Вы находитесь на странице: 1из 204

DETAILED ESTIMATES

Improvement of Three (3) Classroom School Building with Comfort Rooms each
at Valdez Elementary School, Valdez, Floridablanca, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
1.00 lot Signages, barricades, barracks, etc. 20,000.00 10,000.00
Materials: 10,000.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
4.00 2.00 Laborers 300.00 2,400.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 7,400.00

Sub-Total : 17,400.00
Profit Tax and Overhead : 5,220.00
Total Cost : 22,620.00

Item II: Demolition of Existing Stucture


Qty: 1.00 lot

A. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 6.00 Foreman 600.00 3,600.00
6.00 6.00 Laborers 300.00 10,800.00
1.00 4.00 Concrete Cutter 1,250.00 5,000.00
Labor and Equipment: 19,400.00

Sub-Total : 19,400.00
Profit Tax and Overhead : 5,820.00
Total Cost : 25,220.00

Item III: Excavation and Backfilling


Qty: 22.54 cu.m

A. Labor and Equipment

Page 1
Qty. Days Item Description Unit Cost Total
1.00 2.00 Foreman 600.00 1,200.00
1.00 2.00 Skilled Laborers 300.00 600.00
4.00 2.00 Laborers 301.00 2,408.00
Labor and Equipment: 4,208.00

Sub-Total : 4,208.00
Profit Tax and Overhead : 1,262.40
Total Cost : 5,470.40
Unit Cost : 242.70

Item IV: Filling Materials


Qty: 82.13 cu.m

A. Materials
Qty. Item Description Unit Cost Total
82.13 cu.m Filling Materials 200.00 16,426.00
Materials: 16,426.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 4.00 Foreman 600.00 2,400.00
6.00 4.00 Laborers 301.00 7,224.00
1.00 4.00 Plate Compactor 650.00 2,600.00
Labor and Equipment: 12,224.00

Sub-Total : 28,650.00
Profit Tax and Overhead : 8,595.00
Total Cost : 37,245.00
Unit Cost : 453.49

Item V: Concrete Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
312.00 bags Cement 220.00 68,640.00
19.00 cu.m Sand 260.00 4,940.00
34.00 cu.m Gravel 3/4" 830.00 28,220.00
86.00 pcs 16mm dia. Bars 350.00 30,100.00

Page 2
80.00 pcs 12mm dia. Bars 350.00 28,000.00
400.00 pcs 10mm dia. Bars 140.00 56,000.00
30.00 kgs Tie Wires 70.00 2,100.00
Materials: 218,000.00
B. Labor and Equipment
Qty. Days Item Description Unit Cost Total
1.00 14.00 Foreman 600.00 8,400.00
4.00 14.00 Skilled Laborers 450.00 25,200.00
8.00 14.00 Laborers 301.00 33,712.00
1.00 12.00 One Bagger Mixer 650.00 7,800.00
Labor and Equipment: 75,112.00

Sub-Total : 293,112.00
Profit Tax and Overhead : 87,933.60
Total Cost : 381,045.60

Item VI: Masonry Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
170.00 bags Cement 220.00 37,400.00
10.00 cu.m Sand 260.00 2,600.00
2,520.00 pcs 5" CHB 8.00 20,160.00
150.00 pcs 10mm dia. Bars 140.00 21,000.00
10.00 kgs Tie Wires 70.00 700.00
Materials: 81,860.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 8.00 Foreman 600.00 4,800.00
3.00 8.00 Skilled Laborers 450.00 10,800.00
4.00 8.00 Laborers 301.00 9,632.00
Labor and Equipment: 25,232.00

Sub-Total : 107,092.00
Profit Tax and Overhead : 32,127.60
Total Cost : 139,219.60

Item VII: Carpentry Works


A. Forms and Scaffoldings

Page 3
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
12.00 pcs 1/2" Marine Plywood 480.00 5,760.00
200.00 bd.ft Form Lumber 48.00 9,600.00
1.00 lot Scaffoldings (H-Frame) 5,000.00 5,000.00
20.00 kilos Cw Nails 70.00 1,400.00
Materials: 21,760.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 6.00 Foreman 600.00 3,600.00
2.00 6.00 Skilled Laborers 450.00 5,400.00
4.00 6.00 Laborers 301.00 7,224.00
Labor and Equipment: 12,624.00

Sub-Total : 34,384.00
Profit Tax and Overhead : 10,315.20
Total Cost : 44,699.20

B. Ceiling
Qty: 208.00 sq.m

A. Materials
Qty. Item Description Unit Cost Total
208.00 sq.m 4.5 mm Fiber Cement Board (hardiflex or 520.00 108,160.00
equivalent) on Metal Furring as shown on the
plans

Sub-Total : 108,160.00
Profit Tax and Overhead : 32,448.00
Total Cost : 140,608.00
Unit Cost : 676.00

Item VIII: Fabricated Materials


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total

Page 4
Jalousie Type Window w/ 12 mm Grills;
18.90 sq.m 6 sets - 2.10 m x 1.50 m; 2,700.00 51,030.00
6.30 sq.m 6 sets - 0.70 m x 1.50 m; 2,700.00 17,010.00
1.08 sq.m 3 sets - 0.60 m x 0.60 m; 2,700.00 2,916.00
3.00 sets 1.00m x 2.10m Panel Door w/ Gal. Jamb 6,500.00 19,500.00
3.00 sets 0.60 m x 2.10 m PVC Door w/ Jamb 2,500.00 7,500.00
3.00 sets Blackboards 2,500.00 7,500.00
Materials: 105,456.00
B. Labor and Equipment
Qty. Days Item Description Unit Cost Total
1.00 10.00 Foreman 600.00 6,000.00
2.00 10.00 Skilled Laborers 475.00 9,500.00
2.00 10.00 Laborers 301.00 6,020.00
1.00 10.00 Welding machine 850.00 8,500.00
Labor and Equipment: 30,020.00

Sub-Total : 135,476.00
Profit Tax and Overhead : 40,642.80
Total Cost : 176,118.80

Item IX: Roof Framing


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
20.00 pcs 1.5mm x 2" x 6" Tuublar Bars 2,400.00 48,000.00
8.00 pcs 1.2mm x 2" x 6" C-Purlins 625.00 5,000.00
66.00 pcs 1.2mm x 2" x 4" C-Purlins 550.00 36,300.00
14.00 pcs 12mm Sag Rods 820.00 11,480.00
6.00 gals Red Lead Primer 565.00 3,390.00
1.00 lot Misc. Consumbles (Welding Rods, etc) 2,000.00 2,000.00
Materials: 106,170.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 12.00 Foreman 600.00 7,200.00
2.00 12.00 Skilled Laborers 475.00 11,400.00
2.00 12.00 Laborers 301.00 7,224.00
1.00 10.00 Welding machine 850.00 8,500.00
Labor and Equipment: 34,324.00

Sub-Total : 140,494.00

Page 5
Profit Tax and Overhead : 42,148.20
Total Cost : 182,642.20

Item X: Tinsmithry Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
222.00 li.m #26 Pre-Painted Corrugated Long Span 300.00 66,600.00
9.00 pcs #26 Pre-Painted Ridge Roll 350.00 3,150.00
12.00 pcs #26 Pre-Painted Flashing 305.00 3,660.00
32.00 pcs 1/2" x 12" Fascia Board 540.00 17,280.00
1.00 lot Misc. Consumables (Screws, Rivets, Sealants, 2,000.00 2,000.00
touch-up paint) Materials: 92,690.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 8.00 Foreman 600.00 4,800.00
2.00 8.00 Skilled Laborers 475.00 7,600.00
2.00 8.00 Laborers 301.00 4,816.00
Labor and Equipment: 17,216.00

Sub-Total : 109,906.00
Profit Tax and Overhead : 32,971.80
Total Cost : 142,877.80

Item XI: Painting Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
26.00 gals Flat Enamel Paint 500.00 13,000.00
17.00 gals Flat Latex Paint 520.00 8,840.00
32.00 gals Semi Gloss Latex Paint 550.00 17,600.00
6.00 gals Quick Dry Enamel 620.00 3,720.00
6.00 gals Painter's Putty 520.00 3,120.00
12.00 gals Concrete Neutralizer 200.00 2,400.00
8.00 gals Paint Thinner 240.00 1,920.00
1.00 lot Misc. Consumables (brushes, rollers, etc) 2,000.00 2,000.00
Materials: 52,600.00

Page 6
B. Labor and Equipment
Qty. Days Item Description Unit Cost Total
1.00 12.00 Foreman 600.00 7,200.00
4.00 12.00 Skilled Laborers 450.00 21,600.00
2.00 12.00 Laborers 30.00 720.00
Labor and Equipment: 29,520.00

Sub-Total : 82,120.00
Profit Tax and Overhead : 24,636.00
Total Cost : 106,756.00

Item XII: Electrical Works


A. Electrical lines
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
3.00 rolls #12 THHN Wire 3,400.00 10,200.00
40.00 li.m #8 THHN Wire 120.00 4,800.00
1.00 unit Circuit Breaker 8,000.00 8,000.00
15.00 sets Flourescent Lamps 475.00 7,125.00
3.00 sets CFL bulb w/ socket 180.00 540.00
18.00 pcs Junction Box 25.00 450.00
24.00 pcs Utility Box 20.00 480.00
3.00 sets 1-Gang Switch 125.00 375.00
3.00 sets 3-Gang Switch 185.00 555.00
12.00 sets Convenience Outlet 185.00 2,220.00
1.00 lot Misc. Consumbles 3,000.00 3,000.00
Materials: 37,745.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 8.00 Foreman 600.00 4,800.00
1.00 8.00 Skilled Laborers 500.00 4,000.00
1.00 8.00 Laborers 301.00 2,408.00
Labor and Equipment: 11,208.00

Sub-Total : 48,953.00
Profit Tax and Overhead : 14,685.90
Total Cost : 63,638.90

Page 7
B. Wall Fans
Qty: 6.00 sets

A. Materials
Qty. Item Description Unit Cost Total
6.00 sets Wall Fans (standard or equivalent) 2,000.00 12,000.00

Sub-Total : 12,000.00
Profit Tax and Overhead : 3,600.00
Total Cost : 15,600.00
Unit Cost : 2,600.00

Item XIII Plumbing Works


A. Waterlines and Sewerlines
Qty: 1.00 lot

A. Materials (incl. Labor)


Qty. Item Description Unit Cost Total
1.00 lot PVC Pipe Sewerlines (orange pipes) 5,000.00 5,000.00
1.00 lot PVC Pipe Waterlines (blue pipes) 5,000.00 5,000.00
Materials, Labor and Equipment: 10,000.00

Sub-Total : 10,000.00
Profit Tax and Overhead : 3,000.00
Total Cost : 13,000.00

B. Fixtures
Qty: 1.00 lot

A. Materials (incl. Labor)


Qty. Item Description Unit Cost Total
3.00 sets Water Closet and Lavatory w/ complete 6,000.00 18,000.00
accessories and fittings
Materials 18,000.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 2.00 Foreman 600.00 1,200.00
1.00 2.00 Skilled Laborers 450.00 900.00
1.00 2.00 Laborers 300.00 600.00
Labor and Equipment: 2,700.00

Page 8
Sub-Total : 20,700.00
Profit Tax and Overhead : 6,210.00
Total Cost : 26,910.00

C. Tile Works
Qty: 1.00 lot

A. Materials (incl. Labor)


Qty. Item Description Unit Cost Total
3.00 sets 0.30 m x 0.30 m Tiles 410.00 1,230.00
3.00 bags Tile Grout 800.00 2,400.00
3.00 bags Tile Adhesive 260.00 780.00
Materials 4,410.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 2.00 Foreman 600.00 1,200.00
1.00 2.00 Skilled Laborers 450.00 900.00
1.00 3.00 Laborers 300.00 900.00
Labor and Equipment: 3,000.00

Sub-Total : 7,410.00
Profit Tax and Overhead : 2,223.00
Total Cost : 9,633.00

Page 9
242.70

70.35
598.00
5,749.10

453.49

37.18
316.00
18.59
33.46
85.00

Page 10
80.00
400.00

76,300.00

20.71
176.00
10.35
2,536.00
155.00

28,651.00

Page 11
7,616.00

676.00

Page 12
187.00
212.00

36,909.60

37,159.50

Page 13
13,210.75

Page 14
2,600.00

Page 15
410

I 22,620.00
II 25,220.00
III 5,470.46
IV 37,245.13
V 381,045.60
VI 139,219.60
VII 185,307.20
VIII 176,118.80
IX 182,642.20
X 142,877.80
XI 106,756.00
XII 79,238.90
XIII 49,543.00
1,533,304.69

Page 16
DETAILED ESTIMATE FOR THE
Improvement of Four (4) Classroom School Building with Comfort Room at San Vicente
Elementary School, San Vicente, Sto. Tomas, Pampanga

Item I: Mobilization/Demobilization
Quantity: 1.00 lot

I. Materials:
None

II. Equipment Quantity No of Days Rate per Day Total


Elf Truck 1 2 P 2,500.00 P 5,000.00

III. Labor Quantity No of Days Rate per Day Total


Laborers 5 2 300.00 3,000.00
3,000.00

Total Direct Cost: P 8,000.00


Indirect Cost(Mark-ups, Tax, etc.): 2,400.00
Total Amount: 10,400.00

Item II. Excavation and Backfilling


Quantity: 46.87 cu.m

I. Materials:
None

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 5 P 550.00 P 2,750.00
Laborer 3 5 300.00 4,500.00
7,250.00

Total Direct Cost: P 7,250.00


Indirect Cost(Mark-ups, Tax, etc.): 2,175.00
Total Amount: 9,425.00

Unit Cost per cu.m at 201.09

Item III: Demolition of Existing Structure (incl. Waste Disposal)


Quantity: 1.00 lot

I. Materials:
None

Page 17
II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 5 P 550.00 P 2,750.00
Laborers 4 5 300.00 6,000.00
8,750.00

Total Direct Cost: P 8,750.00


Indirect Cost(Mark-ups, Tax, etc.): 2,625.00
Total Amount: 11,375.00

Item IV: Filling Materials


Quantity: 213.16

I. Materials: Quantity Unit Cost Total


Common Borrow/Fillin 213.16 cu.m P 185.00 P 39,434.60

II. Equipment Quantity No of Days Rate per Day Total


Plate Compactor 1 3 1,250.00 3,750.00

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 5 550.00 P 2,750.00
Laborer 4 5 300.00 6,000.00
8,750.00

Total Direct Cost: P 51,934.60


Indirect Cost(Mark-ups, Tax, etc.): 15,580.38
Total Amount: 67,514.98

Unit Cost per cu.m at 316.73

Item V. Concrete Works


Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


Cement 460.00 bags P 210.00 P 96,600.00
Sand 32.00 cu.m 240.00 7,680.00
Gravel 48.00 cu.m 830.00 39,840.00
16 mm dia. Bars x 6 46.00 pcs 333.00 15,318.00
12 mm dia. Bars x 6 260.00 pcs 185.00 48,100.00
10 mm dia. Bars x 6 540.00 pcs 130.00 70,200.00
Tie Wires 30.00 kgs 65.00 1,950.00
279,688.00

II. Equipment Quantity No of Days Rate per Day Total


One Bagger Mixer 1 20 750.00 15,000.00

Page 18
III. Labor Quantity No of Days Rate per Day Total
Foreman 1 22 550.00 12,100.00
Skilled Laborer 2 22 450.00 19,800.00
Laborer 8 22 300.00 52,800.00
84,700.00

Total Direct Cost: P 379,388.00


Indirect Cost(Mark-ups, Tax, etc.): 113,816.40
Total Amount: 493,204.40

Item VI. Masonry Works


Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


Cement 330.00 bags P 220.00 P 72,600.00
Sand 32.00 cu.m 240.00 7,680.00
Gravel 2.00 cu.m 830.00 1,660.00
5" CHB 4,700.00 pcs 7.00 32,900.00
10 mm dia. Bars x 6 330.00 pcs 130.00 42,900.00
Tie Wires 20.00 kgs 65.00 1,300.00
159,040.00

II. Equipment Quantity No of Days Rate per Day Total


One Bagger Mixer 1 11 750.00 8,250.00

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 13 550.00 7,150.00
Skilled Laborer 2 13 450.00 11,700.00
Laborer 8 13 300.00 31,200.00
50,050.00

Total Direct Cost: P 217,340.00


Indirect Cost(Mark-ups, Tax, etc.): 65,202.00
Total Amount: 282,542.00

Item VII.Carpentry Works


A. Forms and Scaffoldings
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


1/4" Marine Plywoood 12.00 pcs P 370.00 P 4,440.00
2" x 2" x 12' Form L 100.00 bd.ft 40.00 4,000.00
2" x 3" x 12' Coco L 100.00 bd.ft 40.00 4,000.00
12,440.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total

Page 19
Foreman 1 3 P 550.00 1,650.00
Skilled Laborer 1 3 450.00 1,350.00
Laborer 2 3 300.00 1,800.00
4,800.00

Total Direct Cost: P 17,240.00


Indirect Cost(Mark-ups, Tax, etc.): 5,172.00
Total Amount: 22,412.00

B. Ceiling Works
Quantity: 240.00 sq.m

I. Materials (incl. labor) Quanity Unit Cost Total


1/4" Hardiflex Ceiling 240.00 sq.m P 570.00 P 136,800.00
136,800.00

Total Direct Cost: P 136,800.00


Indirect Cost(Mark-ups, Tax, etc.): 41,040.00
Total Amount: 177,840.00

Unit Cost per sq.m at 741.00

Item VIII. Fabricated Materials


Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


8 sets - 2.80 m x 1.5 359.52 sq.ft P 275.00 P 98,868.00
8 sets - 0.70 m x 1.5 89.88 sq.ft 275.00 24,717.00
4 sets - 0.60 m x 0.6 15.41 sq.ft 275.00 4,237.20
1.00m x 2.10m 4.00 sets 6,000.00 24,000.00
Panel Door w/
Galvanized Jamb
0.70 m x 2.10 m 4.00 sets 3,200.00 12,800.00
PVC
1.20 Door w/ Jamb
m x 4.8 m 4.00 sets 3,600.00 14,400.00
Blackboard 179,022.20

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 10 P 550.00 5,500.00
Skilled Laborer 3 10 430.00 12,900.00
Laborer 4 10 320.00 12,800.00
31,200.00

Total Direct Cost: P 210,222.20


Indirect Cost(Mark-ups, Tax, etc.): 63,066.66
Total Amount: 273,288.86

Page 20
Item IX. Roof Framing Works
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


2" x 6" Tubular,1.5mm 31.00 pcs. 2,235.00 P 69,285.00
2" x 4" C-Purlins, 1. 67.00 pcs. 520.00 34,840.00
2" x 6" C-Purlins,1.2 14.00 pcs. 620.00 8,680.00
Sag Rod 12mm (std) 21.00 pcs. 215.00 4,515.00
Miscellaneous (Welding 1.00 lot 2,500.00 2,500.00
119,820.00

II. Equipment Quantity No of Days Rate per Day Total


Welding Machine 1 9 500.00 4,500.00

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 10 550.00 5,500.00
Skilled Laborer 1 10 430.00 4,300.00
Laborer 5 10 320.00 16,000.00
25,800.00

