MATERIALS SCHEDULE

FOR PROPOSED RESIDENTIAL

FOR ANN KIRAZA

MATERIAL SCHEDULE

PREPARED BY:
KALEMA SOLOMON
0777006704
ELEMENT DESCRIPTION PAGE NO MATERIAL COST
(USHS)

MATERIALS SCHEDULE
PROPOSED RESIDENTIAL HOUSE
FOR ANN KIRAZA
MATERIAL SUMMARY

MAIN WORKS 97,332,180


27,450,750
FINISHES
28,953,000
FIXTURES AND FITTINGS
6,300,000
ELECTRICALS
3,150,000
PLUMBING
16,705,000
EXTERNAL WORKS

SUB TOTAL 179,890,930

LABOUR COSTS (27 % FINAL MATERIAL COST) 48,570,551

TOTAL PROJECT COST FOR MATERIALS AND LABOUR 228,461,481


ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

MATERIALS SCHEDULE
ACTIVITY NO.1
SUBSTRUCTURE
The work in this activity includes all works up to and including the
ground floor slab

A SETTING OUT
Building line/string ROLLS 2 8,000 16,000
Pegs- 50mm x 50mm x 3.0m(2' x 2') long wrot softwood PC 10 4,000 40,000

B HARDCORE FILLING SM 137


150mm thick hardcore bed in granite broken stones-5 tonne truck TRIPS 2 150,000 300,000
Damp proof Membrane ROLLS 2 120,000 240,000

C MURRAM FILLING CM 14
200mm murram filling to make up levels; well rolled and
TRIPS 2 150,000 INCLUDED
compacted to 95% MDD

D SAND BLINDING SM 137


50mm thick sand blinding on tops of hardcore 5 tonne truck TRIPS 2 180,000 360,000

E ANTI-TERMITE TREATMENT SM
Insecticide treatment to surface of hardcore, tops of foundation TINS 2 100,000 200,000
walling and bottoms of excavations

SAWN FORMWORK TO:

F STARTER COLUMNS 26
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 26 8,000 208,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 10 6,000 60,000
iii Eucalyptus Poles 150mm girth PC 5 3,000 15,000
iv Nails KG 1 4,000 4,000

REINFORCEMENT BARS FOR:

G PAD FOUNDATION
High yield Square Twisted steel bars T16x 12 Metres Long-
ii PC 60 46,000 2,760,000
columns
iii 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 INCLUDED

STARTER COLUMNS:
ii High yield Square Twisted steel bars T16 x 12Metres PC 11 46,000 506,000
iii Mild Steel Round Bars R8 x 12 Metres Long PC 11 25,000 275,000
iv 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000

CONCRETE
GRADE 10 (MIX 1:4:8) IN BLINDING FOR PAD
H CM 3
FOUNDATIONS(50mm thick)
i Aggregate (Hand Crushed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand (6tonne truck) TRIPS 1 220,000 220,000
iii Cement (50kg bag) BAGS 10 30,000 300,000

GRADE 20 (MIX 1:2:4) IN PAD FOUNDATIONS &


I CM 9
STARTER COLUMNS
i Aggregate (Hand Crushed 20mm) 6tonne truck TRIPS 2 270,000 540,000
ii Lake Sand (6 tonne truck) TRIPS 1.0 220,000 220,000
iii Cement (50kg bag) BAGS 60 31,000 1,860,000

TOTAL CARRIED TO COLLECTION 8,474,000


1/1/1
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

A GRADE C15 (MIX 1:3:6) IN STRIP FOUNDATION CM 10


i Aggregate (Hand Crushed 20mm) 6tonne truck TRIPS 2 270,000 540,000
ii Lake Sand (6 tonne truck) TRIPS 1 220,000 220,000
iii Cement (50kg bag) BAGS 44 31,000 1,364,000

B PLINTH WALLING/BRICKWORK SM 86

200mm Thick PLINTH BRICK WALLING IN CEMENT


C
SAND (1:4) MORTAR

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 5,670 280 1,587,600
ii Cement (50kg bag) BAG 40 30,000 1,200,000
iii Lake Sand (forward 6tonne truck) TRIPS 2 220,000 440,000
iv Hoop iron ROLLS 6 31,000 186,000
v 1000 GAUGE DPC ROLLS 250,000 INCLUDED

