General Manager (M-3 Section) PKM National Highway Authority House No. 90, Excise & Taxation Society Near Motorway Link Road, Lahore.
Project: Consultancy Services as Assistant to Employers Representative (AER)
for Peshawar-Karachi Motorway(PKM), Lahore-Multan Section, M-3 (230km) on EPC/Turnkey Basis
Subject: Recommendation for establishment of revised baseline schedule to evaluate
the progress based on construction phase of the project Dear Sir, AER would like to bring in to your kind notice that the baseline schedule currently in use for the monitoring of project progress is established based on the budget allocated for whole project including the cost to be paid to the Contractor during Defect Liability period after the completion of construction phase of the project. It is quite understandable that this way of establishing the baseline creates confusion while evaluating the actual progress of the project. In order to overcome this problem, we have instructed the Contractor to establish the baseline schedule based on work activities of the Construction phase of the project only so as to enable us to measure the progress on actual grounds. Moreover, it will help us to set a uniform criteria for the assessment of project progress for weekly and monthly reports. For your convenience a document showing the actual reflection of the proposed baseline is being attached to this letter. Assuring you of our best services and cooperation at all times, we remain. Faithfully Yours,
SHIM, Myung Seob
Chief Resident Engineer
*Attachment: 1. Proposed Cash Flow
2. Progress reporting format Cc: 1. Member (Motorway, South), NHA, Lahore 2. Project Director (PKM, Section III), NHA, Lahore 3. Program Manager (PMU), NHA, Islamabad 4. CR20G-ZKB (JV) 5. All JV Members