Total Direct Cost: P 150,120.00


Indirect Cost(Mark-ups, Tax, etc.): 45,036.00
Total Amount: 195,156.00

Item X. Tinsmithry Works


Quantity: 280.00 sq.m

I. Materials: Quanity Unit Cost Total


0.40 mm Pre-painted 280.00 li.m 328.00 P 91,840.00
0.40 mm Flashing 10.00 pcs. 370.00 3,700.00
0.40 mm Ridge Roll 11.00 pcs. 370.00 4,070.00
1/2" Hardi Fascia Boa 38.00 pcs. 350.00 13,300.00
Miscellaneous 1.00 lot 5,000.00 5,000.00
117,910.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 7 550.00 3,850.00
Skilled Laborer 2 7 450.00 6,300.00
Laborer 4 7 300.00 8,400.00
18,550.00

Total Direct Cost: P 136,460.00


Indirect Cost(Mark-ups, Tax, etc.): 40,938.00
Total Amount: 177,398.00

Unit Cost per sq.m at 633.56

Page 21
Item XI. Painting Works
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


Flatwall Enamel 6.00 tins P 2,125.00 P 12,750.00
Flat Latex 8.00 tins 2,050.00 16,400.00
Semi-Gloss latex 4.00 tins 2,250.00 9,000.00
All-Around Putty 8.00 gals 320.00 2,560.00
Red Lead Primer 5.00 gals 540.00 2,700.00
Quick Dry Enamel 5.00 gals 500.00 2,500.00
Miscellaneous 1.00 lot 2,000.00 2,000.00
47,910.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 9 P 550.00 4,950.00
Skilled Laborer 3 9 450.00 12,150.00
Laborer 2 9 300.00 5,400.00
22,500.00

Total Direct Cost: P 70,410.00


Indirect Cost(Mark-ups, Tax, etc.): 21,123.00
Total Amount: 91,533.00

Item XII. Electrical Works


A. Electrical Works (Wirings, Switches, Etc.)
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


Flourescent Lights 1 20.00 sets 430.00 P 8,600.00
CFL Lights w/ recepta 4.00 pcs. 180.00 720.00
Three gang switch 4.00 sets 160.00 640.00
One gang switch 4.00 sets 95.00 380.00
Entrance Cap 1" 1.00 pc. 90.00 90.00
Junction Box 20.00 pcs. 27.00 540.00
Utility Box 20.00 pcs. 20.00 400.00
Flexible hose 1/2" 80.00 mts. 8.00 640.00
3.5mm THHN strande 3.00 rolls 3,200.00 9,600.00
14.0mm THHN strand 20.00 mts. 90.00 1,800.00
Circuit Breaker 1.00 set 5,000.00 5,000.00
Convinience outlet ( 12.00 sets 190.00 2,280.00
Miscellaneous 1.00 lot 2,500.00 2,500.00
33,190.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 8 P 550.00 4,400.00
Page 22
Skilled Laborer 1 8 450.00 3,600.00
Laborer 1 8 300.00 2,400.00
10,400.00

Total Direct Cost: P 43,590.00


Indirect Cost(Mark-ups, Tax, etc.): 13,077.00
Total Amount: 56,667.00

B. Electrical Works (Wall Fans)


Quantity: 8.00 units

I. Materials: Quanity Unit Cost Total


Wall Fans 8.00 sets 2,100.00 P 16,800.00
16,800.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 1 P 550.00 550.00
Laborer 1 1 320.00 320.00
870.00

Total Direct Cost: P 17,670.00


Indirect Cost(Mark-ups, Tax, etc.): 5,301.00
Total Amount: 22,971.00

Unit Cost per sq.m at 2,871.38

Item XIII. Plumbing Works


A. Waterlines and Sewerlines
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


PVC Pipe 3" 8.00 pcs. 420.00 P 3,360.00
PVC Elbow 3" 16.00 pcs. 70.00 1,120.00
PVC Blue 1" 16.00 pcs. 120.00 1,920.00
PVC Blue 1/2" 12.00 pcs. 90.00 1,080.00
PVC Tee Blue 1/2 8.00 pcs. 28.00 224.00
Elbow Blue 1/2" 8.00 pcs. 28.00 224.00
Stainles Faucet 4.00 pcs. 350.00 1,400.00
Gate Valve 1/2" 4.00 pcs. 350.00 1,400.00
Reducer PVC Blue 1" t 4.00 pcs. 65.00 260.00
Miscellaneous 1.00 lot 2,500.00 2,500.00
13,488.00

II. Equipment
None

Page 23
III. Labor Quantity No of Days Rate per Day Total
Foreman 1 3 P 550.00 1,650.00
Skilled Laborer 1 3 450.00 1,350.00
Laborer 2 3 300.00 1,800.00
4,800.00

Total Direct Cost: P 18,288.00


Indirect Cost(Mark-ups, Tax, etc.): 5,486.40
Total Amount: 23,774.40

B. Fixtures
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


Water Closet 4.00 sets P 3,500.00 P 14,000.00
Lavatory 4.00 sets 1,500.00 6,000.00
20,000.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 4 P 550.00 2,200.00
Skilled Laborer 2 4 450.00 3,600.00
Laborer 1 4 300.00 1,200.00
7,000.00

Total Direct Cost: P 27,000.00


Indirect Cost(Mark-ups, Tax, etc.): 8,100.00
Total Amount: 35,100.00

C. Tile Works
Quantity: 1.00 lot

I. Materials: Quanity Unit Cost Total


0.30 m x 0.30 m Ungl 475.00 pcs 35.00 P 16,625.00
Tile Grout 10.00 bags 55.00 550.00
Tile Adhesives 4.00 bags 265.00 1,060.00
18,235.00

II. Equipment
None

III. Labor Quantity No of Days Rate per Day Total


Foreman 1 3 P 550.00 1,650.00
Skilled Laborer 2 3 450.00 2,700.00
Laborer 2 3 300.00 1,800.00
6,150.00

Page 24
Total Direct Cost: P 24,385.00
Indirect Cost(Mark-ups, Tax, etc.): 7,315.50
Total Amount: 31,700.50

Page 25
46.87

201.09

Page 26
213.16

13,802.11

12,500.00

316.73

475.00
33.31
49.98
46.00
268.00
521.00

97,890.80

Page 27
99,700.00

350.00
33.63
2.06
4,820.00
310.00
6.00

55,664.00
58,300.00

Page 28
3,732.00
4,800.00

240.00

741.00

1,824.29

968.40

32,224.00

Page 29
29,955.00
30,300.00

280.00

17,686.50

633.56

Page 30
6.75
8.25
4.5

23,955.00

Page 31
10,952.70

8.00

5,880.00

2,871.38

1,824.29

Page 32
4,720.80

7,000.00

1,824.29

18
24
380

6,382.25

Page 33
I 10,400.00
II 9,425.09
III 11,375.00
IV 67,514.17
V 493,204.40
VI 282,542.00
Page 34
VII 200,252.00
P VIII 273,288.86
IX 195,156.00
X 177,396.80
XI 91,533.00
XII 79,638.04
XIII 90,574.90
1,982,300.26

Page 35
Detailed Estimates/Bill of Quantities
Project Name: Concreting of Pangclara Barangay Road
Location: Pangclara, Candaba, Pampanga

Item I: Subgrade Preparation


Qty: 960.00 m

I. Equipment Quantity No of Days Rate Total


Road Grader 1 0.5 P 10,500.00 P 5,250.00
P 5,250.00

II. Labor Quantity No of Days Rate Total


Foreman 1 1 480.00 480.00
Laborer 2 1 280.00 560.00
P 1,040.00

Direct Cost: 6,290.00


OPT: 1,635.40
Total: P 7,925.40

Unit CostP 8.26 /m

Item II:Aggregate Base Coarse


Qty: 83.00 cu.m

I. Materials: Quanity Unit Cost Total


Aggt. Base Coarse 83.00 m P 525.00 P 43,575.00
P 43,575.00

II. Equipment Quantity No of Days Rate Total


Road Grader 1 0.5 P 10,500.00 P 5,250.00
Road Roller 1 1 10,000.00 10,000.00
Mini Water Truck 1 1 2,500.00 2,500.00
P 17,750.00

III. Labor Quantity No of Days Rate Total


Foreman 1 1 P 480.00 480.00
Laborer 4 1 280.00 1,120.00
P 1,600.00

Direct Cost: 62,925.00


OPT: 16,360.50
Total: P 79,285.50

Unit CostP 955.25 /m


Item IVPCCP
Qty: 800.00 m

I. Materials: Quanity Unit Cost Total


RMC, G1 - 3/4" 3500 psi @ 14 da 120.00 m P 3,500.00 P 420,000.00
16mm x 6m 12.00 pcs 340.00 4,080.00
Rental of Forms 1.00 lot 15,000.00 15,000.00
Misc. Connsumables 1.00 lot 5,000.00 5,000.00
P 444,080.00

II. Equipment Quantity No of Days Rate Total


Concrete Vibrator w/ Screeder 1 5 1,000.00 P 5,000.00
Mini Water Truck 1 5 2,500.00 12,500.00
Concrete Cutter 1 4 1,200.00 4,800.00
P 22,300.00

III. Labor Quantity No of Days Rate Total


Foreman 1 5 P 480.00 2,400.00
Skilled Laborer 4 5 372.50 7,450.00
Laborer 8 5 277.50 11,100.00
P 20,950.00

Direct Cost: 487,330.00


OPT: 126,705.80
Total: P ###

Unit CostP 767.54 /m

SUMMARY
Project Name: Concreting of Pangclara Barangay Road
Location: Pangclara, Candaba, Pampanga

Item No. Quantity Unit Cost Subtotal


I 960.00 8.26 7,929.60
II 83.00 955.25 79,285.75
III 800.00 767.54 614,032.00
Grand Total: 701,247.35

Prepared by:
Item Detailed
I 7,925.40
II 79,285.50
III 614,035.80
Total 701,246.70

8.26

955.25
120

767.54
Detailed Estimates
Name of Project : Improvement/Upgrading of San Nicolas Barangay Road

Location: San Nicolas, San Luis, Pampanga

Item I: Subgrade Preparation


Quantity: 1200 sq.m

I. Materials: Quantity Daily Rate Total Cost


NONE

Sub Total
II. Equipment Quantity Days Daily Rate Total Cost
Road Grader 1 1 9,000.00 9,000.00

Sub Total 9,000.00


III. Labor Quantity Days Rate Total
Foreman 1 1 600.00 600.00
Laborer 1 4 320.00 1,280.00

Sub Total 1,880.00


Total Direct Cost (A+B+C): 10,880.00
OCM, Profit and Tax (26%): 2,828.80
Total Cost: 13,708.80

UNIT COST: 11.42


Detailed Estimates
Name of Project : Improvement/Upgrading of San Nicolas Barangay Road

Location: San Nicolas, San Luis, Pampanga

Item II: Embankment/Filling Materials


Quantity: 413 cu.m

I. Materials: Quantity Unit Cost Total Cost


Filling Materials 413 cu.m 225.00 92,925.00

Sub Total 92,925.00


II. Equipment Quantity Days Daily Rate Total Cost
Road Grader 1 3 9,000.00 27,000.00
Road Roller 1 5 6,000.00 30,000.00
Water Truck 1 5 2,500.00 12,500.00

Sub Total 69,500.00


III. Labor Quantity Days Rate Total
Foreman 1 5 600.00 3,000.00
Laborer 1 5 320.00 1,600.00

Sub Total 4,600.00


Total Direct Cost (A+B+C): 167,025.00
OCM, Profit and Tax (26%): 43,426.50
Total Cost: 210,451.50
UNIT COST: 509.57

Detailed Estimates
Name of Project : Improvement/Upgrading of San Nicolas Barangay Road

Location: San Nicolas, San Luis, Pampanga

Item III: Aggregate Base Coars


Quantity: 228 cu.m

I. Materials: Quantity Unit Cost Total Cost


Aggregate Base Course 228 cu.m 520.00 118,560.00

Sub Total 118,560.00


II. Equipment Quantity Days Daily Rate Total Cost
Road Grader 1 2 9,000.00 18,000.00
Road Roller 1 3 6,000.00 18,000.00
Water Truck 1 3 2,500.00 7,500.00

Sub Total 43,500.00


III. Labor Quantity Days Rate Total
Foreman 1 3 600.00 1,800.00
Laborer 1 3 320.00 960.00

Sub Total 2,760.00


Total Direct Cost (A+B+C): 164,820.00
OCM, Profit and Tax (26%): 42,853.20
Total Cost: 207,673.20

UNIT COST: 910.85

Detailed Estimates
Name of Project : Improvement/Upgrading of San Nicolas Barangay Road

Location: San Nicolas, San Luis, Pampanga

Item IV: 0.15 m thick PCCP


Quantity: 1000 sq.m

I. Materials: Quantity Unit Cost Total Cost


RMC, 3500 psi at 28 Days 152 cu.m 3,500.00 532,000.00
16 mm Temperature Bars 40 pcs 350.00 14,000.00
12 mm Spikes 12 pcs 200.00 2,400.00
6" C-Purlins Forms 1 lot 18,000.00 18,000.00
Asphalt Sealants 30 kgs 85.00 2,550.00
Tie Wires and Other 1 lot 5,000.00 5,000.00

Sub Total 573,950.00


II. Equipment Quantity Days Daily Rate Total Cost
Vib. Screeder 1 8 550.00 4,400.00
Concrete Cutter 1 4 1,200.00 4,800.00
Water Truck 1 6 2,500.00 15,000.00

Sub Total 24,200.00


III. Labor Quantity Days Rate Total
Foreman 1 10 600.00 6,000.00
Skilled Laborer 4 10 450.00 18,000.00
Laborer 7 10 320.00 22,400.00
Sub Total 46,400.00
Total Direct Cost (A+B+C): 644,550.00
OCM, Profit and Tax (26%): 167,583.00
Total Cost: 812,133.00

UNIT COST: 812.13

Detailed Estimates
Name of Project : Improvement/Upgrading of San Nicolas Barangay Road

Location: San Nicolas, San Luis, Pampanga

Item V: 18" dia. RC pipe Culvert with Head Walls


Quantity: 14 li.m

I. Materials: Quantity Unit Cost Total Cost


RC Pipe, 18" 14 pcs 900.00 12,600.00
Cement 12 bags 220.00 2,640.00
Sand 1 pcs 250.00 250.00
Gravel 2 lot 625.00 1,250.00
Forms, Ties, Nails and Other 1 lot 1,500.00 1,500.00

Sub Total 18,240.00


II. Equipment Quantity Days Daily Rate Total Cost
One Bagger Mixer 1 1 550.00 550.00

Sub Total 550.00


III. Labor Quantity Days Rate Total
Foreman 1 3 600.00 1,800.00
Skilled Laborer 2 3 450.00 2,700.00
Laborer 2 3 320.00 1,920.00
Sub Total 6,420.00
Total Direct Cost (A+B+C): 25,210.00
OCM, Profit and Tax (26%): 6,554.60
Total Cost: 31,764.60

UNIT COST: 2,268.90


Item II: Subgrade Preparation
Quantity: 326.04

I. Materials:
None

II. Equipment Quantity Days Daily Rate Total Cost


Road Grader 1 1 12,000.00 12,000.00
12,000.00

III. Labor Quantity No of Days Rate Total


Foreman 1 1 550.00 550.00
Laborers 2 1 300.00 600.00
1,150.00

Total Direct Cost: 13,150.00


Indirect Cost(Mark-ups, Tax, etc.): 3,616.25
Total Amount: 16,766.25
Cost per sq.m: 51.42
Item III: Embankment
Quantity: 157 cu.m

I. Materials: Quanity Unit Cost Total


Aggt. Base Course 157.00 m 160.00 25,120.00
25,120.00

II. Equipment Quantity Days Daily Rate Total Cost


Road Grader 1 1 12,000.00 12,000.00
Road Roller 1 1 10,000.00 10,000.00
Plate Compactor 1 1 1,250.00 1,250.00
Water Truck 1 1 2,500.00 2,500.00
25,750.00

III. Labor Quantity No of Days Rate Total


Foreman 1 1 550.00 550.00
Skilled Laborer 1 1 410.00 410.00
Laborer 2 1 300.00 600.00
1,560.00

Total Direct Cost: 52,430.00


Indirect Cost(Mark-ups, Tax, etc.): 14,418.25
Total Amount: 66,848.25
Cost per cu.m 425.79

Item IV: Aggregate Base Course


Quantity: 35 cu.m

I. Materials: Quanity Unit Cost Total


Aggt. Base Course 35.00 m 460.00 16,100.00
16,100.00

II. Equipment Quantity Days Daily Rate Total Cost


Plate Compactor 1 2 1,250.00 2,500.00
Water Truck 1 2 2,500.00 5,000.00
7,500.00

III. Labor Quantity No of Days Rate Total


Foreman 1 2 550.00 1,100.00
Skilled Laborer 1 2 410.00 820.00
Laborer 2 2 300.00 1,200.00
3,120.00

Total Direct Cost: 26,720.00


Indirect Cost(Mark-ups, Tax, etc.): 7,348.00
Total Amount: 34,068.00
Cost per cu.m 973.37

Item V: 0.15m Thick PCCP


Quantity: 296.4 sq.m

I. Materials: Quanity Unit Cost Total


Cement 410.00 bags 220.00 90,200.00
Sand 23.00 cu.m 340.00 7,820.00
Gravel 45.00 cu.m 820.00 36,900.00
16 mm dia. Def bars x 6.0 m 12.00 pcs 195.00 2,340.00
Form Lumber, Ties, CW Nails, Sealants 1.00 lot 7,500.00 7,500.00
144,760.00

II. Equipment Quantity No of Days Rate Total


One Bagger Mixer 1 4 1,500.00 6,000.00
Concrete Vibrator w/ Screeder 1 4 1,250.00 5,000.00
Mini Water Truck 1 7 2,500.00 17,500.00
Concrete Cutter 1 2 1,500.00 3,000.00
25,500.00

III. Labor Quantity No of Days Rate Total


Foreman 1 4 550.00 2,200.00
Skilled Laborer 4 4 410.00 6,560.00
Laborer 8 4 300.00 9,600.00
18,360.00

Total Direct Cost: 188,620.00


Indirect Cost(Mark-ups, Tax, etc.): 51,870.50
Total Amount: 240,490.50
Cost per sq.m: 811.37

Item VI. 5" CHB Line Canal w/ Cover


Quantity: 296.4 sq.m

I. Materials: Quanity Unit Cost Total


5" CHB 1,634.00 pcs 7.00 11,438.00
Cement 314.00 bags 220.00 69,080.00
Sand 28.00 cu.m 340.00 9,520.00
Gravel 32.00 cu.m 820.00 26,240.00
12 mm dia. Def bars x 6.0 m 452.00 pcs 195.00 88,140.00
10 mm dia. Def bars x 6.0 m 64.00 pcs 196.00 12,544.00
Form Lumber, Ties, CW Nails, Sealants 1.00 lot 9,500.00 9,500.00
226,462.00

II. Equipment Quantity No of Days Rate Total


One Bagger Mixer 1 18 1,500.00 27,000.00
Mini Water Truck 1 7 2,500.00 17,500.00
17,500.00

III. Labor Quantity No of Days Rate Total


Foreman 1 18 550.00 9,900.00
Skilled Laborer 4 18 410.00 29,520.00
Laborer 8 18 300.00 43,200.00
82,620.00

Total Direct Cost: 326,582.00


Indirect Cost(Mark-ups, Tax, etc.): 89,810.05
Total Amount: 416,392.05
Cost per sq.m: 4,214.49
11.42
509.57
910.85

150
812.13

150
2,268.90
51.42
425.79

Item Detailed POW Difference


I 13,708.80 6,976.70 -6,732.10
II 16,764.98 10,004.24 -6,760.74
III 66,849.03 67,355.72 506.69
IV 34,067.95 40,709.77 6,641.82
IV 240,490.07 254,685.42 14,195.35
IV 416,391.61 411,810.02 -4,581.59
Total 788,272.44 791,541.87 3,269.43

