MATERIAL SCHEDULE
PREPARED BY:
KALEMA SOLOMON
0777006704
ELEMENT DESCRIPTION PAGE NO MATERIAL COST
(USHS)
MATERIALS SCHEDULE
PROPOSED RESIDENTIAL HOUSE
FOR ANN KIRAZA
MATERIAL SUMMARY
MATERIALS SCHEDULE
ACTIVITY NO.1
SUBSTRUCTURE
The work in this activity includes all works up to and including the
ground floor slab
A SETTING OUT
Building line/string ROLLS 2 8,000 16,000
Pegs- 50mm x 50mm x 3.0m(2' x 2') long wrot softwood PC 10 4,000 40,000
C MURRAM FILLING CM 14
200mm murram filling to make up levels; well rolled and
TRIPS 2 150,000 INCLUDED
compacted to 95% MDD
E ANTI-TERMITE TREATMENT SM
Insecticide treatment to surface of hardcore, tops of foundation TINS 2 100,000 200,000
walling and bottoms of excavations
F STARTER COLUMNS 26
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 26 8,000 208,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 10 6,000 60,000
iii Eucalyptus Poles 150mm girth PC 5 3,000 15,000
iv Nails KG 1 4,000 4,000
G PAD FOUNDATION
High yield Square Twisted steel bars T16x 12 Metres Long-
ii PC 60 46,000 2,760,000
columns
iii 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 INCLUDED
STARTER COLUMNS:
ii High yield Square Twisted steel bars T16 x 12Metres PC 11 46,000 506,000
iii Mild Steel Round Bars R8 x 12 Metres Long PC 11 25,000 275,000
iv 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000
CONCRETE
GRADE 10 (MIX 1:4:8) IN BLINDING FOR PAD
H CM 3
FOUNDATIONS(50mm thick)
i Aggregate (Hand Crushed 20mm) 6tonne truck TRIPS 1 270,000 270,000
ii Lake Sand (6tonne truck) TRIPS 1 220,000 220,000
iii Cement (50kg bag) BAGS 10 30,000 300,000
B PLINTH WALLING/BRICKWORK SM 86
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 5,670 280 1,587,600
ii Cement (50kg bag) BAG 40 30,000 1,200,000
iii Lake Sand (forward 6tonne truck) TRIPS 2 220,000 440,000
iv Hoop iron ROLLS 6 31,000 186,000
v 1000 GAUGE DPC ROLLS 250,000 INCLUDED
GROUND FLOOR
E REINFORCEMENT
i A-98 BRC Mesh 2.4X48m ROLLS 2 650,000 1,300,000
12,568,600
RESIDENTIAL
MATERIALS SCHEDULE
ACTIVITY NO.2
SUPERSTRUCTURES-GROUND FLOOR
COLUMNS
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 52 8,000 416,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 25 6,000 150,000
iii Eucalyptus Poles 150mm girth PC 20 3,000 60,000
iv Nails KG 15 4,000 60,000
C CONCRETE WORK
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 10,500 280 2,940,000
ii Cement (50kg bag) BAGS 75 31,000 2,325,000
iii Lake Sand 6tonne truck TRIPS 7 220,000 1,540,000
iv Hoop iron Roll 10 30,000 300,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 118 280 33,040
ii Cement (50kg bag) BAGS 50 31,000 1,550,000
iii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iv Hoop iron Roll 8 30,000 240,000
v 1000 gauge polythene DPC ROLL 1 120,000 INCLUDED
I SCAFFOLDINGS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 8 8,000 64,000
ii Eucalyptus Poles 150mm girth PC 15 3,000 45,000
iii Nails KG 5 4,000 20,000
STAIRS-GROUND FLOOR
E SAWN FORMWORK
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 9 8,000 72,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 6 6,000 36,000
iii Eucalyptus Poles 150mm girth PC 4 3,000 12,000
iv Nails KG 2 4,000 8,000
F STAIRS REINFORCEMENT
i High yield Square Twisted steel bars T12 x 12Metres PC 10 25,000 250,000
ii 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000
A CONCRETE WORK
B SCAFFOLDINGS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 15 8,000 120,000
ii Eucalyptus Poles 150mm girth PC 8 3,000 24,000
iii Nails KG 1 4,000 4,000
396,000
APARTMENT BLOCK
MATERIALS SCHEDULE
ACTIVITY NO.3 FIRST FLOOR
SUPERSTRUCTURES-FIRST FLOOR
COLUMNS
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 52 8,000 416,000
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 25 6,000 150,000
iii Eucalyptus Poles 150mm girth PC 20 3,000 60,000
iv Nails KG 15 4,000 60,000
B STAIRCASE
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 9 8,000 72,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 6 6,000 36,000
iii Eucalyptus Poles 150mm girth PC 4 3,000 12,000
iv Nails KG 2 4,000 8,000
C BEAMS
D SLABS
i 300mm x 25mm x 3.1m (12'x1') long Wrot Softwood PC 16 8,000 128,000
ii 100mm x 50mm x 3.1m (4'x2') long Wrot Softwood PC 215 6,000 1,290,000
iii Eucalyptus Poles PC 600 3,000 1,800,000
iv Nails KG 80 4,000 320,000
COLUMNS
i High yield Square Twisted steel bars T20 x 12 Metres PC 35 71,000 2,485,000
