Вы находитесь на странице: 1из 25

R.C.C. Work Estimation Area Sft. 13287.

9 Length(ft)
Total Floor Area
SL.
Items Unit Quantity Rate
No.
A Upto Plinth Level
1 Footing Casting TOILET (1:1.5:3) ......OK Cft 72
Cement Bag 16 420.00
S Sand Cft 16 60.00
L Sand Cft 16 20.00
CHIPS NOS 648 99.00
Sub. Total:
2 3" CC Work ( for Footing 1:2:4) Cft
Cement Bag 0 440.00
S Sand Cft 0 40.00
L Sand Cft 0 20.00
Bricks Nos 0 8.00
Sub. Total:

4 Short Column Casting (1:1.5:3) HT UP TO ANC B=12FT Cft 430


...... Cement Bag 94 420.00
S Sand Cft 97 60.00
L Sand Cft 97 20.00
stone Cft 387 99.00
Sub. Total:

4 Ramp Casting (1:1.5:3) ...... Cft 162


Cement Bag 35 420.00
S Sand Cft 36 60.00
L Sand Cft 36 20.00
CHIPS Cft 145 99.00
Sub. Total:

5 Earth Filling (For footing ) Cft 1,600 0.00


6 Earth Cutting (For footing) Cft 1,600 0.00

7 Grade Beam Casting (1:1.5:3) ...... Cft 806


Cement Bag 176 420.00
S Sand Cft 181 60.00
L Sand Cft 181 20.00
CHIPS cft 725 99.00
Sub. Total:
8 R.C.C Ground Floor Casting (1:2:4) Cft 7,180
...... Cement Bag 1,231 420.00
S Sand Cft 1,615 60.00
L Sand Cft 1,615 20.00
Bricks CFT 6,462 99.00

Sub. Total:
8 (1:3:6) JHAMA BRICKS CONCRETE OK Cft 135
Cement Bag 16 420.00
L Sand Cft 61 20.00
CHIPS Cft 122 99.00
Sub. Total:

9 3" Brick Soling (for Ground Floor) OK Sft 14,121


Bricks Nos 42,364 10.00
Sub. Total:

10 3" Brick Soling ( below GB) OK Sft 663


Bricks Nos 2,034 10.00
Sub. Total:

11 C.C. Work (For B/W Below GB of Periphery) Cft 0


Cement Bag 0 430.00
Sand Cft 0.0 20.00
Brick Chips Cft 0 0.00
Bricks Nos 0.0 7.00
Sub. Total:

12 10" B/W Bellow GB of Periphery (2'-6'') Sft 0


Cement Bag 0 440.00
L Sand Cft 0 16.00
L Sand Cft 0 16.00
Bricks Nos 0 8.00
Sub. Total:

16 R.C.C Lintel (1:1.5:3) Cft 225


...... Cement Bag 49 420.00
S Sand Cft 51 60.00
L Sand Cft 51 20.00
Bricks CFT 202 99.00
Sub. Total:
4 MS ROD 60 GRADE BSRM/AKS/KSRM ......
Reinforcement (For column) Kg 25,550 58.00
Sub. Total:
18 Sand filling and back filling ok 26,123.7
Sand Cft 26,124 20.00
Sub. Total:
21 COMPACTED SAND KHOWA (1:1) OK Cft 3,352
S Sand Cft 1,676 60.00
Bricks Nos 15,086 10.00

23 250 mm Brick Wall 1st Floor Sft 883


Cement Bag 139 420.00
L Sand Cft 1,034 20.00
Bricks Nos 10,995 10.00
Sub. Total:
22 12mm Thick Plaster 1 : 6 Sft 6,756
Cement Bag 69 420.00
Sand Cft 339 20.00
Sub. Total:
25 Tiles Work with labor Cost Sft 0 120

Sub. Total:
27 4" R.C.C 3rd Floor slab Casting (1:2:4) Cft
Cement Bag 0 400.00
S Sand Cft 0 50.00
L Sand Cft 0 15.00
Bricks Nos 9.50
Reinforcement Ton 52.00
Sub. Total:
28 5" Brick Wall 3rd Floor Sft
Cement Bag 0 400.00
L Sand Cft 0 15.00
L Sand Cft 0 15.00
Bricks Nos 0 9.50

Sub. Total:
28 12mm Thick Plaster Sft
Cement Bag 0 400.00
Sand Cft 0 15.00
Sub. Total:

30 Tiles Work with labor Cost Sft 0 120


Sub. Total:
31 #REF! Cft
Cement Bag 0 400.00
S Sand Cft 0 50.00
L Sand Cft 0 15.00
Bricks Nos 0 9.50
Reinforcement (For Column, Tie Beam,lintel) Ton 52.00
Sub. Total:
32 4" R.C.C 4th Floor slab Casting (1:2:4) Cft 0
Cement Bag 0 400.00
S Sand Cft 0 50.00
L Sand Cft 0 15.00
Bricks Nos 0 9.50
Reinforcement Ton 0.000 52.00
Sub. Total:
33 5" Brick Wall 3rd Floor Sft 0
Cement Bag 0 400.00
L Sand Cft 0 15.00
L Sand Cft 0 15.00
Bricks Nos 0 9.50

Sub. Total:
34 12mm Thick Plaster Sft 0
Cement Bag 0 400.00
Sand Cft 0 15.00
Sub. Total:

35 Tiles Work with labor Cost Sft 0 120


Cement Bag 0 0.00
48.00
22.00
8.00
Sub. Total:
36 #REF! Cft 0
Cement Bag 0 455.00
S Sand Cft 0 48.00
L Sand Cft 0 22.00
Bricks Nos 0 7.60
Reinforcement (For Column, Tie Beam,lintel) Ton 0.000 58,000.00
Sub. Total:
37 4" R.C.C 5th Floor slab Casting (1:2:4) Cft 0
Cement Bag 0 455.00
S Sand Cft 0 48.00
L Sand Cft 0 22.00
Bricks Nos 0 7.60
Reinforcement Ton 0.000 58,000.00
Sub. Total:
38 5" Brick Wall 3rd Floor Sft 0
Cement Bag 0 455.00
L Sand Cft 0 22.00
L Sand Cft 0 22.00
Bricks Nos 0 8.00

Sub. Total:
39 12mm Thick Plaster Sft 0
Cement Bag 0 455.00
Sand Cft 0 22.00
Sub. Total:
40 Tiles Work with labor Cost Sft 0 120
Cement Bag 0 0.00
48.00
22.00
8.00
Sub. Total:
41 #REF! Cft 0
Cement Bag 0 455.00
S Sand Cft 0 48.00
L Sand Cft 0 22.00
Bricks Nos 0 7.60
Reinforcement (For Column, Tie Beam,lintel) Ton 0.000 58,000.00
Sub. Total:
42 4" R.C.C Roof slab Casting (1:2:4) Cft 0
Cement Bag 0 455.00
S Sand Cft 0 48.00
L Sand Cft 0 22.00
Bricks Nos 0 7.60
Reinforcement Ton 0.000 58,000.00
TOTAL

17 Labor Cost & Shatter Materials Cost Sft 13,288


TOTAL WITH LABOR

*** Considering 1.0Tsf as Bearing Capacity of Soil at 5ft depth


Note: The following items is not considered.
01) Painting,02) Plumbing ,03) Earth filling & Compaction 04) water drain 05) Floor net finishing & til
\

RCC MATERIALS SUMMARY


Iteams Units Quantity Rate
CEMENT Bags 1,825 420
Sylhet SAND Cft 3,673 60
Local SAND Cft 29,554 20
BRICKS CFT 8,692 99.0
BRICKIS PCS 70,478 10.0
REINFORCEMENT Kg 25,550 58
Labor Cost & Shatter Materials Cost
Transportation
Earth Cuting & Filling
Total Cost
Page _______

width(ft)
13,288 Sft.

Total Value Unit Rate

Size 4'X3.833'X10"
6,597.82
972.00
324.00
64,152.00
72,045.82 5.42 1000.636363636

0.00
0.00
0.00
0.00
0.00 0.00

39,420.60 600
5,820.00 350
1,935.83 350
38,329.49 350
85,505.92 6.43 198.7654235689

14,811.02
2,181.98
727.33
14,401.07
32,121.40 #REF! 198.7363636364

0.00 0.00
0.00 0.00

73,861.07
73,861.07
3,627.11
71,816.70
223,165.95 16.79 276.8727272727
516,942.04
96,926.63
32,308.88
639,715.77

1,285,893.31 #REF! 179.1

6,811.63
1,216.36
12,057.61
20,085.59 1.51 148.61559648

423,637.82
423,637.82 31.88 30

20,340.00
20,340.00 1.53 30.6787330317
#REF!

0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00 0.00

20,599.61
3,034.76
1,011.59
20,029.44
44,675.40 198.7363636364

1,481,900.00
1,481,900.00 #REF! 58
522,474.13
522,474.13 39.32

100,571.21
150,856.81
251,428.02 18.92 #REF!

58,583.70
20,676.60
109,947.00
189,207.30 14.24

29,012.68
6,782.18
35,794.86 2.69
0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00 3RD FLOOR
0.00 0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 #REF!

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00 4TH FLOOR
0.00 0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00
0.00 #REF!

