Академический Документы
Профессиональный Документы
Культура Документы
09/03/2009
TECHNICAL SPECIFICATIONS
OF
LAYING 220KV POWER CABLE IN
NATURAL VENTILATED TRENCH
FOR
220 KV TRANSMISSION LINE
PART II
TECHNICAL SPECIFICATIONS FOR LAYING, TESTING AND
COMMISSIONING OF 220KV XLPE POWER CABLE IN NATURAL
VENTILATEDCONCRETE TRENCH
SECTION-I
1.1.1. The successful Bidder shall have to arrange technical supervision during
installation of cable laying and termination.
1.1.2. The successful Bidder shall arrange for the services of fully qualified and
competent supervising Engineer / Engineers and necessary minimum number
of jointers, semi-skilled labourers, as he deems it absolutely necessary.
1.1.3. Provision of special tools /Plants / appliances required for conductor jointing
and stripping / dressing and application of XLPE insulation etc. shall be made
by the successful Bidder.
1.1.4. The successful Bidder shall furnish all necessary information, including
drawings, manuals and instructions relating to both cable laying and jointing
practice.
1.1.5. The associated civil works, which are necessary for laying / installation of
power cable, though not specifically mentioned, but shall be completely in the
scope of successful Bidder.
1.1.6. The route map showing the proposed installation of power cable will be issued
to the successful Bidder. Cables are to be laid in Double natural ventilated
trench as per instruction of E.I.C.
1.1.7. Successful Bidder has to arrange at his own cost for first-aid, fire protection,
electricity and water requirement at site. He shall also arrange for sign board,
caution board GSECL, safety & security personnel etc. on cable route.
GETCO/E/TSLUC058/R0 DT. 09/03/2009
1.1.8. The successful Bidder has to bear with any temporary interruption that may
occur during actual erection work, when the matter with other agency is
involved.
1.1.9. No idling charges or cost over run for the entire project shall be entertained.
1.1.10. Approval for installation of the cable in a Double natural ventilated trench from
Electrical Inspector shall be arranged by Purchaser. However, permission for
commencement of work and permission for commissioning of cable after
completion of laying has to be arranged by the successful Bidder.
1.1.11. Successful Bidder shall arrange space for working office, workshop & store /
yard for storing requisite materials like kits, cables etc.
1.1.12. The Arbitration in the dispute shall be strictly as per standard commercial terms
& conditions of the GETCO.
1.1.13. Videography of entire process of laying of cable, jointing of cable and jointing of
End terminations shall be done and submitted to Chief Engineer (Engg),
Corporate Office, Vadodara.
1.2.1. The 220kv (E) XLPE cable shall be installed underground in two natural
ventilated concrete trenches leaving spacing of 500mm in between two trenches
and laying two circuits(Trefoil formation) in a trench in two tier. The vertical
spacing between two tier should be sufficient to provide adequate natural
ventilation, necessary design calculation shall be submitted in support and
covering the trenches with perforated roof complying with all applicable
standards and relevant IS & their amendments.
1.2.2 The sealing of power cable ends during the storage; execution & completion of
jointing work shall be in the scope of successful Bidder. Under no
circumstances, the cable ends shall be kept open. The amount due to damages
done because of water / moisture ingress OR penetration in the cable /
conductors during execution shall be recovered from successful Bidder. It shall
be responsibility of successful Bidder to repair OR replace free of cost without
affecting the completion schedule.
1.2.3 Three single core cables shall be laid in trefoil formation for one circuit. Two
circuits in two tier form shall be laid in single trench. The maximum available
width is 3000 mm. The single trench shall be 450mm inside width, the depth of
the trench should be sufficient for two tier with adequate natural ventilation and
spacing between two trenches shall be 500mm. Both the trenches shall be
provided with support of required sizes of channel or angle section so as to
bear the load of cables etc.Design calculation for selection of section shall be
submitted and got approved from CE (ENGG), Corporate Office, Vadodara. The
GETCO/E/TSLUC058/R0 DT. 09/03/2009
1.2.4 The power cable shall be laid generally at a depth to provide natural air
ventilation, design calculation in support shall be submitted.
1.2.5 The cables shall be completely left open to get sufficient air for ventilation.
The cable trench is to be constructed in two tier having 350mm inside width and
height sufficient for two tier rack having free natural air ventilation. Type of
cable trench to be design as per soil strata of sub station and is in the scope of
Bidder.The soil investigation report is available for reference. Top slab of cable
trench should be perforated and sufficient to with stand the live load as per Is
456 .Peforation shall be sufficient to provide adequate natural air vaentilation if
necessary design calculation for the same shall be submitted in support.
1.2.6 The cable drum must be handled correctly and with care during transport and
laying of the power cables, in order to avoid damage to the cables. Any
damages done because of poor handing of the cables to the properties of
corporation, private OR to anybody shall be responsibility of successful bidder
& the GETCO reserves the right to recover the amount due to such damages.
1.2.8 The minimum bending radius of the cable shall be 20xD where D is diameter of
the cable.
1.2.10
The contractor has to keep allotted 220kv power cable, material supplied by him
in safe custody and transport to the respective sites and will be fully responsible
for any damage to or loss of any or all allotted equipments or materials supplied
by him at any stage during transportation or erection or taking over of the sub
station/ line by the GETCO. The contractor has to return empty cable drum as
instructed by E.I.C. The route map for cable will be issued free of cost to the
contractor before commencement of work, however the changes made by
Engineeer in charge i.e. Ex. Engr. (Const.) shall be incorporated.
