Вы находитесь на странице: 1из 39

TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev.

TABLE OF CONTENTS

1.0 SCOPE

2.0 LINE ROUTES

2.1 Location
2.2 Paralleling and Crossing Transmission Lines
2.3 Paralleling and Crossing Major Highways
2.4 Vertical Clearances above Ground, Road Crossings and Paralleling, Crossing of Rail
Road

3.0 GENERAL GUIDE LINES FOR METALLIC FACILITIES LOCATED IN PROXIMITY


OF TRANSMISSION LINES ( INDUCED / CONDUCTIVE VOLTAGE
INTERFERENCES)

3.1 Inductive & Conductive Voltage Requirements


3.2 Paralleling Facility (Induced Voltage Case)
3.3 Crossing Facility (Conductive Voltage Case)

4.0 SPACING FROM MAIN OIL FACILITIES

5.0 CONDUCTOR SPACING AND CLEARANCE

5.1 Clearance between Phase Conductors on the same Support


5.2 Vertical Clearance between Line Conductors.
5.3 Clearance of Conductor from its own Support - Basic Clearance.
5.4 Clearance between Phase Conductors carried on different Supports
5.5 Clearance of Conductors from other supporting Structures
5.6 Clearance of Conductors from other Installations
5.7 Midspan Clearance
5.8 Air Gap Requirements

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 2 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

6.0 RIGHT-OF-WAY WIDTH REQUIREMENTS

6.1 General
6.2 Conductor Clearance to edge of Right-of-Way
6.3 Right-of-Way Width Requirements for Single Transmission Line
6.4 Right-of-Way Width Requirements for Parallel Transmission Lines
6.5 Example Calculation of Right-Of-Way

7.0 BIBLIOGRAPHY

FIGURE TE-2209-0100-00 Clearance Requirement for Conductors of Same Circuit or Different


Circuit on the Same Support

FIGURE TE-2209-0200-00 Clearance Requirement for Conductors from other Circuits and
Right-Of-Way (ROW) for Single Transmission Line

FIGURE TE-2209-0300-00 Clearance Requirement between Conductors on Different Supports


and Conductors from other Supporting Structures and Right-Of-Way
(ROW) for Two Parallel Transmission Lines

FIGURE TE-2209-0400-00 Right-Of-Way (ROW) Requirement for Two Parallel Transmission


Lines

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 3 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

1.0 SCOPE

The purpose of this standard is to highlight Saudi Electricity Company (SEC), Saudi Arabia
practices with respect to clearances required for various paralleling and crossing facilities
and right of way requirements.

2.0 LINE ROUTES

2.1 Location

2.1.1 Transmission lines shall be located as near as possible to roads for easy
accessibility during construction and later for inspection, insulator
washing, maintenance and repair. Obstacles such as high hills, wadis,
water flooding areas, swampy ground or poor soils shall be avoided.
Selection of routes shall also take into account grade and conditions of the
terrain to be traversed.

2.1.2 Selection of final route for any transmission line shall be coordinated with
the concerned SEC departments.

2.1.3 Coastal or corrosive atmosphere areas shall be avoided wherever possible.


Whenever it is not possible suitable protective measures shall be adopted in
the design of transmission line components including foundations to
combat the corrosion.

2.2 Paralleling and Crossing Transmission Lines

2.2.1 Adequate clearance shall be provided between parallel and crossing


transmission lines. Clearances between adjacent conductors of two parallel
lines and clearances between crossing lines shall be established per
equations 09-1 to 09-19.

2.2.2 Crossing lines shall be arranged so that the higher voltage line or line of
higher security crosses over the line of lower voltage or lower security. It is
preferable that transmission lines shall cross each other at right angles.

2.2.3 The vertical clearance between any crossing lines carried on different
supporting structures shall not be less than those given in Table 09-13.

2.3 Paralleling and Crossing Major Highways

2.3.1 Major highways are defined as any primary or secondary roads which are
normally accessible to traffic with no restriction. Minimum clearances
from the nearest conductor to edge of major highways for restricted and
unrestricted rights of way are given in Table 09-1.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 4 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-1: Minimum Distance from nearest Conductor to edge of Major Highways

Voltage, (kV) Right of Way Not-Restricted, (m) Right of Way Restricted, (m)
69 18
110 25
Maximum Height of
115 Transmission Line Structure 25
132 Plus 5 meters 25
230 30
380 40

2.3.2 Where transmission line routes cross major highways, the angle of
intersection shall be as near as possible to 90 degrees and if not possible,
the angle of intersection shall be between 45 to 135 degrees. The edge of
the nearest transmission line structure foundation shall not be closer than a
distance equal to the maximum height of the structure installed when
measured from the edge of zone of major highways.

2.3.3 When paralleling roads other than major highways, especially roads in
urban areas, lesser clearances than required by paragraph 2.3.1 are
permissible between roads and transmission lines provided that public
safety and safety & reliability of the lines are not affected. When
necessary, the line structures shall be protected by providing crash barriers
around them without jeopardizing access to the line for maintenance. These
protective measures shall be considered individually on a project basis for
their effectiveness.

2.4 Vertical Clearances above Ground and Road Crossings and Paralleling, Crossing of
Rail Road

2.4.1 Vertical clearance is defined as the vertical distance between the highest
point on terrain (grade, road surface, rail road, rail etc.) and the lowest
conductor of the overhead lines. Calculation of actual line clearance at
final tension shall be based on a temperature of 80C for ACSR & AAAC,
85C for ACAR and 93C for ACSR/AW conductor. Grading of existing
natural ground level to meet the vertical clearance requirements shall not
be acceptable unless otherwise approved by SEC.

2.4.2 The minimum vertical clearances required for SEC transmission line
designs for 380 kV and below over various types of roads and terrain are
given in Table 09-2 and shall be followed unless otherwise specified in the
approval letters of different approval agencies involved.

2.4.3 Roads to be crossed by SEC transmission lines have been categorized as


A, designated high clearance roads; and B, for other roads not
requiring high clearance.

2.4.4 There are some areas where certain road crossings shall require additional
clearance. The extra high clearance roads in the industrial areas such as
Jubail, Dammam, Yanbu, etc. may require a vertical clearance in the range
of 18-21 meters above roads or highways.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 5 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

2.4.5 The category of roads to be crossed by the transmission line shall be


determined during base design stage and in case of module paths the
concerned authorities shall be contacted to coordinate the vertical clearance
requirements.

2.4.6 Highways and roads designated to be used for hauling heavy and oversized
loads are classified as Category A. All other roads, highways and
expressways are classified Category B.

2.4.7 On projects where the transmission line is determined to be extremely


important (such as 230 kV and 380 kV System) and power interruption can
not be tolerated, then all roads to be crossed by this line shall be considered
as Category A roads, and the Project Scope of Work and Technical
Specifications for such a project shall explicitly state this requirement.

2.4.8 The road clearances in this Standard for designated high clearance roads
and expressways and highways considerably exceed the minimum
requirements recommended by the NESC for vertical clearances above
roadways.

2.4.9 The vertical clearances over the type of terrain not covered by Table 09-2,
such as canals, waterways, terrain in the vicinity of airports or any unusual
situation which might be developed, shall be resolved separately and
mutually agreed to by interested parties.