973.37
296.4

44.46
409.03
22.23
44.46

811.37

296.4

1633.8
4,214.49
DETAILED ESTIMATES

Contract Name: Improvement of San Mateo Barangay Road, San Mateo, Arayat, Pampanga
Contract ID : PR# 13 - 0357

Item No. I. Removal of Structure and Obstructure (incl. Waste Disposal)


Quantity: 320.00 sq.m
A. Equipment Quantity Days Unit Cost Total
Backhoe with Breaker 1.00 2.00 11,500.00 23,000.00
Concrete Cutter 1.00 2.00 1,250.00 2,500.00
Elf Trcuk 1.00 2.00 4,000.00 8,000.00
Sub-Total 33,500.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 2.00 550.00 1,100.00
Ordinary Labor 6.00 2.00 325.00 3,900.00
Sub-Total 5,000.00

Mat'ls, Labor and Equipment: 38,500.00


Contingencies and Profit: 6,930.00
Value Added Tax: 4,620.00
Total for this Item: 50,050.00

Unit Cost for this Item: 156.41

Item No. II: Embankment/Filling Materials


Quantity: 60.00 cu.m
A. Materials Quantity Unit Cost Total
Filling Materials/Common Barrow 60.00 cu.m 220.00 13,200.00
Sub-Total 13,200.00

B. Equipment Quantity Days Unit Cost Total


Plate Compactor 1.00 3.00 1,500.00 4,500.00
Water Truck 1.00 2.00 3,000.00 6,000.00
Sub-Total 10,500.00

C. Labor Quantity Days Unit Cost Total


Foreman 1.00 3.00 550.00 1,650.00
Ordinary Labor 4.00 3.00 325.00 3,900.00
Sub-Total 5,550.00

Mat'ls, Labor and Equipment: 29,250.00


Contingencies and Profit: 5,265.00
Value Added Tax: 3,510.00
Total for this Item: 38,025.00

Unit Cost for this Item: 633.75

Item No. III: Aggregate Base Coarse


Quantity: 27.40 cu.m
A. Materials Quantity Unit Cost Total
Aggeregate Base Course 27.40 cu.m 525.00 14,385.00
Sub-Total 14,385.00

B. Equipment Quantity Days Unit Cost Total


Road Grader 1.00 1.00 8,500.00 8,500.00
Road Roller 1.00 1.00 5,000.00 5,000.00
Water Truck 1.00 1.00 3,000.00 3,000.00
Sub-Total 16,500.00

C. Labor Quantity Days Unit Cost Total


Foreman 1.00 1.00 550.00 550.00
Ordinary Labor 4.00 1.00 325.00 1,300.00
Sub-Total 1,850.00

Mat'ls, Labor and Equipment: 32,735.00


Contingencies and Profit: 5,892.30
Value Added Tax: 3,928.20
Total for this Item: 42,555.50

Unit Cost for this Item: 1,553.12

Item No. IV: 0.15 m thick PCCP


Quantity: 320.00 sq.m
A. Materials Quantity Unit Cost Total
Ready Mixed Concrete, 3500 pso @ 14 days 50.00 3,600.00 3,650.00 182,500.00
Steel Forms 1.00 lot 12,000.00 12,000.00
16 mm dia. Re-Bars and Dowels 10.00 pcs 195.00 1,950.00
Asphalt Sealant 15.00 kilos 120.00 1,800.00
Misc. Consumables 1.00 lot 1,500.00 1,500.00
Sub-Total 199,750.00

B. Equipment Quantity Days Unit Cost Total


Concrete Screeder w/ Vibrator 1.00 1.00 1,000.00 1,000.00
Concrete Cutter 1.00 1.00 1,500.00 1,500.00
Water Truck 1.00 7.00 3,000.00 21,000.00
Sub-Total 23,500.00

C. Labor Quantity Days Unit Cost Total


Foreman 1.00 2.00 550.00 1,100.00
Skilled labor 4.00 2.00 450.00 3,600.00
Ordinary Labor 8.00 2.00 325.00 5,200.00
Sub-Total 9,900.00

Mat'ls, Labor and Equipment: 233,150.00


Contingencies and Profit: 41,967.00
Value Added Tax: 27,978.00
Total for this Item: 303,095.00

Unit Cost for this Item: 947.17

Item No. V: Grouted Riprap


Quantity: 86.40 cu.m
A. Materials Quantity Unit Cost Total
Boulders 87.00 cu.m 700.00 60,900.00
Cement 292.00 bags 220.00 64,240.00
Sand 30.00 pcs 195.00 5,850.00
PVC Pipes (3") 3.00 pcs 545.00 1,635.00
Misc. Consumables 1.00 lot 1,500.00 1,500.00
Sub-Total 134,125.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 9.00 550.00 4,950.00
Skilled labor 3.00 9.00 450.00 12,150.00
Ordinary Labor 8.00 9.00 325.00 23,400.00
Sub-Total 40,500.00

Mat'ls, Labor and Equipment: 174,625.00


Contingencies and Profit: 31,432.50
Value Added Tax: 20,955.00
Total for this Item: 227,012.50

Unit Cost for this Item: 2,627.46

Item No. VI: Wheel Guards


Quantity: 108.00 pcs
A. Materials Quantity Unit Cost Total
Cement 88.00 bags 220.00 19,360.00
Sand 7.00 pcs 195.00 1,365.00
Gravel 10.00 cu.m 700.00 7,000.00
Re-Bars 650.00 kgs 38.00 24,700.00
Assorted Form Lumber 1.00 lot 3,000.00 3,000.00
Misc. Consumables 1.00 lot 1,500.00 1,500.00
Sub-Total 56,925.00

B. Equipment Quantity Days Unit Cost Total


One Bagger Mixer 1.00 6.00 1,250.00 7,500.00
Sub-Total 7,500.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 6.00 550.00 3,300.00
Skilled labor 2.00 6.00 450.00 5,400.00
Ordinary Labor 6.00 6.00 325.00 11,700.00
Sub-Total 20,400.00

Mat'ls, Labor and Equipment: 84,825.00


Contingencies and Profit: 15,268.50
Value Added Tax: 10,179.00
Total for this Item: 110,272.50

Unit Cost for this Item: 1,021.04

Item No. VII: Reinforced Concrete Works


Quantity: 12.00 cu.m
A. Materials Quantity Unit Cost Total
Cement 102.00 bags 220.00 22,440.00
Sand 6.00 pcs 195.00 1,170.00
Gravel 12.00 cu.m 700.00 8,400.00
Re-Bars 650.00 kgs 38.00 24,700.00
Assorted Form Lumber 1.00 lot 3,000.00 3,000.00
Misc. Consumables 1.00 lot 1,500.00 1,500.00
Sub-Total 61,210.00

B. Equipment Quantity Days Unit Cost Total


One Bagger Mixer 1.00 4.00 1,250.00 5,000.00
Sub-Total 5,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 4.00 550.00 2,200.00
Skilled labor 2.00 4.00 450.00 3,600.00
Ordinary Labor 6.00 4.00 325.00 7,800.00
Sub-Total 13,600.00

Mat'ls, Labor and Equipment: 79,810.00


Contingencies and Profit: 14,365.80
Value Added Tax: 9,577.20
Total for this Item: 103,753.00

Unit Cost for this Item: 8,646.08


156.41

633.75
1,553.12

48.00

947.17

12.96
40,237.50

2,627.46

16.20

17,077.50

1,021.04

1.80
12.00
102.00

18,363.00

8,646.08

I 50,051.20
II 38,025.00
III 42,555.49
IV 303,094.40
V 227,012.54
VI 110,272.32
VII 103,752.96
874,763.91

I #REF!
II 50,051.20
III 42,555.49
IV 303,094.40
#REF!
DETAILED ESTIMATES -PR# 12 - 4129
Improvement of DHVTSU Service/Acess Road, Moras Dela Paz, Sto. Tomas, Pampanga

Item No. I: MOBLIZATION/DEMOBILIZATION


Quantity: 1,722.70 sq.m

A. Equipment Quantity Days Unit Cost Total


Road Grader 1.00 1.00 12,000.00 12,000.00
Sub-Total 12,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 1.00 550.00 550.00
Ordinary Labor 4.00 1.00 325.00 1,300.00
Sub-Total 1,850.00

Direct Cost: 13,850.00


Indirect Cost ( 27%): 3,739.50
Total for this Item: 17,589.50

Item No. II: BREAKING AND REMOVAL OF EXISTING STRUCTURE (provision of Key Holes)
Quantity: 300.00 sq.m
A. Equipment Quantity Days Unit Cost Total
Elf Truck 1.00 5.00 4,000.00 20,000.00
Jack Hammer 1.00 5.00 5,500.00 27,500.00
Concrete Cutter 1.00 5.00 1,500.00 7,500.00
Sub-Total 55,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 5.00 550.00 2,750.00
Skilled labor 2.00 5.00 450.00 4,500.00
Ordinary Labor 5.00 5.00 325.00 8,125.00
Sub-Total 15,375.00

Direct Cost: 70,375.00


Indirect Cost ( 27%): 19,001.25
Total for this Item: 89,376.25
Unit Cost for this Item: 297.92

Page 67
Item No. III: EMBANKMENT/FILLING MATERIALS
Quantity: 554.00 cu.m
A. Materials Quantity Unit Cost Total
Filling Materials/Common Barrow 554.00 cu.m 200.00 110,800.00
Sub-Total 110,800.00

B. Equipment Quantity Days Unit Cost Total


Road Grader 1.00 4.00 12,000.00 48,000.00
Plate Compactor 1.00 10.00 1,500.00 15,000.00
Water Truck 1.00 10.00 3,000.00 30,000.00
Sub-Total 93,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 10.00 550.00 5,500.00
Skilled labor 1.00 10.00 450.00 4,500.00
Ordinary Labor 6.00 10.00 325.00 19,500.00
Sub-Total 29,500.00

Direct Cost: 233,300.00


Indirect Cost ( 27%): 62,991.00
Total for this Item: 296,291.00
Unit Cost for this Item: 534.82

Item No. IV: AGGREGATE BASE COARSE


Quantity: 312.00 cu.m

A. Materials Quantity Unit Cost Total


Aggregate Base Course 312.00 cu.m 550.00 171,600.00
Sub-Total 171,600.00

B. Equipment Quantity Days Unit Cost Total


Road Grader 1.00 3.00 12,000.00 36,000.00
Plate Compactor 1.00 6.00 1,500.00 9,000.00
Water Truck 1.00 6.00 3,000.00 18,000.00
Sub-Total 63,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 6.00 550.00 3,300.00
Skilled labor 1.00 6.00 450.00 2,700.00
Ordinary Labor 4.00 6.00 325.00 7,800.00

Page 68
Sub-Total 13,800.00

Direct Cost: 248,400.00


Indirect Cost ( 27%): 67,068.00
Total for this Item: 315,468.00
Unit Cost for this Item: 1,011.12

Item No. V: 0.15 M THICK PCCP


Quantity: 1,476.00 cu.m
A. Materials Quantity Unit Cost Total
Ready Mixed Concrete, 3500 pso @ 14 days 226.00 cu.m 3,550.00 802,300.00
Steel Forms 1.00 lot 20,000.00 20,000.00
16 mm dia. Re-Bars and Dowels 15.00 pcs 70.00 1,050.00
Asphalt Sealant 42.00 kilos 120.00 5,040.00
Misc. Consumables 1.00 lot 7,500.00 7,500.00
Sub-Total 835,890.00

B. Equipment Quantity Days Unit Cost Total


Concrete Screeder w/ Vibrator 1.00 20.00 1,000.00 20,000.00
Concrete Cutter 1.00 8.00 1,500.00 12,000.00
Water Truck 1.00 20.00 3,000.00 60,000.00
Sub-Total 72,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 20.00 550.00 11,000.00
Skilled labor 4.00 20.00 450.00 36,000.00
Ordinary Labor 10.00 20.00 325.00 65,000.00
Sub-Total 112,000.00

Direct Cost: 1,019,890.00


Indirect Cost ( 27%): 275,370.30
Total for this Item: 1,295,260.30
Unit Cost for this Item: 877.55

Item No. VI: CONCRETE SLOPE PROTECTION


Quantity: 180.00 li.m
A. Materials Quantity Unit Cost Total
Portland Cement 580.00 bags 210.00 121,800.00
Sand 32.00 cu.m 265.00 8,480.00

Page 69
Gravel 63.00 cu.m 720.00 45,360.00
Assorted Form Lumber 1.00 lot 25,000.00 25,000.00
12 mm dia Re-Bars 280.00 pcs 195.00 54,600.00
10 mm dia Re-Bars 412.00 pcs 135.00 55,620.00
Misc. Consumables 1.00 lot 5,000.00 5,000.00
Sub-Total 315,860.00

B. Equipment Quantity Days Unit Cost Total


Concrete Vibrator 1.00 24.00 1,000.00 24,000.00
One Bagger Mixer 1.00 24.00 1,500.00 36,000.00
Water Truck 1.00 24.00 3,000.00 72,000.00
Sub-Total 108,000.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 24.00 550.00 13,200.00
Skilled labor 4.00 24.00 450.00 43,200.00
Ordinary Labor 10.00 24.00 325.00 78,000.00
Sub-Total 134,400.00

Direct Cost: 558,260.00


Indirect Cost ( 27%): 150,730.20
Total for this Item: 708,990.20
Unit Cost for this Item: 3,938.83

Item No. VII. CONCRETE WHEELGUARD


Quantity: 122.00 pcs
A. Materials Quantity Unit Cost Total
Portland Cement 140.00 bags 210.00 29,400.00
Sand 8.00 cu.m 265.00 2,120.00
Gravel 15.00 cu.m 720.00 10,800.00
Assorted Form Lumber 1.00 lot 10,000.00 10,000.00
12 mm dia Re-Bars 42.00 pcs 195.00 8,190.00
10 mm dia Re-Bars 232.00 pcs 135.00 31,320.00
Misc. Consumables 1.00 lot 3,500.00 3,500.00
Sub-Total 95,330.00

B. Equipment Quantity Days Unit Cost Total


Concrete Vibrator 1.00 7.00 1,000.00 7,000.00
One Bagger Mixer 1.00 7.00 1,500.00 10,500.00
Sub-Total 10,500.00

Page 70
B. Labor Quantity Days Unit Cost Total
Foreman 1.00 7.00 550.00 3,850.00
Skilled labor 4.00 7.00 450.00 12,600.00
Ordinary Labor 6.00 7.00 325.00 13,650.00
Sub-Total 30,100.00

Direct Cost: 135,930.00


Indirect Cost ( 27%): 36,701.10
Total for this Item: 172,631.10
Unit Cost for this Item: 1,415.01

Item No. VIII. CONCRETE BOX CULVERT


Quantity: 9.00 li.m
A. Materials Quantity Unit Cost Total
Portland Cement 55.00 bags 210.00 11,550.00
Sand 3.00 cu.m 265.00 795.00
Gravel 6.00 cu.m 720.00 4,320.00
Assorted Form Lumber 1.00 lot 7,500.00 7,500.00
16 mm dia Re-Bars 18.00 pcs 330.00 5,940.00
10 mm dia Re-Bars 118.00 pcs 135.00 15,930.00
Misc. Consumables 1.00 lot 2,500.00 2,500.00
Sub-Total 48,535.00

B. Equipment Quantity Days Unit Cost Total


Concrete Vibrator 1.00 3.00 1,000.00 3,000.00
One Bagger Mixer 1.00 3.00 1,500.00 4,500.00
Water Truck 1.00 3.00 3,000.00 9,000.00
Sub-Total 13,500.00

B. Labor Quantity Days Unit Cost Total


Foreman 1.00 4.00 550.00 2,200.00
Skilled labor 4.00 4.00 450.00 7,200.00
Ordinary Labor 6.00 4.00 325.00 7,800.00
Sub-Total 17,200.00

Direct Cost: 79,235.00


Indirect Cost ( 27%): 21,393.45
Total for this Item: 100,628.45
Unit Cost for this Item: 11,180.94

Page 71
297.92

Page 72
534.82

Page 73
1,011.12

221.40

877.55

63.00
573.30
31.50

Page 74
63.00

110,551.00

242,400.00

3,938.83

14.95
136.00
7.47
14.95

33,365.50

Page 75
40,600.00

1,415.01

6.00
54.60
3.00
6.00

16,987.25

30,700.00

11,180.94

Page 76
I 17,589.50
II 89,376.25
III 296,291.00
IV 315,469.44
V 1,295,263.80
VI 708,989.40
VII 172,631.22
VIII 100,628.46
IX
X
2,996,239.07

Page 77
Name of Project: IMPROVEMENT OF SINDALAN - ANAO ROAD (CAMUNING SECTION)
Location: CAMUNING, MEXICO, PAMPANGA

Item No. I: Mobilization/Demobilization Quantity 1.00 lot

I. Equipment Cost (Fuel and Operator) Days Rate/Day Total


1.00 Lowbed Trailer w/ Primemover 2 10,000.00 P 20,000.00

II. Labor Cost Days Rate/Day Total


2.00 Laborers 2 300.00 P 1,200.00

Sub-Total Cost: 21,200.00


Mark-Ups (25%): 5,300.00
Total Cost: 26,500.00

Item No. II: Breaking and Removal of Existing Quantity #REF! cu.m
Structure
I. Equipment Cost (Fuel and Operator) Days Rate/Day Total
1.00 Backhoe with Breaker 20 12,000.00 P 240,000.00
1.00 Concrete Cutter 12 1,500.00 18,000.00
2.00 Dump Truck 18 11,500.00 414,000.00
P 672,000.00

III. Labor Cost Days Rate/Day Total


1.00 Project Engineer 20 600.00 P 12,000.00
1.00 Foreman 20 500.00 10,000.00
8.00 Laborers 20 300.00 48,000.00
P 70,000.00

Sub-Total Cost: 742,000.00


Mark-Ups (25%): 185,500.00
Total Cost: 927,500.00 Unit Cost: 292.24 /cu.m

Item No. III: Aggregate Base Course Quantity 289.00 cu.m

I. Material Cost Unit Cost Total


289.00 cu.m - Aggregate Base Course 520.00 P 150,280.00

II. Equipment Cost (Fuel and Operator) Days Rate/Day Total


1.00 Road Grader 4 8,000.00 P 32,000.00
1.00 Road Roller 8 6,500.00 52,000.00
1.00 Water Truck 8 2,000.00 16,000.00
P 100,000.00

III. Labor Cost Days Rate/Day Total


1.00 Project Engineer 8 600.00 P 4,800.00
1.00 Foreman 8 500.00 4,000.00
3.00 Laborers 8 300.00 7,200.00
P 16,000.00
Sub-Total Cost: 266,280.00
Mark-Ups (25%): 66,570.00
Total Cost: 332,850.00 Unit Cost: 1,151.73 /cu.m

Item No. IV: 0.20m thick PCCP Quantity 3,390.00 sq.m

I. Material Cost Unit Cost Total


680.00 cu.m - RMC, 3500 @ 14 days 3,600.00 P 2,448,000.00
106.00 pcs - 16 mm Dowels and Spikes 345.00 36,570.00
0.50 drums - Asphalt Sealant 10,000.00 5,000.00
1.00 lot - C- Purlins Forms 30,000.00 30,000.00
1.00 lot - Miscellaneous Items 7,500.00 7,500.00
P 2,527,070.00

II. Equipment Cost (Fuel and Operator) Days Rate/Day Total


1.00 Vibratory Screeder 24 850.00 20,400.00
1.00 Concrete Cutter 8 1,500.00 12,000.00
1.00 Water Truck 18 2,500.00 45,000.00
P 77,400.00

