Вы находитесь на странице: 1из 1

Notes

1 Validity:07 days
2 Work Completion:After 45 Days from the Date of Order L.PO released with 10% of advance Payment
Payment:10% Advance,85% Against work Progress &5% Retention after One year from the date of
3
work completion of work
Exclusion
1 All Authorities for approval,civil defence fees & any other fees
2 Any kind of road works
3 Any kind of supply & Installtion of Manhole cover

Page 1 of 1