0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00 0.00
0.00
0.00
0.00
0.00
0.00
0.00 0.00

0.00
0.00
0.00
0.00
0.00 5TH FLOOR
0.00 0.00 0.00

0.00
0.00
0.00
0.00
0.00 ROOF
0.00 0.00

4,688,275.53
-
#VALUE!
#VALUE! #VALUE!
shing & tiles 06) Door & Windoow

Amount
766,640
220,388
591,084
860,502
704,782
1,481,900
-
-
-
4,625,296 4,688,276 #VALUE!

62,979.75
0
0
0
0
0
0
0
TOOTAL STEEL BUILDING PRODUCTS LTD.
HOUSE #400, ROAD #29, NEW DOHS MOHAKHALI , DHAKA-1206
Date:18/06/2017
Name of the project: Spectra Oxigen Summary of RCC casting from footing to A B
Length =123 ft, width =26.24 ft

Bricks Bricks
Sylhet Local Bricks Total Stone
Cement needed for
SL Items sand Sand chips bricks chips
(Bag) for chips soling
(cft) (cft) (cft) (pcs) (cft)
(pcs) ( pcs )
A Upto Plinth Level
1 Footing Casting (1:1.5:3) 16 16 16 65 6,000 6,000
2 3" Brick Soling ( for Footing) 0 #REF! #REF!
Short Column Casting (1:1.5:3) HT UP
3 TO A B=12FT 94 97 97 387 4,000 4,000
4 Grade Beam Casting (1:1.5:3) 176 181 181 725 5,000 5,000
5 4" R.C.C Ground Floor Casting (1:2:4) 1,231 1,615 1,615 6,462 64,618 64,618 122
6 3" Brick Soling (for Ground Floor) 0 42,364 42,364
7 Brick Soling ( below GB) 0 2,034 2,034
Total = 1,516 1,910 1,910 7,639 79,618 #REF! #REF! 122
SL Items ROD (KG)
A Upto Plinth Level
1 Footing Casting (1:1.5:3) OK 514.5
2 3" Brick Soling ( for Footing) ok
3 Short Column Casting (1:1.5:3) HT UP TO ANC B=12FT 1810.2
4 Grade Beam Casting (1:1.5:3) ok 1522.5
5 4" R.C.C Ground Floor Casting (1:2:4) 1582.35
6 3" Brick Soling (for Ground Floor) ok
7 Brick Soling ( below GB)
reinforcement detail estimate

20 mm total each
sl item name unit 16 mm 12 mm 10 mm
dia item
1 FOOTING kg 490 490
2 GB kg 1010 440 1450
3 column kg 0 1362 362 1724
4 LINTEL kg 482 482
5 4 in floor kg 1507 1507
6 total kg 0 2372 490 2791 5653
TOTAL WITH
7 WASTAGE kg 0 2490.6 514.5 2930.55 5935.65
456345
TOOTAL STEEL BUILDING PRODUCTS LTD.
HOUSE #400, ROAD #29, NEW DOHS MOHAKHALI , DHAKA-1206

Name of the project: Trough House. Green Field Tea


Total Floor Area 13,288
SL Items Unit Quantity
A Upto Plinth Level
1 Footing Casting TOILET (1:1.5:3) ......OK Cft 72
2 3" CC Work ( for Footing 1:2:4) Cft -
3 #REF! #REF! #REF!
4 Short Column Casting (1:1.5:3) HT UP TO ANC B=12 Cft 430
5 Earth Filling (For footing ) Cft 1,600
6 Earth Cutting (For footing) Cft 1,600
7 Grade Beam Casting (1:1.5:3) ...... Cft 806
8 (1:3:6) JHAMA BRICKS CONCRETE OK Cft 135
9 3" Brick Soling (for Ground Floor) OK Sft 14,121
10 C.C. Work (For B/W Below GB of Periphery) Cft -
11 10" B/W Bellow GB of Periphery (2'-6'') Sft -
13 #REF! #REF! #REF!
Grand Total =
14 Labor Cost & Shatter Materials Cost Sft 13,288
Transportation
Grand Total incl Labour Cost & Shatter Materials Cost =

*** Considering 1.0ksf as Bearing Capacity of Soil at 5ft depth from EGL
Note: The following items is not considered.
01) Painting, 02) Plumbing , 03) Earth filling & Compaction 04) water drain
05)Machine Foundation
06
Date:09/08/2016

Sft.
Total Value Tk.

72,046 1,000.64
0
#REF!
85,506
0
0
223,166
20,086
423,638
0
0
#REF!
#REF!
#VALUE!
50,000
#VALUE! #VALUE!

Вам также может понравиться