Вы находитесь на странице: 1из 16

STEEL AUTHORITY OF INDIA LIMITED

BHILAI STEEL PLANT, BHILAI


TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

1.00 INTRODUCTION

Bhilai Steel Plant (BSP) a flagship unit of SAIL intends to expand its present
capacity from 4.0 MTPA to 7.0 MTPA. MECON LIMITED has been
commissioned by BSP for providing engineering and consultancy services
for the entire expansion project.

For the proposed 7 MT Expansion project Balance work External Water


System of SMS-III has been proposed to supply of industrial water for direct
and indirect cooling water circuit of SMS-III as such the package 077-01A
has been awarded to M/s L&T. As the commissioning of SMS-III is
proposed to be in the month of July-2017, the supply of industrial waster
Due to some reasons the package is unable to supply the industrial water
for the commission of SMS-III. As such the package-078B is proposed to
supply the industrial water for direct and indirect water circuit for BOF , CCP
and SRU of SMS-III. This specification shall be read in conjunction with
GTS , SBD and Commercial documents. The documents deal with the
technical requirement of makeup & Drinking water system.

2.00 Intent of Specification

The intent of specification covers complete erection of industrial water pipelines


along with fittings, valve, and blanking arrangement in pedestal / trestle. Testing
commissioning and painting of entire system.

Copyright 2017. MECON Limited. All Rights Reserved. Page 1 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

3.00 General Scope of Work

03.01 The scope of work of this TS shall cover the followings;

A Laying of Pipeline on trestles and pedestals as per drawings issued to the


contractor by the Purchaser/Consultant. Painting, Testing and
commissioning of a system as a whole for industrial water system for BOF,
SRU and CCP.

C Fabrication of structural trestles , bridges and other structures as required


for pipeline. The working drawings shall be issued to the contractor by the
purchaser / consultant.

03.02 The intent of this Specification is to make the Contractor appreciate his total
involvement / commitment for this package matching the requirement of the
Industrial water System for BOF, CCP and SRU of SMS-III as specified in
this document.
03.03 All the Type of resources , consumables etc requirement to complete the
execution of pipeline , civil and structural work shall be in the scope of work.
04.00 Time schedule for completion of the work shall be 2 months from the date of
issue of letter of award. Work shall be carried out as per the availability of the
fronts.

Copyright 2017. MECON Limited. All Rights Reserved. Page 2 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

04.00 The specification covers laying of Make-Up and Drinking water pipelines
along with fittings, etc. for the makeup and drinking water consumption of
various unit in 7.0 MT modernization program on a Non Turnkey basis.

4.1 The tenderer shall quote for full scope of work as covered under various chapters of
this specification.
4.2 The above work shall be executed on item rate basis covering scope and services
as described in the respective section of this specification and the data /
drawings / information, if any that will be made available to the successful
Tenderer by the Purchaser after placement of order.
4.3 The intent of the specification is to make the Tenderer appreciate his total
involvement / commitment for this package to enable him to submit a detailed
comprehensive offer matching the requirement of the Industrial Water works
for BOF , CCP and SRU of SMS-III under the 7MT expansion project.
4.4 The offer shall be complete in all respects and any additional equipment,
accessories, auxiliaries, services, work etc. which are not specifically
mentioned in the specification but are required for smooth and trouble free
operation shall be included by the Tenderer in the offer.
4.5 Metric systems and English language shall only be used throughout the tender and
in the drawings.
4.6 Timely completion is the essence of this T.S. The contractor shall satisfy himself
before submitting the offer, the nature and location of work place, kind of
equipment and facilities needed during performance of the work, general and
local conditions as well other matters which can, in any way, affect the work
covered in this specification.
4.7 The successful Tenderer shall be responsible for coordinating the work in different
areas and execute the work in agreed time schedule.
4.8 The Tenderers scope shall include transfer of R.L. and benchmark from the nearest
Plant Permanent Benchmark and establishing the same in one corner of the
plot for further reference. Tenderers scope shall also include arrangement of
all the tools and tackles and labour required for successful completion of the
work.
4.9 Provision of all labour, materials, consumables, equipment, fuel, transportation and
all incidental items not shown or specified but reasonably implied or
necessary for the completion of works, all in strict accordance with approved
dismantling scheme/ procedures/ sequence, general safety requirements,