III. Labor Cost Days Rate/Day Total


1.00 Project Engineer 29 600.00 P 17,400.00
1.00 Foreman 29 500.00 14,500.00
3.00 Skilled Labor 29 500.00 43,500.00
10.00 Laborers 29 300.00 87,000.00
P 162,400.00

Sub-Total Cost: 2,766,870.00


Mark-Ups (25%): 691,717.50
Total Cost: 3,458,587.50 Unit Cost: 1,020.23 /sq.m

Item No. V: 18 " Reinforced Concrete Culvert Quantity 22.00 li.m

I. Material Cost Unit Cost Total


16.00 bags - Cement (40 kgs) 205.00 P 3,280.00
2.00 cu.m - Sand 275.00 550.00
2.00 cu.m - Gravel 700.00 1,400.00
22.00 pcs - 18" RC Pipes 925.00 20,350.00
1.00 lot - Miscellaneous Items 1,000.00 1,000.00
P 26,580.00

II. Labor Cost Days Rate/Day Total


1.00 Project Engineer 3 600.00 P 1,800.00
1.00 Foreman 3 500.00 1,500.00
1.00 Skilled Labor 3 500.00 1,500.00
3.00 Laborers 3 300.00 2,700.00
P 7,500.00

Sub-Total Cost: 34,080.00


Mark-Ups (25%): 8,520.00
Total Cost: 42,600.00 Unit Cost: 1,936.36 /cu.m
#REF!
1,151.73

678.00 6169.8
339

1,020.23

4.06593407

10259

1,936.36
Det
I 26,500.00
II #REF!
III 332,849.97
IV 3,458,579.70
V 42,599.92
VI
VII
VIII
IX
#REF!
DETAILED ESTIMATES

Item I: MOBILIZATION/DEMOBLIZATION
Qty: 1.00 lot

A. Materials:
Quanity Description Unit Cost Total
1.00 lot Bunk Houses, Store Room, etc. P 8,000.00 P 8,000.00
1.00 lot Signages, Billboards, etc. 5,000.00 5,000.00
P 13,000.00
B. Equipment
Quantity Days Description Rate Total
1 2 Stake Truck P 3,000.00 P 6,000.00
P 6,000.00
C. Labor
Quantity Days Description Rate Total
4 2 Laborer 280.00 2,240.00
P 2,240.00

Direct Cost: 21,240.00


Mark-ups, Tax and Profit: 5,841.00
Total: P 27,081.00

Item II: SUBGRADE PREPARATION


Qty: 2907.50 cu.m

A. Equipment
Quantity Days Description Rate Total
1 1 Road Grader P 12,000.00 P 12,000.00
P 12,000.00

B. Labor
Quantity Days Description Rate Total
1 1 Foreman P 480.00 480.00
4 1 Laborer 280.00 1,120.00
P 1,600.00

Direct Cost: 13,600.00


Mark-ups, Tax and Profit: 3,740.00
Total: P 17,340.00

Unit Cost: P 5.96

Item III: EMBANKMENT/FILLING MATERIALS


Qty: 640.68 cu.m

A. Materials:
Quanity Description Unit Cost Total
640.68 m Filling Materials P 225.00 P 144,153.00
P 144,153.00
B. Equipment
Quantity Days Description Rate Total
1 4 Road Grader P 12,000.00 P 48,000.00
1 6 Road Roller 6,500.00 39,000.00
1 6 Plate Compactor 1,500.00 9,000.00
1 6 Mini Water Truck 2,500.00 15,000.00
P 111,000.00
C. Labor
Quantity Days Description Rate Total
1 6 Foreman P 480.00 2,880.00
1 6 Skilled Laborer 380.00 2,280.00
4 6 Laborer 280.00 6,720.00
P 11,880.00

Direct Cost: 267,033.00


Mark-ups, Tax and Profit: 73,434.08
Total: P 340,467.08

Unit Cost: P 531.42

Item IV: AGGREGATE BASE COURSE


Qty: 267.49 cu.m

A. Materials:
Quanity Description Unit Cost Total
267.49 m Aggt. Base Coarse P 550.00 P 147,119.50
P 147,119.50
B. Equipment
Quantity Days Description Rate Total
1 2 Road Grader P 10,000.00 P 20,000.00
1 3 Road Roller 6,500.00 19,500.00
1 3 Plate Compactor 1,500.00 4,500.00
1 3 Mini Water Truck 2,500.00 7,500.00
P 51,500.00
C. Labor
Quantity Days Description Rate Total
1 3 Foreman P 480.00 1,440.00
1 3 Skilled Laborer 380.00 1,140.00
4 3 Laborer 280.00 3,360.00
P 5,940.00
Direct Cost: 204,559.50
Mark-ups, Tax and Profit: 56,253.86
Total: P 260,813.36

Unit Cost: P 975.04

Item V: 0.15 m THICK PCCP (RMC 3500 psi @ 28 DAYS)


Qty: 2326.00 m

A. Materials:
Quanity Description Unit Cost Total
349.00 m RMC, G1 - 3/4" 3500 psi @ 28 days P 3,500.00 P 1,221,500.00
12.00 pcs 16mm Dowels 340.00 4,080.00
15.00 pcs 12mm Spikes 195.00 2,925.00
1.00 lot 6" Forms 25,000.00 25,000.00
1.00 lot Sealants and Tie Wires 8,000.00 8,000.00
P 1,261,505.00

B. Equipment
Quantity Days Description Rate Total
1 12 Concrete Vibrator w/ Screeder 1,500.00 P 18,000.00
1 14 Mini Water Truck 2,500.00 35,000.00
1 6 Concrete Cutter 1,200.00 7,200.00
P 60,200.00

Quantity No of DaysIII. Labor Rate Total


1 14 Foreman P 480.00 6,720.00
4 14 Skilled Laborer 380.00 21,280.00
10 14 Laborer 280.00 39,200.00
P 67,200.00

Direct Cost: 1,388,905.00


Mark-ups, Tax and Profit: 381,948.88
Total: P 1,770,853.88

Unit Cost: P 761.33

Item VI: 4" CHB Line Canal w/ Cover


Qty: 2326.00 m

A. Materials:
Quanity Description Unit Cost Total
1,490.00 bags Cement, 40 kgs P 218.00 P 324,820.00
110.00 cu.m Screened Sand 250.00 27,500.00
62.00 cu.m 3/4" Gravel 810.00 50,220.00
15,500.00 pcs 4" CHB 5.50 85,250.00
1,950.00 lot 10 mm dia Deformed Bars 135.00 263,250.00
16.00 pcs 1/2" thick plywood 480.00 7,680.00
250.00 bd.ft Assorted Form Lumber and Bracings 42.00 10,500.00
50.00 kgs CW Nails and Tie Wires 70.00 3,500.00
P 772,720.00

B. Equipment
Quantity Days Description Rate Total
1 24 One Bagger Mixer 1,500.00 P 36,000.00
1 8 Concrete Cutter 1,200.00 9,600.00
P 45,600.00

Quantity No of DaysIII. Labor Rate Total


1 28 Foreman P 480.00 13,440.00
4 28 Skilled Laborer 380.00 42,560.00
8 28 Laborer 280.00 62,720.00
P 118,720.00

Direct Cost: 937,040.00


Mark-ups, Tax and Profit: 257,686.00
Total: P 1,194,726.00
5.96
531.42
975.04

348.9

761.33

348.9
I 27,081.00
II 17,328.70
III 340,470.17
IV 260,813.45
V 1,770,853.58
VI 1,194,726.00
3,611,272.90
DETAILED ESTIMATES
Construction of Covered Court with Reinforced Concrete Slab at Barangay San Fancisco,
Lubao, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
1.00 lot Signages, barricades, barracks, etc. 20,000.00 20,000.00
Materials: 20,000.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
4.00 2.00 Laborers 300.00 2,400.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 7,400.00

Sub-Total : 27,400.00
Profit Tax and Overhead : 8,220.00
Total Cost : 35,620.00

Item II: Embankment/Filling Materials


Qty: 184.80 cu.m

A. Materials
Qty. Item Description Unit Cost Total
184.80 cu.m Filling Materials (common barrow) 225.00 41,580.00
Materials: 41,580.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 4.00 Foreman 600.00 2,400.00
6.00 4.00 Laborers 300.00 7,200.00
1.00 3.00 Plate Compactor 2,500.00 7,500.00
Labor and Equipment: 17,100.00

Sub-Total : 58,680.00
Profit Tax and Overhead : 17,604.00
Total Cost : 76,284.00
Unit Cost : 412.79

Page 91
Item III: Excavation and Backfilling
Qty: 97.92 cu.m

A. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 6.00 Foreman 600.00 3,600.00
1.00 6.00 Skilled Laborers 300.00 1,800.00
6.00 6.00 Laborers 301.00 10,836.00
Labor and Equipment: 16,236.00

Sub-Total : 16,236.00
Profit Tax and Overhead : 4,870.80
Total Cost : 21,106.80
Unit Cost : 215.55

Item IV: Concrete Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
780.00 bags Cement 210.00 163,800.00
47.00 cu.m Sand 260.00 12,220.00
84.00 cu.m Gravel 3/4" 830.00 69,720.00
144.00 pcs 16mm dia. Bars 340.00 48,960.00
68.00 pcs 12 mm dia. Bars 200.00 13,600.00
530.00 pcs 10mm dia. Bars 140.00 74,200.00
60.00 kgs Tie Wires 70.00 4,200.00
Materials: 386,700.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 30.00 Foreman 600.00 18,000.00
4.00 30.00 Skilled Laborers 450.00 54,000.00
8.00 30.00 Laborers 301.00 72,240.00
1.00 30.00 One Bagger Mixer 650.00 19,500.00
Labor and Equipment: 163,740.00

Sub-Total : 550,440.00
Profit Tax and Overhead : 165,132.00
Total Cost : 715,572.00

Page 92
Item V: Masonry Works
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
1,020.00 pcs 5" CHB 8.00 8,160.00
70.00 bags Cement 210.00 14,700.00
7.00 cu.m Sand 260.00 1,820.00
72.00 pcs 10mm x 6m RSB 130.00 9,360.00
Materials: 34,040.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 5.00 Foreman 600.00 3,000.00
2.00 5.00 Skilled Laborers 450.00 4,500.00
6.00 5.00 Laborers 301.00 9,030.00
Labor and Equipment: 13,530.00

Sub-Total : 47,570.00
Profit Tax and Overhead : 14,271.00
Total Cost : 61,841.00

Item VI: Carpentry Works


Forms and Scaffoldings
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
12.00 pcs 1/2" Marine Plywood 480.00 5,760.00
250.00 bd.ft Form Lumber 48.00 12,000.00
1.00 lot Scaffoldings (H-Frame) 5,000.00 5,000.00
8.00 kilos Cw Nails 70.00 560.00
Materials: 23,320.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 5.00 Foreman 600.00 3,000.00
2.00 5.00 Skilled Laborers 450.00 4,500.00
4.00 5.00 Laborers 301.00 6,020.00
Labor and Equipment: 10,520.00

Page 93
Sub-Total : 33,840.00
Profit Tax and Overhead : 10,152.00
Total Cost : 43,992.00

Item VII: Steel Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
322.00 pcs 1/4" x 2-1/2" x 2-1/2" Angle Bars 1,550.00 499,100.00
154.00 pcs 1/4" x 2" x 2" Angle bars 875.00 134,750.00
70.00 pcs 16mm dia. Sag Rods and Cross Bracings 350.00 24,500.00
24.00 pcs 16mm dia. Turn Buckles 80.00 1,920.00
12.00 pcs 12mm MS Plate (0.35 m x 0.40 m) 820.00 9,840.00
72.00 pcs Bolt and Washers 210.00 15,120.00
224.00 pcs 1.5mm x 2" x 6" C-Purlins 820.00 183,680.00
23.00 pcs 1.5mm x 2" x 4" C-Purlins 665.00 15,295.00
24.00 gals Primer Paint 620.00 14,880.00
1.00 lot Misc. Consumbles (Welding Rods, etc) 5,000.00 5,000.00
Materials: 904,085.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 25.00 Foreman 600.00 15,000.00
4.00 25.00 Skilled Laborers 475.00 47,500.00
6.00 25.00 Laborers 301.00 45,150.00
1.00 22.00 Welding machine 850.00 18,700.00
1.00 6.00 Elf Truck with Boom 7,500.00 45,000.00
Labor and Equipment: 171,350.00

Sub-Total : 1,075,435.00
Profit Tax and Overhead : 322,630.50
Total Cost : 1,398,065.50

Item VIII: Tinsmithry Works


Qty: 776.00 li.m

A. Materials
Qty. Item Description Unit Cost Total
776.00 li.m 0.40mm Color Steel Supreme (Rib Type) 350.00 271,600.00

Page 94
15.00 pcs 0.40mmx 24" Gutter 650.00 9,750.00
20.00 pcs 0.40mm x 24" Flashing 450.00 9,000.00
32.00 pcs 0.40mm x 16" Ridge Cap 450.00 14,400.00
24.00 pcs 3" PVC Pipe 510.00 12,240.00
24.00 pcs 3" PVC Elbow 60.00 1,440.00
5,432.00 pcs Tekscrews 2.00 10,864.00
1,000.00 pcs Rivets 0.75 750.00
1.00 lot Miscellaneous (sealants, straps, etc.) 2,500.00 2,500.00
Materials: 332,544.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 12.00 Foreman 600.00 7,200.00
4.00 12.00 Skilled Laborers 500.00 24,000.00
4.00 12.00 Laborers 30.00 1,440.00
Labor and Equipment: 32,640.00

Sub-Total : 365,184.00
Profit Tax and Overhead : 109,555.20
Total Cost : 474,739.20
Unit Cost : 611.78

Item IX: Painting Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
3.00 gals Flat Latex Paint (Concrete columns) 520.00 1,560.00
4.00 gals Semi Gloss (Concrete columns) 550.00 2,200.00
20.00 gals Quick Dry Enamel 575.00 11,500.00
1.00 lot Misc. Consumables (brushes, rollers, etc) 2,000.00 2,000.00
Materials: 17,260.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 5.00 Foreman 600.00 3,000.00
3.00 5.00 Skilled Laborers 500.00 7,500.00
3.00 5.00 Laborers 30.00 450.00
Labor and Equipment: 10,950.00

Sub-Total : 22,450.00

Page 95
Profit Tax and Overhead : 6,735.00
Total Cost : 29,185.00

Page 96
412.79

Page 97
215.55

93.41
794.00
46.71
84.07
143.00
62.00
518.00

###

Page 98
3,400.00
260.00
26.00
220.00
11,914.00

8,162.00

Page 99
313.00
142.00
69.00

219.00

###

340

Page 100
340

###

611.78

Page 101
I 35,620.00
II 76,283.59
III 21,106.66
IV 715,572.00
V 61,841.00
VI 43,992.00
VII 1,398,065.50
VIII 474,739.20
IX 29,185.00
2,856,404.95

Page 102
DETAILED ESTIMATES

Project Name: Construction of Covered Court with Reinforced Slab


Location : Sto. Tomas, Lubao, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

I. Materials: Quanity Unit Cost Total


Temporary Facilities, Signages, Barricades 1.00 lot P 20,000.00 P 20,000.00
P 20,000.00

II. Labor and Equipment Unit Cost Total


1.00 Foreman 2.00 days P 650.00 P 1,300.00
2.00 Skilled 2.00 days 420.00 1,680.00
4.00 Laborer 2.00 days 300.00 2,400.00
1.00 Elf Truck 2.00 days 1,750.00 3,500.00
P 8,880.00

Direct Cost: P 28,880.00


In-Direct Cost: 7,797.60
Bid Total: P 36,677.60

Item II:Embankment (Levelling and Compaction only)


Qty: 228.00 cu.m

I. Materials:
None

II. Labor and Equipment Unit Cost Total


1.00 Foreman 6.00 days P 650.00 P 3,900.00
1.00 Skilled 6.00 days 420.00 2,520.00
6.00 Laborer 6.00 days 300.00 10,800.00
1.00 Plate Compactor 5.00 days 1,200.00 6,000.00
P 17,220.00

Direct Cost: P 17,220.00


In-Direct Cost: 4,649.40
Total: P 21,869.40
Unit Cost: 95.92

Bid Total: P 21,869.76


Item III: Excavation and Backfilling
Qty: 104.46 cu.m

I. Materials:
None

II. Labor and Equipment Unit Cost Total


1.00 Foreman 3.00 days P 650.00 P 1,950.00
2.00 Skilled 3.00 days 420.00 2,520.00
6.00 Laborer 3.00 days 300.00 5,400.00
P 9,870.00

Direct Cost: P 9,870.00


In-Direct Cost: 2,664.90
Total: P 12,534.90
Unit Cost: 120.00

Bid Total: P 12,535.20

Item III: Concrete Works:


Qty: 21.50 cu.m

I. Materials: Quanity Unit Cost Total


Cement 750.00 bags P 220.00 P 165,000.00
Sand 44.00 cu.m 260.00 11,440.00
Gravel 3/4" 88.00 cu.m 830.00 73,040.00
16mm x 6m RSB 160.00 pcs 350.00 56,000.00
12mm x 6m RSB 108.00 pcs 200.00 21,600.00
10mm x 6m RSB 564.00 pcs 135.00 76,140.00
Tie Wires 40.00 kgs 75.00 3,000.00
P 406,220.00

II. Labor and Equipment (35%) P 142,177.00


Direct Cost: P 548,397.00
In-Direct Cost: 148,067.19
Bid Total: P 696,464.19

Item V: Masonry Works


Qty: 1.00 lot

I. Materials: Quanity Unit Cost Total


Cement 98.00 bags P 220.00 P 21,560.00
Sand 11.00 cu.m 260.00 2,860.00
5" CHB 1,575.00 pcs 7.50 11,812.50
10mm x 6m RSB 96.00 pcs 135.00 12,960.00
Tie Wires 40.00 kgs 75.00 3,000.00
P 52,192.50

II. Labor and Equipment (35%) P 18,267.38


Direct Cost: P 70,459.88
In-Direct Cost: 19,024.17
Bid Total: P 89,484.04

Item VI: Carpentry Works


Qty: 1.00 lot
I. Materials: Quanity Unit Cost Total
Assorted Form Lumber 300.00 bd.f P 42.00 P 12,600.00
1/4" thick Plywood 16.00 pcs 350.00 5,600.00
CW Nails 4.00 kgs 65.00 260.00
P 18,460.00

II. Labor and Equipment (35%) P 6,461.00


Direct Cost: P 24,921.00
In-Direct Cost: 6,728.67
Bid Total: P 31,649.67

Item VII: Steel Works


Qty: 1.00 lot

I. Materials: Quanity Unit Cost Total


1/4" x 2-1/2" x 2-1/2" Angle Bars 202.00 pcs 1,550.00 313,100.00
1/4" x 2" x 2" Angle bars 220.00 pcs 875.00 192,500.00
1/4" x 1-1/2" x 1-1/2" Angle Bars 14.00 pcs 580.00 8,120.00
16mm dia. Sag Rods and Cross Bracings 70.00 pcs 350.00 24,500.00
16mm dia. Turn Buckles 24.00 pcs 80.00 1,920.00
12mm MS Plate (0.35 m x 0.40 m) 12.00 pcs 820.00 9,840.00
1.5mm x 2" x 6" C-Purlins 192.00 pcs 800.00 153,600.00
1.5mm x 2" x 3" C-Purlins 23.00 pcs 460.00 10,580.00
Bolt and Washers 72.00 pcs 210.00 15,120.00
Primer Paint 16.00 gals 620.00 9,920.00
Misc. Consumbles (Welding Rods, etc) 1.00 lot 15,000.00 15,000.00
P 754,200.00