GROUND FLOOR

GRADE 15 (MIX 1:3:6) IN OVERISTE CONCRETE SLAB


D CM 13
100mm Thick (MAIN BLOCK AND PARKING LOT)

i Aggregate (Hand Crushed 20mm) 6tonne truck TRIPS 4 270,000 1,080,000


ii Lake Sand (forward 6 tonne truck) TRIPS 2 220,000 440,000
iii Cement (50kg bag) BAGS 60 31,000 1,860,000
iv 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 23 8,000 184,000
v 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 12 6,000 72,000

E REINFORCEMENT
i A-98 BRC Mesh 2.4X48m ROLLS 2 650,000 1,300,000

SPLASH APRON (600 x 100mm) GRADE 15 (1:3:6 concrete


F SM 112 8
mix)

i Cement BAGS 35 31,000 1,085,000


ii Sand(6tonne Truck) TRIPS 2 220,000 440,000
iii Aggregates( 6tonne truck) TRIPS 1 270,000 270,000
v BRC Mesh A66 ROLLS 1.0 300,000 300,000

12,568,600

FROM PAGE 1/1/1


8,474,000

FROM PAGE 1/1/2 12,568,600

TOTAL CARRIED TO MATERIAL SUMMARY 21,042,600


1/1/2
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

RESIDENTIAL
MATERIALS SCHEDULE
ACTIVITY NO.2
SUPERSTRUCTURES-GROUND FLOOR

A SAWN FORMWORK TO:

COLUMNS
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 52 8,000 416,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 25 6,000 150,000
iii Eucalyptus Poles 150mm girth PC 20 3,000 60,000
iv Nails KG 15 4,000 60,000

B REINFORCEMENT BARS FOR COLUMNS:


ii High yield Square Twisted steel bars T16 x 12 Metres PC 35 46,000 1,610,000
ii Mild Steel Round Bars R8 x 12 Metres Long PC 30 25,000 750,000
iii 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000

C CONCRETE WORK

GRADE C20 (MIX 1:2:4) IN COLUMNS CM 4


i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand 6tonne truck TRIPS 1 220,000 220,000
iii Cement (50kg bag) BAGS 25 30,000 750,000

200mm & 100mm Thick BRICK WALLING IN CEMENT


D SM 163
SAND (1:4) MORTAR

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 10,500 280 2,940,000
ii Cement (50kg bag) BAGS 75 31,000 2,325,000
iii Lake Sand 6tonne truck TRIPS 7 220,000 1,540,000
iv Hoop iron Roll 10 30,000 300,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 118 280 33,040
ii Cement (50kg bag) BAGS 50 31,000 1,550,000
iii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iv Hoop iron Roll 8 30,000 240,000
v 1000 gauge polythene DPC ROLL 1 120,000 INCLUDED

I SCAFFOLDINGS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 8 8,000 64,000
ii Eucalyptus Poles 150mm girth PC 15 3,000 45,000
iii Nails KG 5 4,000 20,000

STAIRS-GROUND FLOOR

E SAWN FORMWORK
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 9 8,000 72,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 6 6,000 36,000
iii Eucalyptus Poles 150mm girth PC 4 3,000 12,000
iv Nails KG 2 4,000 8,000

F STAIRS REINFORCEMENT
i High yield Square Twisted steel bars T12 x 12Metres PC 10 25,000 250,000
ii 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000

TOTAL CARRIED TO COLLECTION 14,441,040


1/2/1
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

A CONCRETE WORK

GRADE C20 (MIX 1:2:4) IN STAIRS AND LANDINGS CM 2


i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1.0 270,000 INCLUDED
ii Lake Sand 6tonne truck TRIPS 1.0 220,000 INCLUDED
iii Cement (50kg bag) BAGS 8 31,000 248,000

