Scope of Works
Asphalt removal and reinstating for the restoration of cable fault at Al Dhafra Air Base
Description of Works
Villa Area.
Compliance N/A
a. Company profile
b. Technical and financial proposal
Deliverables
c. Method statement to be submitted for approval
d. Provide service reports after completion
Details of work:
Cable fault identified on 11KV ring inside villa area at Al Dhafra air base. The exact fault location
point is traced beneath a road in villa area. Asphalt for 25 Sq.M should be removed for proper
access to the cable. As multiple cable passes through nearby cable duct/sleeve, an identification
to be conducted for live status. Two numbers of 11KV, 3Cx240 Sq. mm CU/XLPE/SWA cable
straight through joint kit to be provided for rectification. A length of 5 meter should be cut with
fault point at center for apply of joint. New cable should be pulled through the duct/sleeve.
Bill of Quantity:-
S.No. Work Description Quantity Remarks
1. Removal of asphalt 25 Sq.M.
2. Reinstate of asphalt 25 Sq.M.
3. Supply of 11KV, 3Cx240 Sq. mm
02 Nos
CU/XLPE/SWA Cable straight through joint kit
4. Apply of 11KV, 3Cx240 Sq. mm CU/XLPE/SWA
02 Nos
Cable straight through joint kit
5.
6