II. Labor and Equipment (48%) P 362,016.00


Direct Cost: P 1,116,216.00
In-Direct Cost: 301,378.32
Bid Total: P 1,417,594.32

Item VII: Tinsmithry Works


Qty: 776.00 li.m

I. Materials: Quanity Unit Cost Total


0.40mm Color Steel Supreme (Rib Type) 776.00 li.m P 350.00 P 271,600.00
0.40mmx 24" Gutter 15.00 pcs 550.00 8,250.00
0.40mm x 24" Flashing 20.00 pcs 350.00 7,000.00
0.40mm x 16" Ridge Cap 32.00 pcs 350.00 11,200.00
3" PVC Pipe 24.00 pcs 510.00 12,240.00
3" PVC Elbow 24.00 pcs 60.00 1,440.00
Misc. Consumables (screws, rivets, sealants, etc 1.00 lot 8,000.00 8,000.00
P 319,730.00

II. Labor and Equipment (35%) P 111,905.50


Direct Cost: P 431,635.50
In-Direct Cost: 116,541.59
Total: P 548,177.09
Unit Cost: 706.41

Bid Total: P 548,174.16

Item IX: Painting Works


Qty: 1.00 lot

I. Materials: Quanity Unit Cost Total


Flat Latex Paint (Concrete columns) 3.00 gals 520.00 1,560.00
Semi Gloss (Concrete columns) 4.00 gals 550.00 2,200.00
Quick Dry Enamel 14.00 gals 575.00 8,050.00
H Frame Scaffoldings 1.00 lot 4,000.00 4,000.00
Misc. Consumables (brushes, rollers, etc) 1.00 lot 3,000.00 3,000.00
P 18,810.00

II. Labor and Equipment (45%) P 8,464.50


Direct Cost: P 27,274.50
In-Direct Cost: 7,364.12
Bid Total: P 34,638.62
95.92
120.00

87.9120879121 800
800 747.2527
43.956043956
87.9120879121
161
105
556
196
215
12
379.6

706.41

I 36,677.60
II 21,869.76
III 12,535.20
IV 696,464.19
V 89,484.04
VI 31,649.67
VII 1,417,594.32
VIII 548,174.16
IX 34,638.62
2,889,087.56
DETAILED ESTIMATES
Construction of Multi Purpose Covered Area with Reinforced Concrete Slab at Diosdado Macapagal
Memorial High School, Solib, Floridblanca, Pampanga

Item No. I: Mobilization/Demobilization


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Barricades and Signages 1 lot P 5,000.00 P 5,000.00
Mat'l Cost: P 5,000.00

Labor Cost: Days Rate/Day Total


6 - Laborers 2 P 320.00 P 3,840.00
Labor Cost: P 3,840.00
`
Equipment Cost: Days Rate/Day Total
1 - Stake Truck 2 P 3,000.00 P 6,000.00
Equipment Cost: P 6,000.00

Direct Cost: P 14,840.00


Overhead and Profit: 2,968.00
VAT: 2,136.96
Total: P 19,944.96

Item No. II: Excavation & Backfilling


QTY: 57.24 cu.m

Labor Cost: Days Rate/Day Total


1 - Foreman 4 550.00 2,200.00
7 - Laborers 4 320.00 8,960.00
Labor Cost: P 11,160.00

Direct Cost: P 11,160.00


Overhead and Profit: 2,232.00
VAT: 1,607.04
Total: P 14,999.04

Unit Cost: 262.04 262.04

Item No. III: Filling Materials


QTY: 32.00 cu.m

Material Cost: Quantity Unit Cost Total


Filling Materials/Common Barrow 32.00 m P 250.00 P 8,000.00

CC3 Page 112


Mat'l Cost: P 8,000.00

Labor Cost: Days Rate/Day Total


1 - Foreman 2 550.00 1,100.00
4 - Laborers 2 320.00 2,560.00
Labor Cost: P 3,660.00

Equipment Cost: Days Rate/Day Total


1 - Plate Compactor 2 P 1,200.00 P 2,400.00
Equipment Cost: P 2,400.00

Direct Cost: P 14,060.00


Overhead and Profit: 2,812.00
VAT: 2,024.64
Total: P 18,896.64

Unit Cost: 590.52 590.52

Item No. IV. Concrete Works


QTY: 43.97 cu.m

Material Cost: Quantity Unit Cost Total 43.97


5" CHB 366 pcs. P 7.50 P 2,745.00 2,813.00
Cement 374 bags 220.00 82,280.00 373.75
Sand 37 cu.m. 250.00 9,250.00 26.38
Gravel 40 cu.m. 750.00 30,000.00 39.57
16 mm x 6.0 m 86 pcs. 345.00 29,670.00 169.00
12 mm x 6.0 m 14 pcs. 135.00 1,890.00 35.00
10 mm x 6.0 m 92 pcs. 90.00 8,280.00 292.00
G.I. wire #16 25 kls. 70.00 1,750.00
Mat'l Cost P 163,120.00

Labor Cost: Days Rate/Day Total


1 - Foreman 14 550.00 7,700.00
3 - Skilled Laborers 14 450.00 18,900.00
6 - Laborers 14 320.00 26,880.00
Labor Cost: P 53,480.00

Equipment Cost: Days Rate/Day Total


1 - One Bagger Mixer 12 P 1,500.00 P 18,000.00
Equipment Cost: P 18,000.00 43.82

Direct Cost: P 234,600.00


Overhead and Profit: 46,920.00
VAT: 33,782.40
Total: P 315,302.40

Unit Cost: 7,170.85 7,170.85


CC3 Page 113
Item No. V: Forms & Scaffolding
QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


1/2" Plywood 6 pcs P 440.00 P 2,640.00
Form Lumber 150 bd.ft 42.00 6,300.00
Scaffoldings 1 lot 5,000.00 5,000.00
Mat'l Cost P 13,940.00

Labor Cost: Days Rate/Day Total


1 - Foreman 3 550.00 1,650.00
2 - Skilled Laborers 3 450.00 2,700.00
3 - Laborers 3 320.00 2,880.00
Labor Cost: P 7,230.00 51.87

Direct Cost: P 21,170.00


Overhead and Profit: 4,234.00
VAT: 3,048.48
Total: P 28,452.48

Item No. VI: Steel Works


QTY: 1.00 lot

I. Material Costs: Quanity Unit Cost Total


1/4" x 2-1/2" x 2-1/2" Angle Bars 196.00 pcs P 1,550.00 P 303,800.00
1/4" x 2" x 2" Angle bars 34.00 pcs 890.00 30,260.00
1/4" x 1-1/2" x 1-1/2" Angle bars 36.00 pcs 645.00 23,220.00
16mm dia. Sag Rods and Cross Bracings 24.00 pcs 365.00 8,760.00
16mm dia. Turn Buckles 16.00 pcs 120.00 1,920.00
12mm MS Plate (0.35 m x 0.40 m) 10.00 pcs 1,000.00 10,000.00
Bolt and Washers 60.00 pcs 225.00 13,500.00
1.5mm x 2" x 6" C-Purlins 126.00 pcs 825.00 103,950.00
1.5mm x 2" x 4" C-Purlins 16.00 pcs 675.00 10,800.00
Primer Paint 16.00 gals 630.00 10,080.00
Misc. Consumbles (Welding Rods, etc) 1.00 lot 5,000.00 5,000.00
etc.) Mat'l Cost P 521,290.00 182,451.50

Labor Cost: Days Rate/Day Total


1 - Foreman 20 550.00 11,000.00
4 - Skilled Laborers 20 500.00 40,000.00
7 - Laborers 20 320.00 44,800.00
Labor Cost: P 95,800.00

CC3 Page 114


Equipment Cost: Days Rate/Day Total
1 - Elf Truck with Boom 6 P 5,500.00 P 33,000.00
1 - Welding Machine 20 1,200.00 24,000.00
Equipment Cost: P 24,000.00

Direct Cost: P 641,090.00


Overhead and Profit: 128,218.00
VAT: 92,316.96
Total: P 861,624.96

Item No. VII: Tinsmithry Works


QTY: 482.00 li.m

I. Material Costs: Quanity Unit Cost Total


0.40mm Color Steel Supreme (Rib Type) 482.00 li.m P 425.00 P 204,850.00
0.40mmx 24" Gutter 23.00 pcs 650.00 14,950.00
0.40mm x 24" Flashing 14.00 pcs 550.00 7,700.00
0.40mm x 16" Ridge Cap 12.00 pcs 550.00 6,600.00
3" PVC Pipe 20.00 pcs 510.00 10,200.00
3" PVC Elbow 20.00 pcs 60.00 1,200.00
Tekscrews 3,374.00 pcs 2.00 6,748.00
Rivets 800.00 pcs 0.75 600.00
Miscellaneous (sealants, straps, etc.) 1.00 lot 2,500.00 2,500.00
etc.) Mat'l Cost P 255,348.00 89,371.80

Labor Cost: Days Rate/Day Total


1 - Foreman 16 550.00 8,800.00
4 - Skilled Laborers 16 500.00 32,000.00
7 - Laborers 16 320.00 35,840.00
Labor Cost: P 76,640.00

Direct Cost: P 331,988.00


Overhead and Profit: 66,397.60
VAT: 47,806.27
Total: P 446,191.87

Unit Cost: 925.71 925.71

Item No. IX: Painting Works


QTY: 1.00 LOT

Material Cost: Quantity Unit Cost Total


Flat Latex Paint 1.00 gals. 525.00 P 525.00
Semi Gloss Latex Paint 1.00 gals. 550.00 550.00

CC3 Page 115


Quick dry enamel ( silver) 16.00 gals. 575.00 9,200.00
Concrete neutralizer 1.00 gals. 150.00 150.00
Patching compound 2.00 kgs. 35.00 70.00
Misc. Consumables 1.00 lot 3,000.00 3,000.00
Mat'l Cost P 13,495.00

Labor Cost: Days Rate/Day Total


1 - Foreman 3 550.00 1,650.00
3 - Skilled Laborers 3 500.00 4,500.00
2 - Laborers 3 320.00 1,920.00
Labor Cost: P 8,070.00 59.80

Direct Cost: P 21,565.00


Overhead and Profit: 4,313.00
VAT: 3,105.36
Total: P 28,983.36

CC3 Page 116


I 19,944.96
II 14,999.17
III 18,896.64
IV 315,302.27
V 28,452.48
VI 861,624.96
VII 446,192.22
VIII 28,983.36
1,734,396.06

CC3 Page 117


DETAILED ESTIMATES
Construction of Multi Purpose Covered Area with Concrete Slab at San Juan Bano
Elementary School, San Juan Bano, Arayat, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
1.00 lot Signages, barricades, barracks, etc. 8,000.00 8,000.00
Materials: 8,000.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
4.00 2.00 Laborers 300.00 2,400.00
1.00 2.00 Elf/Stake Truck 4,000.00 8,000.00
Labor and Equipment: 10,400.00

Sub-Total : 18,400.00
Profit Tax and Overhead : 5,888.00
Total Cost : 24,288.00

Item II: Excavation and Backfilling


Qty: 57.24 cu.m

A. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 5.00 Foreman 600.00 3,000.00
1.00 5.00 Skilled Laborers 300.00 1,500.00
6.00 5.00 Laborers 301.00 9,030.00
Labor and Equipment: 13,530.00

Sub-Total : 13,530.00
Profit Tax and Overhead : 4,329.60
Total Cost : 17,859.60
Unit Cost : 312.01

Item III: Concrete Works


Qty: 39.65 cu.m

A. Materials
Qty. Item Description Unit Cost Total
338.00 bags Cement 210.00 70,980.00
20.00 cu.m Sand 260.00 5,200.00
36.00 cu.m Gravel 3/4" 830.00 29,880.00
82.00 pcs 16mm dia. Bars 340.00 27,880.00
60.00 pcs 10mm dia. Bars 140.00 8,400.00

Page 118
30.00 kgs Tie Wires 70.00 2,100.00
Materials: 144,440.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 10.00 Foreman 600.00 6,000.00
4.00 10.00 Skilled Laborers 450.00 18,000.00
8.00 10.00 Laborers 301.00 24,080.00
1.00 10.00 One Bagger Mixer 650.00 6,500.00
Labor and Equipment: 54,580.00

Sub-Total : 199,020.00
Profit Tax and Overhead : 63,686.40
Total Cost : 262,706.40
Unit Cost : 6,625.63

Item IV: Carpentry Works


Forms and Scaffoldings
Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
6.00 pcs 1/2" Marine Plywood 480.00 2,880.00
200.00 bd.ft Form Lumber 48.00 9,600.00
1.00 lot Scaffoldings (H-Frame) 10,000.00 10,000.00
4.00 kilos Cw Nails 70.00 280.00
Materials: 22,760.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 3.00 Foreman 600.00 1,800.00
2.00 3.00 Skilled Laborers 450.00 2,700.00
4.00 3.00 Laborers 301.00 3,612.00
Labor and Equipment: 8,112.00

Sub-Total : 30,872.00
Profit Tax and Overhead : 9,879.04
Total Cost : 40,751.04

Item V: Steel Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
188.00 pcs 1/4" x 2-1/2" x 2-1/2" Angle Bars 1,550.00 291,400.00
34.00 pcs 1/4" x 2" x 2" Angle bars 890.00 30,260.00

Page 119
36.00 pcs 1/4" x 1-1/2" x 1-1/2" Angle bars 645.00 23,220.00
24.00 pcs 16mm dia. Sag Rods and Cross Bracings 365.00 8,760.00
16.00 pcs 16mm dia. Turn Buckles 120.00 1,920.00
10.00 pcs 12mm MS Plate (0.35 m x 0.40 m) 1,000.00 10,000.00
60.00 pcs Bolt and Washers 225.00 13,500.00
126.00 pcs 1.5mm x 2" x 6" C-Purlins 825.00 103,950.00
16.00 pcs 1.5mm x 2" x 4" C-Purlins 675.00 10,800.00
16.00 gals Primer Paint 630.00 10,080.00
1.00 lot Misc. Consumbles (Welding Rods, etc) 5,000.00 5,000.00
Materials: 508,890.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 20.00 Foreman 600.00 12,000.00
4.00 20.00 Skilled Laborers 500.00 40,000.00
6.00 20.00 Laborers 301.00 36,120.00
1.00 20.00 Welding machine 1,200.00 24,000.00
1.00 5.00 Elf Truck with Boom 7,500.00 37,500.00
Labor and Equipment: 149,620.00

Sub-Total : 658,510.00
Profit Tax and Overhead : 210,723.20
Total Cost : 869,233.20

Item VI: Tinsmithry Works


Qty: 482.00 li.m

A. Materials
Qty. Item Description Unit Cost Total
482.00 li.m 0.40mm Color Steel Supreme (Rib Type) 425.00 204,850.00
23.00 pcs 0.40mmx 24" Gutter 650.00 14,950.00
14.00 pcs 0.40mm x 24" Flashing 550.00 7,700.00
12.00 pcs 0.40mm x 16" Ridge Cap 550.00 6,600.00
20.00 pcs 3" PVC Pipe 510.00 10,200.00
20.00 pcs 3" PVC Elbow 60.00 1,200.00
3,374.00 pcs Tekscrews 2.00 6,748.00
800.00 pcs Rivets 0.75 600.00
1.00 lot Miscellaneous (sealants, straps, etc.) 2,500.00 2,500.00
Materials: 255,348.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 12.00 Foreman 600.00 7,200.00
4.00 12.00 Skilled Laborers 520.00 24,960.00
4.00 12.00 Laborers 30.00 1,440.00
Labor and Equipment: 33,600.00

Sub-Total : 288,948.00

Page 120
Profit Tax and Overhead : 92,463.36
Total Cost : 381,411.36
Unit Cost : 791.31

Item VII: Painting Works


Qty: 1.00 lot

A. Materials
Qty. Item Description Unit Cost Total
3.00 gals Flat Latex Paint (Concrete columns) 520.00 1,560.00
4.00 gals Semi Gloss (Concrete columns) 550.00 2,200.00
20.00 gals Quick Dry Enamel 575.00 11,500.00
1.00 lot Misc. Consumables (brushes, rollers, etc) 2,000.00 2,000.00
Materials: 17,260.00

B. Labor and Equipment


Qty. Days Item Description Unit Cost Total
1.00 5.00 Foreman 600.00 3,000.00
3.00 5.00 Skilled Laborers 500.00 7,500.00
3.00 5.00 Laborers 30.00 450.00
Labor and Equipment: 10,950.00

Sub-Total : 22,450.00
Profit Tax and Overhead : 7,184.00
Total Cost : 29,634.00

Page 121
312.01

39.65
337.03
19.83
35.69
82.00
518.00

Page 122
50,554.00

6,625.63

7,966.00

313.00
142.00

Page 123
142.00
69.00

219.00

178,111.50

340

340

89,371.80

Page 124
791.31

I 24,288.00
II 17,859.45
III 262,706.23
IV 40,751.04
V 869,233.20
VI 381,411.42
VII 29,634.00
1,625,883.34

Page 125
Vertical

BILL OF QUANTITIES

Item I: Mobilization/Demobilization
Qty: 1.00 lot

Qty. Days Item Description Unit Cost Total


1 lot Temporary Facilities 10,000.00 10,000.00
6.00 4.00 Laborers 300.00 7,200.00
1.00 4.00 Elf/Stake Truck 2,500.00 10,000.00
Labor and Equipment: 27,200.00
Contingencies and Mark-ups: 7,344.00
Total: 34,544.00

Item II-A: Breaking and Removal of Existing Structure (


Qty: 220.00 sq.m

Qty. Days Item Description Unit Cost Total


1.00 6.00 Foreman 550.00 3,300.00
1.00 6.00 Skilled Laborers 450.00 2,700.00
6.00 6.00 Laborers 300.00 10,800.00
1.00 6.00 Elf/Stake Truck 2,500.00 15,000.00
1.00 4.00 Jack Hammer 2,000.00 8,000.00
1.00 4.00 Concrete Cutter 1,200.00 4,800.00
Labor and Equipment: 44,600.00
Contingencies and Mark-ups: 12,042.00
Total: 56,642.00
Unit Cost: 257.46

Item II-B: Filling Materials


Qty: 601.00 cu.m

Qty. Item Description Unit Cost Total


601.00 cu.m Common Barrow/Filling Materials (in-place) 250.00 150,250.00
Materials Labor and Equipment: 150,250.00
Contingencies and Mark-ups: 40,567.50
Total: 190,817.50
Unit Cost: 317.50

Item II-C: Aggregate Base Course

Page 126 of 6
Vertical

Qty: 240.00 cu.m

Qty. Item Description Unit Cost Total


240.00 cu.m Aggregate Base Course (in-place) 700.00 168,000.00
Materials Labor and Equipment: 168,000.00
Contingencies and Mark-ups: 45,360.00
Total: 213,360.00
Unit Cost: 889.00

Item II-D: 0.15 m thick PCCP


Qty: 1745.00 sq.m

Qty. Item Description Unit Cost Total


262.00 cu.m - RMC, 3500 @ 28 Days 3,500.00 P 917,000.00
25.00 pcs - 16 mm Dowels and Spikes 345.00 8,625.00
20.00 kilos - Asphalt Sealant 205.00 4,100.00
1.00 lot - C- Purlins Forms 20,000.00 20,000.00
1.00 lot - Miscellaneous Items 2,000.00 2,000.00
Materials: 951,725.00
Labor and Equipment: 142,758.75
Contingencies and Mark-ups: 295,510.61
Total: 1,389,994.36
Unit Cost: 796.56

