For network stability in using fast response
presented in graphical manner. equipment to maintain a secure transmission
system.
Keywords- Distributed generation (DG); optimal location; For system black-start to start generation and
optimal size; grid search method; radial distribution network; restore a portion of the utility system without
active power loss; voltage profile outside support after a system collapse.

I. INTRODUCTION The optimal placement of DG has attracted many


researchers attention recently due to its ability to obviate
Distributed power generation is a technology that could defects caused by improper installation of DG units, such
help to enable efficient, renewable energy production both as rise in system losses, decline in power quality, voltage
in developed and developing world. Distributed generation increase at the end of feeders and etc [4]. Integrating DG
(DG) is related with the use of small generating unit sources within the network can improve both the reliability
installed at strategic point of electric power system or and efficiency of the power supply; release the available
locations of load centre's [1]. Distributed generation is an capacity of the distribution substation as well as reducing
electric power source connected directly to the distribution thermal stresses caused by loaded substations, feeders, and
network or on the customer site of the meter [2].DG can be ancillary equipment; improve the system voltage profiles as
used in an isolated way, supplying the customers local well as the load factor; and delay the imminent upgrade of
demand, or integrated into the grid supplying energy to the present system or the need to build newer infrastructure.
remainder of the electric power system. DG technologies The extent of these benefits depends on how the DG is
includes engines, small wind turbines, fuel cells and placed and sized in a system. In addition to supplying the
photovoltaic system .DG technologies can run on system with the power needed to meet certain demands as
renewable energy resources, fossil fuels or waste heat. an installation incentive, the real power losses could be
Equipment ranges in size from less than a (kW) to tens of minimal if the DG is optimally sited and sized. DG optimal
megawatts (MW). Despite their small size, DG allocation and sizing is an ongoing research area [5]. The
technologies are having a stronger impact in electricity exact solution of the DG allocation can be obtained by a
markets. In some markets, DGs are actually replacing the

978-1-4673-0766-6/12/$31.00 2012 IEEE


complete enumeration of all feasible combinations of sites The grid search algorithm involves setting up a suitable
and sizes of DGs in the network [3]. grid in the design space, evaluating the objective function
In this paper the classical grid search algorithm based at all the grid points, and finding the grid point
on successive load flows has been employed to obtain corresponding to the lowest function value [9]. For
optimal location and size of multiple DG units in radial example, if the lower and upper bounds on the ith design
power system network system to minimize total active variable are known to be li and ui, respectively, we can
power losses and improve the voltage profile of the system. divide the range (li, ui) into pi 1 equal parts so that xi(1),
The proposed methods are tested by a series of simulations xi(2), ., xi(pi) denote the grid points along the xi axis (
on 12-bus radial distribution system with different sizes of i=1,2,..n). This leads to a total of p1 p2 ..pn
DG source. Simulation results have been given to verify the grid points in the design space. For problems with a small
proposed method. number of design variables, the grid method can be used
conveniently to find and approximate minimum. Also, the
II. PROBLEM FORMULATION grid method can be used to find a good starting point for
one of the more efficient method. The algorithm for
The total active power loss for a radial distribution
placement of multiple DG units has been given below:
system with N-1 branches is given by [13]
Step 1: Initialize system parameters.
Step 2: Run load flow analysis for the original base system
and obtain total real/active (PLOSS) and reactive power loss
(QLOSS) in the system, voltage profile and current profile at
each bus.
where Ik and Rk are the real part of current magnitude and
resistance, respectively, of branch k. N is the total number
of bus while N-1 is the total number of branches in the
system. The branch current can be obtained from the load
flow solution. The total power loss in the system is the sum where Ik and Rk are the real part of current magnitude and
of real power loss (PLOSS) and reactive power loss (QLOSS) resistance, respectively, of branch k. N is the total number
respectively. of bus while N-1 is the total number of branches in the
system.
The objective function is to minimize real power loss of Step 3: Initialize i = 1 (i = bus no. of DG); i = 1,2,3N.
the radial distribution system by injected real power of DG Step 4: Check whether i > N, if the given condition is
(PDG) for DG placement subjected to restrain voltages along satisfied go to step 11 otherwise go to next step.
the radial system within 1 0.05 p.u. and power generation Step 5: Set PDG=0 (PDG= size of DG); 0 PDG PLoad.
limit i.e. maximum DG size is selected as total load size of Step 6: Check whether PDG > PLoad, if the given condition
the system[7,8]. The maximum number of DG which can is satisfied go to step 10 otherwise go to next step.
be installed in a DG is also restricted to NDG = 3. This Step 7: Run the load flow for the new modified system with
optimization problem is converted to a single objective DG and obtain total real/active (PLOSS) and reactive power
problem and the mathematical formulation of the problem loss (QLOSS) in the system, voltage profile and current
is expressed as follows: profile at each bus.
To minimize: f (PDG) = PLoss Step 8: Identify the maximum saving for minimum
Subject to constraints: real/active power loss (PLOSS) and the corresponding DG
i. |Vi | 1 0.05 p.u. , i = 1,2,3..N size (PDG). The corresponding bus is a candidate bus where
ii. 0 PDG PLoad DG can be placed.
iii. 0 NDG 3 Step 9: Modify the active load at this bus, PDG =PDG+ ( =
III. METHODOLOGY step size; step size is 1% of PLoad).Go to Step 6.
Step 10: Initialize i = i+1 and go to Step 4.
To find the optimum location and size of multiple DG Step 11: Find minimum real/active power PLOSS.
units classical grid search algorithm based on successive Step 12: Check for voltage constraint as follows: |Vi | 1
load flows has been implemented [7, 8]. The Grid Search 0.05 p.u., i = 1, 2, 3..N. If the given condition is satisfied
algorithm is applied by placing a DG to each bus, by go to step 14 otherwise go to next step.
changing the size of DG from 0% of total load power to Step 13: Reject unsuitable values.
100% of total load power with the step size of 1% (step size Step14: For minimum real/active PLoss, Find optimum
of 0.01MW) of total load power. The total power loss has location (i) and the corresponding DG size (PDG). Identify
been calculated by a complete power flow analysis for each the maximum saving. Compare the reactive power loss
case. The case with minimum losses determines the (QLOSS), voltage profile and current profile of the modified
optimum location and size of DG. After that, the bus system with those of original base system.
voltages are controlled whether the bus voltages are within Step 15: Place the DG of size (PDG) at the optimum location
the acceptable range. (i).
Step 16: Check whether the saving obtain is more than the system voltage drop is reduced drastically when
1Kw. If yes, go to step 2. Otherwise, go to next step. compared with initial voltage drop.
Step17: Print all the candidate locations to place DG
sources and the sizes.

