Академический Документы
Профессиональный Документы
Культура Документы
Submitted by
Loveneet Saini
BE13104023
25 January to 25 May,2016
I hereby declare that the project work entitled Performance Improvement of Electrostatic
Precipitator: Analysis and Modification is an authentic record of my own work carried out at
Thermal Training Institute, GGSSTP, Roopnagar as requirements of 17 Weeks project
semester for the award of degree of B.E. (Electrical Engineering), PEC University of
Technology, Chandigarh, under the guidance of Er. Naveen Malhotra and Dr. Jagdish Kumar,
during 25th January 2016 to 25th May2016.
(Signature of student)
Loveneet Saini
13104023
Date: ___________________
Certified that the above statement made by the student is correct to the best of our knowledge
and belief.
It gives me immense pleasure to take this opportunity to thank GGSSTP Ropar along with its
Stafffor giving me such a great opportunity to do project work under this North Indias
Largest Capacity Thermal Power Plant (1260 MW). It gave me opportunity to learn the work
carried out here, got a glimpse of the new environment and hard work of power sector. I
would like to express my sincere gratitude to Er. Naveen Malhotrafor his invaluable
guidance and enormous help, encouragement and comforting behaviour, which helped me to
complete my internship successfully.
I would also like to acknowledge Mr. Satwinder Singh, Mr. Manjeet Singh, Mr Kulwant
Singh, Mr Puri who helped me in one way or other with their constant involvement during
my training.
I would also like this opportunity to express my sincere gratitude to my faculty coordinator,
Dr. Jagdish Kumar for his constant guidance, valuable suggestions and moral support. I
acknowledge gratefully the help of GGSSTP Ropar staff and members who were always eager
to help me with their warm attitude and technical knowledge. Finally, no word will be enough
to express my deepest reverence to family and friends without whom enthusiasm and support
I wouldnt have been able to pursue my goals.
2. Acknowledgement 2
3. Summary 5
8. Turbines 22-25
19. Conclusion 95
Table of Figures
As Student Intern in the Guru Gobind Singh Super Thermal Power Plant, I got the
opportunity to explore the ideas of the modern electrical engineering which forms the
backbone of the very power system, which lights up the world we live in. I got the
opportunity to reconcile the knowledge of theoretical framework with its actual practical
realizations.
1.Generation
2.Protection
3.LT Switchgears
4.HT Switchgears
Initial stage of my training involved getting a thorough knowledge of how the process of
generating electricity begins and the subsequent steps necessary to make electricity available
to the consumer. During my analysis I found that, Electrostatic Precipitator (ESP) of stage 3
of the planthas poor precipitation efficiency, hence posed a menace to surrounding
environment.This motivated me to work on ways to resolve this menace. To resolve this, I
carried out analysis of electrostatic precipitator and the fundamental principles of electro
physics on which precipitator works.
Finally using the extensive research of Mr. Frederick cottrel and others I presented the use of
advance microprocessors to boost stage 3 ESP efficiencies so as to meet the pollution control
norms of the Ministry of Forest and Environment, India.
The project report begins with introduction to the working of power plant with the overview
of the Thermal power plant. Mechanical aspects of coal and ash handling are also presented.
Then is the brief overview of the analysis that have been followed for the completion of the
project.
In order to have a better look into the project flowcharts, snapshots, Graphs have been
supplemented wherever necessary. It gives the insight of the theoretical framework presented
and outlines the fundamental ideas used for modification of electrostatic precipitator
The report concludes giving the final results and future scope of the work done followed by
references.
Govt. of Punjab unbundled Punjab State Electricity Board into two companies
In exercise of the Power conferred by article -45 of the Articles of Association of Punjab State
Power Corporation Limited and Punjab State Transmission Corporation Ltd.and all other
Powers enabling him on this behalf, Governor of Punjab is appoint the following Chairman
cum Managing Directors and Directors of the above Corporations with immediate effect. The
appointment will be initially for a period of one year from the date of joining:-
POWERCOM
4. Er.G.S.Chhabra Director/Generation
5. Sh.S.C.Arora Director/Finance
6. Sh.H.C.Seth Director/H.R
TRANSCOM
The Punjab State Electricity Board (PSEB) was a statutory body formed on 1-2-1959 under
the Electricity Supply Act.1948. Subsequently with the re-organization of the erstwhile State
of Punjab under the Punjab Re-organization Act 1966 this form came into existence w.e.f. 1st
including share from Central Sector Projects. The Board's gross generation during the
year2008-09 was 38880 Million Units. PSEB operated its own Generation Power Plants and
also got power as its share from BBMB. The PSEB also constructed and maintained its
Transmission and Distribution system for providing efficient services to the various categories
of electricity consumers in the state. PSEB proudly serving more than 66.31 lakhs consumers
comprising of approximate 54.86 lakhs. General, 1.12 lakhs Industrial and 10.33 lakhs
Agricultural connections till 31.3.2009
Plant the ever increasing gap between power demand and its availability was one of the main
reasons for envisaging the Guru Gobind Singh Super Thermal Power Plant for the state of
Punjab after Guru Nanak Dev Thermal Power Plant, Bhatinda.
Thermal power station burn fuels and use the resultant steam to drive the turbo generator. The
object is to convert heat into mechanical energy in the. turbine and to convert mechanical
energy into electrical energy by rotating magnets inside a set of magnets. The coal brought to
the station by means of trains travel from the coal handling plant by conveyor belts to the coal
bunkers. From where it is fed to pulverizing mills which grind it to a ne powder. Finely
powdered coal mixed with preheated air is blown into the boiler by primary air fan where it
burns more like a gas than as a solid with additional amount of air called the secondary air
supplied by the secondary draft fan. As the coal has been ground nely the resultant ash is ne
powder. Some of its contents bind together to form lumps which fall in ash pits at the bottom
of the furnace. The ash mixed with water is then taken to the pits for subsequent disposal. The
electrodes charged by high voltage electricity in the electrostatic precipitator trap most of the
ash. The dust is then conveyed by water to the disposal area or to the bunkers while the
cleaned ue gases pass on through the ID fan to discharge through the chimney. Meanwhile
the heat released from the burning of coal has been absorbed by many kms of tubing which
line the boiler. Inside these tubes is water, which takes the heat and is converted into steam at
high temperature and pressure. This steam at high temperature and pressure is sent to the
turbine where it is discharged through the nozzles on to the turbine blades. The energy of the
steam striking on the blades makes the turbine to rotate. Coupled to the turbine is the rotor of
the generator. So when the turbine rotates the rotor of the generator turns. The rotor is housed
inside a stator having heavy coils of copper bars in which electricity is produced through the
movement of magnetic eld produced by the rotor. Electricity passes from stator winding to
the transformer, which increases its voltage level so that it can be transmitted over the lines to
far off places.
The steam, which has given away its energy, is changed back into water in the condenser.
Condenser contains many kms of tubing through which cold water is continuously pumped.
The steam passing over the tubes continuously loses heat and is rapidly changed back into
water. But the two waters i.e. the boiler feed water and cooling water must never mix. Boiler
water must be absolutely pure otherwise the tubing of the boiler may get damaged due to the
formation of salts inside the tubes due to the presence of different impurities in water.
The coal handling plant is that unit of thermal plant which involves complete processing of
coal from the moment it arrives in the coal yard to the time it is fed to the boiler. The coal is
transported to the coal yard from the coal mines through railways. A rake: is a train containing
about 58-60 wagons. Each wagon contains about 58 tons of coal.
WAGON - Shunters are used for placing the wagons on rail table. Shunter or loco has the hp.
of 450h.p. and 650h.p. the whole wagon get unload in 4 minutes (app). The weight of wagon
is measured with the help of electronic motion wave bridge. Approximately weight of wagon
is 82 ton. Each wagon contains 58 tons of coal. The types of wagon are ntype and c-type.