Copyright 2017. MECON Limited. All Rights Reserved. Page 3 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

including revisions and amendments thereto as may be required during the


execution of the work.
4.10 Temporary staging, scaffoldings, bracings, ties, guy ropes shall be provided to
prevent accidents, damage to existing structures, shop equipments, service
lines etc.
4.11Supply of all tools & tackles, temporary supports, staging / scaffoldings, safety belts,
guy ropes, consumables like gas etc. and all other materials as deemed
necessary for proper completion of work are included in the scope of work.
4.12 The tenderer shall visit the site and satisfy themselves, in all respects with
site conditions, etc. before submission of offer. After acceptance of the offer
by the Purchaser, claim for extra payment submitted by the tenderer on
ground of local working conditions, fouling with the existing installations etc
will not be considered.

5 TECHNICAL SPECIFICATION FOR PIPE WORK


5.1 Scope of Works

The scope of works is as follows;


1) Temporary Laying of Industrial for Direct and Indirect water circuit for BOF,
CCP and SRU to various units of SMS-III as per drawings.
2) Connection to incoming header & distribution network.
3) Includes dismantling of existing pipes and supports, re-routing/laying of the
pipelines as per scheme including submission of drawings/sketches,
manufacture/fabrication, assembly, shop testing and inspection, painting,
unloading, storage, preservation, handling at site, insurance, complete
installation of the piping system and other associated works including
testing, commissioning, painting and handing over to BSP on non-turnkey
basis.

4) All the items, though not specifically mentioned but needed to make the
system complete and reliable for safe and satisfactory operation, shall also
be considered included, unless otherwise specifically excluded elsewhere.

5.2 Units Covered under the Scope of work

The specification covers temporary laying of industrial water pipelines along


with fittings, etc for the supply of industrial to direct and indirect water circuit

Copyright 2017. MECON Limited. All Rights Reserved. Page 4 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

of BOF, CCP and SRU of SMS-III. However, the scope of work shall be as
per actual site conditions and shall also not be limited to the units mentioned
here.
5.3 Preamble to schedule of items for inclusion in rates

05.03.01 General

This preamble to the schedule of items is an integral part of the schedule and
shall have as much force as though this is incorporated into the description of
the items themselves.

Contractor's rate for any items of work in the schedule of items , unless
otherwise stated, shall include the cost of all materials, including wastages,
conveyance and delivery, unloading, storing, fabrication, hoisting, all labour
for finishing to required shape and size, tools & tackles , power, fuel,
consumables, all taxes royalties, other revenue expenses, temporary facilities
like roads, drains etc., providing temporary storage facilities for cement, steel
and other materials and their subsequent dismantling, scaffolding and other
temporary works, setting out, fitting and fixing in position, site drainage,
dewatering, offering samples for approval, cost of all tests, rectification of all
defects, replacement of defective materials and work, interruptions to work
required to accommodate the work of other agencies working on the site,
continuation of work beyond working hour, in the night and holidays also if
situation warrants so, site clearance on completion, maintenance work during
the period of maintenance, bye-work necessary to complete any particular
item of work as per specification and direction of the engineer, overheads,
profit and other incidental charges.

05.03.02 Pipeline erection, testing & commissioning

This section covers site fabrication, erection, cleaning, testing, purging /


flushing, cleaning, painting of pipe work and associated structures including
supports.

The term 'pipe work' referred herein generally covers pipes, fittings ( bends,
reducer / expander, blanking arrangement pipe supports painting, etc.

Copyright 2017. MECON Limited. All Rights Reserved. Page 5 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

All pipelines must be levelled to true horizontal and vertical axes first and then
erected. The scheme/layout drawings/specifications for carrying out the
erection of piping shall be provided by the Purchaser /consultant. Pipes shall
be laid and supported suiting to site conditions in such a way as to look
aesthetically good.