B SCAFFOLDINGS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 15 8,000 120,000
ii Eucalyptus Poles 150mm girth PC 8 3,000 24,000
iii Nails KG 1 4,000 4,000

396,000

FROM PAGE 1/2/1 14,441,040

FROM PAGE 1/2/2 396,000

TOTAL CARRIED TO MATERIAL SUMMARY 14,837,040


1/2/2
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

APARTMENT BLOCK
MATERIALS SCHEDULE
ACTIVITY NO.3 FIRST FLOOR
SUPERSTRUCTURES-FIRST FLOOR

A SAWN FORMWORK TO:

COLUMNS
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 52 8,000 416,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 25 6,000 150,000
iii Eucalyptus Poles 150mm girth PC 20 3,000 60,000
iv Nails KG 15 4,000 60,000

B STAIRCASE
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 9 8,000 72,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 6 6,000 36,000
iii Eucalyptus Poles 150mm girth PC 4 3,000 12,000
iv Nails KG 2 4,000 8,000
C BEAMS

i 300mm x 25mm x 3m (12'x1') long Wrot Softwood PC 80 8,000 640,000


ii 100mm x 50mm x 3m (4'x2') long Wrot Softwood PC 30 6,000 180,000
iii Eucalyptus Poles PC 30 3,000 90,000
iv Nails KG 40 4,000 160,000

D SLABS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 16 8,000 128,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 215 6,000 1,290,000
iii Eucalyptus Poles PC 600 3,000 1,800,000
iv Nails KG 80 4,000 320,000

E REINFORCEMENT BARS FOR :

COLUMNS

i High yield Square Twisted steel bars T20 x 12 Metres PC 35 71,000 2,485,000
ii High yield Square Twisted steel bars T16 x 12 Metres PC 30 46,000 1,380,000
iii Mild Steel Round Bars R8 x 12 Metres Long PC 1.0 11,000 11,000
iv 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000

F BEAMS

ii High yield Square Twisted steel bars T16 x 12 Metres PC 52 46,000 2,392,000
iv Mild Steel Round Bars R8 x 12 Metres Long PC 30 11,000 330,000
v 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000

G SLAB

i High yield Square Twisted steel bars T12 x 12 Metres PC 110 25,000 2,750,000
ii High yield Square Twisted steel bars T10 x 12 Metres PC 40 17,000 680,000
iii BRC A-142 NO 1 754,000 754,000
iv 1.8mm Binding wire (25Kg) ROLL 2 80,000 160,000

H STAIRCASE
i High yield Square Twisted steel bars T12 x 12 Metres PC 10 25,000 250,000
iii 1.8mm Binding wire (25Kg) ROLL 1 80,000 INCLUDED

TOTAL TO BE CARRIED TO COLLECTION 16,774,000


1/3/1
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

A CONCRETE AND/OR MAXSPANS:

GRADE 20 (MIX 1:2:4) IN COLUMNS CM 4


i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand 6tonne truck TRIPS 1 220,000 220,000
iii Cement (50kg bag) BAGS 25 31,000 775,000
-
-
B GRADE 20(MIX 1:2:4) IN BEAMS CM 7 -
-
i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iii Cement (50kg bag) BAGS 44 31,000 1,364,000
-
C GRADE 20 (MIX 1:2:4) IN 250mm thick SLAB CM 10 -
-
i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 2 270,000 540,000
ii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iii Cement (50kg bag) BAGS 60 31,000 1,860,000
iv 300 x 300 x 150mm Maxspans NO 1,110 3,000 3,330,000
v Damp proof Membrane ROLLS 2 120,000 240,000
-
-
GRADE 20 (MIX 1:2:4) IN STAIRS AND LANDINGS CM 2 -
-
i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand 6tonne truck TRIPS 1.0 220,000 INCLUDED
iii Cement (50kg bag) BAGS 12 31,000 372,000
iv Damp proof Membrane ROLLS 120,000 INCLUDED
INCLUDED
230mm & 150mm Thick BRICK WALLING IN CEMENT
D SM 176
SAND (1:4) MORTAR