During measuring of wagon, the speed of train should be 5km/hr l 0km/hr and weight is
measured with electronics motion wave bridge.
Wagon tippler
These are 5 in no. & is used for unloading of the coal wagons. Tippler consists of rail table
(the rail table is turned at an angle of 135), tracks, pits (in pit, there is suspension), at the top
of wagon tippler, there is holding beam for holding the wagon.
The wagon is unloaded on grating. The ac. motor is of 95 hp. The whole process is
mechanical.
MUTH- (manual unloading track hopper) when there is fault in wagon tippler, it is
used. Coal is unloaded manually on grating.
MANUAL UNLOADING
Manual unloading is done by the labour itself by using the suitable equipments. The wagon
capacity is 58 ions and it itself weights 2 ions. The capacity of bunker hall is 660 tons, which
is sufficient for 22 hours. The raw coal has a size of the order of 500 mm approx. This coal is
sent to the primary crusher on conveyor belts and reduced to a size of 125 mm. This coal from
primary crusher is sent to secondary crusher. Secondary crusher further reduces the size of the
coal to 25mm. This coal from secondary crusher is sent to coal mills on the conveyor belts.
CHP also has stackers and reclaimer.
RAIL WAGON
The rail mil track gauge is 1676m and the provision is made for the passage though the
installation of all standard Indian rolling stock of this size. The tippler will accept the
following for any one operation. One standard boxcar wagon 8 wheeler orlow 4 wheeler 0
type wagons handled in pair.
CONVEYER
The conveyors are rubber type and usually 1250 or 1500 mm wide. It is a rubberized belt with
nylon ply. The belt is braided. This combination of plies is a carcass. Four plies comprise one
carcass. The conveyor belt capacity is 1250t/hr.
PRIMARY CRUSHER
Primary crusher reduces the size of coal to 125 mm. It is a hollow shell with diameter 12 and
length 22. It is a hollow shell supported on tie rods connected with perforated plates to make a
circle. On these dewing, perforated plates are present with holes of diameter 125mm.
SECONDARY CRUSHER
Coal for further reduction of size is fed from primary crusher to the secondary crusher
bymean of a screen, which is not stationary but vibrates. The secondary crusher is a ring
granulator system; its design is different from the primary crusher.
There are two types of hammers:
1. Ring-type hammers
2.Tooth-type hammer
TRAVEL SYSTEM
The total system makes the stacker to move to and fro along the conveyor. The total track
length is 750 m. The speed of travel system is 7.1 m/s in slow mode and 14.16 in fast mode
TYPES OF MILLS
1. Low speed mills: they have a speed of rotation of 10 to 15 rpm. These mills have a
cascading system. The coal gets pulverized due to cascading of valves and balls and then coal
gets sucked.
2. Medium speed mills: the speed of rotation is 50 rpm.
3. High speed mills: the high-speed mills have a speed of rotation 80 to 85 rpm. The wear and
tear being very high, these mills are not installed in RTP.
Each unit has six bowl mills. There are total 36 bowl mills. For generating power of 210mw, 4
bowl mills are sufcient. Each mill capacity is 39.6Usec. The coal mills are designed for
performance coal. But coal we get is performance coal HGI - 55 with following
specications.
volatile matter - 4500 kcal/kg.
ash contents - 28%.
The hgi being high, the coal is hard to mill and more is of stone type. There are 3 no. Of
grinding rolls, which grind coal before it, is fed to the furnace.
Introduction to Boiler
A boiler is a combination of systems and equipment in which chemical energy is converted
into thermal energy, which is then transferred to working uid, so as to convert it into steam at
high temperature and pressure.
In GGSSTP, there are six boilers for six units. A boiler is a 210 MW Radiant Reheat, Natural
Circulation, Single drum, Semi-outdoor, Dry bottom, Water Tube and designed for coal as
principle fuel. The Heavy Fuel Oil (HFO) ring capacity is equivalent to 22.5% boiler
Maximum Continuous Rating (MCR). Four burners are capable for 7.5% boiler MCR heat
input. A layout arrangement is of conventional type that is with the mills in front of the boiler.
The complete furnace section is of fusion welded wall type, arranged as a gas and pressure
tight envelop. The extended sidewall section (where re-heaters are located) is covered with
water-cooled n welded walls. The maximum ue gas velocity in the pressure part system is
limited to 10-12 m/sec at 100% boiler MCR load. All headers are located outside the gas path,
except for the economizer inlet header; intermediate headers and LTSH inlet header are
located in the low gas temperature section. Two numbers of Reheater De-super heater are
provided at the inlet of the reheater for emergency control of nal reheated steam.
In a boiler, there are Down Comers, Super heaters, Re-heaters, Ring heaters, Economizers,
Air Pre-heater, Steam Cooled Walls. All the four walls of furnace consist of pipes in which
water ows and is connected to the drum by Down Corners. This arrangement of boiler avails.
Cold water to come down and Hot water to rise through risers. The complete pressure parts
are suspended from the boiler steel roof structure and arranged for free expansion downwards.
Drum
The boiler drum is made of alloy steel plate of 97mm thickness and has an outside diameter of
1800mm. The drum is fusionwelded type with welded-on hemispherical dished ends. The
drumdished ends are provided with manholes and manhole covers. Drum is welded with
Furnace Walls
The combustion chamber is formed of water wall tubes of outside diameter of 60mm and is
placed at a distance of 125mm in front and rear waterwalls. On the sidewalls the water-wall
tubes are set at a distance of 65mm.In the region above the burners of front and rear water
walls, radiation wall superheater tubes are arranged in between the widely pitched water-walls
tubes. The lower parts of the front and rear water wall tubes are provided with at ns to
cover the entire combustion chamber. In the corner where the pulverized coal burners are
located, the tubes are bent suitably to provide opening for the setting of the tilting comer
burners.
The seam less water-wall tubes is welded to the bottom and top headers by means of Stubs.
Adequate dimensioning of downcomers ensures perfect natural circulation of water in the
various circulation contours. The guides and springs supporting suspensions are so designed
and dis-positioned so as to ensure proper expansion and contraction of the tubular system
without occurrence of any undue stresses.
There are four furnace walls consisting of re tubes fabricated from seamless carbon steel and
fusion welded. These four walls are front, rear, right and left water walls.
Down Comers
These are six numbers of down comer pipes, connecting the steam drum and water wall lower
ring header.
Riser Pipes
118 numbers of riser pipes are rolled upward to take the steam water mixture from the outlet
of the water-wall header to the steam drum.
Super Heaters
Steam coming out of the drum is circulated through a number of super- heaters. There is 14
number of super heater headers. The steam superheater has a total heating surface of 3782m 2.
It consists of six stages between which two regulating injections controlled by automatic
regulator of superheater steam temperature are arranged. The tubular pendent loops are
arranged across the full width of the boiler.
Saturated steam from the boiler drum is led to the wall superheater I located in the upper part
of the front and rear water walls of the furnace. From there it is led through the tubes which
from the ceiling of the horizontal pass to the convection horizontal superheater II located in
the second pass of the boiler. The rst auxiliary regulating injection is arranged at the end of
the superheater II before the inlet of the steam to the radiant platen type superheater III and
superheater IV. The final outlet superheater IV is also arranged in horizontal pass of the boiler.
The regulating injection is suspended between the fifth stage and sixth stage of the superheat.
The final superheater is suspended between the rows of the grid tubes in the horizontal pass of
the boiler. The second regulating injection is suspended between the fifth and sixth stage of
superheat. The final superheater is suspended between the rows of the grid tubes in the
horizontal pass of the boiler. The superheater tubes are welded to the inlet and outlet headers
by means of stub. the flow of steam in superheater is as follows:
Steam cool wall roof tubes (SCW) -> SCW side tubes -> Extended SCW side tubes->
Front SCW tubes->SC roof and rear wall tubes-> Super heater rear horizontal
Assemblies->LTSH-> SHDESH platen super heater-> Pendant super heater.