The flowchart for the placement of single DG in the


radial distribution power system network has been shown
in Fig.1 in the APPENDIX.
TABLE I: LINE LOSS WITH SINGLE DG
IV. LOAD FLOW STUDY
Due to the high R/X ratios and unbalanced operation in Bus No. Optimum Active Line Reactive Line
distribution systems, the Newton-Raphson and ordinary Size of DG Losses (MW) Losses (MVAr)
(MW): PDG1 PLOSS QLOSS
Fast Decoupled Load Flow method may provide inaccurate 1 0.43500 0.02069 0.00806
results and may not be converged [14]. Therefore, 2 0.43500 0.01867 0.00721
conventional load flow methods cannot be directly applied 3 0.43500 0.01703 0.00653
to distribution systems. An efficient load flow solution 4 0.40455 0.01480 0.00561
technique is required for application to radial 5 0.35670 0.01257 0.00469
6 0.34365 0.01200 0.00445
distribution networks. This method exploits 7 0.33495 0.01158 0.00428
the radial nature of the network and uses forward and 8 0.28275 0.01088 0.00410
backward propagation to calculate branch currents and 9 0.23490 0.01076 0.00414
node voltages. In this paper, network topology based 10 0.22185 0.01102 0.00424
forward/backward sweep algorithms using Kirchhoffs 11 0.20880 0.01130 0.00435
12 0.20010 0.01670 0.00448
Laws or making use of the well-known bi-quadratic
equation have been used for load flow analysis Due to its
low memory requirements, computational efficiency and From table I: it can be seen that for DG size of 0.23490
robust convergence characteristic[15,12]. MW at bus 9, active line losses are reduced from 0.02069
MW to 0.01076 MW and reactive line losses are reduced
from 0.00806 MVAr to 0.00414 MVAr.
V. RESULT AND DISCUSSION
TABLE II: LINE LOSS WITH 2 DGs
The proposed method is tested on 12- bus radial
distribution feeder with different sizes of DG. The load and Bus No. Optimum Active Line Reactive Line
line data of the 12 bus distribution test system can be found Size of DG Losses (MW) Losses (MVAr)
in [10].The classical grid search algorithm is employed (MW): PDG2 PLOSS QLOSS
with the power flow program MATPOWER [11] to 1 0.43500 0.01076 0.00414
validate the results. The classical grid search algorithm 2 0.22275 0.01033 0.00395
3 0.19440 0.01010 0.00386
takes computation time depending upon size of the system 4 0.15225 0.00993 0.00379
and power steps. 5 0.11310 0.00999 0.00382
6 0.10440 0.01005 0.00384
The parameters of 12-bus system are given in [10]. The 7 0.08700 0.01012 0.00387
total real power and reactive power loads on this system are 8 0.04350 0.01054 0.00401
9 0.23490 0.01076 0.00414
0.4350 MW and 0.4050 MVAr. The initial real and reactive
10 0.01305 0.01073 0.00410
power losses in the system are 0.02069 MW and 0.00806 11 0.01305 0.01072 0.00410
MVAr. Based on the method described previously, the 12 0.01305 0.01072 0.00410
optimal sizes of DG are calculated at all buses for the test
system. From table II: it can be seen that for DG size of 0.15525
MW at bus 4, active line losses are reduced from 0.01076
Based on classical grid search method described above MW to 0.00993 MW and reactive line losses are reduced
the optimal sizes of DG are calculated at all buses for the from 0.00414 MVAr to 0.00379 MVAr.
test system. Fig.2 shows the optimal sizes of DG units at all
buses for test system. The real and reactive power losses for TABLE III: VOLTAGE PROFILE
the corresponding DG unit sizes are shown in Fig.3 and
Fig.4. Improvement in voltage profile and current profile Bus No. Voltage Profile Voltage Profile Voltage Profile
was observed from Fig.5 and Fig.6 for 12bus distribution without with single with double
DG (p.u.) DG (p.u.) DG (p.u.)
feeder. Results of proposed method, total power losses with
1 1.00000 1.00000 1.00000
and without DG obtained have been tabulated in Table I, 2 0.99433 0.99655 0.99793
Table II, Table III and Table IV for the test system 3 0.98902 0.99366 0.99655
respectively. It has been observed that the total power 4 0.98057 0.98950 0.99505
losses are significantly reduced for all test systems. With 5 0.96983 0.98526 0.99084
the increase in integration of more number of DG units in 6 0.96654 0.98420 0.98979
7 0.96376 0.98347 0.98906
8 0.95533 0.98398 0.98957