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 11,600 280 3,248,000
ii Cement (50kg bag) BAGS 90 31,000 2,790,000
iii Lake Sand 6tonne truck TRIPS 4 220,000 880,000
iv Hoop iron ROLL 8 35,000 280,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 118 280 33,040
ii Cement (50kg bag) BAGS 50 31,000 1,550,000
iii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iv Hoop iron ROLL 8 35,000 280,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000

20,132,040

FROM PAGE 1/3/1 16,774,000

FROM PAGE 1/3/2 20,132,040

TOTAL CARRIED TO MATERIAL SUMMARY 36,906,040


ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

RESIDENTIAL
ACTIVITY 4-RINGBEAMS, ROOFING, CEILING AND
ROOF SLABS

A SAWN FORMWORK

i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 80 8,000 640,000


ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 30 6,000 180,000
iii Eucalyptus Poles 150mm girth PC 30 3,000 90,000
iv Nails KG 40 4,000 160,000

B REINFORCEMENT BARS

i High yield Square Twisted steel bars T16 x 12 Metres PC 52 46,000 2,392,000
iv Mild Steel Round Bars R8 x 12 Metres Long PC 30 11,000 330,000
v 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000

C GRADE 20 (MIX 1:2:4) CONCERETE CM 7

i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 1 270,000 270,000


ii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iii Cement (50kg bag) BAGS 44 30,000 1,320,000

D SAWN FORMWORK TO ROOF SLABS

i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 100 8,000 RE-USED
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 50 6,000 RE-USED
iii Eucalyptus Poles 150mm girth PC 3,000 RE-USED
iv Nails KG 20 4,000 80,000

E REINFORCEMENT BARS TO ROOF SLABS

i High yield Square Twisted steel bars T12x 12 Metres PC 35 25,000 875,000
ii High yield Square Twisted steel bars T10 x 12 Metres PC 15 17,000 255,000
iv 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000

F CONCERETE FOR ROOF SLABS CM 8

i Aggregate (Machine crashed 20mm) 6tonne truck TRIPS 3 270,000 810,000


ii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iii Cement (50kg bag) BAGS 70 31,000 2,170,000
iv Damp proof Membrane ROLLS 120,000 INCLUDED

230mm thick ROOF BRICK WALL IN CEMENT SAND


G SM
(1:4) MORTAR

i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 5,000 280 1,400,000
ii Cement (50kg bag) BAGS 30 30,000 900,000
iii Lake Sand 6tonne truck TRIPS 1 220,000 220,000
iv Hoop iron ROLL 4 35,000 140,000
v 1000 gauge polythene DPC ROLL 1 120,000 INCLUDED

TOTAL CARRIED TO COLLECTION 13,272,000


ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

A ROOF STRUCTURE

i 225*25mm fascia board+ barge boards PCS 26 9,000 234,000


ii 4*2 inches rafters PCS 35 6,000 210,000
iii 4*3 inches wall plate PCS 100 7,000 700,000
iv 4*2 inches Ties and struts PCS 80 6,000 480,000
v 4*2 inches purlins PCS 20 6,000 120,000
vi 4*2 inches Tie beam PCS 25 6,000 150,000
vii Assorted nails KG 30 4,000 120,000
viii Whoop iron ROLLS 15 35,000 525,000

B ROOF COVERING

i Versatile roofing sheets NO 60 91,425 5,485,500


iii Assorted nails KG 100 4,000 400,000

C METAL LATHE CEILING 130

i 4*2 inches ceiling joists @800mm c/c spacing NO 80 6,000 480,000


ii 2*2 inches timber branderings @600mm c/c spacing NO 100 6,000 600,000
iii expanded metal ROLLS 7 30,000 210,000
iv Assorted nails KG 30 4,000 120,000

PERGOLA

Allow a provisional sum for construction of a Pergola structure at 1,440,000


80,000ugx per Sqm

11,274,500

FROM PAGE 1/4/1 13,272,000

FROM PAGE 1/4/2 11,274,500

TOTAL CARRIED TO MATERIAL SUMMARY 24,546,500


ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

MATERIAL SUMMARY

ACTIVITY 1-SUBSTRUCTURE 21,042,600

ACTIVITY 2-GROUND FLOOR 14,837,040

ACTIVITY 3-FIRST FLOOR 36,906,040

ACTIVITY 4-RINGBEAMS, ROOFING, CEILING AND


24,546,500
ROOF SLABS

MAIN WORKS TOTAL TO BE CARRIED TO MAIN


97,332,180
MATERIAL SUMMARY
ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
GENERAL FINISHES