Table 09-2: Minimum Vertical Clearances for Roads and Terrain Crossings (see note 5)

Transmission Voltage (Line to Line)


Category Type of Crossing
69kV 110kV 115kV 132kV 230kV 380kV
(m) (m) (m) (m) (m) (m)
Designated High
A. 14.0 14.0 14.0 15.0 18.0 18.0
Clearance Roads (1)
Expressways &
B. 12.0 12.0 12.0 13.0 15.0 15.0
Highways
City Streets, Alleys
Driveways, Parking
Lots & Other Areas
C. 12.0 12.0 12.0 13.0 15.0 15.0
Traversed by
Vehicles, Paved or
Unpaved
Open Terrain, Desert
D. 7.5 7.5 7.5 7.5 8.0 10.0
Areas, etc (3, 4).
E. Railroads (2) 15.5 15.5 15.5 16.0 18.0 18.0
Ground Facilities,
Pipelines (Oil, Water,
F. 9.5 9.5 9.5 9.5 9.5 13.5
Gas) &
Communication lines
Notes:

1. Roads categorized as A are those specifically designated by SEC Lines Maintenance


Department as roads requiring vertical clearance in excess of clearances listed in Category

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 6 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

B and C. Vehicle traffic is expected to exceed 5.5 meter height and the transmission
lines need not normally be removed from service.

2. Assumed height of the rail car is 6 meters.

3. For transmission lines when located in open terrain within 5km and 2km from the
boundary limits of cities/towns and villages respectively, the required clearances listed
under Category D shall be increased by a minimum of two (2) meters.

4. When transmission lines are located in desert area affected by shifting sand dunes, the
clearance listed in Category D shall be increased by a minimum of two (2) meters in the
spans indicating shifting sand dunes.

5. The clearances shall be increased @ 3 % for each 300m in excess of 1,000m altitude
above mean sea level.

2.4.10 Paralleling and Crossing Railroads

a. Minimum clearances from the nearest conductor to edge of the


rail track for restricted and unrestricted rights of way are given
Table 09-3.

b. Where transmission line routes cross railroad tracks, the angle of


intersection shall preferably be 90 degrees and if not possible, the
angle of intersection shall be between 70 to 110 degrees. The edge of
the transmission line structure foundation shall not be closer than 50
meters on 69kV through 380kV transmission lines to the edge of the
railroad track.

Whenever the required crossing angle is not satisfied, the Engineer


responsible for base design/detailed engineering shall perform an
induced voltage study and recommend possible steps to be taken to
reduce any adverse effects.

c. The minimum vertical clearances required for SEC transmission


lines for 69 kV to 380kV, over the railroad tracks are given in
Table 09-2.

Table 09-3: Minimum Clearances for Paralleling of Railroad

Voltages, (kV) Right-of-Way


Unrestricted, (m) Restricted, (m)
69 40 25
110 40 25
115 40 25
132 40 25
230 40 30
380 40 40

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 7 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

3.0 GENERAL GUIDELINES FOR METALLIC FACILITIES LOCATED IN PROXIMITY


OF TRANSMISSION LINES (INDUCED/CONDUCTIVE VOLTAGE
INTERFERENCES)

3.1 Inductive and Conductive Voltage Requirements.

The guidelines listed below shall be followed for all the requests of customer
metallic facilities, such as pipelines, rail road, communication cables, cathodic
protection systems, etc., (whether overhead, above-ground or under-ground) to cross
and/or run in close proximity to SEC transmission lines. The following guidelines
shall be applied to all facilities in a single location in case more than one facility is
involved in the request.

3.1.1 SEC approval for allowing other parties to construct and install their
projects in parallel to and/or crossing the transmission lines shall be
granted if the project proponent satisfy all the following conditions:

a. Accepts full liability and any consequential damages due to the


electrical interference (induced/conductive voltage) effects and
satisfies conditions given in Clause 3.3.1 and 3.3.2 below (for
crossing only).

b. Performs at his expense induced/conductive voltage study and


proves to SECs satisfaction that the resulting touch voltages are
within the limits specified in Clause 3.1.2 and 3.1.3 below and
satisfies the conditions given in Clause 3.3.1 and 3.3.2 below (for
crossing only).

c. Satisfies the requirements specified in Clause 3.2 and 3.3.

3.1.2 The maximum touch voltage limit to insure safety to personnel during
steady-state conditions shall be as follows:

Conditions Limits
Continuous Voltage 15 volts
Continuous Current 10 milli-amperes

3.1.3 The maximum touch voltage limit to insure safety to personnel during fault
conditions shall be according to the following ANSI/IEEE 80 equation:

116 + (017
. )
Vtouch =
t
Where:

= Surface soil resistivity in ohms-meters

t = Fault duration in seconds. This shall be taken as 0.5 seconds or backup


clearing time whichever is higher.
TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 8 OF 39
TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Therefore, for 500 ohm-meter top soil resistivity and 0.5 second fault
clearing time, the safe touch voltage limit is 284 volts.

3.1.4 If the proponents induced/conductive voltage study show the need to


install mitigation to limit the touch voltage, Transmission Asset Planning
Department (TAPD) shall review the case to determine that the appropriate
procedures are followed.

3.2 Paralleling Facility (Induced Voltage Case)

When the rights of ways are unrestricted following minimum spacing between the
centerlines of transmission lines and above grade or below grade metallic facility
shall be maintained. In case the minimum distances cannot be maintained the
request shall be referred to TAPD for review.

Table 09-4: Clearances for Induced Voltage for Metallic Facility

Voltage Level Clearance, (m)


69kV to 132kV 150
230kV and 380kV 300

3.3 Crossing Facility (Conductive Voltage Case)

3.3.1 The minimum vertical clearance between the transmission lines and ground
facilities shall be per Table 09-2.

3.3.2 When ground facilities cross transmission line access roads, the facility
crossing shall be designed to provide safe passage of vehicular traffic. For
unpaved crossing of above grade facility, refer TES-P-122.11.

3.3.3 When the facility routes cross overhead transmission line the preferred
angle of intersection is 90 degrees and if not possible crossing angle
between 70 to 110 degrees shall be acceptable.

3.3.4 The facility shall cross the transmission line at mid span between towers,
otherwise the crossing shall be minimum 100 meters away from the nearest
transmission line foundation for 230 kV and 380 kV transmission lines and
minimum 50 meters away from the nearest transmission line foundation for
69kV, 110kV, 115kV and 132kV transmission lines.

3.3.5 If the facility runs parallel to the transmission line after the intersection
then it shall also meet minimum distance requirements mentioned under
clause 3.2 above. If the metallic facility is crossing below the grade and
changing its direction at a distance less than 300 meters (for 230kV and
380kV transmission lines) and 150 meters (for 69kV, 110kV, 115kV and
132kV transmission lines) from crossing, the facility shall be grounded at
the point where the direction is changing.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 9 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

If the metallic facility is crossing above the grade, the facility shall be
grounded up to 100 meters along the length of the facility in both
directions from the crossing point. If the facility is changing its direction at
a distance greater than 100 meters and less than 300 meters (for 230kV and
380kV transmission lines) and 150 meters (for 69kV, 110kV, 115kV and
132kV transmission lines) from the crossing point, additional grounding
shall be provided at the point where the direction is changing. The
grounding of the metallic facility shall be to the satisfaction of the
concerned party.