The reheater II is suspended in the horizontal pass of the boiler and the tubular loops are
arranged after the pendant coils of the convection superheater V. The reheatertubes are welded
to the inlet and exit headers by means of stubs. The material is carbon molybdenum and
chromium molybdenum. Austentine Stainless Steel temperature are controlled by spraying
water coming out of boiler feed pump discharge.
Air Pre-Heaters
They are trisected types as they are the last stage in the heat recovery cycle. It preheats the
primary air and secondary air with ue gases. There are two numbers of air pre heaters and
contain heating elements in three layers. These are hot, intermediate and cold layers. Its
heating surface is about 1900 sq.
Furnace (11560C) > Platen SH (10260C) > Reheater (920C) > Final SH (6660C) >
LTSH (346C) > Economizer(140C) > APH > ESP > Induced Daft Fan > Chimney.
Boiler Parameters
Superheater outlet steam flow 690T / hr.
Steam pressure at SH outlet 155kg/cm2
Steam temperature at SH outlet 540C.
Re-heater outlet steam ow 597.5T/Hr
Steam pressure at RH inlet 37.6kg/cm2
Steam pressure at RH outlet 36. l k g/cm2
Steam temperature at RH outlet 5400C
Steam temperature at RH inlet 3420C
Feed water temperature 2430C
entering economizer
Ambient air temperature 400C
Heat Igniter
The equipment gives the high intensity electrical spark which immediately ignites the oil
articles surrounding the spark, thus creating a ame pocket in the oil spray. The ame
propagation into the oil spray from this pocket gives the successful ignition. The igniter works
in combustion with the discriminating ame scanner, which is capable of sensing the
Boiler Auxiliaries
ID Fans 3 Nos.
FD Fans 2 Nos.
PA Fans 2 Nos.
ESP 28 Nos.
Ash Handling Plant
Fuel Oil System
Scanner Air Fan
Soot Blowers 56 Nos.
Soot Blower
Soot blowers have been provided for cleaning and soot blowing the water walls, super heater,
and reheater tubes for efcient heat transfer in both radiation and convection Zones. Soot
blowers are operated to keep the external heating surfaces clean. Recording and comparing
the exit gas temperature at various loads and furnace condition can establish proper soot
blowing schedule. Abnormal low steam temperature may be due to a fouled SH/RH externally
or internally and abnormal high steam temperature may be due to a dirty furnace.
TURBINES
Steam Turbines
The steam turbine is a prime mover that converts the stored mechanical energy in steam into
rotational mechanical energy. A turbine pair consists of a ring of fixed blade and a ring of
moving blades. The blades are so designed that the steam glides over the blade surface
without striking it. As the steam ows over the covered surface of blade, it exerts a pressure
Figure 3: A Typical Power Station Steam Turbine and Its External Equipment
Specications
The Electric Generator is the most important part of the power station. All other units in the
power station are installed to drive the alternator. Generator uses the principle of
electromagnetic induction to generate electric power. In the simplest form, generator consists
of a revolving rotor and fixed stator. The stator carries a three-phase winding, in which
alternating emf is induced when shaft of rotor is moved with the help of prime mover. Rotor
carries field magnet and coils, which provide the magnetic flux of the machine. Current
brought into field circuit by means of two rotor slip rings and set of brushes on them excites
the field. The magnitude of induced emf in winding of stator depends upon the strength of
magnetic field, the speed of rotation and number of stator coils in series.
Rotor
Generator Cooling
Terminal Box
The beginnings and the ends of the stator winding are brought out to the slip ring side ofthe
stator body and brought out through 9 terminal bushings in the terminal box. Three phases
and six neutral terminals are brought out from the stator frame through bushings, which are
capable of withstanding high voltage and provided with gas tight joints. The terminal box is a
welded construction of (Non-Magnetic) Austenitic Steel Plates to eliminate Stray losses due
to eddy currents, which causes excessive heating.
Stator core
A rotating magnetic ux threads with the core. In order to minimize the magnetizing and eddy
current losses in this active portion of the stator, the entire core is built up of thin laminations.
For reasons of manufacture, each lamination layer is made up of a number of
individualsegments.
The segments are stamped out with accurately nished die from sheets of cold rolled
highquality silicon steel. Before insulating with varnish each segment is carefully debarred.
The stator body is turned on end while the core is stacked with lamination segments in
individual layers. The segments are assembled in an interleaved manner from layer to layer so
that a monolithic core of high mechanical strength and uniform permeability to magnetic ux
is obtained. The stampings are held in position by twenty core bars having dovetail section.
Insulating paper pressboard are also put between the layers ofstampings to provide additional
insulation and to localize short-circuit, which may occur due to failure of varnish insulation of
sheet stamping.
To ensure tight monolithic core the stampings are hydraulically compressed during the
Stator Winding
The stator has a threephase, double layer, short pitch and bar type of winding; havingtwo
parallel paths. Each slot accommodates two bars. The slot lower bars and slot upperbars are
displaced from each other by one winding pitch and connected at their ends so asto formring.
Conductor Construction
Each bar consists of solid as well as hollow conductors with cooling water passingthrough the
latter. Alternate arrangements of hollow and solid conductors ensure anoptimum solution for
increasing current and to reduce losses.
The conductors of small rectangular cross-section are provided with glass lapped
strandinsulation. These are arranged side by side in two layers. A separator insulates
theindividual layers from each other. In the straight slot portion the strands are transposed
by360 degrees to reduce the eddy losses. The transposition provides for a
mutualneutralization of voltages induced in the individual strands due to the slot cross-eld
andend winding eld and ensures that no circulating currents will arise.
The current owing through the conductor is thus uniformly distributed over the entirebar
cross section so that the current dependent losses are reduced. At the crossover pointsputting
insulating strips of thermosetting tape reinforces the insulation. To ensure thatstrands are
rmly bonded together and to give dimensional stability in slot portion, alayer of glass tape is
wrapped over the complete stack. After that the stack is pressed andcured in steam-heated
hydraulic press. Prior to applying the bar insulation, overhangs onboth ends of the bar is
formed as an involute in hydraulic press. Coil plugs for electricaland water connections are
brazed at both the ends.
Bearings
Generator bearings are of pedestal type with spherical seating to allow self-alignment andare
supported on a separate pedestal on slip ring side and in the L-P casting on the turbineside.
The pedestal is massive steel casting providing high rigidity. Bearing bush is also ofsteel lined
with high quality white metal. Oil under pressure is supplied to bearingthrough a diaphragm
that is pre-selected to regulate the ow so as to get temperature risewithin the limit. Oil
catcher and deectors are provided to check the axial leakage of oil.Thrust bearings are
provided to control radial alignment.
Synchronizing Conditions
Phase sequence should be same.
Generator and system voltage should be in phase.
Effective value of voltage should be same.
Frequency should be same.
Generator can be synchronized in auto as well as manual mode.
Unloading and Shutdown
Reduce the load on unit by operating the turbine side controls.Simultaneously, reduce the
reactive load by de-exciting the machine.Open the generator line circuit breaker.
Cut out the auxiliary to manual mode.
Seal oil supply should be kept ON as long as gas is under pressure.
Bearing oil supply should also be kept in operation.
Generator Auxiliaries
Static System
In order to maintain system stability, it is necessary to have fast excitation system,
whichmeans that the eld current can be adjusted extremely fast according to the
changingoperating conditions. Because of these reasons, static excitation system is preferred
toconventional excitation systems.
In this system the AC power is tapped off from the generator terminals, stepped
down,rectied by fully controlled thyristor bridges, and then fed to the generator eld
winding.Any deviation in the terminal voltage is sensed by an error detector and causes
thevoltage regulator to advance or retard the ring angle of the thyristors thereby keepingthe
terminal voltage.
