1 KALI PRAWAN 122 days Fri 9/15/17 Mon 3/5/18
Page 1
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
14 Rebar ready and pass 0 days Fri 3/9/18 Fri 3/9/18 3/9
inspection
15 Main anchor installation 2 days Sat 3/10/18 Mon 3/12/18
16 Concrete ready and pass 0 days Tue 3/13/18 Tue 3/13/18 3/13
inspection
17 Abutment plate 3 days Wed Fri 3/16/18
installation 3/14/18
18 Spillway pipeline work 2 days Sat 3/17/18 Mon 3/19/18
Page 2
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
27 CONTROL HOUSE 16 days Mon 4/9/18 Mon 4/30/18
INSTALLATION
28 Structure & security ready 0 days Mon 4/9/18 Mon 4/9/18 4/9
& pass inspection
29 Install Air/instrument 1 day Tue 4/10/18 Tue 4/10/18
panel
30 Pipeline work 5 days Wed 4/11/18Tue 4/17/18
31 Install electrical panel + 5 days Wed Tue 4/24/18
wiring 4/18/18
32 Operation test for air 2 days Wed Thu 4/26/18
system 4/25/18
33 CONTROL ROOM 2 days Fri 4/27/18 Mon 4/30/18
COMMISSIONING
34 CONNECTING PIPELINE 14 days Tue 5/1/18 Fri 5/18/18
INSTALLATION
35 Pipe trenches ready 0 days Tue 5/1/18 Tue 5/1/18 5/1
Page 3
ID Task Task Name Duration Start Finish Half 2, 2017 Half 1, 2018
Mode A S O N D J F M A M J J
40 HANDOVER 1 day Sat 5/19/18 Sat 5/19/18
41 FINAL TRAINING 3 days Sun 5/20/18 Tue 5/22/18