Introduction
PMI Project Management Experience Verification Form Template Version 1.3 Excel file is recommended to b
4500 hours of project management experience & apply for PMP Certification Examination successfully.
Instructions to Use
:Enter the start date & end date of Project in mm/dd/yyyy format.
:Based on the above information, the Number of calendar days | Number of working days | Number of gros
working hours (70%) will be calculated automatically.
:Enter the no. of hours against specific activities in each of the Process Groups - Initiation | Planning | Exec
:Please note that the no. of hours entered by you - SUBTOTAL BY PROJECTS should be equal to Number of
:Do not edit grey color fields as they are calculated automatically
Disclaimer
As a commitment to help participants in applying for PMP Certification Examination, KnowledgeWoods Cons
participants document their Project Management Experience. Participants hereby agree to absolve Knowled
damages that may arise due to any reason whatsoever.
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools 144
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 144
CLOSING PROCESS Formalize and obtain final acceptance for the project. 54
Page 2 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools 406
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 406
CLOSING PROCESS Formalize and obtain final acceptance for the project. 60
TOTAL HOURS---->
developed detail project plan including breakdown activity list, Schedule, cost &
Project Description with vendors for procurement of support services.Lead & manage project during
execution phase with regular M&C of quality & risks mitigation of all constraints.
Page 3 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools 170
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 170
CLOSING PROCESS Formalize and obtain final acceptance for the project. 57
TOTAL HOURS---->
Managed the LTE Rollout Project for Celcom Malaysia. Identified stakeholders of
project. Based on Project Charter, I developed detail project plan with support of
sponsor & key stakeholders for scope,time,cost & resource. Created standard
M&C of quality and risks mitigation.At closing get Deliverables (760 LTE Nodes On
updated.
Page 4 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools 60
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 60
CLOSING PROCESS Formalize and obtain final acceptance for the project. 40
TOTAL HOURS---->
Worked as Project Lead for 3G Nodes software upgrade Project for XL-Axiata
Indonesia. Developed detail project plan with support of sponsor and other
Project Description procedures of execution. Lead and manage project during execution phase with
regular monitoring and control of quality and risks mitigation. Finally get
deliverables (500 3G Nodes with latest software and accepted level of Network
Page 5 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 0
CLOSING PROCESS Formalize and obtain final acceptance for the project.
TOTAL HOURS---->
Project Description
Page 6 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 0
CLOSING PROCESS Formalize and obtain final acceptance for the project.
TOTAL HOURS---->
Project Description
Page 7 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 0
CLOSING PROCESS Formalize and obtain final acceptance for the project.
TOTAL HOURS---->
Project Description
Page 8 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 0
CLOSING PROCESS Formalize and obtain final acceptance for the project.
TOTAL HOURS---->
Project Description
Page 9 of 10
367311988.xls
Name
Education background Baccalaureate (or global equivalent)
PM-experience required ( Hrs ) 4500
PM-experience Specified ( Hrs ) SUBTOTAL BY PROJECTS (IN Hrs) 4696
--->>>
MONITORING & CONTROLLING PROCESS Measure project performance using appropriate tools
and techniques.
Subtotal by process group - MONITORING & CONTROLLING (In Hrs) --->>> 0
CLOSING PROCESS Formalize and obtain final acceptance for the project.
TOTAL HOURS---->
Project Description
Page 10 of 10