DRAFT FANS
When combustion takes place in the furnace, then the draft fans are used. There are threetypes
of drat fans.
1) ID fan induced draft fan
2) FD fan forced drat fun
3) PA fan primary air fan
F.D. FANS
A) FUNCTION
i) To supply air at required pressure to furnace for proper combustion.
ii) To control the quality of air furnace.
B) SPECIFICATION
1) Type - AP-118/11
Where;
AP-I-single stage axial profane bladed fan
18-nominal tip diameter of impeller in decimeter
11- nominal hub diameter of impeller in decimeter
2) No. Of fans: 2 per boiler (both running)
P.A. FAN
A) FUNCTION
1)Pa fan is a part of FD fan system i.e. it also supplies air in the furnace forcombustion air
supplied by PA fan and FD fan combine together to make total airow in furnace.
2)Air supplied by PA fan is used to dry and transport the pulverized coal from coalmill to
furnace and referred to as primary air.
B) SPECIFICATIONS
1)Type NDV 22 tie stuck
Where NDV-radius single own switch
22-nominal tip diameter of impeller in diameter
tie stack- type of diffuser.
The 415V LT supply is mostly used to run various LT motors (Wagon Tippler, BeetleCharger,
Scanner Fan, Conveyor Belt, LOP, JOP, Sump Pump, Tippler Trolley and SCRMotor) or
equipment and lighting loads at GGSSTP, Ropar. These supplies are availableat number of
Low-Tension Switchgear situated at different locations depending upon theservice required
for various equipments. There are also 415V LT buses situated atdifferent locations to run
auxiliaries for each unit. The various Low-Tension Switchgearsystems are as follows:
220V DC Buses
Unit DC buses feed the control and protection system of the unit. DC seal oil pump,
FOP(DC), LOP (DC) and JOP(DC) ofthe are also fed from unit DC buses. Control
andprotection supplies of common auxiliaries and common 415V/6.6KV buses are fed
fromstation DC bus.
Unit DC buses 5 and 6 have been divided into two sections with provision of a buscoupler
within the two sections. One section of unit DC buses is energized from. Thenormal source
i.e. from the respective battery charger while the Second section lsenergized from station DC
bus. Bus-Coupler of unit DC buses is kept open: Normalsources of control and protection
supplies of the unit are fed from rst section of unit DCbuses while the standby sources of
control or protection supplies of unit are fed from thesecond section of the unit DC buses.
Buses
Station Bus
The sources of rst 6.6 KV supply is from station transformer, which is 50 MVA,220/66 KV,
step down transformer. And takes power from 220 KV grid and feed it tostation bus of
respective stage. There are two buses per station transformer. There is onestation transformer
for each stage and the station transformer no.2 is standby for all thethree stages.
When the fault occurs in any one of the three transformers, supply is taken from thestation
transformer no.2 through the tiebreakers.
At Stage-I, Cooling Water Pump House, Coal Handling Plant, Coal Handling cum
AshHandling Bus section are fed from the station bus.
Unit Bus
The second source from which the 6.6 KV supply is taken is the Unit AuxiliaryTransformer
which is 15 MVA, 15.75 KV/6.6 KV step down transformer, which takespower from its
respective generator. There are two UAT per unit. Unit buses are fed fromthese UATs through
tiebreakers. The main load on the unit bus is the motors of the boilerfeed pump, condensate
extraction pumps, induced draft fans, forced draft fans, primaryair fans, bowl mills etc.
There is an interconnection between the unit bus and the station bus through thetiebreakers
and isolators. When unit is not running or the UAT is faulty, this breakerautomatically closes
and the breaker between the unit bus and the station bus openautomatically. In case the UAT
is faulty, the unit bus is changed over to the station bus inthe auto mode.
The load fed by HT buses (6.6KV) are as follows:
Primary Air Fan.
Induced Draft fan.
Forced Draft fan.
Coal Mills.
Boiler Feed Pumps.
Condensate Extraction Pump.
Electrostatic Precipitator Transformer.
Cooling Water Pump.
Conveyor Belts (6.6KV only).
Crushers.
Unit Service Transformer.
Station Service Transformer.
The arrangement of station and unit buses of Stage 2 & 3 is same as in the stage 1. Butthe
additional load of BCW system has come up. The load of CWP and BCW has beendivided on
the station and unit buses.
Specifications
Make ABB
MVA Rating 150MVA
Voltage 6.6KV
Breaking voltage capacity7.6KV
Current 1200A
Rated Frequency 50-60 Cycles/Sec
Specifications
MakeJoyti Ltd.
MVA Rating 145MVA
Voltage 6.6KV
Breaking voltage capacity 7.2KV
Current 1250A
Rated Frequency 50-60 Cycles/Sec.
TRANSFORMER YARD
Transformer yard is the area where different kinds of transformers have been installedwith
different functioning. Here 15.75kv generated by the generator is stepped-up to220kv for the
primary transmission, with the help of generator transformer(GT).With thehelp of unit
auxiliary transformers (UAT)the 15.75kv is steppeddown to the 6.6kv forproviding supplies
to the different unit auxiliaries. Station transformed (ST) have beeninstalled, which step down
the 220/6.6 KV is used to charge the station buses in the HTswitchgears.Unit service
transformers(UST) have been installed to step down the 6.6kvto 415v for the It auxiliaries,
like this station service transformers(SST) have beeninstalled to charge 415 volt buses for It
auxiliaries. Moreover, neutral groundingtransformers (NGT) are also there for grounding the
neutrals of the star side of thegenerator transformer, station transformer etc.
INTRODUCTION TO TRANSFORMER
Transformer is a device, or a machine that is used to step up or down the input voltageusing
electro -magnetic induction without change in supply frequency. It consists ofprimary
winding and secondary winding. Primary winding is used as an input power totransformer
while secondary winding acts as output terminal. The step up and step downtransformer are
categorized on the basis of the turns on primary and secondary side. Ifprimary winding is
having more turns than secondary winding than it is called step downtransformer and step up
in opposite case.Actually, the transformer is an electromagnetic energy conversion device,
since theenergy received by the primary is rst converted to magnetic energy and it is
thenreconverted to useful electrical energy in the other circuit (secondary winding circuitthird
winding circuit etc.) Thus primary and secondary windings of a transformer are notconnected
electrically, but are coupled magnetically. This coupling magnetic eld allowsthe transfer of
energy in either direction, from high voltage circuits. If the transfer ofenergy occurs at the
same voltage, the purpose of the transformer is merely to isolate thetwo electric circuits and
this use is very rare in power application
PRINCIPLE OF WORKING
A transformer works on the principle of electromagnetic induction. According to thisprinciple,
an e.m.f. is induced in a coil if it links a changing flux. In a transformer electrical
energytransfers from one circuit to another circuit talus place without the use of moving part
It has therefore, thehighest possible efficiency out ofall the electrical machines and requires
almost negligible amount ofmaintenance.
In core-type transformer, half of the l.v. (and h.v.) winding is on one limb and the otherhalf is
on the second limb. In shell-type transformer, the LV. and h.v. windings aresandwiched.
TYPE OF TRANSFORMERS
There are six types ofTransformers: -
l. Generator transformer (l for each unit).
2. Unit auxiliary transformer
3. Station transformer (1 for two units).
4. Unit service transformer
5. Service station transformer
STATION TRANSFORMER
When unit is not operational then, unit buses can be fed from station transformer
busesthrough the breakers and on synchronization of unit, unit board can be fed from
15mva,15.75kv/6.6kv unit auxiliary transformer. On tripping of unit. supply of respective
unitbuses, is automatically switched over to station buses, coal handling and ash handling
bussections.