Item II-E: 0.10 m thick PCCP


Qty: 435.88 sq.m

Qty. Item Description Unit Cost Total


44.00 cu.m - RMC, 3500 @ 28 Days 3,500.00 P 154,000.00
25.00 pcs - 16 mm Dowels and Spikes 345.00 8,625.00
8.00 kilos - Asphalt Sealant 205.00 1,640.00
1.00 lot - C- Purlins Forms 12,000.00 12,000.00
1.00 lot - Miscellaneous Items 1,200.00 1,200.00
Materials: 177,465.00
Labor and Equipment: 26,619.75
Contingencies and Mark-ups: 55,102.88
Total: 259,187.63
Unit Cost: 594.63

Page 127 of 6
Vertical

Item III-A: 5" CHB Catch Basins


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


670.00 pcs 5" CHB 8.00 5,360.00
62.00 bags Cement 210.00 13,020.00
6.00 cu.m Sand 260.00 1,560.00
2.00 cu.m Gravel 3/4" 830.00 1,660.00
46.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 6,440.00
30.00 pcs 16mm dia. Square Bars x 6.0 m 360.00 10,800.00
14.00 pcs 2-1/2 Angle Bars x 1/4" thick x 6.0 m 1,420.00 19,880.00
5.00 kilos Welding Rod 125.00 625.00
1.00 lot Miscellaenous Consumbles 2,000.00 2,000.00
Materials: 61,345.00
Labor and Equipment: 24,538.00
Contingencies and Mark-ups: 23,188.41
Total: 109,071.41

Item III-B: 5" CHB Line Canal w/ Cover


Qty: 193.20 li.m

Qty. Item Description Unit Cost Total


1,490.00 pcs 5" CHB 8.00 11,920.00
646.00 bags Cement 210.00 135,660.00
45.00 cu.m Sand 260.00 11,700.00
58.00 cu.m Gravel 3/4" 830.00 48,140.00
158.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 22,120.00
472.00 pcs 12mm dia. Deformed Bars x 6.0 m 140.00 66,080.00
150.00 bd.ft Assorted Form Lumbers 42.00 6,300.00
6.00 pcs 1/4 " Thick Plywood 360.00 2,160.00
1.00 lot Miscellaenous Consumbles 2,000.00 2,000.00
Materials: 306,080.00
Labor and Equipment: 122,432.00
Contingencies and Mark-ups: 115,698.24
Total: 544,210.24
Unit Cost: 2,816.82

Page 128 of 6
Vertical

Item III-C: PVC Pipes (incl. installation)


Qty: 193.20 li.m

Qty. Item Description Unit Cost Total


31.00 pcs 4" dia PVC Pipe x 3.0 m 980.00 30,380.00
10.00 bags 8" PVC Pipes x 3.0 m 1,550.00 15,500.00
1.00 lot Assorted PVC Connector (Couplings, Elbows etc.) 1,500.00 1,500.00
6.00 liters PVC Cement 375.00 2,250.00
1.00 lot Miscellaenous Consumbles 1,000.00 1,000.00
Materials: 50,630.00
Labor and Equipment: 20,252.00
Contingencies and Mark-ups: 19,138.14
Total: 90,020.14

Item IV-A: Repair and Upgrading of Existing Fence


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


2,020.00 pcs 5" CHB 8.00 16,160.00
240.00 bags Cement 210.00 50,400.00
25.00 cu.m Sand 260.00 6,500.00
6.00 cu.m Gravel 3/4" 830.00 4,980.00
154.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 21,560.00
52.00 pcs 12mm dia. Deformed Bars x 6.0 m 205.00 10,660.00
250.00 bd.ft Assorted Form Lumbers 42.00 10,500.00
6.00 pcs 1/4 " Thick Plywood 360.00 2,160.00
32.00 units 1.0 m x 3.0 m Tubular Grills 7,500.00 240,000.00
28.00 tins Flat latex Paint 2,150.00 60,200.00
24.00 gals Quick Dry Enamel 575.00 13,800.00
6.00 pcs 1/4 " Thick Plywood 360.00 2,160.00
1.00 lot Miscellaenous Consumbles (Nails, Ties, brushes etc.) 2,000.00 2,000.00
Materials: 441,080.00
Labor and Equipment: 154,378.00
Contingencies and Mark-ups: 160,773.66
Total: 756,231.66

Item IV-B: Steel Gates


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


118.25 sq.ft 1 unit - 5.0 m x 2.2 m Main Steel Gate 330.00 39,022.50

Page 129 of 6
Vertical

24.83 sq.ft 1 unit - 1.1 m x 2.1 m Service Steel Gate 300.00 7,449.75
Materials Labor and Equipment: 39,022.50
Contingencies and Mark-ups: 10,536.08
Total: 49,558.58

Item V: Repair and Improvement of Existing Guardhouse


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


240.00 pcs 5" CHB 8.00 1,920.00
32.00 bags Cement 210.00 6,720.00
4.00 cu.m Sand 260.00 1,040.00
6.00 cu.m Gravel 3/4" 830.00 4,980.00
22.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 3,080.00
50.00 bd.ft Assorted Form Lumbers 42.00 2,100.00
2.00 pcs 1/4 " Thick Plywood 360.00 720.00
4.00 gals Flat latex Paint 525.00 2,100.00
3.00 tins Semi Gloss Latex Paint 2,150.00 6,450.00
4.00 gals Quick Dry Enamel 575.00 2,300.00
82.00 pcs 0.30 m x 0.30 m Tiles 32.00 2,624.00
8.00 sq.m Stone Works (Facade) 1,200.00 9,600.00
6.00 bags Tile Adhesives 275.00 1,650.00
2.00 bags TileGrouts 85.00 170.00
34.00 sq.m 4.5mm Hardiflex Ceiling on Metal Furring 520.00 17,680.00
1.00 sets 2.1 m x 0.80 m Panel Door Swing Type 6,250.00 6,250.00
1.00 sets 2.1 m x 0.70 m PVC Door Swing Type 2,750.00 2,750.00
65.86 sq.ft Steel Casement Window 250.00 16,465.00
4.00 pcs 2" x 4" x 1.2mm C-Purlins 540.00 2,160.00
10.00 pcs 2" Angular Bars x 3/16" x 6.0m 675.00 6,750.00
5.00 pcs 1-1/2" Angular Bars x 3/16" x 6.0m 540.00 2,700.00
38.00 li.m #26 Long Span, Rib Type 325.00 12,350.00
12.00 pcs Flashing, 24" 300.00 3,600.00
3.00 pcs Stainlless Gutter, 24" 925.00 2,775.00
1.00 lot 3" Down Spouts 2,500.00 2,500.00
1.00 set 30 Amp Circuit Breaker 360.00 360.00
2.00 sets 1-G Switch 95.00 190.00
2.00 sets 3-G Switch 220.00 440.00
5.00 sets Convenience Outlet 185.00 925.00
1.00 rolls 3.5 THHN Wire 3,600.00 3,600.00
2.00 sets Wall Lights 1,350.00 2,700.00
8.00 sets 18 Watts Pinlights with Casing 420.00 3,360.00
6.00 pcs Junction Box 25.00 150.00

Page 130 of 6
Vertical

12.00 pcs Utility Box 20.00 240.00


1.00 sets Stainless Faucets 425.00 425.00
1.00 set Stainless Kitchen Sink 1,750.00 1,750.00
1.00 pcs Floor Drain 120.00 120.00
3.00 pcs 2" dia. Stainless Pipe x 6.0 m 120.00 360.00
1.00 lot Water Lines and Sewer Lines 3,000.00 3,000.00
1.00 lot Miscellaenous Consumbles (Nails, Ties, brushes etc.) 5,000.00 5,000.00
Materials: 144,054.00
Labor and Equipment: 57,621.60
Contingencies and Mark-ups: 54,452.41
Total: 256,128.01

Item VI: Street Lighting


Qty: 26.00 units

Qty. Item Description Unit Cost Total


71.00 bags Cement 210.00 14,910.00
5.00 cu.m Sand 260.00 1,300.00
7.00 cu.m Gravel 3/4" 830.00 5,810.00
42.00 pcs 16mm dia. Deformed Bars x 6.0 m 350.00 14,700.00
44.00 pcs 12mm dia. Deformed Bars x 6.0 m 205.00 9,020.00
82.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 11,480.00
150.00 bd.ft Assorted Form Lumbers 42.00 6,300.00
4.00 pcs 1/4 " Thick Plywood 360.00 1,440.00
3.00 gals Flat latex Paint 525.00 1,575.00
8.00 gals Quick Dry Enamel 575.00 4,600.00
26.00 units 50 W Street Lights in Casing 1,350.00 35,100.00
26.00 pcs Secondary Rack w/ Insulators 380.00 9,880.00
10.00 boxes 8.0 THHN Wires 8,500.00 85,000.00
1.00 units 30 AT Circuit Breakes 420.00 420.00
2.00 sets 1-Gang Switch 150.00 300.00
26.00 sets 0.40 m x 0.40 m x 16 mm Steel Plate 320.00 8,320.00
104.00 pcs 20 mm x 12" Machine Bolts 125.00 13,000.00
1.00 lot Miscellaenous Consumbles (Nails, Ties, brushes etc.) 2,000.00 2,000.00
Materials: 225,155.00
Labor and Equipment: 56,288.75
Installation of Lamp Posts: 15,000.00
Contingencies and Mark-ups: 80,039.81
Total: 376,483.56
Unit Cost: 13,972.14

Page 131 of 6
Vertical

Item VII: Covered Pathway


Qty: 12.50 li.m

Qty. Item Description Unit Cost Total


14.00 bags Cement 210.00 2,940.00
1.00 cu.m Sand 260.00 260.00
2.00 cu.m Gravel 3/4" 830.00 1,660.00
6.00 pcs 16mm dia. Deformed Bars x 6.0 m 350.00 2,100.00
12.00 pcs 12mm dia. Deformed Bars x 6.0 m 205.00 2,460.00
18.00 pcs 10mm dia. Deformed Bars x 6.0 m 140.00 2,520.00
75.00 bd.ft Assorted Form Lumbers 42.00 3,150.00
1.00 pcs 1/4 " Thick Plywood 360.00 360.00
4.00 gals Red Lead Primer 620.00 2,480.00
3.00 gals Quick Dry Enamel 575.00 1,725.00
3.00 units 3" Dia. GI Pipe 2,750.00 8,250.00
22.00 pcs 1-1/2" GI Pipes 1,250.00 27,500.00
18.00 pcs 1/2" Flatbar 360.00 6,480.00
36.00 li.m Pre-Painted Curve Roofing Sheets 350.00 12,600.00
12.00 pcs Stainless Gutters 950.00 11,400.00
8.00 units 3" PVC Downspouts 520.00 4,160.00
3.00 pcs 2" x 6" C-Purlins 625.00 1,875.00
1.00 lot Miscellaenous Consumbles (Nails, Ties, brushes etc.) 2,000.00 2,000.00
Materials: 93,920.00
Labor and Equipment: 23,480.00
Contingencies and Mark-ups: 31,698.00
Total: 149,098.00
Unit Cost: 11,927.84

Item VIII: Landscaping


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


464.00 sq.m Landscaping (Incl. plants, rocks, soil, etc) 275.00 127,600.00
Materials, Labor and Equipment: 127,600.00
Contingencies and Mark-ups: 34,452.00
Total: 162,052.00

Page 132 of 6
Vertical

257.46

317.50

Page 133 of 6
Vertical

889.00

261.75

796.56

43.59

594.63

Page 134 of 6
Vertical

695.00
60.00
5.13
1.30
42.00
30.00
14.00

695.00
60.00
5.13
1.30
42.00
42.00
30.00
14.00

2,816.82

Page 135 of 6
Vertical

695.00
60.00
5.13
1.30

695.00
60.00
5.13
1.30
42.00
42.00
30.00
14.00
695.00
60.00
5.13
14.00

Page 136 of 6
Vertical

695.00
60.00
5.13
1.30
42.00
30.00
14.00
60.00
60.00
5.13
0.36
92.00
374.00

474.44
474.44

340

Page 137 of 6
Vertical

60.00
5.13
1.30
42.00
42.00
42.00
30.00
14.00
60.00
5.13
0.36
92.00
374.00

474.44

14,480.14

Page 138 of 6
Vertical

60.00
5.13
1.30
42.00
42.00
42.00
30.00
14.00
5.13
5.13
0.36
92.00
374.00

474.44

11,927.84

I 34,544.00
II 2,110,003.22
III 743,301.17
IV 805,790.24
V 256,128.01

Page 139 of 6
Vertical

VI 363,275.64
VII 149,098.00
VIII 162,052.00
4,624,192.29

Page 140 of 6
DETAILED ESTIMATES
PR# 13 - 0433

Item No. I: Mobilization/Demobilization


QTY: 1.00 lot

Labor Cost: Days Rate/Day Total


4 - Laborers 2 P 300.00 2,400.00
Labor Cost: 2,400.00
`
Equipment Cost: Days Rate/Day Total
1 - Stake Truck 2 P 2,500.00 5,000.00
Equipment Cost: 5,000.00

Direct Cost: 7,400.00


In-direct Cost (27 %) 1,998.00
Total: 9,398.00

Item No. II Excavation and backfilling


QTY: 95.98 cu.m

Labor Cost: Days Rate/Day Total


1 - Foreman 7 550.00 3,850.00
4 - Laborers 7 300.00 8,400.00
Labor Cost: 12,250.00

Direct Cost: 12,250.00


In-direct Cost (27 %) 3,307.50
Total: 15,557.50

Item No. III: Demolition of Existing Structure


QTY: 1.00 lot

Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
4 - Laborers 5 300.00 6,000.00
Labor Cost: 8,750.00

Direct Cost: 8,750.00


In-direct Cost (27 %) 2,362.50
Total: 11,112.50

Item No. IV Filling Materials


QTY: 105.84 cu.m

Material Cost: Quantity Unit Cost Total


Filling Materials/Common Barrow 105.84 m P 190.00 20,109.60
Mat'l Cost: 20,109.60

Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
3 - Laborers 5 300.00 4,500.00
Labor Cost: 7,250.00

Equipment Cost: Days Rate/Day Total


1 - Plate Compactor 1 P 1,500.00 1,500.00
Equipment Cost: 1,500.00

Direct Cost: 28,859.60


In-direct Cost (27 %) 7,792.09
Total: 36,651.69

Unit Cost: 346.29

Item No. V. Concrete Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Cement 360.00 bags P 210.00 75,600.00
Sand 24.00 cu.m. 240.00 5,760.00
Washed Gravel 40.00 cu.m. 800.00 32,000.00
16 mm x 6.0 m 90.00 pcs. 345.00 31,050.00
12 mm x 6.0 m 95.00 pcs. 195.00 18,525.00
10 mm x 6.0 m 275.00 pcs. 130.00 35,750.00
Tie Wires 30.00 kls. 75.00 2,250.00
Mat'l Cost 200,935.00

Labor Cost: Days Rate/Day Total


1 - Foreman 14 550.00 7,700.00
2 - Skilled Laborers 14 440.00 12,320.00
7 - Laborers 14 300.00 29,400.00
Labor Cost: 49,420.00

Equipment Cost: Days Rate/Day Total


1 - One Bagger Mixer 12 P 2,200.00 26,400.00
Equipment Cost: 26,400.00

Direct Cost: 276,755.00


In-direct Cost (27 %) 74,723.85
Total: 351,478.85

Item No. VI. Masonry Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Cement 170.00 bags P 210.00 35,700.00
Sand 17.00 cu.m. 240.00 4,080.00
Washed Gravel 2.00 cu.m. 800.00 1,600.00
5" CHB 2350.00 pcs. 7.00 16,450.00
10 mm x 6.0 m 143.00 pcs. 130.00 18,590.00
Tie Wires 7.00 kls. 75.00 525.00
Mat'l Cost 76,945.00

Labor Cost: Days Rate/Day Total


1 - Foreman 8 500.00 4,000.00
2 - Skilled Laborers 8 440.00 7,040.00
7 - Laborers 8 300.00 16,800.00
Labor Cost: 27,840.00

Direct Cost: 104,785.00


In-direct Cost (27 %) 28,291.95
Total: 133,076.95

Item No. VII-A: Forms & Scaffolding


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Form Lumber 250.00 bd.ft P 41.00 10,250.00
Scaffoldings 1.00 lot 5,000.00 5,000.00
Mat'l Cost 15,250.00
Labor Cost: Days Rate/Day Total
1 - Foreman 4 550.00 2,200.00
1 - Skilled Laborers 4 440.00 1,760.00
3 - Laborers 4 320.00 3,840.00
Labor Cost: 7,800.00

Direct Cost: 23,050.00


In-direct Cost (27 %) 6,223.50
Total: 29,273.50

Item No. VII-B: Ficem Board on Metal Furring


QTY: 263.00 sq.m

Material Cost (w/ Installation) Quantity Unit Cost Total


Ficem Board on Metal Furring 263.00 sq.m P 545.00 143,335.00
Mat'l Cost 143,335.00

Direct Cost: 143,335.00


In-direct Cost (27 %) 38,700.45
Total: 182,035.45

Unit Cost: 692.15

Item No. VII: Fabricated Materials


QTY: 1.00 lot

Material Cost (Including Installation): Quantity Unit Cost Total


Glass Jalousie Window w/ Grills
6 sets - 2.10m x 1.50m 203.18 sq.ft P 275.00 55,873.13
6 sets - 1.40m x 1.50m 135.45 sq.ft 275.00 37,248.75
3 sets - 0.60m x0.60m 11.61 sq.ft 275.00 3,192.75
3 sets - 1.00m x 2.10m Panel Door w/ 3.00 sets 6,200.00 18,600.00
Galvanized Jamb
3 sets - 0.60m x 2.10m PVC Door 3.00 sets 2,200.00 6,600.00
3 sets - 1.20m x 4.80m Blackboard 3.00 sets 4,000.00 12,000.00
Mat'l Cost 133,514.63

Labor Cost: 33,378.66

Direct Cost: 166,893.28


In-direct Cost (27 %) 45,061.19
Total: 211,954.47

Item No. IX: Roof Framing Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


2" x 6" Tubular Bar, 1.5mm 25.00 pcs. P 2,230.00 55,750.00
1.2mm - 2" x 4" Purlins 72.00 pcs. 518.00 37,296.00
1.2mm - 2" x 6" Purlins 13.00 pcs. 595.00 7,735.00
10mm Dia. Sagrods 16.00 pcs. 189.00 3,024.00
Miscellaneous 1.00 lot 5,000.00 5,000.00
Mat'l Cost 108,805.00

Labor Cost: Days Rate/Day Total


1 - Foreman 8 550.00 4,400.00
2 - Skilled Laborers 8 440.00 7,040.00
6 - Laborers 8 300.00 14,400.00
Labor Cost: 25,840.00

Equipment Cost: Days Rate/Day Total


1 - Welding Machine 6 P 2,100.00 12,600.00
Equipment Cost: 12,600.00

Direct Cost: 147,245.00


In-direct Cost (27 %) 39,756.15
Total: 187,001.15

Item No. IX: Tinsmithry Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Pre-Painted Long Span, Rib Type, Ga. 26 273.00 li.m P 338.00 92,274.00
Pre-Painted Flashing, Ga. 26 12.00 pcs. 350.00 4,200.00
Pre-Painted Ridge Roll, ga. 26 10.00 pcs. 350.00 3,500.00
1/2" Fascia Board x 10' 30.00 pcs. 420.00 12,600.00
Tekscrew 1600.00 pcs. 1.50 2,400.00
Miscellaneous 1.00 lot 5,000.00 5,000.00
Mat'l Cost 119,974.00

