Daily Mock UP Comments Update

Included
S/N Title Comment Status/ Date Comment
MUR HOTEL

A) Marble to shower wall is to be adjusted MUR 25/10/2016 NOT APPROVED

B) The top edge to upper tiles is to be factory cut with a sharp clean edge HOTEL DONE ON SITE
1 Porcelain Tiles
C) Tile cutting quality not acceptable. Contractor to prepare sample mock
HOTEL DONE ON SITE
up for review and approval
D) Vertical tile junction detail- sample at Main Hotel building to be
HOTEL DONE ON SITE
followed
A) Shower Drain quality issue. Marble insert to be installed. MUR DONE
2 Drains
B) Bathroom Floor Drain, marble insert to be installed. HOTEL FLOOR DRAIN TO ALIGHED WITH TILES EDGES

A) Glass shower screen to be centered within marble panel.


B) Shower Screen manifestation manifestation to be reversed as per HOTEL CLIENT REQUEST THAT THE PROPER SAMPLE TO BE
3 Shower glass
drawings. Room 112 INSTALLED IN THE CURRENT MUR
C) Shower screen glass quality not acceptable

4 Balustrades hand rail Not as per specs/design MUR DONE


CLIENT REQUEST THAT THE LEVEL TO BE ADJUSTED IN THE
5 Bathroom JU-24 - Bathroom Vanity Fixed Shelf 563mm width Hotel
CURRENT MUR
A) JU-23A - Wardrobe 1, overall size 700mm (W) x 2400mm (H) DONE

6 Wardrobe B) JU-23B - Wardrobe 2, overall size 700mm (W) x 2400mm (H) MUR DONE

C) Ironmongery For Wardrobe / Vanity / Counter DONE


JU-22 - Mini Bar Unit/TV Wall Unit including Wood Veneer
7 Mini Bar MUR DONE
Drawer, SS Metal Legs, Decorative Acrylic Panel; overall size
A) Carpet for guestrooms - Type CP-05 - Quality comments MUR DONE NOT ACCEPTABLE
8 Carpets
B) Carpet for corridors - Type CP-04 MUR GAJ COORDINATION ONGOING

9 Skirting Wooden Skirting - Type W-02 MUR DONE

10 Wall Wall (paper) covering - Type WC-03 MUR 28/10/2016

A) 01-300, Roller Blind Block Out with 01-906 MUR DONE


11 Roller Blind
B) 01-301, Roller Blind Sheer with 01-907 MUR DONE

A) 01-400, Side Table DONE


12 Tables MUR
B) 01-401, Desk 1500mm 7/11/2016 DELIVERY ON SITE

A) 01-500 Armchair with 01-903 and 01-908 MUR DONE


13 Chair
13 Chair
B) 01-502, Desk Chair with 01-908 Hotel DATE REQUIRED

A) 01-503, Head Board with 01-901 DONE Done


14 Bed MUR
B) 01-504, Bed Base with 01-900 28/11/2016
A) Main Door:
Main door elevation to be
B) Guest Room bottom connector cutting in
quality issue.
C) Bathroom Door: Robe hooks are still not as per updated specifications. CLIENT REQUEST THAT THE PROPER SAMPLE TO BE
15 Wooden Doors Hotel
GAJ ID elevation details 2 separate INSTALLED IN THE CURRENT MUR
D) Wall mounted door stop missing; to be located at low level. GAJ to
confirm location.
E) Timber above bathroom door architrave is to be cancelled. Architrave
to remain, to have a 5mm shadow gap detail between architrave and wall
A) 01-600 FLOOR LAMP MUR DONE

B) 01-601 PENDANT LAMP MUR DONE


16 LAMPS
C) 01-602 TASK LAMP MUR DONE
SHAZA CONFIRMEED THEIR SELECTION YET GAJ RESPONSE
D) 01-603 BEDSIDE TABLE LAMP MUR DONE
STILL PENDING
SHAZA CONFIRMEED THEIR SELECTION YET GAJ RESPONSE
01-800 Framed Photographic Print on Paper MUR
STILL PENDING
17 Photographic
01-802 Framed Photographic Print on Paper MUR DATE REQUIRED

18 TRAY 01-702 LOOSE TRAY MUR REJECTEED BAD INTERPRETATION OF THE COMMENTS

A) Card Holder MUR DONE


19 GRMS
B) Window Contact Hotel DATE REQUIRED

20 Lights Ceiling down lights MUR Done

A) 13A SPUR for FCU MUR DONE ONLY ONE SAMPLE


21 Wiring Devices
B 13A TSSO-IPTV MUR DONE ONLY ONE SAMPLE

A) Bathroom Telephone MUR DONE


22 Voice Communication
B) Telephone MUR DONE COMPLIANCE TO BE CONFIRMED BY GTGC
A) PDFF SW 07 - Thermostatic Concealed
Hotel DATE REQUIRED
Shower Mixer
B) PDFF SW 08 - Spout in Shower MUR SAMPLE STILL PENDING APPROVAL
Sanitary wares for Standard
23
TWIN & KING Room
C) SA 05 - Towel Rack MUR 28/10/2016

D) SA 07 - Retractable Clothes Line MUR 28/10/2016