>>W>K^^ Dt
9 0.94730 0.98735 0.99292
10 0.94448 0.98464 0.99023
11 0.94358 0.98378 0.98937 >>
12 0.94337 0.98358 0.98917 
'Dt
From table II: it can be seen that with the integration of
single DG in the system there is reduction in maximum >>
voltage drop from 5.663% to 1.653% which further reduces 
to 1.094% with the integration of 2nd DG source into the 12 'Dt
bus test system.
>>
The obtained results are presented in graphical manner '
Dt
shown below in Fig.2, Fig. 3, Fig.4, Fig. 5 and Fig. 6
respectively. Fig. 2 shows optimum size of DG (MW) to be
installed in the radial power system at different bus. From E
this graph it can be seen that the optimum size of second
DG to be installed in system gets significantly reduced Fig. 3: 12-Bus Line Losses P (MW)
LOSS
when compared with the optimum size of first DG to be
installed in the system. Fig. 3 and Fig. 4 shows curve
between active power loss vs bus no. and reactive power
loss vs bus no. respectively for optimum size of DG at
different bus. It can be observed that by installing DGs at

>>Y>K^^Ds

all the potential locations, the total power loss of the system
has been reduced. Fig. 5 and Fig. 6 shows curve for voltage
>>
and current profile at different bus.

'Ds
>>

'Ds
K^'Dt


K >>
 '
'Dt Ds
K
 E
'Dt

Fig. 4: 12-Bus Line Losses Q (MVAr)
LOSS


s
sW




'
E
Fig.2: 12-Bus Optimum Size of DG (MW) s


'
s


'
E
Fig.5: 12-Bus Voltage Profile (p.u.)
CONCLUSION
In this paper the classical grid search algorithm based
on successive load flows has been employed to obtain
optimal location and size of multiple DG units in radial
WZ/  distribution power system network to minimize total power
> losses and improve voltage profile of the system. Improper
 allocation of DG sources in power system would not only
lead to increase power or energy losses, but can also

' jeopardize the system operation. DG should be placed in

the optimal location in order to provide maximum
economical, technical and environmental benefits. The
> proposed methods are tested by a series of simulations on
 12-bus radial distribution feeder with different sizes of DG.
 The obtained results have been presented in graphical
manner. This method is easy to be implemented for the
'
 given accuracy. It is proved that the proposed method can
save huge amount of power and achieve significant
>E improvement in voltage profile and current profile of the
system.
Fig.6: 12-Bus Current Profile Real I (A) for different Line
k
APPENDIX