ii High yield Square Twisted steel bars T16 x 12 Metres PC 30 46,000 1,380,000
iii Mild Steel Round Bars R8 x 12 Metres Long PC 1.0 11,000 11,000
iv 1.8mm Binding wire (25Kg) ROLL 1.0 80,000 80,000
F BEAMS
ii High yield Square Twisted steel bars T16 x 12 Metres PC 52 46,000 2,392,000
iv Mild Steel Round Bars R8 x 12 Metres Long PC 30 11,000 330,000
v 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000
G SLAB
i High yield Square Twisted steel bars T12 x 12 Metres PC 110 25,000 2,750,000
ii High yield Square Twisted steel bars T10 x 12 Metres PC 40 17,000 680,000
iii BRC A-142 NO 1 754,000 754,000
iv 1.8mm Binding wire (25Kg) ROLL 2 80,000 160,000
H STAIRCASE
i High yield Square Twisted steel bars T12 x 12 Metres PC 10 25,000 250,000
iii 1.8mm Binding wire (25Kg) ROLL 1 80,000 INCLUDED
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 11,600 280 3,248,000
ii Cement (50kg bag) BAGS 90 31,000 2,790,000
iii Lake Sand 6tonne truck TRIPS 4 220,000 880,000
iv Hoop iron ROLL 8 35,000 280,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 118 280 33,040
ii Cement (50kg bag) BAGS 50 31,000 1,550,000
iii Lake Sand 6tonne truck TRIPS 2 220,000 440,000
iv Hoop iron ROLL 8 35,000 280,000
v 1000 gauge polythene DPC ROLL 1 120,000 120,000
20,132,040
RESIDENTIAL
ACTIVITY 4-RINGBEAMS, ROOFING, CEILING AND
ROOF SLABS
A SAWN FORMWORK
B REINFORCEMENT BARS
i High yield Square Twisted steel bars T16 x 12 Metres PC 52 46,000 2,392,000
iv Mild Steel Round Bars R8 x 12 Metres Long PC 30 11,000 330,000
v 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000
i 300mm x 25mm x 3.0m (12'x1') long Wrot Softwood PC 100 8,000 RE-USED
ii 100mm x 50mm x 3.0m (4'x2') long Wrot Softwood PC 50 6,000 RE-USED
iii Eucalyptus Poles 150mm girth PC 3,000 RE-USED
iv Nails KG 20 4,000 80,000
i High yield Square Twisted steel bars T12x 12 Metres PC 35 25,000 875,000
ii High yield Square Twisted steel bars T10 x 12 Metres PC 15 17,000 255,000
iv 1.8mm Binding wire (25Kg) ROLL 1 80,000 80,000
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 5,000 280 1,400,000
ii Cement (50kg bag) BAGS 30 30,000 900,000
iii Lake Sand 6tonne truck TRIPS 1 220,000 220,000
iv Hoop iron ROLL 4 35,000 140,000
v 1000 gauge polythene DPC ROLL 1 120,000 INCLUDED
A ROOF STRUCTURE
B ROOF COVERING
PERGOLA
11,274,500
MATERIAL SUMMARY
PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
GENERAL FINISHES
A CEILING PLASTER
B CEILING PAINT
i 1 coat of of primer paint 20 ltr BUCKET 1 55,000 55,000
ii 2 coats white matt emulsion 20 ltr BUCKET 2 190,000 380,000
D CERAMIC TILES
i 6" X 6" floor tiles S.M 272 25,000 6,800,000
ii Tile grout (10kg bags) BAGS 10 25,000 250,000
H MARBLE WORKTOP
i 800mm wide granite tops LM 6 60,000 360,000
F PAINTING
i 1 coat of of undercoat 20 ltr BUCKET 5 55,000 275,000
ii 2 coats of silk vinyl emulsion paint 20 ltr BUCKET 5 235,000 1,175,000
iii 2 coats of weather guard paint 20 ltr BUCKET 8 235,000 1,880,000
iv white cement BAGS 4 75,000 300,000
WALL FINISHES
G PLASTER(30mm thick)
A PAINTING
INTERNAL WALLS 1,284
i 1 coat of of undercoat 20 ltr BUCKET 11 55,000 605,000
ii 2 coats of silk vinyl emulsion paint 20 ltr BUCKET 14 235,000 3,290,000
C WALL TILES SM 35
MATERIAL SUMMARY
PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
FIXTURES AND FITTINGS
DOORS
B IRON MONGERY
100mm Pressed Stainless steel butt hinges PAIRS 14 6,000 81,000
3-Lever mortice lock & furn NO. 9 80,000 720,000
Door stpppers NO. 6 5,000 30,000
Sliding door D1 size 3400 x 2440mm high overall NO. 2 1,450,000 2,900,000
Sliding door D5 size 2800 x 2400mm high overall NO. 2 1,250,000 2,500,000
D WINDOWS
E JOINERY FITTINGS
Kitchen and pantry cupboard overall size 600mm wide x
LM 10 80,000 800,000
800mm high;
Reception counters 900mm wide LM 12 120,000 1,440,000
G WATER CLOSETS
gentex NO. 3 350,000 1,050,000
H KITCHEN/PANTRY SINKS
PROPOSED RESIDENTIAL
MATERIALS SCHEDULE
EXTERNAL WORKS
BOUNDARY WALL+GATE
A BRICKWORK SM 336
i 200 x 100 x 100mm Local Burnt Clay Bricks(delivered on site) NO 10000 280 2,800,000
ii Cement BAGS 60 30,000 1,800,000
iii Sand 6 ton truck TRIPS 3 220,000 660,000
v Whoop Iron wall ties ROLLS 22 35,000 770,000
GATE
B 2000 x 4000 high mild steel sliding gate NO 1 4,000,000 4,000,000
Render
i Cement BAGS 15 30,000 450,000
ii Sand TRIPS 2 180,000 360,000
C PAVED AREAS SM 85
D LANDSCAPING SM 300
E SEPTIC TANK