CEILING FINISHES SM 145

A CEILING PLASTER

ON TOP OF MESH (20mm thick)(1:6)


i sand (forward 6tonne truck) TRIPS 1 180,000 180,000
iii cement BAGS 15 30,000 450,000

CEILING FINAL PLASTER (20mm thick)(1:4)


i sand (forward 6tonne truck) TRIPS 1 180,000 180,000
ii Cement 50kg bag BAGS 20 30,000 600,000
iii lime BAGS 5 25,000 125,000

B CEILING PAINT
i 1 coat of of primer paint 20 ltr BUCKET 1 55,000 55,000
ii 2 coats white matt emulsion 20 ltr BUCKET 2 190,000 380,000

FLOOR AND STAIRCASE FINISHES

C FLOOR SCREED (1:4) 50mm thick SM 1


i sand(forward truck) TRIPS 1 180,000 INCLUDED
ii Cement 50kg bag BAGS 2 30,000 INCLUDED

D CERAMIC TILES
i 6" X 6" floor tiles S.M 272 25,000 6,800,000
ii Tile grout (10kg bags) BAGS 10 25,000 250,000

H MARBLE WORKTOP
i 800mm wide granite tops LM 6 60,000 360,000

UNDER SLABS,EXPOSED COLUMNS BEAMS AND RING


SM 6
BEAMS

E PLASTERING (20mm thick)


i sand (forward 6tonne truck) TRIPS 5 180,000 INCLUDED
iii cement BAGS 20 30,000 INCLUDED
ii lime BAGS 5 25,000 INCLUDED

F PAINTING
i 1 coat of of undercoat 20 ltr BUCKET 5 55,000 275,000
ii 2 coats of silk vinyl emulsion paint 20 ltr BUCKET 5 235,000 1,175,000
iii 2 coats of weather guard paint 20 ltr BUCKET 8 235,000 1,880,000
iv white cement BAGS 4 75,000 300,000

WALL FINISHES
G PLASTER(30mm thick)

H INTERNAL WALLS SM 678


i sand (forward 6tonne truck) TRIPS 5 180,000 900,000
iii cement BAGS 90 30,000 2,700,000
ii lime BAGS 12 25,000 300,000

I EXTERNAL WALLS SM 472


i sand (forward 6tonne truck) TRIPS 4 180,000 720,000
iii cement BAGS 60 31,000 1,860,000
ii lime BAGS 8 25,000 200,000

TOTAL CARRIED TO COLLECTION 19,690,000


ITEM DESCRIPTION UNIT RATE (USHS) AMOUNT (USHS)

A PAINTING
INTERNAL WALLS 1,284
i 1 coat of of undercoat 20 ltr BUCKET 11 55,000 605,000
ii 2 coats of silk vinyl emulsion paint 20 ltr BUCKET 14 235,000 3,290,000

B EXTERNAL WALLS 678


i 1 coat of of undercoat 20 ltr BUCKET 6 55,000 310,750
ii 2 coats of weather guard paint 20 ltr BUCKET 8 235,000 1,880,000

C WALL TILES SM 35

i Wall tiles 6"x6" (45pcs /sq.mtr) S.M 35 30,000 1,050,000


ii Tile grout (10kg bags) BAGS 2 25,000 50,000

D CEILING DOUBLE CORNICES


i sand (forward 6tonne truck) TRIPS 1 180,000 INCLUDED
ii Cement 50kg bag BAGS 15 30,000 450,000
iii lime BAGS 5 25,000 125,000

TOTAL CARRIED TO MATERIAL SUMMARY 7,760,750

MATERIAL SUMMARY

from page '1/5/1 19,690,000

from page '1/5/2 7,760,750

FINISHES TOTAL TO BE CARRIED TO MAIN MATERIAL


27,450,750
SUMMARY
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (USHS)
(USHS)

PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
FIXTURES AND FITTINGS

DOORS

SINGLE LEAF MAHOGANY PANEL DOOR: To


A Architect's detailed drawing
Door D2 size 900 x 2150mm high overall NO. 2 550,000 1,100,000
Door D3 size 800 x 2150mm high overall NO. 3 550,000 1,650,000
Door D4 size 1000 x 2400mm high overall NO. 4 630,000 2,520,000

B IRON MONGERY
100mm Pressed Stainless steel butt hinges PAIRS 14 6,000 81,000
3-Lever mortice lock & furn NO. 9 80,000 720,000
Door stpppers NO. 6 5,000 30,000

GLASS IN ALUMINIUM FRAME DOORS: To


C Architect's detailed drawing

Sliding door D1 size 3400 x 2440mm high overall NO. 2 1,450,000 2,900,000
Sliding door D5 size 2800 x 2400mm high overall NO. 2 1,250,000 2,500,000

D WINDOWS

GLASS IN ALUMINIUM FRAME WINDOWS: To


Architect's detailed drawing
Window W1 size 1800 x 1900mm high overall NO. 5 615,600 3,078,000
Window W2 size 800 x 1900mm high overall NO. 4 270,000 1,080,000
Window W3 size 1800 x 1400mm high overall NO. 1 450,000 450,000
Window W4 size 1200 x 1900mm high overall NO. 3 410,000 1,230,000
Window W5 size 1200 x 1500mm high overall NO. 3 330,000 990,000
Window W8 size 700 x 900mm high overall NO. 8 235,000 1,880,000
Window W7 size 1100 x 1900mm high overall NO. 4 375,000 1,500,000
Window W6 size 750 x 6500mm high overall NO. 2 875,000 1,750,000

E JOINERY FITTINGS
Kitchen and pantry cupboard overall size 600mm wide x
LM 10 80,000 800,000
800mm high;
Reception counters 900mm wide LM 12 120,000 1,440,000

F WASH HAND BASINS


gentex NO. 3 300,000 900,000

G WATER CLOSETS
gentex NO. 3 350,000 1,050,000

H KITCHEN/PANTRY SINKS

stainless steel sinks NO 2 150,000 300,000

STAIRCASE HANRAIL; To Architect's detailed drawing


I
mild steel railings with mahogany handrail LM 8 63,000 504,000

J BALCONY HANDRAILS( MILD STEEL) LM 10 50,000 500,000

TOTAL CARRIED TO MAIN MATERIAL SUMMARY 28,953,000


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(USHS) (USHS)

PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
EXTERNAL WORKS

BOUNDARY WALL+GATE

A BRICKWORK SM 336
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 10000 280 2,800,000
ii Cement BAGS 60 30,000 1,800,000
iii Sand 6 ton truck TRIPS 3 220,000 660,000
v Whoop Iron wall ties ROLLS 22 35,000 770,000

GATE
B 2000 x 4000 high mild steel sliding gate NO 1 4,000,000 4,000,000

Render
i Cement BAGS 15 30,000 450,000
ii Sand TRIPS 2 180,000 360,000

C PAVED AREAS SM 85

i Murram 10 tonne truck TRIPS 1 150,000 150,000


ii Lake sand 6 ton truck TRIPS 1 220,000 220,000
iii Pavers SM 85 30,000 2,550,000
iv Kerbs LM 20 7,000 140,000
v Cement BAGS 5 31,000 155,000

D LANDSCAPING SM 300

i Black soil 75mm thick (10ton truck) TRIPS 1 300,000 300,000


ii Paspalm BAGS 10 20,000 200,000
iii Trees NO 10 15,000 150,000

E SEPTIC TANK

Allow a sum of Two Million Uganda shillings for construction of 10 user


i SUM 2,000,000
septic Tank all to Engineers satisfaction

EXTERNAL WORKS TOTAL CARRIED TO MATERIALS


16,705,000
SUMMARY