SPECIFICATIONS
Made AEG ELEFUNKEN
Type of cooling ONAF/ONAN
Rated (volts) HV50000 40000
LV131500 26000
LV231500 26000
Rated current HV13.2 105
LV1 2636 21755
LV2 2636 2175.5
Frequency 50 Hz
Input to station transformer is fed from 220kv switchyard. There are two outputs of station
transformer each of 6.6kv. Normally for load beyond 45mw station transformers feeds the
auxiliaries. Above transferred to the UAT and a few one remains operating on station
transformer.
Cooling system for station transformer is oil natural air forced at 50 kva and oil natural air
natural (onan) at 40 kva and below. Oil cooling is done with the help of oil radiators an oil
pumps. Forced air cooling is done by providing the air fans on the radiators fms. There are
two sections of air fans each having 6 fans. For protection of system there are lightning
arresters at the input as well as outputs of the transformer. A lightning arrester is connected
between the phase and ground near the transformer to protect its insulation from lightning
surges and switching surges. Lightning arrester discharges the current
SPECIFICATIONS
TRANSFORMER CORE
The core of the transformer is made up of magnetic material made from cold rolled
grainoriented sheet steel to reduce losses. Lower voltage winding is placed near the core
andafter placing the insulation higher voltage winding is placed. This is done to minimize
theinsulation requirements
TRANSFORMER OIL
For high voltage transformers lapthanic base oil is used and for low voltagetransformer
parafnic base oil is used. Cost of lapthanic base oil is near to Rs. 30 perliter and for
lapthanic base oil it is around Rs. 25-26 per liter
Specications:
1. Break down voltage in KV: approximately 240 KV.
2. Resistivity: - the required value is around 0.1 x 102 Q cm.
3. Dissipation factor: - it is higher above 145 KV and has lower value below 145 kv.
4. Flash point: - as per pseb instructions, it should be above 140C.
5. Foam point: ~ as per pseb instructions, it is around 30C.
BUSHING
Bushings are placed on the outer side of the transformer for bringing out the conductingwires
from the winding. These are required as they help to maintain an insulation levelbetween
conductor and transformer body. The conducting wires from the bushing comeoutside for
further connections.
BUCHHOLZ RELAY
RADIATORS
OIL PUMPS
There are four oil pumps two of out of them are in running position two are on standby.Oil
pumps are used for circulating the oil from the transformer to radiator ns. Sinceduring the
operation the oil in use is very much heated up so it is very important tocirculate this oil and
cool it down. For generating transformer forced oil and forced aircooling is used.
COOLING FANS
The fans are intended for blowing air vertically upwards on the bank of radiators toincrease
the rate of cooling in radiators. The fan consists of a cylindrical sheet steelcasing to which
inter rotor motor is attached. There are total 22 cooling fans. These aredivided in two groups
of a, b and c, d each having 11 cooling fans. Generator transformercan work on 125 KV load
radiators without fans and oil. It can work on 175 KV load withcooling fans. It can work on
220 KV load with cooling fans and radiators.
TAP CHANGERS
The transformer output voltage and hence providing taps either on primary side or
onsecondary side can control the consumer terminal voltage. In transformer at
generatingstation, primary voltage can be kept constant, consequently the taps should be
providedon secondary side. If the transformer is energized at from a variable volt -age source,
asat the receiving end of transmission line, the taps should be provided on primary side.
DEHYDRATING BREATHERS
It gives back up protection to buchholz relay. The dehydrating breather removespractically all
moisture from the air, which ows through it into the conservator, whentransformer is
cooling. This has the effect of largely preventing any reduction ofdielectric strength of the
insulation due to moist ambient air and any formation ofcondensation in the conservator. Thus
the dehydrating breather increases the operationalintegrity of the transformer.
There are two types of dehydrations: -
l. Nitrogen gas is lled with cylinders in conservator tank to avoid moisture.
2. In this case silica gel breather passes air, which goes to conservator, passedthrough the
breather containing silica gel.
As silica gel goes on consuming its color goes on changing from blue to red.Dehydrating
breather operates on the pressure of 0.42kg and is of diaphragmconstruction.
Apart from these above-mentioned protections, there are other protections also likedifferential
protection, over current protection, over temperature protection and lightningarresters etc.
Oil Natural Air Natural (ONAN) In this type of cooling systems, oil aswell as air ows
naturally.
Oil Natural Air Forced (ON AF) When loud on the transformer is between125 MVA to 180
MVA this type of cooling is provided. As natural air is not soefcient to cool down the oil and
bring it to safe limits. So air is forced on theradiating ns with the help of fans installed below
the radiator ns.
Oil Forced Air Forced (OFAF) With further increase in load, more heat is generated,which
necessitates forced cooling of oil. This is achieved by energizing the pumps placedat the
bottom near the main tank. These pumps force the oil to ow frequently throughthe radiating
ns for cooling of the transformer.
BUS SYSTEM
Conductors to which a number of circuits are connected are called bus bar. Buses are provided
for the transmission of electricity from supply to various sub-stations.
BUS COUPLER -I can be used as G.T. breaker for units 1, II, III.
BUS COUPLER -II can be used as G.T. breaker for units IV, V,VI.
Circuit Breakers
Circuit Breakers are the switches used to break the electrical circuits Onload by manual
for automatic operation. They differ from conventional switches in the manner that circuit
breakers are very sophisticated switches, which can limit the fault current and are generally
used for high voltage and high current operations.
We have 2 type of Circuit Breakers at Switchyard:
1. ABCB (air blast circuit breaker, for unit 1 &2)
2. SF6(sulphur hexaouride breaker, for unit 3, 4, 5, 6)
ABCB
It is an air blast circuit breaker, here closing, tripping and quenching is done withthe help of
air. When contacts are separated arc is struck, simultaneously the blast valve is opened The
blast cools the arc and sweeps away the ionized medium between the contacts. Thus the arc is
extinguished and current is interrupted.
SF6 BREAKER
In this case closing is done with the help of a spring. Tripping is done with the help of air,
quenching is done by SF6 gas. Under normal conditions the moving contact is connected with
the xed contact. The movable cylinder is coupled with the moving contact. When the moving
contact is separated from the xed contact the arc comes into play but due tocompressed
sulphur hexauoride, this arc gets extinguished. To avoid the condition of closing of two
breakers, two isolators are automatically opened
ISOLATORS
Isolators are used for making and breaking the contact but this can be done without load. It is
just like a switch, when main contact is made b/w springs an arc is produced. In isolators,
parallel operation is possible. Never on or closes the isolators while on load. There are four
jaws, two for input supply and two for output supply, i.e. supplying cables containers under
pole parts contain transfer oil. The current capacity of isolator is 1200 amp and they are of
double break type. A d.c. motor working on 110v carries out their operation. They can be
operated from local as well as from remote control.
Isolators are of two types:
a. Off load isolators.
b. On load isolators.
Earthing switches are mounted on isolating switches base on line side. Earth usually
compromises a vertical break switch arm with contact at extremity which engages with
isolator contact on line side.
CT has ve secondary cores which are used for different purposes such as, formeasurement of
current, for protection etc. CT is connected in series before load in any of the three phases
POTENTIAL TRANSFORMER
Made Nagpur transformers ltd.
Insulation level 460/1050 kv
No. of Phases 1
Frequency 50 hz
Highest system voltage 245 kv
Voltage factor 1.5 for 203cc
Neutral earthed
Adopted ratio 220 kv/l10 v
PT is always connected in parallel between any two phases but here in the switch yard
only one phase is connected to PT and other terminal of PT is connected to earth.
BATTERY ROOM
COMPRESSOR ROOM
Compressors are installed in the compressor room in the substation. The function ofthese
compressors is to supply pressurized air for the circuit breakers. There are fourcompressors
out of which three works at a time and one is on standby. The compressorsare capable of
generating the air pressure of 60 kg. This compressed air is then passedthrough silicon valve
and lters to remove any moisture contents. After that air pressureis reduced to 31 kg., which
is suitable for the operations of circuit breakers.