GETCO/E/TSLUC058/R0 DT. 09/03/2009
The Contractor has to open site store at sub station site or at place near by the
sub station site and ensure for safe custody of all the stored materials at his own
cost.
The Contractor shall have total responsibility for the entire materials stored,
loose, semi assembled and/or erected by him at site in his custody. The
Contractor shall make suitable security arrangements at his own cost to ensure
the protection of all materials, equipment and works from theft, fire pilferage and
any other damages and loss. It shall be the responsibility of the contractor to
arrange for security till the works are finally taken over by the GETCO/GSECL.
1.3. CROSSINGS:
1.3.1 (a) Where road crossing comes in way of laying power cable, the power cable
shall be laid through NP-4 RCC Hume pipes. The required length of Hume pipe
shall be arranged by the successful Bidder at no extra cost.
(b) The RCC Hume pipe inner dia-meter shall not be less than 800 mm.
(c) The RCC pipes to be laid shall have minimum depth in such a way that the
back filling on top surface of the pipe shall be at least 700mm in depth. The
pipe joints shall be smooth so that cables are not damaged during pulling &
operation.
(d) During the crossing of utilities like water line, drainage lines, telephone lines,
gas lines etc, sufficient care shall be taken & protection shall be made available
so that other utilities do not damage the cable mechanically and / or electrically
or do not effect the performance of the cable.
1.4.1 The identification Board shall be placed on all four side of the trench with
warnings as shown below with letter sizes in line with relevant IS.
1.4.2 The cable trench roof should be duly embossed on top side as under:
1.4.3.1 The Bill of Quantities shall be read in conjunction with the Technical
Specifications, laying of cable and drawings.
1.4.3.2 The quantities given in the Bill of Quantities are estimated and provisional, and
are given to provide a common basis for Bidders.
a)Insulation Resistance of each cable drum length after laying and before
jointing.
c) Serving insulation resistance after laying each cable length shall withstand a
voltage of 10kv DC for one minute between each reinforcement and external
conducting surface; In addition, the serving insulation resistance shall be
measured and checked with the values obtained during routine factory tests.
d) On completion of the cable laying and jointing work, the complete installation
shall be checked with a D.C. voltage of 3 Uo applied for 15 minutes between
each conductor and sheath.
f) Test for 5 min. with system voltage applied between the conductor and the
screen.
1.6 GENERAL:
1. The cable laying shall have to be done, as per actual site condition at
the time of execution, and as per the instruction of the engineer-in-
charge.
GETCO/E/TSLUC058/R0 DT. 09/03/2009
1. Check that the cable trench and support member or cable trays in the trench are
dry (not water logged), clean and dressed. If required, pumps should be used to
drain out water from the trench.
2. There should be no sharp stone or hard particle on the route of cable in trench or
on the support member or cable tray that may damage the cable outer sheath.
3. Depending upon the site conditions, rollers could be placed on support member
or cable tray or on the ground in the walk way. The rollers should be placed at a
distance of 3 4 Metres. At bends, special corner rollers should be placed so
that the cable does not touch the side wall of trench.
4. Drum should be mounted on the cable jacks and should rotate freely. The jack
could be positioned near the end of trench at a levelled hard surface.
5. A man should be stationed near the drum with a plank wedged against the flange
so that overrunning of the drum could be prevented if pulling stops.
6. Ensure the drum is rolled against the direction of marked ROLL THIS WAY on
the drum and the cable is laid out from the top of the drum.
7. Lay a strong rope from the other end to cable drum on the route from where the
cable has to pass. Attach the end of the pulling rope to the leading end of
cable using a cable stocking on pulling eye to pull the cable.
8. One man should be provided at each roller and a gang of men should be
provided at the pulling rope attached to pulling eye/cable stocking. All the
persons should face towards the drum site. The total number of persons required
for pulling should be decided depending upon weight per metre of cable and
route conditions.
9. One Supervisor should be positioned near the drum. He should make evenly
timed calls for pulling or stopping the pulling operation. If required, and local
body allows, two to three loud speakers could be used by the supervisor for
making the call.
10. .There should be signal men carrying red & green flags placed at every 50
Metres. These signal men should show green flag when the pulling of cable has
to be done and red flag when the pulling of cable has to be stopped.
GETCO/E/TSLUC058/R0 DT. 09/03/2009
11. .Ensure that when the supervisor gives call for pulling the cable, all the men grip
and pull the cable simultaneously.
13. For heavy cables with complicated route, apply graphite grease on cable at the
end of the ramp (after the drum), before the cable enters the trench. If the site
conditions requires, the graphite grease should be applied by the men at rollers
during the course of pulling.
14. During laying, if outersheath damage is observed, the portion of cable which is
damaged should be marked with red PVC tape. After laying of the cable when
cable is still on the rollers, visual check for any outersheath damage should be
done. The bottom portion of the cable should be checked with the help of a
mirror. The damaged sheath should be repaired before outersheath testing.
16. If the cable had been laid on rollers on walkway, place the cable on support
member or cable tray.
17. Dress the cable and do the snaking as per advice of cable manufacturer, if
required.
19. After laying the cables, it should be checked again to see that all cable
ends are undamaged and sealed. If cable has to be cut, both the cable
ends should be re-sealed immediately by good quality heat shrinkable
cap.
20. A sample drawing for cable trench laying (drg. no. GETCO/C/02/SIKKA/CBLT-19
R0) is attached for reference to the bidder. However, the successful bidder shall
submit his own drawing with strength calculation & in accordance with safety
norms for approval to GETCO.
Name: _______________________
Designation: ___________________
Date: _____________
GETCO/E/TSLUC058/R0 DT. 09/03/2009