Вы находитесь на странице: 1из 2

Project : AVIC Mixed Development Project

Daily Diary : By Supervision Consultant, CECB. (Zone A)

Date : 03/01/2016

1.0 Weather:

Duration 06hrs 08hrs- 10hrs 12hrs 14hrs 16hrs 18hrs 22hrs 24hrs 02hrs 04hrs
_
08hrs 10hrs 12hrs 14hrs 16hrs 18hrs 20hrs 24hrs 02hrs 04hrs 06hrs
Weather S S S S S S
* S Sun Shine, HR-Heavy Rain, LR Light Rain, G- Gloomy, W Windy

2.0 Manpower:
A: Main contractor:

Category Nos. Category Nos. Category Nos.


Project manager 1 Masonry workers 7 Surveyor 1
Site Manager 1 R/f fabricators 44 Carpenters 59
Site Engineer 2 Mech. Workers 1 Welders 3
Tech. assistant 4 Operators 4 General workers 23
Foreman 10 Concreters 6 Survey Helper 03
B: Nominated sub-contractor:

Category Nos. Category Nos. Category Nos.

3.0 Machineries & Equipment:

Category Nos. Category Nos. Category Nos.


Tower crane 2 Breakers 0 Excavators 0
Mobile crane 0 Vibrators 0 Mixers 0
Bar bending machines 2 Pump car 1 water pumps 1
Bar cutting machines 2 Survey instruments 2 Jack Hammers 2
compressors 1 Welding plants 1

4.0 Inspection Carried out:

Location Element Works inspected By whom Status


L03 at grid Slab & beams Slab curing Heshan completed
23A-29/B1-D
Area
L03 at grid Slab & R/f fabrication work Heshan In progress
29-32/A-D Beams
L03 at 5- slab Scaffolding fixing Heshan In progress
12/A-D
L04 at grid 2- Beams and R/f fabrication work Heshan In progress
5/A-D arch pin
L03 at 23A- Setting out Grid line marking Heshan In progress
29/B1-D from TS
GF west Ramp area Anti-termite Heshan completed
boundary area treatment done

1 of 2
5.0 Drawings / Sketches referred for inspection:

Description Construction Shop Sketches/


Issue Drawings Log note
Podium Level -Civil X X
Transfer Level-Civil X X
LV & ELV layout drawings at L03 X X
Fire protection level 01 X X
HVAC system level 01 X X

6.0 Effects of work (accidents, breakdown, delay etc...):

7.0 Details of Material used for construction:

Material Status of Approval Reference No


R/F (Lanwa) Approved CSCEC/AVIC/REPORT/265

8.0 Defects observed:

Location Element Type of defects Action taken Status

9.0 Site Instruction / Defect Notification issued:

Description Instruction Ref No Remarks

10.0 Approved Method statements received:

11.0 General Comments:

Prepared By: S.M.J.M.T.Situge Date: 05/01/2016