Labor Cost: Days Rate/Day Total


1 - Foreman 11 550.00 6,050.00
2 - Skilled Laborers 11 440.00 9,680.00
5 - Laborers 11 300.00 16,500.00
Labor Cost: 32,230.00

Direct Cost: 152,204.00


In-direct Cost (27 %) 41,095.08
Total: 193,299.08

Item No. XI: Painting Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Flat Latex Paint 5.00 tins 2,000.00 10,000.00
Semi Gloss Latex Paint 3.00 tins 2,100.00 6,300.00
Flat enamel 3.00 tins 2,200.00 6,600.00
Quick dry enamel 3.00 gals. 525.00 1,575.00
Red Lead Primer 6.00 gals. 525.00 3,150.00
Concrete neutralizer 6.00 gals. 165.00 990.00
Patching compound 40.00 kgs. 35.00 1,400.00
Misc. Consumables 1.00 lot 5,000.00 5,000.00
Mat'l Cost 35,015.00

Labor Cost: Days Rate/Day Total


1 - Foreman 6 550.00 3,300.00
4 - Skilled Laborers 6 440.00 10,560.00
1 - Laborers 6 300.00 1,800.00
Labor Cost: 15,660.00

Direct Cost: 50,675.00


In-direct Cost (27 %) 13,682.25
Total: 64,357.25

Item No. XII-A: Electrical Works


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Main Circuit Breaker 1.00 unit 7,000.00 7,000.00
Box Type, Flourescent Lamp 40W 15.00 units 455.00 6,825.00
3-Gang Switch 3.00 sets 240.00 720.00
1-Gang Switch 3.00 sets 135.00 405.00
Connvenience Outlet (single) 6.00 sets 130.00 780.00
Connvenience Outlet (single) 6.00 sets 165.00 990.00
Junction Box 18.00 sets 25.00 450.00
Utility Box 20.00 sets 25.00 500.00
Misc. (Wires, Conduits, etc) 1.00 lot 25,000.00 25,000.00
Mat'l Cost 42,670.00

Labor Cost: Days Rate/Day Total


1 - Foreman 8 550.00 4,400.00
2 - Skilled Laborers 8 440.00 7,040.00
1 - Laborers 8 300.00 2,400.00
Labor Cost: 13,840.00

Direct Cost: 56,510.00


In-direct Cost (27 %) 15,257.70
Total: 71,767.70

Item No. XII-B: Wall Fans


QTY: 6.00 units

Material Cost (Including Installation): Quantity Unit Cost Total


Branded Wall Fans 6.00 units P 2,500.00 15,000.00
Mat'l Cost 15,000.00

Direct Cost: 15,000.00


In-direct Cost (27 %) 4,050.00
Total: 19,050.00

Unit Cost: 3,175.00

Item No. XIII-A: Water lines and Sewer Lines


QTY: 1.00 LOT

Material Cost: Quantity Unit Cost Total


1/2" PVC Blue Pipe 14.00 pcs 250.00 3,500.00
1/2" Gate Valve 1.00 pcs 220.00 220.00
1/2" Faucets 3.00 sets 350.00 1,050.00
4" PVC pipes 9.00 pcs 750.00 6,750.00
4" Clean Out 5.00 pcs 60.00 300.00
2" PVC Pipes 6.00 pcs 240.00 1,440.00
Floor Drains 3.00 pcs 150.00 450.00
Misc. (Fittings, etc.) 1.00 lot 2,000.00 2,000.00
Mat'l Cost 15,710.00

Labor Cost: Days Rate/Day Total


1 - Foreman 3 550.00 1,650.00
2 - Skilled Laborers 3 440.00 2,640.00
1 - Laborers 3 300.00 900.00
Labor Cost: 5,190.00

Direct Cost: 20,900.00


In-direct Cost (27 %) 5,643.00
Total: 26,543.00

Item No. XIII-B: Fixtures


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


Water Closet w/ Lav. (Package) 3.00 sets 5,500.00 16,500.00
Mat'l Cost 16,500.00

Labor Cost: Days Rate/Day Total


1 - Foreman 3 550.00 1,650.00
2 - Skilled Laborers 3 440.00 2,640.00
1 - Laborers 3 300.00 900.00
Labor Cost: 5,190.00

Direct Cost: 21,690.00


In-direct Cost (27 %) 5,856.30
Total: 27,546.30

Item No. XIII-C: Tile Worls


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


0.30 m x 0.30 m Ceramic tiles 434.00 unit 34.00 14,756.00
Tile Adhesives 5.00 units 265.00 1,325.00
Tile grouts 9.00 sets 70.00 630.00
Miscellaneous 1.00 lot 1,500.00 1,500.00
Mat'l Cost 18,211.00

Labor Cost: Days Rate/Day Total


1 - Foreman 4 550.00 2,200.00
2 - Skilled Laborers 4 440.00 3,520.00
1 - Laborers 4 300.00 1,200.00
Labor Cost: 6,920.00

Direct Cost: 25,131.00


In-direct Cost (27 %) 6,785.37
Total: 31,916.37

Item No. XIV. Perimeter Fence


QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


5" CHB 4600.00 pcs. 7.00 32,200.00
Cement 560.00 bags P 210.00 117,600.00
Sand 48.00 cu.m. 240.00 11,520.00
Washed Gravel 28.00 cu.m. 800.00 22,400.00
12 mm x 6.0 m 245.00 pcs. 195.00 47,775.00
10 mm x 6.0 m 415.00 pcs. 130.00 53,950.00
Tie Wires 30.00 kls. 75.00 2,250.00
Mat'l Cost 287,695.00

Labor Cost: Days Rate/Day Total


1 - Foreman 18 550.00 9,900.00
2 - Skilled Laborers 18 440.00 15,840.00
7 - Laborers 18 300.00 37,800.00
Labor Cost: 63,540.00

Equipment Cost: Days Rate/Day Total


1 - One Bagger Mixer 16 P 2,200.00 35,200.00
Equipment Cost: 35,200.00

Direct Cost: 386,435.00


In-direct Cost (27 %) 104,337.45
Total: 490,772.45
127.63
8,750.00
7,038.36

346.29

351
24.76
37.15
86
95
288

70,327.25
75,820.00

168
15.87
1.03
2280
147

26,930.75

4,575.00
692.15
25
75
14
18

38,081.75

38,440.00

270
12
11
32
1569.75

29,993.50
20
12
10
4
5
7
30

14,006.00
14,081.10

3,175.00
5,498.50

5,775.00

420
6,373.85

4700
590
47.62
26.07
253
418

100,693.25

98,740.00

I 9,398.00
II 15,557.50
III 11,112.50
IV 36,651.33
V 351,478.85
VI 133,076.95
VII 211,308.95
VIII 211,954.47
IX 187,001.15
X 193,299.08
XI 64,357.25
XII 90,817.70
XIII 86,005.67
XIV 490,772.45
2,092,791.85
DETAILED ESTIMATES for Improvement of Elevated Three (3) Classroom School
Building with Comfort Room at Betis Elementary School, Betis, Guagua, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

Qty. Days Item Description Unit Cost Total


4.00 2.00 Laborers 300.00 2,400.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 7,400.00
Contingencies and Mark-ups: 1,998.00
Total: 9,398.00

Item II: Demolition of Existing Structure


Qty: 1.00 lot

Qty. Days Item Description Unit Cost Total


1.00 4.00 Foreman 550.00 2,200.00
1.00 4.00 Skilled Laborers 450.00 1,800.00
6.00 4.00 Laborers 300.00 7,200.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 14,000.00
Contingencies and Mark-ups: 3,780.00
Total: 17,780.00
Item III: Filling Materials
Qty: 187.11 cu.m

Qty. Item Description Unit Cost Total


187.11 cu.m Common Barrow/Filling Materials 180.00 33,679.80
Materials: 33,679.80
Labor and Equipment: 10,103.94
Contingencies and Mark-ups: 11,821.61
Total: 55,605.35
Unit Cost: 297.18

Item IV: Concrete Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


320.00 bags Cement 210.00 67,200.00
22.50 cu.m Sand 260.00 5,850.00

Page 161
35.00 cu.m Gravel 3/4" 830.00 29,050.00
136.00 pcs 16mm dia. Bars 340.00 46,240.00
184.00 pcs 12mm dia. Bars 200.00 36,800.00
444.00 pcs 10mm dia. Bars 130.00 57,720.00
Materials: 242,860.00
Labor and Equipment: 85,001.00
Contingencies and Mark-ups: 88,522.47
Total: 416,383.47

Item V: Masonry Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


3,570.00 pcs 5" CHB 7.00 24,990.00
272.00 bags Cement 210.00 57,120.00
28.00 cu.m Sand 260.00 7,280.00
228.00 pcs 10mm x 6m RSB 130.00 29,640.00
Materials: 119,030.00
Labor and Equipment: 47,612.00
Contingencies and Mark-ups: 44,993.34
Total: 211,635.34

Item VI: Carpentry Works


A. Forms and Scaffoldings
Qty: 1.00 lot

Qty. Item Description Unit Cost Total


5.00 pcs 1/4" Marine Plywood 365.00 1,825.00
200.00 bd.ft Form Lumber 48.00 9,600.00
1.00 lot Scaffoldings 4,500.00 4,500.00
8.00 kilos Cw Nails 70.00 560.00
Materials: 16,485.00
Labor and Equipment: 5,769.75
Contingencies and Mark-ups: 6,008.78
Total: 28,263.53

B. Ceiling Works
Qty: 216.87 sq.m

Qty. Item Description Unit Cost Total

Page 162
216.87 sq.m 4.5mm Hardiflex Ceiling on Metal Furring 490.00 106,266.30
Materials: 106,266.30
Labor and Equipment: 31,879.89
Contingencies and Mark-ups: 37,299.47
Total: 175,445.66
Unit Cost: 808.99

Item VII: Fabricated Materials


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


Jalousie Type Window with 12 mm Grills
6.00 sets 1.40 m x 1.50 m: 6,100.92 36,605.52
6.00 sets 2.10 m x 1.50 m: 9,151.38 54,908.28
3.00 sets 0.6 m x 0.6 m: 1,045.87 3,137.62
3.00 sets 1.00m x 2.10m Panel Door w/ Galvanized Jamb 6,000.00 18,000.00
3.00 sets 0.60 m x 2.10 m PVC Door w/ Jamb 2,000.00 6,000.00
3.00 sets 1.20 m x 4.8 m Blackboard 3,500.00 10,500.00
Materials: 129,151.42
Labor and Equipment: 25,830.28
Contingencies and Mark-ups: 41,845.06
Total: 196,826.76

Item VIII: Roof Framing Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


30.00 pcs 2" x 6" x 1.5 mm Tubular 2,250.00 67,500.00
64.00 pcs 2" x 4" x 1.2mm C- Purlins 575.00 36,800.00
14.00 pcs 2" x 6" x 1.2mm C-Purlins 675.00 9,450.00
16.00 pcs 12mm Dia. Sag Rods 195.00 3,120.00
1.00 lot Welding Rod, Acetylene etc. 8,000.00 8,000.00
Materials: 124,870.00
Labor and Equipment: 43,704.50
Contingencies and Mark-ups: 45,515.12
Total: 214,089.62

Item IX: Tinsmithry Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


233.20 li.m #26 Long Span, Rib Type 320.00 74,624.00

Page 163
10.00 pcs Ridge Roll 325.00 3,250.00
18.00 pcs Flashing 300.00 5,400.00
32.00 pcs Fascia Board, 1/2" x 10' x 10" 375.00 12,000.00
1.00 lot Rivets, Tekscrews, Sealants 6,250.00 6,250.00
Materials: 101,524.00
Labor and Equipment: 35,533.40
Contingencies and Mark-ups: 37,005.50
Total: 174,062.90

Item X: Painting Works


Qty: 1.00 lot
Qty. Item Description Unit Cost Total
5.00 tins Flat Latex 2,000.00 10,000.00
8.00 tins Flat Wall Enamel 2,100.00 16,800.00
10.00 tins Semi Gloss Latex 2,300.00 23,000.00
4.00 tin Quick Dry Enamel 2,200.00 8,800.00
1.00 lot Brush, Rollers, Thinners, Rags etc. 10,000.00 10,000.00
Materials: 68,600.00
Labor and Equipment: 34,300.00
Contingencies and Mark-ups: 27,783.00
Total: 130,683.00

Item XI-A: Electrical Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


12.00 sets Convenience Outlet 185.00 2,220.00
3.50 rolls 3.5 THHN Wire 3,600.00 12,600.00
20.00 li.m 14 THHN Wire 125.00 2,500.00
1.00 unit Circuit Breaker 6,500.00 6,500.00
15.00 sets 20 W Flourescent Lamp 140.00 2,100.00
18.00 pcs Junction Box 25.00 450.00
24.00 pcs Utility Box 20.00 480.00
1.00 lot Misc. Consumbles 2,500.00 2,500.00
Materials: 29,350.00
Labor and Equipment: 17,610.00
Contingencies and Mark-ups: 12,679.20
Total: 59,639.20

Item XI-B: Waterlines and Sewer Lines


Qty: 6.00 units

Page 164
Qty. Item Description Unit Cost Total
6.00 units Wall Fans (Standard or Equivalent) 2,500.00 15,000.00
Materials: 15,000.00
Labor and Equipment: 3,000.00
Contingencies and Mark-ups: 4,860.00
Total: 22,860.00
Unit Cost: 3,810.00

Item XII: Railings


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total
24.00 pcs 2" dia GI Pipes, Schedule 40.00 742.00 17,808.00
1.00 lot Welding Rod, Acetylene etc. 3,750.00 3,750.00
Materials: 21,558.00
Labor and Equipment: 7,545.30
Contingencies and Mark-ups: 7,857.89
Total: 36,961.19

Item XIII.A: Waterlines and Sewer Lines


Qty: 1.00 lot
Qty. Item Description Unit Cost Total
3.00 units Water Lines and Sewer Lines (Labor and Equi 8,000.00 24,000.00
Labor and Equipment: 24,000.00
Contingencies and Mark-ups: 6,480.00
Total: 30,480.00

Item XIII.B: Fixures


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total
3.00 units Water Closet w/ Lavatory and aceessories 5,500.00 16,500.00
Materials: 16,500.00
Labor and Equipment: 3,300.00
Contingencies and Mark-ups: 5,346.00
Total: 25,146.00

Item XI.C: Tile Works


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total

Page 165
248.00 pcs 0.30 m x 0.30 m Tiles 30.00 7,440.00
6.00 bags Tile Grout 80.00 480.00
2.00 bags Tile Adhesives 270.00 540.00
Materials: 7,920.00
Labor and Equipment: 2,772.00
Contingencies and Mark-ups: 2,886.84
Total: 13,578.84

Page 166
297.18

340.00
22.00

Page 167
34.00
144.00
186.00
458.00
40.00

3,400.00
260.00
26.00
220.00

Page 168
808.99

474.44

474.44

474.44

340

Page 169
3,810.00

Page 170
I 9,398.00
II 17,780.00
III 55,605.35
IV 416,383.47
V 211,635.34
VI 203,709.19
VII 196,826.76
VIII 214,089.62
IX 174,062.90
X 130,683.00
XI 82,499.20
XII 36,961.19
XIII 69,204.84
1,818,838.86

Page 171
DETAILED ESTIMATES
For the Supply Labor, Materials, and Necessary Equipment for the Improvement of
Five (5) Classroom School Building with Comfort Rooms each at Dau Homesite
Elementary School, Dau Homesite, Mabalacat, Pampanga (Purchase Request No. 13-
2109)

Item No. I: Mobilization/Demobilization


QTY: 1.00 lot

a. Labor Cost: Days Rate/Day Total


4 - Laborers 2 P 320.00 2,560.00
Labor Cost: 2,560.00
`
b. Equipment Cost: Days Rate/Day Total
1 - Stake Truck 2 P 3,200.00 6,400.00
Equipment Cost: 6,400.00

Direct Cost: 8,960.00


Mark-ups and Profit: 1,433.60
Tax: 1,075.20
Total: 11,468.80

Item No. II: Demolition of Existing Structure


QTY: 1.00 lot

a. Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
8 - Laborers 5 320.00 12,800.00
Labor Cost: 15,550.00

b. Equipment Cost: Days Rate/Day Total


1 - Handheld Jackhammer 4 P 550.00 2,200.00
Equipment Cost: 2,200.00

Direct Cost: 15,550.00


Mark-ups and Profit: 2,488.00
Tax: 1,866.00
Total: 19,904.00

Item No. III Excavation and Backfilling


QTY: 19.86 cu.m

a. Labor Cost: Days Rate/Day Total


1 - Foreman 3 550.00 1,650.00
4 - Laborers 3 320.00 3,840.00
Labor Cost: 5,490.00

Direct Cost: 5,490.00


Mark-ups and Profit: 878.40
Tax: 658.80
Total: 7,027.20

Unit Cost: 353.84

Item No. IV Filling Materials


QTY: 144.58 cu.m

a. Material Cost: Quantity Unit Cost Total


Filling Materials/Common Barrow 144.58 cu.m P 200.00 28,916.00
Mat'l Cost: 28,916.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
5 - Laborers 5 320.00 8,000.00
Labor Cost: 10,750.00

c. Equipment Cost: Days Rate/Day Total


1 - Plate Compactor 5 P 850.00 4,250.00
Equipment Cost: 4,250.00

Direct Cost: 43,916.00


Mark-ups and Profit: 7,026.56
Tax: 5,269.92
Total: 56,212.48

Unit Cost: 388.80

Item No. V. Concrete Works


QTY: 1.00 lot
a. Material Cost: Quantity Unit Cost Total
Cement 360.00 bags P 210.00 75,600.00
Sand 22.00 cu.m. 240.00 5,280.00
Washed Gravel 44.00 cu.m. 800.00 35,200.00
16 mm x 6.0 m 28.00 pcs. 345.00 9,660.00
12 mm x 6.0 m 180.00 pcs. 195.00 35,100.00
10 mm x 6.0 m 452.00 pcs. 130.00 58,760.00
Tie Wires 30.00 kls. 75.00 2,250.00
Mat'l Cost 221,850.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 18 550.00 9,900.00
3 - Skilled Laborers 18 440.00 23,760.00
6 - Laborers 18 320.00 34,560.00
Labor Cost: 68,220.00

c. Equipment Cost: Days Rate/Day Total


1 - One Bagger Mixer 12 P 950.00 11,400.00
Equipment Cost: 11,400.00

Direct Cost: 301,470.00


Mark-ups and Profit: 48,235.20
Tax: 36,176.40
Total: 385,881.60

Item No. VI. Masonry Works


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Cement 348.00 bags P 210.00 73,080.00
Sand 30.00 cu.m. 240.00 7,200.00
Washed Gravel 2.00 cu.m. 800.00 1,600.00
5" CHB 3850.00 pcs. 7.50 28,875.00
10 mm x 6.0 m 228.00 pcs. 130.00 29,640.00
Tie Wires 12.00 kls. 75.00 900.00
Mat'l Cost 141,295.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 14 500.00 7,000.00
4 - Skilled Laborers 14 440.00 24,640.00
4 - Laborers 14 320.00 17,920.00
Labor Cost: 49,560.00
Direct Cost: 190,855.00
Mark-ups and Profit: 30,536.80
Tax: 22,902.60
Total: 244,294.40