CONTROL ROOM
All the apparatus installed at the substation can be controlled in two ways; one ismanually at
local and second is by automatic at remote control. Control room consists ofvarious control
panels including metering equipments, relays and protection equipments.
All the activities of substation can be monitored by the control room and can becontrolled by
using it.
All the controls installed in substation are 220 volts D.C. operated. The control panel
alsoshows Visually the operation of various circuit breakers. All the relays and
protectionsystems are installed on the secondary side of the current transformer and
potentialtransformer. All the cables laid to the control room are underground and are
passedthrough concrete ducts. The network of grounding wires to protect the bus bars, lines
andother installed equipments from lightening hazards, surrounds the entire substation.
FEEDER PROTECTION:
Overcurrent protection
Earth fault protection
Distance protection
Differential protection
Carrier current protection
After tripping of turbine the forward power ow will become zero, since the generator isstill
connected with system, it will draw power from the system; when reverse powerows (the
power ow towards generator) becomes more than 1 MW, then after twoseconds the reverse
MOTOR PROTECTION
All motors whether L.T to be protected against various abnormal conditions mentionedbelow:
a) Over load or over current
b) Short circuit or insulation failure
c) Earth fault
d) Over voltage
e) Low voltage
f) Single phasing.
Several protective relays are provided. The relays sense the abnormal conditions & closethe
trip circuit of motor circuit breaker. Thus, the breaker trips to isolate the motor from A.C.
supply.
DIFFERENTIAL PROTECTION
This is an additional protection provided in case of H.T motors above 1000 kw rating. Atthe
plant, ID, PA and BFP motors have been provided with this protection.The differential relay
operation responds to the vector difference between currententering the stator winding and
current leaving the stator winding of motor.
The C.Ts are connected in star in both sides of the stator winding of motor. Duringnormal
condition and external fault the protection system is balanced and C.Ts ratios ofboth sides
match each other so that secondary currents are equal, and relay does notoperate.
Electrostatic precipitator (ESP) is that unit of ash handling plant that collects the ash with
the help of electric eld, using electrodes.
SPECIFICATIONS
BASIC THEORY
An ESP controls particulate emissions by: (1) charging the particles, (2) applying an electric
field to move the particles out of the gas stream, then (3) removing the collected dust.
Particles are charged by gas ions that are formed by corona discharge from the electrodes. The
ions become attached to the particles, thus providing the charge.
PARTICLE CHARGING
As particles move through the electric field they acquire an electrostatic charge by two
mechanisms, bombardment charging and diffusion charging, as illustrated in Figure 21. Both
types of particle charging act simultaneously, but bombardment charging is of greater
importance for larger particles and diffusion charging is more important for submicron
particles. The magnitude of the charging for both mechanisms is lowest for particles in the
size range of 0.1 to 1 microns, therefore, the minimum collection efficiency will occur for this
size range. However, a well designed ESP will be capable of collecting greater than 90% of
even these difficult to collect particles.
Bombardment charging is of primary importance for particles greater than 1 micron. Ions and
electrons move along the lines of force between the electrodes normal to the direction of flow
of particles in the gas stream. Some of the ions and electrons are intercepted by uncharged
particles, and the particles become charged. Because the particles are now charged, ions of
like charge are now repulsed by the particle, thus reducing the rate of charging. After a time,
the charge on the particles will reach a maximum that is proportional to the square of the
particle diameter. Because extremely small particles (less than 0.1 micron) have an erratic
path in the gas stream due to Brownian motion, they can acquire a significant charge
bydiffusion charging. Thus, an ESP can be an efficient collection device for submicron
particles. However, these
PARTICLE MIGRATION
Most charged particles migrate under the influence of the electric field towards the plate,
although a few particles in the vicinity of corona discharge will migrate towards the wire. The
presence of charged particles in the gas space affects the overall electric field. Near the plate,
the concentration of charged particles will be high, and interparticle interferences can occur.
Finally, particles will collect as a dust layer on the plates, and a portion of their charge may be
transferred to the collecting electrode. Ideally, charged particles will migrate to the plate
before exiting the ESP, as illustrated in Figure 22, and will stick to the dust layer on the
collecting electrode until it is cleaned. When the plate is rapped, the dust layer should fall as a
sheet into dust collection hoppers without re-entraining into the gas stream.
The velocity at which charged particles migrate towards the plate can be calculated by
balancing the electrical forces with the drag force on the particle moving through the flue gas.
The electric field produces a force on the charged particle proportional to the magnitude of the
field and the charge:
After applying these simplifying assumptions, the migration velocity for particles larger than
1 micron charged by bombardment charging is calculated using
Equation 2:
where
D = dielectric constant for the particle
e= permittivity, 8.8541012 coulombs/volt-meter
Ec = strength of the charging electric field
Ep= strength of precipitating (collecting) electric field
Dp= particle diameter
g= gas viscosity
C= Cunningham slip correction factor
DEUTSCH EQUATION
Using the migration velocity to complete a material balance for particles moving toward the
ESP plates and particles being carried through the ESP with the gas flow, a common
description of particle collection efficiency for mono disperse (same size) particles can be
derived:
where
= fractional collection efficiency
= migration velocity
A = plate area
Q = volumetric gas flow
Any consistent set of units can be used for , A, and Q. The expression A/Q is the specific
collection area (SCA) of the ESP, commonly expressed as square feet per thousand actual
cubic feet per minute (ft2/kacfm). When calculating plate area, remember that the surface area
of interior plates includes area exposed to gas flow on both sides of the plate, while the two
exterior plates are exposed on only one side. An inherent assumption in the Deutsch Equation
is that when particles reach the plates, they are permanently removed from the gas stream.
This assumption works reasonably well for low-efficiency ESPs. However, when the
collection efficiency is high (greater than 99%), mechanisms other than balancing migration
velocity with treatment time dominate the particle emissions. Sneakage, rapping
reentrainment, scouring re-entrainment, low-resistivity re-entrainment, and poor gas
distribution can become controlling non-ideal effects that limit collection efficiency. For very
high efficiency ESPs, empirical modifications of the Deutsch Equation have been used to fit
observed data. These include the
Rapping Re-Entrainment
Another non-ideal effect in a dry ESP is rapping re-entrainment. The dust layer of collected
particles on the collection plates is knocked loose periodically by rapping or knocking the
plates, often with a trip hammer. Most of the dust falls as a sheet into collection hoppers, but
some particulate is re-entrained into the gas stream. Factors affecting rapping re-entrainment
include the aspect ratio of the ESP (length of the ESP divided by plate height), rapping
intensity, dust cohesivity, and dust cake thickness (rapping frequency). With a low aspect
ratio, dust has further to fall to reach the hopper before it would exit the ESP.
Particles in a cohesive dust cake will tend to stick together as a falling sheet when the plates
are rapped. This minimizes re-entrainment. The rapping intensity needs to be strong enough to
shear the dust cake from the plate, but not strong enough to produce a cloud. Increasing dust
cohesivity with conditioning additives is one of the primary mechanisms for improving fine
particle collection.
The frequency of rapping should be adjusted to allow a sufficient dust layer to accumulate so
that the layer will fall as a cohesive sheet. Experimental studies with fly ash have shown that a
re-entrainment cloud forms when the plate loading is below 0.1 g/cm2, while the dust layer
develops a more cohesive sheet when rapped at a higher loading. However, if the dust layer
becomes too thick, it can act as an insulator and cause a potential gradient to build up within
the layer. This reduces the electric field strength in the gas space, and could lead to sparking
within the dust layer with subsequent re-entrainment.