05.02.03 Measurement

Measurement of work shall be carried out from the working drawing /


sketches issued by purchaser/consultant and mode of measurement shall be
as specified in this document or as per the latest IS: 1200.

Measurement at site shall be taken only in case of site deviation from


drawings / sketches issued to the Contractor or in cases where measurement
from drawings is not possible.

05.02.04 Time Schedule

Time schedule for completion of the work shall be 2 months from the date of
issue of letter of award. Work shall be carried out as per the availability of the
fronts.

05.02.05 Site Visit/ Local conditions

The contractor, before submitting his tender, shall visit the site and ascertain
the local conditions, labour rules, availability of area, traffic restrictions, all
obstructions in the area and also ascertain all site conditions including the
subsoil conditions and shall allow for any extras likely to be incurred due to
all such conditions in his quoted price. After award of the work, no additional
claims will be entertained on these accounts under any circumstances,
whatsoever, from the successful contractor.

05.02.06 Completeness

Any item of work which has not been specifically mentioned but is required
for completing the dismantling or for new construction work shall be under the
scope of the tenderer. The tenderer shall clearly indicate such additional
requirements, if any, with adequate justification.

Copyright 2017. MECON Limited. All Rights Reserved. Page 6 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

05.02.07 Purchasers obligations

Concerned departments of Bhilai Steel Plant shall provide the free issue
items.
Owner shall provide construction power & water free of cost within a distance
of 300m.

05.02.08 Deviations

The Tenderer shall clearly indicate any deviations and/or exclusions from
technical specifications in respect of the scope of work, specification and any
other details mentioned in the tender documents.
After placement of order, the successful tenderer shall strictly follow the
technical specification, material specification and any other parameters
indicated in the tender specification or its amendments, if any.

Incase of any difference/discrepancies in the provisions of;

Bill of Quantities
Special conditions of contract
Scope of work
General conditions of contract

The stipulations under special conditions of contract and scope of work shall
prevail.

05.02.09 In the event of any discrepancies between drawings and specifications, it


may be noted that drawings shall supersede the specifications. Similarly in
case of any discrepancies between description in
a) Drawings
b) Specifications
c) Schedule of items/ Bill of Quantities

The provisions in the schedule of items shall prevail.

05.02.10 Working Drawings

Copyright 2017. MECON Limited. All Rights Reserved. Page 7 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

Three copies of working drawings shall be issued to the successful tenderer


for construction purposes. Drawings shall be issued in phased manner
conforming to detail project schedule and review of site progress from time to
time. Contractor shall submit monthly programme for execution of works for
various units in advance to facilitate smooth flow of drawings.

05.02.11 Bench Mark

Standard bench mark reference pillar indicating the absolute level and
reference axes shall be indicated to the contractor. Contractor shall construct
all other survey pillars required by them for survey work with reference to the
bench mark pillar. Contractor shall take all precautions to protect the survey
pillars from being damaged / dislocated during progress of work, by providing
suitable barbed wire fencing around the survey pillars.

05.02.12 Site Instruction Book

For issuing site instructions to contractor by purchaser/consultant, the


contractor shall maintain triplicate order books with pages numbered. All
written site instruction shall be given on this book which shall be signed by
the contractor as token of his acceptance of the same. One carbon copy of
the instruction shall be left in the book for contractor for his taking necessary
action and record. Any instruction given to the contractor in the order book
shall have the same force as that of any instruction conveyed to the
contractor through a registered letter.

05.02.13 Dimensions

Figured dimensions shall prevail in preference to scaled dimension. Large


scale details will supersede small scale details shown in drawings. In case of
discrepancy between the two, the contractor shall obtain clearance of
purchaser/consultant before proceeding with work.

05.02.14 Works not to be misused

All works under or in course of execution or executed shall not be used by


the Contractor for any of his purpose e.g. storage of materials, residence,
office etc. under any circumstances.