Item No. VII-A: Forms & Scaffolding


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Assorted Form Lumber (Plywood, 1.00 lot P 8,000.00 8,000.00
Good Lumber, Coco Lumber, etc.)
Scaffoldings. Stagings, Batterboards 1.00 lot 6,000.00 6,000.00
Mat'l Cost 14,000.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 4 550.00 2,200.00
2 - Skilled Laborers 4 440.00 3,520.00
2 - Laborers 4 320.00 2,560.00
Labor Cost: 8,280.00

Direct Cost: 22,280.00


Mark-ups and Profit: 3,564.80
Tax: 2,673.60
Total: 28,518.40

Item No. VII-B: Ficem Board on Metal Furring


QTY: 363.00 sq.m

a. Material Cost (w/ Installation) Quantity Unit Cost Total


Ficem Board on Metal Furring (0.60 363.00 sq.m P 545.00 197,835.00
m x 0.40 m Furring spacing) Mat'l Cost 197,835.00

Direct Cost: 197,835.00


Mark-ups and Profit: 31,653.60
Tax: 23,740.20
Total: 253,228.80

Unit Cost: 697.60


Item No. VII: Fabricated Materials
QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Glass Jalousie Window w/ 12 mm square bar Grills
8 sets - 2.8m x 1.50m 33.60 sq.m P 2,700.00 90,720.00
12 sets - 1.40m x 1.50m 25.20 sq.m 2,700.00 68,040.00
5 sets - 0.60m x0.60m 1.80 sq.m 2,700.00 4,860.00
5 sets - 1.00m x 2.10m Panel Door 5.00 sets 6,250.00 31,250.00
w/ Galvanized Jamb
5 sets - 0.60m x 2.10m PVC Door 5.00 sets 3,750.00 18,750.00
5 sets - 1.20m x 4.80m Blackboard 5.00 sets 3,250.00 16,250.00
Mat'l Cost 229,870.00

b. Labor Cost (Fabrication/Installation): 57,467.50

Direct Cost: 287,337.50


Mark-ups and Profit: 45,974.00
Tax: 34,480.50
Total: 367,792.00

Item No. IX: Roof Framing Works


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


2" x 6" Tubular Bar, 1.5mm 36.00 pcs. P 2,230.00 80,280.00
1.2mm - 2" x 4" Purlins 116.00 pcs. 518.00 60,088.00
1.2mm - 2" x 6" Purlins 22.00 pcs. 595.00 13,090.00
12 mm Dia. Sagrods 30.00 pcs. 189.00 5,670.00
Miscellaneous 1.00 lot 5,000.00 5,000.00
Mat'l Cost 164,128.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 10 550.00 5,500.00
4 - Skilled Laborers 10 440.00 17,600.00
4 - Laborers 10 320.00 12,800.00
Labor Cost: 35,900.00

c. Equipment Cost: Days Rate/Day Total


1 - Welding Machine 7 P 1,000.00 7,000.00
1 - Cutting Outfit 7 1,500.00 10,500.00
Equipment Cost: 7,000.00

Direct Cost: 207,028.00


Mark-ups and Profit: 33,124.48
Tax: 24,843.36
Total: 264,995.84

Item No. X: Tinsmithry Works


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Pre-Painted Long Span, Rib Type, Ga. 26 406.00 li.m P 338.00 137,228.00
Pre-Painted Flashing, Ga. 26 12.00 pcs. 350.00 4,200.00
Pre-Painted Ridge Roll, ga. 26 20.00 pcs. 350.00 7,000.00
1/2" Fascia Board x 12' 28.00 pcs. 520.00 14,560.00
Tekscrew 2300.00 pcs. 1.50 3,450.00
Blid Rivets 1000.00 pcs. 0.75 750.00
Misc. (Sealants, GI Straps, Touch-up Paint) 1.00 lot 3,000.00 3,000.00
Mat'l Cost 170,188.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 10 550.00 5,500.00
3 - Skilled Laborers 10 440.00 13,200.00
3 - Laborers 10 320.00 9,600.00
Labor Cost: 28,300.00

Direct Cost: 198,488.00


Mark-ups and Profit: 31,758.08
Tax: 23,818.56
Total: 254,064.64

Item No. XI: Painting Works


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Flat Latex Paint 10.00 tins 2,000.00 20,000.00
Semi Gloss Latex Paint 6.00 tins 2,100.00 12,600.00
Flat enamel 6.00 tins 2,200.00 13,200.00
Quick dry enamel 6.00 gals. 525.00 3,150.00
Red Lead Primer 12.00 gals. 525.00 6,300.00
Concrete neutralizer 12.00 gals. 165.00 1,980.00
Glazing Putty 6.00 gals. 520.00 3,120.00
Paint Thinner 4.00 gals. 380.00 1,520.00
Misc. Consumables (brushes, gauze, 1.00 lot 5,000.00 5,000.00
tinting color, acry color, rollers, etc.) Mat'l Cost 66,870.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 10 550.00 5,500.00
4 - Skilled Laborers 10 440.00 17,600.00
2 - Laborers 10 320.00 6,400.00
Labor Cost: 29,500.00

Direct Cost: 96,370.00


Mark-ups and Profit: 15,419.20
Tax: 11,564.40
Total: 123,353.60

Item No. XII-A: Electrical Works


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Main Circuit Breaker 1.00 unit 7,000.00 7,000.00
Box Type, Flourescent Lamp 40W 25.00 units 455.00 11,375.00
3-Gang Switch 5.00 sets 240.00 1,200.00
1-Gang Switch 5.00 sets 135.00 675.00
Connvenience Outlet (single) 10.00 sets 130.00 1,300.00
Connvenience Outlet (Double) 10.00 sets 165.00 1,650.00
Junction Box 32.00 sets 25.00 800.00
Utility Box 30.00 sets 25.00 750.00
3.5 THHN Wire 5.00 rolls 3,600.00 18,000.00
Entrance Cap 1.00 sets 250.00 250.00
Porcelein Ball 4.00 sets 180.00 720.00
Flexible Conduit 4.00 roll 250.00 1,000.00
Misc. (Wires, Conduits, etc) 1.00 lot 2,000.00 2,000.00
Mat'l Cost 46,720.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 8 550.00 4,400.00
2 - Skilled Laborers 8 550.00 8,800.00
1 - Laborers 8 320.00 2,560.00
Labor Cost: 15,760.00
Direct Cost: 62,480.00
Mark-ups and Profit: 9,996.80
Tax: 7,497.60
Total: 79,974.40

Item No. XII-B: Wall Fans


QTY: 10.00 units

a .Material Cost (Including Installation): Quantity Unit Cost Total


Branded Wall Fans 10.00 units P 2,500.00 25,000.00
Mat'l Cost 25,000.00

Direct Cost: 25,000.00


Mark-ups and Profit: 4,000.00
Tax: 3,000.00
Total: 32,000.00

Unit Cost: 3,200.00

Item No. XIII-A: Water lines and Sewer Lines


QTY: 1.00 LOT

a. Material Cost: Quantity Unit Cost Total


1/2" PVC Blue Pipe 22.00 pcs 250.00 5,500.00
1/2" Gate Valve 5.00 pcs 220.00 1,100.00
1/2" Faucets 5.00 sets 350.00 1,750.00
4" PVC pipes 14.00 pcs 750.00 10,500.00
4" Clean Out 5.00 pcs 60.00 300.00
2" PVC Pipes 12.00 pcs 240.00 2,880.00
Floor Drains 5.00 pcs 150.00 750.00
Assorted Fittings, etc. 1.00 lot 2,000.00 2,000.00
Mat'l Cost 24,780.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
2 - Skilled Laborers 5 480.00 4,800.00
1 - Laborers 5 320.00 1,600.00
Labor Cost: 9,150.00

Direct Cost: 33,930.00


Mark-ups and Profit: 5,428.80
Tax: 4,071.60
Total: 43,430.40

Item No. XIII-B: Fixtures


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


Water Closet w/ Lav. (Package) 5.00 sets 5,000.00 25,000.00
Mat'l Cost 25,000.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 5 550.00 2,750.00
1 - Skilled Laborers 5 440.00 2,200.00
1 - Laborers 5 300.00 1,500.00
Labor Cost: 6,450.00

Direct Cost: 31,450.00


Mark-ups and Profit: 5,032.00
Tax: 3,774.00
Total: 40,256.00

Item No. XIII-C: Tile Worls


QTY: 1.00 lot

a. Material Cost: Quantity Unit Cost Total


0.30 m x 0.30 m Ceramic tiles 550.00 unit 34.00 18,700.00
Tile Adhesives 7.00 bags 265.00 1,855.00
Tile grouts 12.00 bags 70.00 840.00
Miscellaneous 1.00 lot 500.00 500.00
Mat'l Cost 21,895.00

b. Labor Cost: Days Rate/Day Total


1 - Foreman 4 550.00 2,200.00
2 - Skilled Laborers 4 440.00 3,520.00
1 - Laborers 4 300.00 1,200.00
Labor Cost: 6,920.00

Direct Cost: 28,815.00


Mark-ups and Profit: 4,610.40
Tax: 3,457.80
Total: 36,883.20
Item No. XIV. Perimeter Fence
QTY: 1.00 lot

Material Cost: Quantity Unit Cost Total


5" CHB 4600.00 pcs. 7.00 32,200.00
Cement 560.00 bags P 210.00 117,600.00
Sand 48.00 cu.m. 240.00 11,520.00
Washed Gravel 28.00 cu.m. 800.00 22,400.00
12 mm x 6.0 m 245.00 pcs. 195.00 47,775.00
10 mm x 6.0 m 415.00 pcs. 130.00 53,950.00
Tie Wires 30.00 kls. 75.00 2,250.00
Mat'l Cost 287,695.00

Labor Cost: Days Rate/Day Total


1 - Foreman 18 550.00 9,900.00
2 - Skilled Laborers 18 440.00 15,840.00
7 - Laborers 18 300.00 37,800.00
Labor Cost: 63,540.00

Equipment Cost: Days Rate/Day Total


1 - One Bagger Mixer 16 P 2,200.00 35,200.00
Equipment Cost: 35,200.00

Direct Cost: 386,435.00


n-direct Cost (27 %) 104,337.45
Total: 490,772.45
353.84

388.80
39.52941176
336
24.76
37.15
28
177
445

77,647.50

79,620.00

345
15.87
1.03
3878
222

49,453.25
4,200.00

697.60
25
75
14
18

57,444.80

42,900.00
270
12
11
32
2334.5

42,547.00

20
12
10
4
5
7
30
30

26,748.00

15,417.60
3,200.00

8,673.00
8,750.00

420

7,663.25
I 11,468.80
II 19,904.00
III 7,027.26
IV 56,212.70
V 385,881.60
VI 244,294.40
VII 281,747.20
VIII 367,792.00
IX 264,995.84
X 254,064.64
XI 123,353.60
XII 111,974.40
XIII 120,569.60
2,249,286.05
4700
590
47.62
26.07
253
418

100,693.25

98,740.00
DETAILED ESTIMATES for Improvement of Elevated Three (3) Classroom School
Building with Comfort Room at Betis Elementary School, Betis, Guagua, Pampanga

Item I: Mobilization/Demobilization
Qty: 1.00 lot

Qty. Days Item Description Unit Cost Total


4.00 2.00 Laborers 300.00 2,400.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 7,400.00
Contingencies and Mark-ups: 1,998.00
Total: 9,398.00

Item II: Demolition of Existing Structure


Qty: 1.00 lot

Qty. Days Item Description Unit Cost Total


1.00 4.00 Foreman 550.00 2,200.00
1.00 4.00 Skilled Laborers 450.00 1,800.00
6.00 4.00 Laborers 300.00 7,200.00
1.00 2.00 Elf/Stake Truck 2,500.00 5,000.00
Labor and Equipment: 14,000.00
Contingencies and Mark-ups: 3,780.00
Total: 17,780.00
Item III: Filling Materials
Qty: 187.11 cu.m

Qty. Item Description Unit Cost Total


187.11 cu.m Common Barrow/Filling Materials 180.00 33,679.80
Materials: 33,679.80
Labor and Equipment: 10,103.94
Contingencies and Mark-ups: 11,821.61
Total: 55,605.35
Unit Cost: 297.18

Item IV: Concrete Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


320.00 bags Cement 210.00 67,200.00
22.50 cu.m Sand 260.00 5,850.00

Page 194
35.00 cu.m Gravel 3/4" 830.00 29,050.00
136.00 pcs 16mm dia. Bars 340.00 46,240.00
184.00 pcs 12mm dia. Bars 200.00 36,800.00
444.00 pcs 10mm dia. Bars 130.00 57,720.00
Materials: 242,860.00
Labor and Equipment: 85,001.00
Contingencies and Mark-ups: 88,522.47
Total: 416,383.47

Item V: Masonry Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


3,570.00 pcs 5" CHB 7.00 24,990.00
272.00 bags Cement 210.00 57,120.00
28.00 cu.m Sand 260.00 7,280.00
228.00 pcs 10mm x 6m RSB 130.00 29,640.00
Materials: 119,030.00
Labor and Equipment: 47,612.00
Contingencies and Mark-ups: 44,993.34
Total: 211,635.34

Item VI: Carpentry Works


A. Forms and Scaffoldings
Qty: 1.00 lot

Qty. Item Description Unit Cost Total


5.00 pcs 1/4" Marine Plywood 365.00 1,825.00
200.00 bd.ft Form Lumber 48.00 9,600.00
1.00 lot Scaffoldings 4,500.00 4,500.00
8.00 kilos Cw Nails 70.00 560.00
Materials: 16,485.00
Labor and Equipment: 5,769.75
Contingencies and Mark-ups: 6,008.78
Total: 28,263.53

B. Ceiling Works
Qty: 216.87 sq.m

Qty. Item Description Unit Cost Total

Page 195
216.87 sq.m 4.5mm Hardiflex Ceiling on Metal Furring 490.00 106,266.30
Materials: 106,266.30
Labor and Equipment: 31,879.89
Contingencies and Mark-ups: 37,299.47
Total: 175,445.66
Unit Cost: 808.99

Item VII: Fabricated Materials


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


Jalousie Type Window with 12 mm Grills
6.00 sets 1.40 m x 1.50 m: 6,100.92 36,605.52
6.00 sets 2.10 m x 1.50 m: 9,151.38 54,908.28
3.00 sets 0.6 m x 0.6 m: 1,045.87 3,137.62
3.00 sets 1.00m x 2.10m Panel Door w/ Galvanized Jamb 6,000.00 18,000.00
3.00 sets 0.60 m x 2.10 m PVC Door w/ Jamb 2,000.00 6,000.00
3.00 sets 1.20 m x 4.8 m Blackboard 3,500.00 10,500.00
Materials: 129,151.42
Labor and Equipment: 25,830.28
Contingencies and Mark-ups: 41,845.06
Total: 196,826.76

Item VIII: Roof Framing Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


30.00 pcs 2" x 6" x 1.5 mm Tubular 2,250.00 67,500.00
64.00 pcs 2" x 4" x 1.2mm C- Purlins 575.00 36,800.00
14.00 pcs 2" x 6" x 1.2mm C-Purlins 675.00 9,450.00
16.00 pcs 12mm Dia. Sag Rods 195.00 3,120.00
1.00 lot Welding Rod, Acetylene etc. 8,000.00 8,000.00
Materials: 124,870.00
Labor and Equipment: 43,704.50
Contingencies and Mark-ups: 45,515.12
Total: 214,089.62

Item IX: Tinsmithry Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


233.20 li.m #26 Long Span, Rib Type 320.00 74,624.00

Page 196
10.00 pcs Ridge Roll 325.00 3,250.00
18.00 pcs Flashing 300.00 5,400.00
32.00 pcs Fascia Board, 1/2" x 10' x 10" 375.00 12,000.00
1.00 lot Rivets, Tekscrews, Sealants 6,250.00 6,250.00
Materials: 101,524.00
Labor and Equipment: 35,533.40
Contingencies and Mark-ups: 37,005.50
Total: 174,062.90

Item X: Painting Works


Qty: 1.00 lot
Qty. Item Description Unit Cost Total
5.00 tins Flat Latex 2,000.00 10,000.00
8.00 tins Flat Wall Enamel 2,100.00 16,800.00
10.00 tins Semi Gloss Latex 2,300.00 23,000.00
4.00 tin Quick Dry Enamel 2,200.00 8,800.00
1.00 lot Brush, Rollers, Thinners, Rags etc. 10,000.00 10,000.00
Materials: 68,600.00
Labor and Equipment: 34,300.00
Contingencies and Mark-ups: 27,783.00
Total: 130,683.00

Item XI-A: Electrical Works


Qty: 1.00 lot

Qty. Item Description Unit Cost Total


12.00 sets Convenience Outlet 185.00 2,220.00
3.50 rolls 3.5 THHN Wire 3,600.00 12,600.00
20.00 li.m 14 THHN Wire 125.00 2,500.00
1.00 unit Circuit Breaker 6,500.00 6,500.00
15.00 sets 20 W Flourescent Lamp 140.00 2,100.00
18.00 pcs Junction Box 25.00 450.00
24.00 pcs Utility Box 20.00 480.00
1.00 lot Misc. Consumbles 2,500.00 2,500.00
Materials: 29,350.00
Labor and Equipment: 17,610.00
Contingencies and Mark-ups: 12,679.20
Total: 59,639.20

Item XI-B: Waterlines and Sewer Lines


Qty: 6.00 units

Page 197
Qty. Item Description Unit Cost Total
6.00 units Wall Fans (Standard or Equivalent) 2,500.00 15,000.00
Materials: 15,000.00
Labor and Equipment: 3,000.00
Contingencies and Mark-ups: 4,860.00
Total: 22,860.00
Unit Cost: 3,810.00

Item XII: Railings


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total
24.00 pcs 2" dia GI Pipes, Schedule 40.00 742.00 17,808.00
1.00 lot Welding Rod, Acetylene etc. 3,750.00 3,750.00
Materials: 21,558.00
Labor and Equipment: 7,545.30
Contingencies and Mark-ups: 7,857.89
Total: 36,961.19

Item XIII.A: Waterlines and Sewer Lines


Qty: 1.00 lot
Qty. Item Description Unit Cost Total
3.00 units Water Lines and Sewer Lines (Labor and Equi 8,000.00 24,000.00
Labor and Equipment: 24,000.00
Contingencies and Mark-ups: 6,480.00
Total: 30,480.00

Item XIII.B: Fixures


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total
3.00 units Water Closet w/ Lavatory and aceessories 5,500.00 16,500.00
Materials: 16,500.00
Labor and Equipment: 3,300.00
Contingencies and Mark-ups: 5,346.00
Total: 25,146.00

Item XI.C: Tile Works


Qty: 1.00 lot
Qty. I. Materials Unit Cost Total

Page 198
248.00 pcs 0.30 m x 0.30 m Tiles 30.00 7,440.00
6.00 bags Tile Grout 80.00 480.00
2.00 bags Tile Adhesives 270.00 540.00
Materials: 7,920.00
Labor and Equipment: 2,772.00
Contingencies and Mark-ups: 2,886.84
Total: 13,578.84

Page 199
297.18

340.00
22.00

Page 200
34.00
144.00
186.00
458.00
40.00

3,400.00
260.00
26.00
220.00

Page 201
808.99

474.44

474.44

474.44

340

Page 202
3,810.00

Page 203
I 9,398.00
II 17,780.00
III 55,605.35
IV 416,383.47
V 211,635.34
VI 203,709.19
VII 196,826.76
VIII 214,089.62
IX 174,062.90
X 130,683.00
XI 82,499.20
XII 36,961.19
XIII 69,204.84
1,818,838.86

Page 204

Вам также может понравиться