Particulate Resistivity
Once particles reach the dust layer on the collecting electrode, they must stick to the surface
until it is cleaned. This is not a problem in a wet ESP because the particle sticks to the wet
collection surface until they are washed off by flushing. But in a dry ESP, re-entrainment
Figure 23: Comparison of Potential Gradient In Clean Vs. Dust Laden Plate
efficiency when re-entrainment is a factor, the ESP must be oversized to allow particles to be
captured again. The forces that hold particles onto the plate include molecular adhesive forces
of the London-van der Waals type and electrostatic forces. The optimum resistivity for good
removal in a dry ESP is approximately 1109 to 11010 ohm-cm.
When charged particles arrive at the plate, they are partially discharged. Theextent of
electrostatic adhesion depends on the rate at which charge leaks away fromthe particles,
which depends on the resistivity of the dust layer. The resistivity of some dusts, including lead
smelter fume and coal-fired-boiler fly ash from low-sulfur or alkaline coals, is relatively high.
When the resistivity is high, the rate of discharge from the collected particle layer is low. A
potential gradient builds up within the layer of collected particles.
Figure 23 illustrates the potential gradient as voltage vs. distance between the discharge and
collection electrodes. Two points on the curve are fixed. The discharge electrode is charged to
the maximum voltage for the limits of the power supply. The collection electrodes are
grounded. Without a resistive dust layer, the potential gradient will appear as in Figure 23,
with the greatest gradient at the discharge electrode where corona is formed. Figure 23
illustrates the effect of a highly resistive dust layer. A substantial portion of the voltage drop
occurs across the dust layer, leaving a reduced potential gradient across the gas space. With
the lower gradient, the driving force for particle migration is reduced. If the dust resistivity is
where
e= resistivity
A = constant
E = electron activation energy (a negative value)
k = Boltzmanns constant
T = absolute temperature
Thus, resistivity decreases as temperature increases.
At lower temperatures, less than 200F, surface conduction is the predominant mechanism of
charge transfer. Electric charges are carried in a surface film adsorbed on the particulate. The
presence of moisture increases surface conduction. Humidification of the flue gas upstream of
Gas-Flow Distribution
An idealized assumption that is used when applying the Deutsch Equation is that the gas flow
and the particulate concentration in the gas are distributed uniformly. Customized flow vanes,
baffles, and/or perforated-plate gas distributors often are used at the inlet to produce uniform
flow. Sometimes these devices are used at the outlet also. A typical specification for uniform
flow distribution requires that 85% of the velocity distribution is within 1.15 times the
average velocity, and 99% of the velocity distribution is within 1.40 times the average
velocity.
Two approaches are used to ensure uniform velocity distribution: scale-model studies and
Computational Fluid Dynamics (CFD) modeling. CFD modeling is relatively new, but is
becoming common as software, computing power, experience, and availability have enabled
this tool to be used in a variety of fluid-flow applications. Although uniform gas distribution
is generally accepted as the ideal gas flow distribution, computer modeling and a full-scale
demonstration at a coal-fired power station in South Africa show that a skewed distribution
reduced particulate emissions by more than 50%.
In this patented configuration, the inlet flow distribution is skewed with low flow at the top of
the precipitator and higher flow at the bottom
At the outlet, the gas flow is skewed with high flow at the top of the precipitator and low flow
at the bottom, as shown in Figure 24. This distribution utilizes the fact that collected dust
exits the precipitator by falling to the bottom. Dust cake dislodged by rapping is less likely to
Having the effective migration velocity enables sizing the required collection area for the
desired efficiency under similar conditions, bearing in mind the simplifying assumptions and
limitations of the Deutsch Equation discussed previously.
HUMIDIFICATION
Cooling a hot flue gas stream by evaporating a spray of fine water droplets produces a net
decrease in the gas volumetric flow rate, increases the gas density, increases the moisture
content of the gas stream, and reduces the particulate resistivity. Increasing both the gas
density and the moisture content, increases the spark-over voltage at which the gas breaks
down. Therefore, higher field strength can be achieved before spark rate limits further voltage
increases.
A key concern with spraying water droplets is that the water droplets are completely
evaporated before they impact the interior surfaces in ductwork. If water wets the walls of the
ductwork, particulate may stick and accumulate and corrosion may be accelerated rapidly.
Generally, at least 1 s residence time for drying in a straight section of duct is desired for a
fine spray with a Sauter mean diameter of 50 microns. Dual-fluid atomizing nozzles are
typically used to achieve the fine spray, because high-pressure hydraulic nozzles would
require 500 to 5000 psi with very small orifices that are prone to plugging and wear.
AMMONIA
Addition of ammonia or ammonia compounds is another method of conditioning that has been
used to improve ESP performance, particularly in the petroleum refining industry on fluid
catalytic cracking (FCC) units. Catalyst dust from FCC units typically has a high resistivity.
Several hypotheses for the mechanism for improved ESP performance by NH 3 conditioning
have been proposed. Explanations include neutralization of sulphuric acid in the case of low-
resistivity fly ash; reduction of back corona as characteristics of the gas are changed; and
higher voltage operation due to an enhanced potential gradient resulting from space charge
effects.
The presence of very fine ammonium sulfate particles produced by the reaction of ammonia
and SO3 increases space charge, which would decrease the electric field strength near the
corona discharge and allow a steeper gradient near the collecting plate. Although excessive
space charge can lead to corona quenching, moderate space charge produces a higher driving
force for particle migration outside of the corona discharge region. The space charge effect
can be beneficial when the enhancement in the collecting electric field more than compensates
for the decreased corona discharge. Another explanation is that ammonia reacts with sulfuric
acid mist in the flue gas, forming ammonium bisulfate, NH4HSO4, and ammonium sulfate,
(NH4)2SO4. Ammonium bisulfate is deliquescent (absorbs water readily, then dissolves in the
INTRODUCTION
Effective control of the power applied to an electrostatic precipitator is essential in optimizing
its performance. Since the power level at which the electrostatic precipitator s performance
will be optimized is constantly changing, it is important that the high voltage control system
quickly and accurately adjust power levels so that optimum power is maintained.
Special functions and integration to centralized monitoring data recording and reporting
systems are readily achievable. Intermittent energization or power modulated precipitation
can be utilized. Data is reported to a central monitoring unit (CMU) which make possible the
reproduction of secondary voltage and current waveforms on the cathode ray tube (CRT)
display of the CMU.
The functions that a microprocessor must perform to ensure that the high voltage
control operates in an optimum manner will now be reviewed.
CONTROL FUNCTIONS
The primary control function is to optimize the collection efficiency of the electrostatic
precipitator. This is achieved by operating at the maximum sustainable power level. This
power level comprises the voltage and current levels that are slightly below the level which
will cause a breakdown of the electric field in the form of a spark. If the conditions at which
sparking occurs were constant the control of power levels to the precipitator would be quite
simple. However, the maximum power level achievable depends upon a set of constantly
changing variables.
Power Optimization
Microprocessor based control systems must be capable of analyzing and responding to these
changing conditions in real time so as to ensure that maximum electrostatic precipitator
collection efficiency is maintained. In order to achieve this, the control must effectively
perform several functions. First, the control must constantly check to determine the maximum
power level that is achievable. This is accomplished by comparing operating information to
historical data and other preprogrammed control performance data. If a spark does occur, the
process of extinguishing the spark and returning to the optimum power level must be as rapid
as possible. Also, the spark must be identified as self extinguishing or nonself
extinguishing. If the spark is self extinguishing, the power level can be returned close to the
pre-spark power level in the next half cycle of operation. Should the spark not self extinguish,
the control must turn off power for one half cycle in order to extinguish the spark. In the next
half cycle of operation, the alternating current (AC) side of the transformerrectifier will
have the same polarity as the half cycle in which the spark occurred and energization to a high
power level would saturate the transformer and induce another spark. This condition is
effectively avoided by control design so that re-energization occurs in the following half cycle
of operation. The power level that the system is energized to will then be as close to the pre-
spark power level as possible. A simplified control logic for power optimization is shown in
Figure 25.