05.02.15 Sequence of work


Copyright 2017. MECON Limited. All Rights Reserved. Page 8 of 16
STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

Contractor shall plan the sequence of all works so as to achieve the desired
progress keeping in mind overall safety and stability at all points of time.

If due to a particular design or specification or availability of machines or any


other reason, a particular sequence of operation is demanded by the
engineer due to which some interruptions are inherent to any one or more
types of work or items of execution, then no claim for such interruption shall
be entertained and contractor shall have to follow the sequence as instructed
by the engineer.

05.02.16 Damages

Any existing services or other properties if damaged or demolished during the


course of execution either willingly or negligently, shall be repaired and re-
erected to its original shape & size by the Contractor at his own cost.

The Contractor will take all precautions against damages due to rain and
storm and no liability shall rest with the purchaser for any loss for redoing of
any work on this account.

Existing underground services coming in the way of trench or foundation


excavation etc. have to be adequately safeguarded by the Contractor at his
own cost so as to avoid any damage to those services. In case of any
accidental damage, the Contractor shall arrange to rectify and reinstall those
services immediately at his own cost.

05.02.17 Testing

All pipelines, sewer, manholes, drainage lines shall be tested for smooth flow
without any stagnation as per specification. Smoke test shall be conducted
on sewer lines. Pressure test shall be carried out in all water supply lines as
per specifications by dividing the whole system, if required, into suitable
number of sub-systems by using stop cocks etc. for isolation of system.
Before, putting the bib-cocks etc. entire water supply plumbing lines shall be
pressure tested for ensuring no leakage condition. All such tests shall be
carried out by the Contractor at his own cost.

05.02.18 Quality Assurance

Copyright 2017. MECON Limited. All Rights Reserved. Page 9 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

a) To ensure quality of construction, the contractor shall ensure inspection


and testing of all materials and works at his own cost conforming to
specifications.
b) All certificates and guarantees obtained by the contractor from different
suppliers of materials, subcontractors doing part job, manufacturers of
doors, windows etc. shall be passed on to the purchaser.
c) All defective materials / works which do not conform to the specifications
shall be rejected / dismantled and removed from site by the Contractor at
his own cost.

d) Before starting any concreting or erection work at site, the stage passing
certificates have to be obtained from the engineer in the formats prepared
after mutual discussion and agreement.

e) As-built survey details marking location of all bolts and inserts shall be
submitted by the Contractor so as to enable further structural/equipment
erection without any loss of time.

f) Before covering up any work within excavated pits, clearance has to be


taken from engineer in respect of completion of said works as per
drawing and specification.

05.02.19 Explosives

Use of any kind of explosives either for rock blasting excavation or for any
other works is not envisaged. However controlled blasting can be taken up
for hard rock excavation with written permission of client on case to case
basis.

05.02.20 Construction Materials

a) All construction materials needed for civil works including cement shall
have to be arranged and procured by the Contractor.

b) Responsibility for ensuring the quality and custody of cement shall rest
with the Contractor. If the contractor uses the cement without any check
on quality which may result in poor quality concrete, then dismantling and
redoing such defective structures shall be at contractors cost. No claim
whatsoever due to poor quality of cement shall be entertained later.

Copyright 2017. MECON Limited. All Rights Reserved. Page 10 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

c) Tools, tackles & labour: The contractor shall make his own arrangements
for all tools, tackles and labour including hutment etc.

d) Purchaser will provide pipes as free issue item, as mentioned in BOQ.

05.02.21 Safety

The Contractor shall ensure that the safety requirements are met in respect
of men, materials, adjoining structures, equipment etc. and shall be totally
responsible in case any mishap occurs due to negligence or otherwise. In this
connection the contractor shall strictly adhere to the rules norms and
regulations as applicable. The successful bidder shall collect the Bhilai Steel
Plant safety rules from the client. The successful bidder shall strictly adhere
to the safety regulations mentioned therein. The penalties for violation of
safety norms as per purchaser stipulations are applicable

05.03 Preliminary Acceptance

After completing the construction or dismantling of a unit (as the case may
be) or agreed upon thereof, the Contractor shall give a notice in writing
stating that the job is completed in all respects and ready for preliminary
acceptance. The job shall jointly be inspected by the Owner, Consultant and
Contractor to ascertain whether the job is completed as per requirements and
technical specifications. All observed defects, deficiencies and omissions
shall be noted. If the defects, deficiencies and omissions are not major in the
opinion of Purchaser / Consultant, the contractor will be issued a preliminary
acceptance certificate mentioning observed defects, deficiencies and
omissions. The noted defects, deficiencies and omissions shall be made
good by the contractor within a period of 2 to 3 weeks time.

