AC Air Conditioning

AEC Alamur Engineering Consultant


ATE Al Turki Enterprises LLC
AV Audio Visual
BMU Building Maintenance Unit
CUM Cumulative
DG Diesel Generator
EI Engineer's Instruction
EMLPT Emergency Main Low Tension Panel
EOT Extension of Time
FCU Fan Coil Unit
HQ Head Quarters
HRW Heat Recovery Wheel
HSE Health. Safety and Environment
HVN HSE Violation Notice
IFC Issued for Construction
MEP Mechanical, Electrical and Plumbing
NCR Non-Conformity Report
NSC Nominated Sub Contract
OCEC Oman Convention and Exhibition Centre
OMANTEL Oman Telecommunications Company SAOG
OMRAN Oman Tourism Development Company SAOC
PRFV Potential Request for Variation
RFI Request for Instruction
RFV Request for Variation
RO. / OMR Omani Riyals
SSH DAR SSHI LLC
TBD To be decided
VE Value Engineering

All the bonds and insurances are active, meetings are


regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.
All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.All the bonds and insurances are active, meetings are
regular. There has been an increase of 57 manpower &
resources during the month of August 2017.
As of 31st August 2016, there have been 10 months lapsed
from the commencement of the project works. The
contractor has submitted 9 payment applications and all
have been certified by today.