4.0 SPACING FROM MAIN OIL FACILITIES

Horizontal spacing between the edge of the foundation of the transmission lines and edge of
the main oil facilities shall be provided for safe operation and maintenance of both.

Minimum spacing for 69 kV to 380 kV transmission lines to main oil facilities shall be as
follows:

Table 09-5 Minimum Spacing for Oil Facilities

Oil Facility Type Spacing, (m)


Oil Wells and GOSPs 200
Oil Trunk 150
Ground Flares and Burn Pits 150
Elevated Flare Stacks 60
Oil-Water Separators and Skimming Ponds 60
Other Oil Process Areas 60

5.0 CONDUCTOR SPACING AND CLEARANCE

5.1 Horizontal Clearance between Phase Conductors on the same Support

5.1.1 Horizontal Clearance - Fixed Support

Phase conductors attached to fixed supports shall have horizontal


clearances from each other not less than the larger value required by
equations given below:

a. Phase Conductors of the Same Circuit

i. H = 300+10 (U-8.7) (Eq.09-1)


ii. F = 7.6 (U)+8 2.12 S (Eq.09-2)

b. Phase Conductors of Different Circuits

i. H = 725+10 (Uo-50) (Eq.09-3)


ii. F = 7.6 (Uo)+ 8 2.12 S (Eq.09-4)

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 10 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Where:

H = Basic horizontal clearance between phase conductors in mm.

F = The horizontal clearance due to sag between phase conductors in


mm.

U = The maximum operating voltage phase to phase over 8.7 kV

Uo= Maximum operating voltage between line conductors of different


circuits which shall be the greater of the phasor difference
between the conductor involved, or the phase-to-ground voltage
of the higher voltage circuit. For circuits having the same phases
and nominal voltage, either circuit may be considered to be the
higher voltage circuit.

S = Final unloaded sag based on computed ruling span at every day


conductor temperature, no wind, in mm.

A margin of 0.6m shall be added to the claculated values to account


for design errors.

The clearances shall be increased @ 3 % for each 300m in excess of


1,000m altitude above mean sea level.

5.1.2 Horizontal Clearance - Suspension Insulators

Where suspension insulators are used and are not restrained from
movement, the clearance shall be increased so that one string of insulators
may swing transversely through a range of insulator swing up to its
maximum design swing angle without reducing the values given in
equations 09-1 to 09-4 and 09-11 to 09-16. The maximum design swing
angle shall be based on 1064 N/m2 wind on the insulator.

a. The insulator swing shall be calculated as follows:

For maximum angle of swing:


2T Sin (/2 ) + (HS x Pc )
= Arc Tan (Eq.09-5)
(VS x W c ) + Wi /2

For minimum angle of swing:

2T Sin ( / 2) ( HS x Pc )
= Arc Tan (Eq.09-6)
( VS x Wc ) + Wi / 2
Where

= angle with the vertical through which the insulator string swings

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 11 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

= line angle in degrees

T = conductor tension at the temperature and wind loading for which


the clearance is specified, in Newtons

HS = horizontal span, which is 1/2 the sum of adjacent spans, in


meters

VS = vertical span, which is the distance between the low point of


sag in adjacent spans, in meters

Pc = wind load per unit length of conductor (conductor diameter times


wind pressure), in Newtons/meter

Wc = weight per unit length of bare conductor, in Newtons/meter

Wi = weight of insulator string divided by number of conductors per


phase, in Newtons

b. The horizontal swing of insulators can be obtained from the equation:

B = (Insulator assembly length) Sin

Where: is the maximum swing angle calculated per equation 09-5.

5.1.3 Horizontal Clearance for different Circuits where one or both Circuits
exceed 98kV Phase-to-Ground

a. The clearances specified in equations 09-1 to 09-4 and equations 09-5


and 09-6 may be reduced for circuits with known switching surge
factors shall not be less than the clearances derived from the equation
below:

1.667
U (SSF) a
Min. clearance (H) = 1000 L L b (Eq.09-7)
500k
Where:

UL-L = Maximum alternating current crest operating voltage between


phases of different circuits. If the voltages are of the same
phasor and magnitude, one phase conductor shall be
considered grounded.

SSF = Maximum switching surge factor expressed in per unit peak


operating voltage between phases of different circuit. (SSF
value shall be obtained from Transmission Asset Planning
Department).

a = 1.15, the allowance for three standard deviations

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 12 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

b = 1.03, the allowance for nonstandard atmospheric conditions.

k = 1.4, the configuration factor for a conductor-to-conductor gap

The clearance shall be increased @ 3 % for each 300m in excess of


450m above mean sea level.

b. The clearance derived from above equation shall not be less than the
basic clearance given in equations 09-1 to 09-4.

5.1.4 The method on how to determine the horizontal clearance between


conductors of the same or different circuits on the same support is shown
in Figure TE-2209-0100-00.

5.2 Vertical Clearance between Line Conductors

All conductors located at different levels on the same supporting structure of the
same or different circuits for the same sag, shall have vertical clearances not less
than required by the equations given below:

5.2.1 For Phases of the same Circuit

a. Vs = 830+10 (U-50) (Eq.09-8)

Where:

Vs = Basic vertical clearance phase-to-phase, in mm


U = Maximum operating voltage phase-to-phase, over 50 kV

b. Minimum vertical clearances calculated based on the above equation


are tabulated below:

Table 09-6: Vertical Clearances between Line Conductors for same


Circuit on the same Structure
Vertical Clearance between Phases of the
Nominal Voltage, (kV)
same Circuit on the same Structure, (m)
69 1.10
110 1.60
115 1.60
132 1.80
230 2.90
380 4.60
Notes:
1. A margin of 0.15m shall be added to account for design errors.

2. The clearances at the supporting structures shall be increased to


compensate the reduction in span clearances caused by jumping of
conductors in the longer spans.

3. The clearances shall be increased @ 3 % for each 300m in excess of


1,000m altitude above mean sea level.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 13 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

5.2.2 For different Circuits on the same Structure of different Nominal Voltage

a. Vc = 830+10[(U01+U02)-50] (Eq.09-9)

Where:

Vc = Basic vertical clearance between circuits in mm

U01 = Maximum phase-to-ground voltage of circuit at upper level,


over 50 kV

U02 = Maximum phase to ground voltage of circuit at lower level,


over 50 kV

When the circuits have the same nominal voltage, either circuit may
be considered to be the higher voltage circuit.

b. Minimum vertical clearances were calculated based on the above


equation and tabulated below:

Table 09-7: Vertical Clearance between different Circuits on the


same Structure for different Voltages

Vertical Clearance between different


Nominal Circuit Voltages, (kV) Circuits on the same structure of different
Nominal Voltages, (m)
69/69 1.20
110/110 1.75
115/115 1.80
132/132 2.0
230/230 3.25
380/380 5.15
Notes:
1. A margin of 0.15m shall be added to account for design errors.

2. The clearances at the supporting structure shall be so adjusted that the


clearances at any point in the span shall not be less than the values given
in the table when measured with upper conductor at final unloaded sag at
the maximum temperature for which the conductor is designed to operate
and the lower conductor at final unloaded sag under the same ambient
conditions and without electrical loading.