05.04 Final Acceptance

The contractor shall attend to all defects deficiencies and omissions noted
down during preliminary acceptance and after rectifying or making good the
above in all respects, shall inform 10 days in advance to Purchaser/
Consultant for conducting final acceptance. During final acceptance all
defects deficiencies and omissions noted during preliminary acceptance were
checked. Any defects / deficiencies /omissions not notified during preliminary
acceptance, if pointed out during final acceptance shall be made good by the
contractor. Final acceptance certificate shall be issued by
Copyright 2017. MECON Limited. All Rights Reserved. Page 11 of 16
STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

Purchaser/Consultant only after all the defects / deficiencies / omissions


noted under preliminary acceptance and final acceptance have been
rectified.

05.05 Maintenance period/Warranty period

Maintenance period of one year shall start after issuance of final acceptance
certificate. The contractor shall maintain and attend to all defects arising in
the structures constructed by them during the maintenance period .If any
major defects arises during such period, the contractor shall
reconstruct/rectify the same in stipulated period mutually discussed with
Purchaser/Consultant. Maintenance period of such area of work shall be
extended for a period of one year after rectification of major defects.

Copyright 2017. MECON Limited. All Rights Reserved. Page 12 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

Table A

SCHEDULE OF ITEMS/ BILL OF QUANTITIES

ITEM No. DESCRIPTION OF ITEM UNIT QTY. RATE AMOUNT


(Rs.) (Rs.)
1. Supply of Industrial Water Supply for Indirect Water Circuit of BOF, CCP and SRU from
Pump House ( WTP-6) of BRM
(A) Pipelines over Existing Trestle.

(i) Taking delivery of free issue of straight length RM 24


pipes in standard length of size DN - 600
( 610.0 X 12.0), loading /unloading ,
transportation from shop / stores/ revisioning
erection , laying installation of various
pipelines along with its fittings ( bends,
reducers/expanders, blanking arrangements ),
leveling alignment , welding including final
testing and painting with one coat and two
coats of synthetic enamel paint commissioning
as per , drawings / specification or as directed
by engineer in charge over existing
structures / trestles for height up to 10 mtrs.
(ii) Taking delivery of free issue of straight length RM 24
pipes in standard length of size DN - 500
( 508.0 X 12.0), loading /unloading ,
transportation from shop / stores/ revisioning
erection , laying installation of various
pipelines along with its fittings ( bends,
reducers/expanders, blanking arrangements) ,
leveling alignment , welding including final
testing and painting with one coat and two
coats of synthetic enamel paint commissioning
as per , drawings / specification or as directed
by engineer in charge over existing
structures / trestles for height up to 10 mtrs.
(iii) Taking delivery of free issue of straight length RM 204
pipes in standard length of size DN - DN - 400
( 406.4 x 12.0), loading /unloading ,
transportation from shop / stores/ revisioning
erection , laying installation of various
Copyright 2017. MECON Limited. All Rights Reserved. Page 13 of 16
STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