TABLE IV: 12 BUS SYSTEM RESULT

System No DG Single DG Double DG


Parameter Profile Profile Profile
Active/Real Line 0.02069 0.01076 0.00993
Loss PLOSS at bus 9 at bus 4
(MW)
% Reduction in - 47.99 52.01
Loss
Reactive Line 0.00806 0.00414 0.00379
Loss
QLOSS (MVAr)
% Reduction in - 48.64 52.98
Loss
Maximum 1.0000at bus 1
Voltage (p.u.)
Minimum 0.94337 0.98347 0.98906
Voltage (p.u.) at bus 12 at bus 7 at bus 7
% Maximum 5.663 1.653 1.094
voltage drop
Optimum - 9 4 9
Location
Optimum Size - 0.23490 0.15225 0.23490
(MW)

In table IV, for 12 bus distribution system the total


power losses with and without DG are tabulated. It is seen
that active power losses are reduced from 0.02069 MW to
0.00993 MW and reactive power losses are reduced from
0.00806 MVAr to 0.00379 MVAr with the integration of 2
DG units in the system i.e., DG unit of size 0.23490 MW at
bus 9 and 0.15225 MW at bus 4. Also maximum voltage
drop in the system has been reduced from 5.663% to
1.094%. With the integration of more DG units in the
system, there is huge amount of power saving and
significant improvement in voltage profile and current
profile of the system.
Fig. 1: Flowchart for Single DG Placement
REFERENCES [9] S.S. Rao, Engineering Optimization: Theory and Practice, third ed.,
Wiley-Interscience, New York, 1996.
[1] L.L.Lai and T.F.Chan, Distributed Generation: induction and
permanent magnet generators,Wiley,2007. [10] P.Ravi Babu, C.P.Rakesh, G.Srikanth, M.Naveen Kumar and
D.Prabhuvardhan Reddy, A Novel Approach for Solving
[2] T. Ackermann, G. Andersson and L. Soder, Distributed generation: Distribution Networks, Annual IEEE India Conference
a definition, Electric Power Systems Research,Elsevier, 2001. (INDICON), 2009
[3] M. Gandomkar,M. Vakilian, M. Ehsan, Optimal distributed [11] R.D. Zimmerman, C.E. Murillo-Snchez, D. Gan, MATPOWER : A
generation allocation in distribution network using Hereford Ranch MATLAB Power System Simulation Package,
algorithm, Proceedings of the Eighth International Conference on www.pserc.cornell.edu /matpower/matpower. html (access date:
Electrical Machines and Systems, 2005.Volume 2, Issue , 27-29 April 20,2007).
Sept. 2005, pp. 916 918.
[12] D. Thukaram, H.M.W. Banda, J. Jerome, A robust three-phase power
[4] M. Sedighizadeh, M. Fallahnejad, M. R. Alemi, M. Omidvaran and flow algorithm for radial distribution systems, Electric Power
D. Arzaghi-haris, Optimal Placement of Distributed Generation Systems Research 50 (3) (1999),pp 227236.
Using Combination of PSO and Clonal Algorithm,IEEE
International Conference on Power and Energy (PECon [13] S. F.Mekhamer, Hawary,S.A.Soliman,M.A.Moustafa,M.M.Mansour,
2010),Malaysia New Heuristic Strategies for Reactive Power Compensation of
Radial Distribution Feeders, IEEE trans. Power Delivery,Vol. 17,
[5] M. F. Alhajri, M. R. Alrashidi and M. E. EL-Hawary, Improved October 2002, pp. 1128-1135
Sequential Quadratic Programming Approach for Optimal
[14] J. B. V. Subrahmanyam, Load Flow Solution of Unbalanced Radial
Distribution Generation Deployments via Stability and Sensitivity
Analyses, Electric Power Components and Systems, 38,pp 1595 Distribution Systems, Journal of Theoretical and Applied
1614, 2010 Information Technology,2005
[6] S. F.Mekhamer, Hawary,S.A.Soliman,M.A.Moustafa,M.M.Mansour, [15] S. Kumar Injeti, Navuri P Kumar, Optimal Planning of Distributed
New Heuristic Strategies for Reactive Power Compensation of Generation for Improved Voltage Stability and Loss Reduction,
Radial Distribution Feeders, IEEE trans. Power Delivery,Vol. 17, International Journal of Computer Applications, Volume 15 No.1,
October 2002, pp. 1128-1135 February 2011
[7] T. Gozel , U. Eminoglu , M.H. Hocaoglu, A tool for voltage
stability and optimization (VS&OP) in radial distribution systems
using matlab graphical user interface (GUI), Simulation Modelling
Practice and Theory 16 (2008),pp 505518, Elsevier,February 2008
[8] T. Gozel , M.H. Hocaoglu, An analytical method for the sizing and
siting of distributed generators in radial systems, Electric Power
Systems Research, 2008

Вам также может понравиться