3. The clearances shall be increased @ 3 % for each 300m in excess of


1,000m altitude above mean sea level.

5.2.3 Clearances for different Circuits where one or both exceed 98kV to Ground

The clearances specified in equations 09-8 and 09-9 may be reduced for
circuits with known switching surge factors, but shall not be less than the
clearances required by the equation below:

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 14 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

( U (SSF) + U L ) a
1.667

Min. Clearance (V) = 1000 H bc (Eq.09-10)


500k
Where:

UH = Higher voltage circuit maximum crest operating voltage to ground

UL = Lower voltage circuit maximum crest operating voltage to ground

SSF = Higher voltage circuit maximum switching surge factor expressed in


per-unit peak voltage to ground. (SSF value shall be obtained from
Transmission Asset Planning Department).

a = 1.15, the allowance for three standard deviations

b = 1.03, the allowance for nonstandard atmospheric conditions.

c = 1.2, the margin safety

k = 1.4, the configuration factor for conductor-to-conductor gap

The clearance shall be increased @ 3 % for each 300m in excess of 450m


above mean sea level.

5.3 Clearance of Conductor from its own Support - Basic Clearance

5.3.1 Clearance in any direction from a line conductor to the surface of its own
support structure shall not be less than that calculated by the following
equation:

Clearance T = 330mm+5mm (U-50) (Eq.09-11)

Where, U = Maximum operating voltage phase-to-phase, over 50kV

Minimum clearances of phase conductor to its own supporting structure


were calculated based on the above equation and tabulated below:

Table 09-8: Clearance of Phase Conductor to its own Support

Clearance of Phase Conductor to


Nominal Voltage, (kV) its own Support Arm and Structure, (m)
No Wind Condition Maximum Wind Condition
69 0.69 0.50
110 1.30 0.70
115 1.30 0.75
132 1.50 0.80
230 2.1 1.35
380 3.50 2.20
Notes:
1. A margin of 0.15m shall be added to account for design errors.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 15 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

2. The clearances (maximum wind) given in the above table shall be maintained when
the insulator strings and conductors swing transversely upto maximum design
swing angle.

3. The clearances shall be increased @ 3 % for each 300m in excess of 1,000m


altitude above mean sea level.

5.3.2 Clearances of Conductor from its own Support-Alternate Clearances for


Voltages exceeding 98kV Phase to Ground

The clearances specified in Eq.09-11 may be reduced for circuits with


known switching surge factor but shall not be less than the clearances
derived from the equation shown below:

1.667
U (SSF) a
Min. Clearance (T) = 1000 L-G b (Eq.09-12)
500k
Where:

UL-G = Maximum alternating current crest operating voltage to ground;

SSF = Maximum switching surge factor expressed in per-unit peak voltage


to ground

a = 1.15, the allowance for three standard deviations with fixed insulator
supports

a = 1.05, the allowance for one standard deviation with free swinging
insulators

b = 1.03, the allowance for nonstandard atmospheric conditions;

k = 1.2, the configuration factor for conductor-to-tower window.

The clearance shall be increased @ 3 % for each 300m in excess of 450m


above mean sea level.

5.3.3 When suspension insulators are used and are not restrained for movement,
the clearance shall be increased so that the insulator strings may swing up
to maximum design angle without reducing the values as tabulated in Table
09-8. The maximum insulator swing angle shall be determined as outlined
in equation 09-5.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 16 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

5.4 Clearance between Phase Conductors carried on different Supports

5.4.1 Horizontal Clearance between Conductors

a. Basic Clearance

The horizontal clearance between adjacent conductors carried out on


different supporting structures shall not be less than required by the
equation below:

Clearance = 1500mm+10mm [(U01+U02)-129] (Eq.09-13)

Where:

U01 = Maximum Phase-to-Ground Voltage of Line #1, over 50 kV

U02 = Maximum Phase-to-Ground Voltage of Line #2, over 50 kV

The clearance shall be maintained when one insulator string swings


upto its extreme position while the string of adjacent conductors
remains at rest.

A margin of 0.6m shall be added to the claculated values to account


for design errors.

The clearance shall be increased @ 3 % for each 300m in excess of


1,000m above mean sea level.

b. Alternate Clearances for Voltages exceeding 98kV Phase-to-Ground

The clearances specified in equation 09-13 may be reduced for


circuits with known switching surge factor but shall not be less than
the clearances derived from the equation 09-7.

5.4.2 Vertical Clearance between Phase Conductors

a. Basic Clearance

The vertical clearance between any crossing or adjacent conductors


carried on different supporting structures of the same or different
nominal voltages shall not be less than that shown in Table 09-9 or as
required by the following equation, whichever is larger.

Clearance = 600mm+10 [(U01-22)+(U02-22)] (Eq.09-14)

Where:

U01 = Maximum phase-to-ground voltage of Line at upper level, over


22 kV

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 17 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

U02 = Maximum phase-to-ground voltage of Line at lower level, over


22 kV

Table 09-9: Minimum Vertical Clearance between Conductors where the


Conductors of one Line cross over the Conductors of another

Lower Level Conductor Upper Level Conductor


Transmission Voltages (Line to Line)
Type of Crossing 69kV 110kV 115kV 132kV 230kV 380kV
(m) (m) (m) (m) (m) (m)
69kV Transmission Lines 1.10 - 1.40 - 2.10 3.10
110kV Transmission Lines - 1.60 - - - 3.30
115kV Transmission Lines
- - 1.70 - 2.40 3.40

132kV Transmission Lines - - - 1.90 - 3.50


230kV Transmission Lines - - - - 3.20 4.10
380kV Transmission Lines - - - - - 5.10
Distribution Lines
0.90 1.20 1.30 1.40 2.05 3.02
(34.5kVand below)
Overhead Ground Wire,
1.40 1.70 1.70 1.80 2.50 3.40
Guys and Span Wires
Communication Lines 2.0 2.20 2.30 2.50 3.10 4.10
Notes:
1. Additional margins of 1.0m and 2.0m (total 3.0m) shall be added to account for design
errors and wind induced dynamic conductor movement/safety during maintenance
operations respectively.

2. The clearances shall be maintained under the conditions, when upper level conductors are at
the final unloaded sag at maximum design temperature of conductor and lower level
conductors are at the initial sag at the minimum design temperature of conductor or at final
unloaded sag under the same ambient condition without electrical loading whichever results
in larger difference.

3. The clearances shall be increased @ 3 % for each 300m in excess of 1,000m altitude above
mean sea level.

b. Alternate Clearances for Voltages exceeding 98 kV Phase-To-


Ground

The clearances specified in equation. 09-14 may be reduced where


the higher voltage circuit has a known switching surge factor but
shall not be less than the clearances derived from the equation 09-10.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 18 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

5.5 Clearance of Conductors from other supporting Structures

Conductors of one line passing near a lighting support, traffic signal support, or a
supporting structure of a second line, without being attached thereto, shall have
clearance from any part of the structure not less than calculated by the equation
below:

5.5.1 Horizontal Clearance

a. Clearance G = 1500mm+10mm (U0-50) (Eq.09-15)

Where U0 is the maximum operating voltage phase-to-ground, in


excess of 50kV.

Minimum horizontal clearance of a line conductor to a rigid


supporting structure, other than its own, based on the above equation
was calculated and tabulated in Table 09-10.

Table 09-10: Horizontal Clearance of Conductor from other


Supporting Structure

Minimum Horizontal Clearance of Conductor


Nominal Voltage, (kV)
from other Supporting Structure, (m)
69 1.50
110 1.70
115 1.75
132 1.85
230 2.50
380 3.50
Note: A margin of 0.6m shall be added to account for design errors and the
clearances shall be increased @ 3 % for each 300m in excess of 1,000m altitude
above mean sea level.

b. These clearances have to be increased by the distance resulting from


horizontal swing of the conductor and insulator assembly due to
wind.

i. The maximum insulator swing angle can be determined by


equation. 09-5.

ii. The maximum design swing angle shall be based on a 1064


N/mm2 wind on the conductor, final sag at every day
temperature. The conductor swing shall be calculated as
follows:

= Arc Tan (Pc/Wc) (Eq.09-16)

Where: Pc and Wc are defined in equation 09-6.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 19 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

The horizontal swing of conductors due to wind can be


obtained from the equation:

C = Sc x sin (Eq.09-17)

Where: Sc is the conductor sag, shall be final sag based on


computed ruling span at every day temperature, with 1064
N/mm2 wind.

5.5.2 Vertical Clearance

Min. Clearance = 1700 mm + 10 mm (U0-50) (Eq.09-18)

Where: U0 = Maximum operating Voltage Phase-to-Ground, in excess of


50kV.

Minimum vertical clearance of a line conductor to a rigid supporting


structure, other than its own, was calculated based on the above equation
and given in Table 09-11.

Table 09-11: Vertical Clearance of Conductor from other Supporting


Structure

Minimum Vertical Clearance of Conductor from


Nominal Voltage, (kV)
other Supporting Structure, (m)
69 1.70
110 1.90
115 1.95
132 2.05
230 2.70
380 3.70
Note: A margin of 1.0m shall be added to account for design errors and the clearances
shall be increased @ 3 % for each 300m in excess of 1,000m altitude above mean sea
level.

5.5.3 Alternate Clearance for Voltages exceeding 98kV to Ground

The clearances specified in equations 09-15 and 09-18 may be reduced for
circuits with known switching surge factors but shall not be less than the
values derived from the following equations.

a. Min. horizontal clearance in mm

U (SSF) a
1.667

= 1500 + 1000 L G bc (Eq.09-19)


500k

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 20 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

b. Min. vertical clearance


U (SSF) a
1.667

= 1800 + 1000 L G bc (Eq.09-20)


500k
Where:

UL-G = The maximum crest operating voltage to ground

SSF = Maximum switching surge factor expressed in per-unit peak


voltage to ground (SSF value shall be obtained from
Transmission Asset Planning Department).

a = 1.15, the allowance for three standard deviations

b = 1.03, the allowance for nonstandard atmospheric conditions

c = Margin of safety, 1.2 for Vertical clearances and 1.0 for


horizontal clearances

k = 1.15, the configuration factor for Conductor-to-Plane gap

The clearances shall be increased @ 3 % for each 300m in excess of 450m


above mean sea level.

5.6 Clearances of Conductors from other Installations

The horizontal and vertical clearances of line conductors from other structures such
as tall buildings, signs, chimneys, TV masts, lighting poles, monuments in the
round-abouts,etc., shall be established as required, taking into consideration all local
conditions and the latest government and owner regulations.

5.6.1 Basic Clearance

Minimum clearances of wires, conductors and cables passing by, but not
attached to building and other installations, shall not be less than those
given in the following table. The horizontal clearance mentioned in the
table shall be maintained when the conductor swings upto the design swing
angle.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 21 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-12: Minimum Clearance of Conductors Adjacent to but not attached to


Buildings and other Installations except Bridges (see notes 5 and 6)

Communication Phase Conductors


Clearance of Cables and
69kV 110kV 115kV 132kV 230kV 380kV
Grounded Guys
(m) (m) (m) (m) (m) (m)
(m)
Buildings
(Horizontal)

To wall and
1.40 2.55 2.80 2.85 2.95 3.60 4.55
projections (3)
To unguarded
1.40 2.55 2.80 2.85 2.95 3.60 4.55
windows (4)

To balconies and
areas accessible to
1.40 2.55 2.80 2.85 2.95 3.60 4.55
pedestrians (1)
Buildings (Vertical)

Above or below roof


or projection not
accessible to
pedestrians (1) 0.90 4.05 4.30 4.35 4.50 5.10 6.10

Above or below
balconies and roofs
accessible to
pedestrians (1) 3.20 4.35 4.60 4.65 4.80 5.40 6.35

Above roofs
accessible to truck
traffic (2) 3.20 4.35 4.60 4.65 4.80 5.40 6.35

Above roofs
accessible to vehicles
but not subject to
truck traffic 4.70 5.85 6.10 6.15 6.30 6.90 7.85
Signs, Chimneys,
radio and television
antennas, lighting
poles, monuments in
the round-abouts
tanks and other
installations not
classified as
buildings:

Horizontal 0.90 2.55 2.80 2.85 2.95 3.60 4.55

Vertical above or
below 0.90 2.70 2.95 3.00 3.10 3.70 4.70
Notes:
1. A roof, balcony or area is considered accessible to pedestrians if the means of access is through a
doorway, ramp, stairway or permanently mounted ladder.
2. For the purpose of this rule, trucks are defined as any vehicle exceeding 2.45 m in height.
3. This clearance may be reduced to 75 mm for the grounded portions of guys.
4. Windows not designed to open may have the clearances permitted for walls and projections.
5. A margin of 1.0m shall be added to account for design errors.
6. The clearances shall be increased @ 3 % for each 300m in excess of 1,000m altitude
above mean sea level.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 22 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

5.6.2 Alternate Clearance for Voltages exceeding 98kV to Ground

The clearance specified in Table 09-12 may be reduced for circuit with
known switching surge factors but shall not be less than the values derived
from equations 09-19 and 09-20.

5.7 Midspan Clearance

The separation between the overhead ground wire and the top conductor is a
function of the actual structure footing resistance, wind speed, the number of
insulators in the insulator string, type of insulator, the span length and the acceptable
number of outages per 100 km per year.

5.7.1 The clearance at midspan between the overhead ground wires and the
conductors shall be greater than that at the structure and shall be well
coordinated so that the flashover occurs at the structure.

5.7.2 Line voltages have little relationship on the required midspan clearances.
The midspan clearances for SEC 69kV through 380 kV transmission lines
shall not be less than those tabulated below. The clearances shall be
maintained at every day temperarure, final sag with no wind and shall be
satisfied for the largest span encountered in a transmission line section.
The values for intermediate spans may be interpolated.

Table 09-13: Midspan Clearance Conductor to OGW


Span, (m) Midspan Clearance Conductor to OGW, (m)
91 2.7
122 3.1
152 3.7
183 4.6
213 6.1
244 7.3
305 9.7
350 11.3
366 11.9
427 13.7
488 15.5
549 17.4
Note: The clearances shall be increased @ 3 % for each 300m in excess of 1,000m
altitude above mean sea level.

5.7.3 For spans longer than those in the above table, the final sag of the overhead
ground wire with no wind at every day temperature shall about 80 per cent
of conductor sag.

5.8 Air Gap Requirements

5.8.1 Shielded Lines

To maintain adequate clearances the air gap distance between any


conductor and structure shall be correlated to the insulation levels
TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 23 OF 39
TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

considering each of the three types of voltage stresses (lightning impulse,


switching surge and power frequency) under the condition at which each is
likely to govern and given in the following table.

Table 09-14: Air Gap Requirement for Shielded Lines

Line Voltage, (kV) Air Gaps, (m)


69 0.69
110 1.30
115 1.30
132 1.50
230 2.1
380 2.60
Note: The clearances shall be increased @ 3 % for each 300m in excess of 1,000m
altitude above mean sea level.

5.8.2 Unshielded Lines

For unshielded lines the following criteria shall be used to specify


clearances of phase conductor to structure. Further the minimum conductor
to structure and conductor to conductor clearances shall not be less than
Eq. 09-1 to Eq. 09-20 or by the correlated air gap clearances to insulation
levels, the larger value shall be used, for various situations. Basic
clearances shall be based on the maximum system voltage under
emergency conditions.

a. For the no wind or normal position of the insulator, the conductor


clearance to structure shall be the air gap equivalent of the insulator
string impulse flashover value plus ten (10) percent.

b. For the 430 N/m2 wind position, the conductor clearance to structure
shall be the air gap equivalent of the insulator string impulse
flashover value.

c. For 1064 N/m2 wind position, the conductor clearance to structure


shall be the air gap equivalent of 60Hz wet flashover value of the
insulator string. The air gap clearance plus the distance allowed for
the swing of insulator by the maximum wind of 1064 N/m2 will
determine the clearance from conductor to structure in the normal
position.

6.0 RIGHT-OF-WAY WIDTH REQUIREMENTS

6.1 General

6.1.1 Right-of-way requirements for 69 kV, 110kV, 115 kV, 132kV, 230 kV and
380 kV transmission lines are discussed in this part. All right-of-way shall
be secured before design and construction.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 24 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

6.1.2 Right-of-way for 69kV to 380kV transmission lines shall be as shown in


Tables 09-16 and 09-17, or shall be calculated using the equations 09-21 to
09-23. The larger value from these equations shall be used.

6.2 Conductor Clearance to edge of Right-of-Way

6.2.1 Minimum horizontal separation between phase conductors on the same


support shall be calculated by equations 09-1 to .09-4. The large value
from these equations shall be used. This value shall be increased by the
distance to the end of the longest insulator support on each line structure.

6.2.2 Minimum horizontal clearances from conductors to edge of right-of-way


shall be based on values in Tables 09-16 and 09-17 or in accordance with
the following equations. The larger value shall be used. Transmission
voltages shall be based on maximum operating voltage under emergency
conditions:

a. Basic Clearance

= 2300 mm + 10 mm (U0-22) (Eq.09-21)

Where:

U0 = Maximum operating voltage phase-to-ground over 22 kV.

b. Alternate clearance in mm

U (SSF) a
1.667

= 1500 + 1000 0 bc (Eq.09-22)


500k
Where:

U0 = Maximum alternating current crest operating voltage to ground

SSF = Maximum switching surge factor expressed in per unit peak


voltage to ground. (SSF value shall be obtained from Transmission
Asset Planning Department).

a = 1.15, the allowance for three standard deviations.

b = 1.03, the allowance for nonstandard atmospheric conditions

c = Margin of safety, 1.2 for Vertical clearances and 1.0 for


Horizontal clearances

k = 1.15, the configuration factor for Conductor-to-Plane gap.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 25 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

6.3 Right-of-Way Width Requirements for Single Transmission Line

6.3.1 Figure TE-2209-0200-00 shows the procedures to be followed to establish


the right-of-way for various types of transmission line structures in
restricted areas.

6.3.2 Explanation of symbols used in Figure TE-2209-0200-00 and steps to be


taken to establish right-of-way requirements in restricted areas are given
below:

A = Distance from centerline of structure to insulator attachment in mm.

1 = Angle of maximum swing for suspension insulator string. It is


preferred to use the 1 as 45 swing.

If 45 swing is used, it will include most conditions for structures currently


being used with the insulator string at maximum blowout or structure
design limitations.

If the minimum right-of-way is required to be obtained for a special area


control then the actual conditions or 1 may be calculated for the worst
conditions of the line under consideration.

B = Offset due to insulator swing for suspension insulators equal to length


of insulator string plus hardware length times Sin 1

2 = Angle of maximum swing for conductors is determined by multiplying


the conductor diameter in meters by the wind pressure in N/mm2 on
conductor and dividing by the conductor unit weight in Newtons per
meter.

Conductor Dia x Wind Pressure


Tan 2 = (Eq.09-23)
Unit Weight

C = Offset due to conductor sag x Sin 2. Conductor sag shall be the final
sag based on computed ruling span at every day temperature with
1064 N/mm2 wind

D = Horizontal clearance from conductor to edge of right-of-way at


maximum swing calculated for conditions established for structure to
be used (see clause 6.2.2)

E = Total distance each side, from centerline to edge of right-of-way.

6.4 Right-of-Way Width Requirements for Parallel Transmission Lines

6.4.1 Figures TE-2209-0300-00 and TE-2209-0400-00 show the procedures to


be followed in order to establish the minimum right-of-way for typical
configurations of parallel transmission lines.
TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 26 OF 39
TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

6.4.2 Steps A through E, as in clause 6.3.2, shall be followed and the angles 1
and 2 shall be determined for each of the two lines that are being
paralleled. Then determine the dimensions required for Items F and G.
The larger of these two shall determine the distance between the parallel
transmission lines.

a. Separation between lines as dictated by minimum clearance between


conductors carried on different Supports

The horizontal clearance between a phase conductor of one line to a


phase conductor of another line shall meet the following conditions:
(a) both phase conductors displaced by a 1064 N/mm2 wind at every
day temperature, final sag; (b) if insulators are free to swing, one
shall be assumed to be displaced by a 1064 N/mm2 wind while the
other shall be assumed to be unaffected by the wind (see Figure TE-
2209-0300-00).

F = Clearance between conductors of parallel transmission lines as


determined by equation 09-3 and 09-4 for phases of different
circuits.

b. Separation between lines as dictated by minimum clearance of


conductors from one line to the supporting structure of another

The horizontal clearance of a phase conductor of one line to the


supporting structure of another when the conductor and insulator are
displaced by a 1064 N/mm2 wind at every day temperature final sag.

G = Clearance of conductor from other supporting structures, as


determined by the equation 09-15.

6.4.3 The separation between lines will depend upon the spans and sags of the
lines as well as how the structures of one line line-up with structures of
another. In order to avoid the unreasonable task of determining the
separation of the structures span-by-span, a standard separation value shall
be used based on a worst case analysis. Thus if structures of one line do not
always line-up with the other, the separation required by clause 6.4.2.b
above shall be based on assumption that the structure of one line is located
next to the mid-span point of the line that has the most sag.

6.5 Example Calculation of Right-of-Way

6.5.1 Information needed to determine the right-of-way requirements for


structure types of any transmission lines are tabulated on Table 09-15.

6.5.2 Typical calculations for a single 230kV double circuit steel tower with 22
units of suspension insulator per string, 402.6 mm (795 kcmil), 26/7
strands ACSR/AW Drake conductor and 335 meters ruling span are:

a. Dimension A
TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 27 OF 39
TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

A = 11.9 m derived from the drawing for Latticed Steel Delta


Configuration 230 kV Double Circuit Tangent Type Tower
TTN (0-1). Dimension A depends on tower structure
design and configuration.

b. Dimension B

Assume 1 = 45

Length of insulator string = 22 x 0.146 m = 3.2 m

Length of hardware string = 2 x 0.400 m = 0.8 m

Total length of Insulator String = 4.0 m

B = Total length of Insulator String x Sin 1

= 4.0 m x sin 45 = 2.83 m

c. Dimension C

Angle of maximum swing for conductors:

28.1 mm / 1000 x 1064


2 = Arc Tan = 63
15.2 N/m

Sag for 335 m ruling span = 10.64 m at 27C, final with 1064 N/mm2
wind

Offset due to conductor swing:

C = 10.64 m x sin 63 = 9.50 m

Offset due to conductor swing for two bundled conductor:

0.5
Cl = 9.5 m + x Cos 63o = 9.72 m
2

d. Dimension D

Horizontal clearance to edge of right-of-way

253
D = 2300mm + 10 mm 22
3

D = 2300 mm + 1241 mm = 3541 mm, say 3.60 m or by equation


09-22 for circuit with known switching surge factors:

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 28 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

1.667
U (SSF) a
D = 1500 mm + 1000 L-G bc
500k

e. Dimension E

Distance each side of centerline to edge of right-of-way

E = A+ B+ C+ D = 11.9 + 2.83 + 9.72 + 3.60 = 28.05 m

Therefore, total width of right-of-way required shall be:

2 x E = 2 x 28.05 m = 56.10 m; say ROW = 56 m

6.5.3 Typical calculation for two parallel 230kV steel tower lines (Figure TE-
2209-0300-00)

Tower configurations are the same as in clause 6.5.2. The separation


between two parallel 230 kV steel tower lines shall be calculated by the
two equations shown below and greater value shall be considered:

Items A, B, C, D, and E to be calculated as in clause 6.5.2.

a. Horizontal Clearance between different phases of different circuits


according to conductor sag per equation 09-3 & 09-4

U U
F = 7.6mm 1 + 2 + 8 2.12S
3 3

Where:

U1 = U2 = 230 kV x 1.1 = 253kV

S = Sag at 27C, final with 1064 N/mm2 wind

F = 7.6mm [146 + 146] + 8 2.12(10640)

= 2220 + 1202 = 3422 mm; say 3.4 m

b. Horizontal Clearance of conductor of one line to the supporting


structure of another (Eq.09-15)

U
G = 1500mm + 10.2 1 50
3

= 1500 + 10 (146-50)

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 29 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

= 1500 + 960 = 2,460 mm, say. 2.50 m

c. Horizontal Clearance may be reduced by the equation for circuits


with known switching surge factors by the (Eq.-09-18).

U(SSF) a
1.667

Min. Clearance G = 1500 + 1000 bc


500k

F = 3.40 m is larger than G, therefore, it is to be considered

Total right-of-way width shall be: E + A + B + C + F + A + E

= 28.05+11.9+2.83+9.72+3.4+11.9+ 28.05= 95.85 m

Say total ROW = 96 m

Table 09-15: Sample Data for Right-Of-Way Calculation

Sr. No. Description Line No. 1 & 2

1 Maximum Line Voltage 253kV


Lattice Steel
2 Type of Structure
(Delta Configuration)
3 Drawing for Tower Type TTN -
Centerline distance to end of longest
4 11.9
insulator, m
5 Number of insulators in the string 22

6 Insulator length, m 4.0

7 Insulator assembly weight, kg 127

8 Conductor Drake, ACSR/AW

9 Stranding 26/7

10 Weight per unit, kg/m 1.551

11 Diameter, mm 28.14

12 Ruling span, m 335

13 Sag at 27 with 1064 N/m2 wind, m 10.64

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 30 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-16: Single Transmission Lines Right-of-Way Width Requirements

Normal
Ruling Maximum
Line Voltage ROW
Structure Conductor Span Span
(kV) Width
(m) (m)
(m)
Lattice Steel, S/C
ACAR 400 550 85
(Horizontal)
380 Lattice Steel, D/C AAAC/ACA
400 550 70/75
(Vertical, V-String) R
Lattice Steel, D/C
ACSR 400 550 50*
(Vertical, I-String)
Lattice Steel, D/C
ACSR 305-350 400 56
(Delta)
Lattice Steel, D/C
230 ACSR 305-350 400 45
(Vertical)
Steel Monopole,
ACSR 200 250 35
D/C (Vetical)
Lattice Steel, D/C AAAC/ACS
305-350 400 35/50
(Vertical/Delta) R
Steel Monopole, ACSR/AAA
200 250 30
D/C (Vetical) C
110/115/132
Wood H-Frame, S/C ACSR 260-275 320 30
Wood/Steel
Monopole, S/C & ACSR 80-100 110-120 15
D/C
Lattice Steel, D/C
ACSR 305-350 400 30
(Vertical)
Wood H-Frame, S/C ACSR 260-275 320 25
69
Wood/Steel
Monopole, S/C & ACSR 80-120 140 15
D/C
Notes:
i. ROW marked with * is applicable in the Inland Area where creepage distance is
31mm/kV.

ii. The figures indicated in the above Table shall be applicable when ROW is un-
restricted. In case of restricted ROW the exact value shall be established based on
the actual span length and the actual conductor data.

iii. Wherever right-of-way is restricted and not possible to accommodate structure pads
and access road per TES-P-122.11, SEC shall review the case to determine
appropriate right-of-way.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 31 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-17: Parallel Transmission Lines Right-of-Way Width Requirements


Normal
Maximum
Line Voltage Ruling Span ROW
Structure Conductor Span
(kV) (m) Width
(m)
(m)
Lattice Steel, S/C
ACAR 400 550
380 (Horizontal) 139
Lattice Steel, S/C
ACAR 400 550
(Horizontal)
Lattice Steel, D/C
ACAR/AAAC 400 550
(Vertical)
380 119
Lattice Steel, D/C
ACAR/AAAC 400 550
(Vertical)
Lattice Steel, D/C
ACSR 400 550
(Vertical, I-String) *
380 100
Lattice Steel, D/C
ACSR 400 550
(Vertical, I-String)
Lattice Steel, S/C
ACAR 400 550
(Horizontal)
380 129
Lattice Steel, D/C
ACAR 400 550
(Vertical)
Lattice Steel, S/C
380 ACAR 400 550
(Horizontal) 125
230 Lattice Steel, D/C (Delta) ACSR 335-350 400
Lattice Steel, D/C
380 ACAR 400 550
(Vertical)
115
230 Lattice Steel, D/C (Delta) ACSR 335-350 400
Lattice Steel, S/C
380 ACAR 400 550
(Horizontal)
115
Lattice Steel, D/C
230 ACSR 335-350 400
(Vertical)
Lattice Steel, D/C
380 ACAR 400 550
(Vertical)
104
Lattice Steel, D/C
230 ACSR 335-350 400
(Vertical)
Lattice Steel, D/C
380 ACAR 400 550
(Vertical)
95
Steel Monopole, D/C
230 ACSR 200 250
(Vertical)
Lattice Steel, D/C
380 ACSR 400 550
(Vertical, I-String) *
83
Lattice Steel, D/C
132 ACSR 335-350 400
(Vertical, I-String)
Lattice Steel, D/C
380 ACSR 400 550
(Vertical, I-String) *
75
Steel Monopole, D/C
132 ACSR 200 250
(Vertical)
Lattice Steel, D/C
380 ACAR/AAAC 400 550
(Vertical)
93
Lattice Steel, D/C
115/110 ACSR/AAAC 335-350 400
(Vertical)
Lattice Steel, D/C
380 ACAR 400 550
(Vertical) 105
115 Lattice Steel, D/C (Delta) ACSR 335-350 400

* Applicable in the Inland Area where creepage distance is 31mm/kV.


TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 32 OF 39
TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-17: Parallel Transmission Lines Right-of-Way Width Requirements


(Continued)
Normal
Maximum
Line Voltage Ruling Span ROW
Structure Conductor Span
(kV) (m) Width
(m)
(m)
Lattice Steel, D/C
380 ACAR 400 550
(Vertical) 88
Lattice Steel, D/C
69 ACSR 335-350 400
(Vertical)
Lattice Steel, D/C (Delta) ACSR 335-350 400
230 96
Lattice Steel, D/C (Delta) ACSR 335-350 400

Lattice Steel, D/C (Delta) ACSR 335-350 400


230 85
Lattice Steel, D/C
ACSR 335-350 400
(Vertical)
Lattice Steel, D/C
ACSR 335-350 400
(Vertical)
230 74
Lattice Steel, D/C
ACSR 335-350 400
(Vertical)
Steel Monopole, D/C
ACSR 200 250
(Vertical)
230 60
Steel Monopole, D/C
ACSR 200 250
(Vertical)
230 Lattice Steel, D/C (Delta) ACSR 335-350 400
91
115 Lattice Steel, D/C (Delta) ACSR 335-350 400
Lattice Steel, D/C
230 ACSR 335-350 400
(Vertical)
73
Lattice Steel, D/C
115 ACSR 335-350 400
(Vertical)
Steel Monopole, D/C
230 ACSR 200 250
(Vertical)
55
Steel Monopole, D/C
115 ACSR 200 250
(Vertical)
Steel Monopole, D/C
230 ACSR 200 250
(Vertical)
45
Steel/Wood Monopole,
69 ACSR 80-120 140
D/C (Vertical)
230 Lattice Steel, D/C (Delta) ACSR 335-350 400
64
Steel/Wood Monopole,
69 ACSR 80-120 140
D/C (Vertical)
Lattice Steel, D/C
230 ACSR 335-350 400
(Vertical)
55
Steel/Wood Monopole,
69 ACSR 80-120 140
D/C (Vertical)
Lattice Steel, D/C
ACSR 335-350 400
(Vertical, I-String) *
132 65
Lattice Steel, D/C
ACSR 335-350 400
(Vertical, I-String)
Steel Monopole, D/C
ACSR 200 250
(Vertical) *
132 45
Steel Monopole, D/C
ACSR 200 250
(Vertical)

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 33 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-17: Parallel Transmission Lines Right-of-Way Width Requirements


(Continued)
Normal
Maximum
Line Voltage Ruling Span ROW
Structure Conductor Span
(kV) (m) Width
(m)
(m)
Steel Monopole, D/C
ACSR/AAAC 200 250
132 (Coastal Area) 55
Steel Monopole, D/C
ACSR/AAAC 200 250
(Coastal Area)
Lattice Steel, D/C
ACSR/AAAC 335-350 400
(Vertical)
110 65-70
Lattice Steel, D/C
ACSR/AAAC 335-350 400
(Vertical)
Steel Monopole, D/C
ACSR/AAAC 200 250
(Vertical)
110 55
Steel Monopole, D/C
ACSR/AAAC 200 250
(Vertical)
Lattice Steel, D/C (Delta) ACSR 335-350 400
115 86
Lattice Steel, D/C (Delta) ACSR 335-350 400
Lattice Steel, D/C
ACSR 335-350 400
(Vertical)
115 65
Lattice Steel, D/C
ACSR 335-350 400
(Vertical)
Steel Monopole, D/C
ACSR 200 250
(Vertical)
115 55
Steel Monopole, D/C
ACSR 200 250
(Vertical)
H-Frame Wood, S/C ACSR 260-275 320
115 60
H-Frame Wood, S/C ACSR 260-275 320

H-Frame Wood, S/C ACSR 260-275 320


115 38
Wood Pole, S/C ACSR 80-100 110-120

Wood Pole, S/C ACSR 80-100 110-120


115 23
Wood Pole, S/C ACSR 80-100 110-120

115 H-Frame Wood, S/C ACSR 260-275 320


45
69 H-Frame Wood, S/C ACSR 260-275 320

115 H-Frame Wood, S/C ACSR 260-275 320


37
69 Wood Pole, S/C ACSR 80-100 110-120

115 Wood Pole, S/C ACSR 80-100 110-120


21
69 Wood Pole, S/C ACSR 80-100 110-120

H-Frame Wood, S/C ACSR 260-275 320


69 42
H-Frame Wood, S/C ACSR 260-275 320

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 34 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

Table 09-17: Parallel Transmission Lines Right-of-Way Width Requirements


(Continued)

Normal
Maximum
Line Voltage Ruling Span ROW
Structure Conductor Span
(kV) (m) Width
(m)
(m)
H-Frame Wood, S/C ACSR 260-275 320
69 23
Wood Pole, S/C ACSR 80-100 110-120

Wood Pole, S/C ACSR 80-100 110-120


69 20
Wood Pole, S/C ACSR 80-100 110-120

Note: Wherever right-of-way is restricted and not possible to accommodate structure pads
and access road per TES-P-122.11, SEC shall review the case to determine appropriate
right-of-way.

7.0 BIBLIOGRAPHY

7.1 Design Manual for High Voltage Transmission Lines, REA Bulletin 1724E-
200, U.S. Department of Agriculture, 2005 Edition

7.2 Transmission Line Design Manual, U.S. Department of the Interior, by


Holland H. Farr

7.3 National Electrical Safety Code, American National Standard Institute, 2007
Edition

7.4 IEC 61936-1, Power Installations Exceeding 1 kV A.C.-Part 1: Common Rules

7.5 Electrical Transmission and Distribution Refence Book, Central Station


Engineers (Westinghouse Electric Corporation), 1964

7.6 Estimating Lightning Performance of Transmission Lines, IEEE Transactions


Volume 83, 1964, J.M. Clayton & F.S. Young

7.7 Shielding of Transmission Lines, IEEE Paper No. 63-640, J.M. Clayton, F.S.
Young and A.R. Hileman

7.8 Application of Insulators in a Contaminated Environment, IEEE Transaction

7.9 Elements of Power System Analysis, William D. Stevens, Jr.

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 35 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 36 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 37 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 38 OF 39


TRANSMISSION ENGINEERING STANDARD TES-P-122.09, Rev. 0

TESP12209R0/MAA Date of Approval: December 12, 2007 PAGE NO. 39 OF 39

Вам также может понравиться