The secondary voltage waveform will indicate when a back corona condition occurs. The
voltage at the onset of conduction, that is the point where the positive slope of the voltage
waveform begins, will decrease in each ensuing half cycle of operation. This is due to the fact
that as back corona continues to increase in intensity the equivalent resistance in the RC
constant changes, the voltage decays more rapidly with time, and conduction begins sooner in
each ensuing half cycle of operation. By monitoring the secondary voltage and current
waveforms, it is possible to detect the presence of back corona. Power levels can then be
adjusted so that the operation of the system is at its optimum point, just below the onset of
back corona. waveforms that are typical of back corona are shown in Figure 26.
To appreciate why precipitator power consumption and performance are affected by IE, it is
necessary to understand the basic principles of IE. Simply, IE modifies the energization of the
precipitator by normally energizing the precipitator for one or more half cycles and then not
energizing the precipitator for a series of half cycles. Figure 27 shows typical oscilloscope
tracings of secondary voltage and current for normal energization and for a one in five (one
half cycle on, four half cycles off) mode of IE. Two items to note are the peaks of the voltage
and current and the manner in which secondary voltage dissipates until the precipitator is re-
energized. In typical cases of high resistivity dust, the peak voltages that can be obtained with
IE are much higher than in cases of conventional energization. This is due to the fact that the
maximum voltage is normally limited to the value .At which back corona is induced. By not
energizing the precipitator for several half cycles in an IE mode of operation the ions
produced during the energization have more time to dissipate through the dust layer. Thus
when the precipitator is again energized it can be at a much higher voltage level without
causing back corona. The average voltage is increased and thus the precipitator efficiency is
increased
In cases of moderate resistivity, the voltage peaks are also increased slightly. However, the
voltage dissipates to a noticeably lower level than during conventional energization. The
result is very little change in the average voltage levels, and thus the collection efficiency of
the precipitator remains unchanged.
With the advent of economical 16 bit microprocessor circuits, it has become feasible to re-
focus the high voltage control design approach by transposing more of the control and
integration functions from circuitry to program instructions. This approach, in addition to
reducing the number of components and improving reliability can support a wide range of
control philosophies. The primary benefit of this type of control is the ability to modify any
control operation through the software. The hardware becomes a true servant of the operation
and is not solely designed for any specific function. A second benefit of this type of design is
the ability to reconstruct operating waveforms from the memory of individual controls which
then can be transmitted to a remote display. allowing for oscilloscope waveforms to be
available and recorded during any operating period without additional test equipment.
These waveforms also provide detailed information which allows the microprocessor to fully
analyze the operation of the system. The advent of integrated circuitry with the necessary
speed and power has permitted this method of operation to be truly realized.
Design considerations to support this mode of operation and monitoring are primarily
concerned with data acquisition without integration or modification, sufficient speed of
operation to allow all data to be timely refreshed, program benchmarks at fundamental power
frequencies and scaled functions thereof, and algorithms developed solely to make full use of
dynamic waveform availability.
Circuitry Considerations
The signals which must be monitored and used for control include the following:
2. Primary current, linked through a current transformer and presented to an analog to digital
converter as a rectified but unfiltered signal.
3. Secondary voltage, derived from a voltage divider and presented to an analog to digital
4. Secondary current, derived from applying the voltage across a resistor to an analog to
digital converter as an unfiltered signal.
5. Reactor voltage, linked through a potential transformer and presented to an analog to digital
converter as a rectified but unfiltered signal.
These signals are level translated through circuitry with a band width of at least one
megahertz. The rectification of the AC signals is primarily to expand the range of the analog
to digital converter as the zero crossing of these signals should remain constant.
Circuitry is incorporated to notify the program when different timing benchmarks have
transpired; the most common of these benchmarks being the zero crossing of the input power
line. This is coordinated with a higher frequency benchmark to represent the maximum
sampling rate with which to decipher the input waveforms. This frequency is high enough to
allow a maximum of 1 degree of silicon controlled rectifier (SCR) angle per increment of
timing. This benchmark is used for SCR output and also to digitize the input signals into
frequency points during each half cycle of line operation.
Metering
The signals in memory are used for local and/or remote metering. Each half cycle's number of
readings for each point must be averaged and combined with the average of other half cycles
to arrive at a smooth value to be used for operator interface. Normally the total number of half
cycles to be averaged is operator set allowing for personal preference. The primary voltage
and primary current are coordinated with the operating phase angle of the SCR's to arrive at
an RMS value for each level.
Such a system of metering and data retrieval separates average voltage or current readings for
each half cycle. This allows the control to separate the displayed currents in each rectifier leg
even though the transformerrectifier has no provisions for independent metering of each
leg. Only one secondary current metering wire is required.. These readings are sensitive to
SCR unbalance or an unsymmetrical power source, allowing for better annunciation of
possible problems. The metering will display peak voltages and currents for any half cycle
System Control
The digitizing of the phase angle and zero crossing allows for the SCR's output and the
metering input to be placed in phase with the operation by delaying the zero crossing in the
program based on the size of the reactor and the delay it presents. The inductance of the linear
reactor causes a phase lag in the voltage applied to the transformer rectifier which also limits
the available control range of the SCR's. Proper framing of the firing angle to the SCR's
prevents this from occurring. Digitizing the phase angle provides for all secondary
information to be properly stored in memory and recalled for the appropriate half cycle.
Having peak and valley information available for the secondary high voltage allows the
control to operate around an acceptable ratio of change between the peak and
valley to further detect the presence of back corona. This is evaluated against
different time frames for more accurate detection of back corona activity.
Spark rate limits have proven to reduce control capabilities and cause severe degradation of
applied power simply to satisfy a preset spark limit. A more reliable system is to weigh the
spark rate, but also keep close records of different operating currents prior to spark initiation
and use these for short range goals in the neverending search for greater secondary voltage.
This spark current limit, sometimes called a floating current limit, makes the control's
operation truly independent of gas conditions.
In the light of the presented theory of working and its application to control efficiencies of
ESP, it can be chalked out that the two most viable processes for increasing efficiencies are:
Gas Conditioning
Microprocessor Control System
The scheme of gas conditioning (by Ammonia or SO3) to boost efficiencies has proved to be
economically unviable according to past field experiences, on the account that such schemes
would require continuous running , amounting to huge expenditure in terms of chemical cost
and running cost and in addition imposing a menace of chemical decomposition, hence
rendering it economically unviable.
On the other hand the microprocessor control scheme is inherently dynamic and requires little
modification to existing system for its implementation hence making it economically more
feasible than other control schemes for improving efficiencies. The unique features of
advanced microprocessor control scheme can be summarized as-
Accurate Back Corona Detection
Power Optimization By Power Modulated Precipitation
Remote Monitoring of actual field operation
All these features effectively summarizes the advantage of using the presented control scheme
to meet efficiencies requirement.
The current efficiencies of stages 1,2 and 3 of GGSSTP Ropar ESPs are close to 99.5%,
hence the scope of improvement of ESPs efficiencies is very bleak. However, in future if
more stringent norms for pollution control are imposed by Ministry of Environment and
Forest India, the implementation of presented scheme of advanced microprocessor control
will successfully boost efficiencies up to 99.6-99.7%
It is important to mention that presented control scheme may be employed for modification of
stage 3 ESPs unit(s), as already been implemented in Stage 1 and 2 in the past. Features like
Accurate Back Corona detection and its removal will improve the efficiency of ESPs
consequently optimizing power and making Stage 3 ESP unit(s) to come at par with other two
stages in terms of operating efficiencies.
REFERENCE: