Daily Report

Project Name: KBK Project


Project Code: 03 YG 00400 Report Date : 26-Sep-2017 Tuesday No. of Day 788 Report No. DPR-482
Project Start Date 2015-8-1 Contract Period 956 Calendar Day AM PM Fine
Weather
Estimate Completion Date 2018-3-13 Remain Period 168 Calendar Day 6~8 8~10 10 ~12 13~15 15~17 17~19 Rain
Work Force
M&E Site Surveyo Office Geotec General Crane Crane Steel
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Welder
engineer Store r Staff h Workers Operator Helper Worker
Today 1 2 1 1 1 1 1 4 5
Operator Helper Manson Steel
Trades M&E Manson Carpenter Smith Stud Bolt Total
(ACP) (ACP) worker Supervis
Today 1 7 5 30
Machine & Equipments onsite
Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
25 Ton Crane 0 0 0 1.5 Hp Submer; pump 3 3 3 19KW Welding Box 6 6 6
Sheet pile machine 0 0 0 1 Hp Motor pump 1 1 1 60 KVA generator 1 1 1
3"x3" Air Compressor 1 1 1 1.5 Hp Motor pump 1 1 1 2Hp compressor 1 1 1
165 KVA Generator 1 1 1 2Hp Pressure pump 1 1 1
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total

FO-OP-01 REV-00 Page: 1/2


Daily Report

Project Name: KBK Project


QC - Test Sampling
Test Item Remarks
Sampl
e
Taken
LTI Free Day UA,UC Near Miss FAI MTC LTA
Daily TBT
HSE Conducted By
Safety Officer

Works Carried out Details


Trades Of Work Location Remark
1 Deck sheet cut and welding work beside H beam at 8th floor At grid (C-D)
2 Shear connectors welding work at 8th floor and GF At grid (4) & (A)
3 Rebar fabrication work for shear connectors
4 Tightening lifeline rope at staircase areas
5 Scaffolding work to install 1st floor down hang wall At grid
6 Housekeeping work

Special Event
Site
Visitors
Purpose Instructi
on site
on
Project Manager Project Engineer Prepare By: Site Engineer
Name U Khin Maung Myint Name Name Aye Wit Yee Soe

Signature Signature Signature

FO-OP-01 REV-00 Page: 2/2


KBK Project
Site Progress Photo
Date: 26.9.2017

Shear connectors welding work at 7th floor

Deck sheet welding work at 8th floor


KBK Project
Site Progress Photo
Date: 26.9.2017

Shear connectors production work

Scaffolding work to install 1st floor down hang wall