pipelines along with its fittings ( bends,


reducers/expanders, blanking
arrangements ) , leveling alignment , welding
including final testing and painting with one
coat and two coats of synthetic enamel paint
commissioning as per , drawings /
specification or as directed by engineer in
charge over existing structures / trestles for
height up to 10 mtrs.
(iv) Taking delivery of free issue of straight length RM 120
pipes in standard length of size DN - 300
(323.8 X 9.52), loading /unloading ,
transportation from shop / stores/ revisioning
erection , laying installation of various
pipelines along with its fittings ( bends,
reducers/expanders, blanking
arrangements) , leveling alignment , welding
including final testing and painting with one
coat and two coats of synthetic enamel paint
commissioning as per , drawings /
specification or as directed by engineer in
charge over existing structures / trestles for
height up to 10 mtrs.
(B) Isolation Valves ( Gate/Butterfly)
(i) Taking delivery of valves , flanges, DN 500 01 Nos
nuts/bolt/washer etc. from shop stores ,
loading / unloading transportation ,erection , DN 400 01 Nos
installation , leveling alignment , initial and
final testing commissioning as per , drawings /
DN 300 02 Nos
specification or as directed by , engineer in
charge.
(C) Blanking Arrangement;
(i) Taking delivery of set of blank flanges, DN 1000 02 Nos
nuts/bolt/washer etc. from shop stores , DN 500 02 Nos
loading / unloading transportation ,erection , DN 450 02 Nos
installation , leveling alignment , initial and DN 400 02 Nos
final testing commissioning as per , drawings /
specification or as directed by , engineer in
charge.

2. Supply of Industrial Water for Direct Water Circuit of CCP from existing Pump
House of Merchant Mill.

Copyright 2017. MECON Limited. All Rights Reserved. Page 14 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

(A) Pipelines.
(i) Taking delivery of free issue of straight length
pipes in standard length of size DN - 600 ( 610.0 RM 24
X 12.0), loading /unloading , transportation
from shop / stores/ revisioning erection , laying
installation of various pipelines along with its
fittings ( bends, reducers/expanders, blanking
arrangements), leveling alignment , welding
including final testing and painting with one coat
and two coats of synthetic enamel paint
commissioning as per , drawings / specification
or as directed by engineer in charge over
existing structures / trestles for height up to 10
mtrs.
(ii) Taking delivery of free issue of straight length
pipes in standard length of size DN - DN - 400 RM 408
( 406.4 x 12.0), loading /unloading ,
transportation from shop / stores/ revisioning
erection , laying installation of various pipelines
along with its fittings ( bends,
reducers/expanders, blanking arrangements ) ,
leveling alignment , welding including final
testing and painting with one coat and two coats
of synthetic enamel paint commissioning as per
, drawings / specification or as directed by
engineer in charge over existing structures /
trestles for height up to 10 mtrs.
(B) Isolation Valve ( Gate / Butter Fly)
(i) Taking delivery of valves , flanges,
nuts/bolt/washer etc. from shop stores , loading / DN 400 02 Nos
unloading transportation ,erection , installation ,
leveling alignment , initial and final testing
commissioning as per , drawings / specification
or as directed by , engineer in charge.
(C) Blanking Arrangement
Taking delivery of set of blank flanges, DN700 02 Nos
nuts/bolt/washer etc. from shop stores , loading / DN 500 02 Nos
unloading transportation ,erection , installation ,
leveling alignment , initial and final testing
commissioning as per , drawings / specification
or as directed by , engineer in charge.
3 Supply of Industrial Water for Direct Water Circuit of BOF and SRU

Copyright 2017. MECON Limited. All Rights Reserved. Page 15 of 16


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT, BHILAI
TECHNICAL SPECIFICATION FOR BALANCE WORK OF
MAKE-UP & DRINKINGWATER FACILITIES FOR ALL UNITS OF
7.0 MT EXPANSION
(Pkg;078B)

(A) Pipeline
Taking delivery of free issue of straight length
pipes in standard length of size DN - 500 ( 508.0 RM 36
X 12.0), loading /unloading , transportation
from shop / stores/ revisioning erection , laying
installation of various pipelines along with its
fittings ( bends, reducers/expanders, blanking
arrangements), leveling alignment , welding
including final testing and painting with one coat
and two coats of synthetic enamel paint
commissioning as per , drawings / specification
or as directed by engineer in charge.

Copyright 2017. MECON Limited. All Rights Reserved. Page 16 of 16

Вам также может понравиться