Академический Документы
Профессиональный Документы
Культура Документы
3, JULY 2010
m).
Index TermsClose proximity to substations, grounding system
safety analysis, overhead line towers. Fig. 1. Head of the tower under consideration (all measures are in
I. INTRODUCTION
through the ground wires toward the remote line end and toward
the substation, respectively. Node is the tower under consid-
eration, node is the tower next to the faulted one, while node
is connected to the substation ground electrode.
(1)
(2)
(4)
Based upon the same consideration as before, the equivalent
Scheme Fig. 3(a) can be also substituted by the parallel con- scheme for the ground wires in the last line span connecting
nection of impedance and current source , depicted in tower and the substation ground electrode is that presented in
Fig. 3(c), with Fig. 5, with as the length of this span. In this case, the current
sources have different orientations, which is in accordance with
(5) the orientation of the currents flowing through phase conductors
in the span under consideration.
By referring to (1), (3), and (5), we can write C. Model of Overhead Line
(6) The overhead line part from the tower under consideration to
its remote end can be modeled by the scheme displayed in Fig. 6,
where obtained by series connection of the corresponding schemes for
line spans. It is implied that the line has the same ground wire
(7) and phase conductors disposition all along its length matching
with this at the span between towers and and that the same
type of ground wire is used. As known from [1], impedance
(8)
takes the grounding effects of line towers into account.
This impedance is equal to
Parameters and are screening factors associated with cur-
rents flowing over corresponding line three-phase systems. (9)
By referring to (6), the equivalent scheme plotted in Fig. 3(c)
can be substituted by the scheme with two current sources de- with and designating the average span length and tower
picted in Fig. 4. ground resistance along the considered line part.
1510 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 25, NO. 3, JULY 2010
Fig. 5. Equivalent scheme for ground wires in the line span connecting tower Fig. 8. Equivalent scheme of the substation and associated lines.
T and substation ground electrode.
Fig. 6. Equivalent scheme for the overhead line part between the tower under
consideration and the remote terminal.
it. The components of these currents leaking into the ground
are obtainable by multiplying the corresponding triple zero-se-
quence currents by lines screening factors . Thus, the total
leakage current produced is equal to
(11)
(19)
Fig. 10. Disposition of transformer station (S ) and line tower (T ) ground elec-
trodes, 110-kV line (L) and the critical route on the ground surface (R). where is the resistivity of the surface material and is the
shock duration. The correction factor for finite thickness of the
surface material is approximately equal to [7] and [8]
G. Determination of Currents Discharging From Ground
Electrodes
(20)
The potentials of nodes in the scheme displayed in Fig. 9 can
be determined from the currents injected in the nodes using the
with being the resistivity of the earth and designating the
following matrix expression:
thickness of surface material.
The maximum-allowable step voltage for those with a body
(15) weight of 50 kg is [7]
(21)
Diagonal elements of square 3 by 3 symmetrical matrix are
self admittances of nodes and offdiagonal elements are negative with the same meaning of notation as in (19).
mutual. The currents leaking into the soil from the tower with
ground fault and substation ground electrodes are III. APPLICATION EXAMPLE
(16) The first tower of a double-circuit 110-kV line, leaving a
220-kV/110-kV transformer station, is located 15 apart from
(17) the edge of the ground grid of the transformer station (Fig. 10).
The head of the line is presented in Fig. 1. The ground wire on
the left-hand side is optical ground wire (OPGW). The safety
H. Distribution of the Potentials on the Ground Surface conditions occurring in the case of a single-phase-to-ground
fault at the tower should be considered as the presence of people
To evaluate the risk of dangerous electrocutions, the potential
in this area is possible. Table I presents the data on the max-
distribution along critical route on the ground surface crossing
imum predicted fault currents in the prospective 10-year period
tower axis should be determined. The potential at any location
for the fault of system , and on the relevant impedances. Other
along the route is obtainable by the superposition of the poten-
detailed data on the line are given in Appendix A. Impedances
tials generated by the tower ground electrode and the ground
are determined for 50 Hz, as is the frequency in the authors
electrode of the adjacent substation. If and are the plane
country.
rectangular coordinates of a location, then the potential at this
The data on the substation grounding system are given in
location is equal to
Table II. The transformer station is grounded by a ground grid
(18) of rectangular shape 176 m 111 m formed by transversal and
perpendicular conductors. Mutual resistance between the
with indices and related to the tower and substation ground station and tower ground electrodes is determined by calculating
electrode, respectively. The potentials generated by the elec- the mean potential of the tower ground electrode generated by
trodes are calculated by applying the adequate software [6], a unit current discharging from the station electrode, using the
based upon the currents discharging into the soil determined appropriate software for grounding system analysis [6]. The
using (16) and (17) and the configuration of ground electrodes. impedance is determined from the data for impedances to
Potential components on the right-hand side of (18) are calcu- ground of ground wires and cable sheaths of overhead lines and
lated as if the corresponding electrodes are acting alone. These cables connected to the transformer station.
potentials are generally complex quantities as they are linearly Table III gives the tripple zero-sequence currents flowing
correlated with the currents injected into soil at nodes and . through the overhead lines and cables to the transformer station
Maximum touch voltage is determined as the maximum po- in the considered ground fault case as well as the screening
tential difference that can be overbridged by a person standing factors and impedances to ground of ground wires of lines and
1512 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 25, NO. 3, JULY 2010
TABLE IV
CURRENTS FLOWING THROUGH THE GROUNDING SYSTEM (22)
TABLE VI
GROUND DATA FOR GROUND WIRES
ground faults at the tower, should take into account the mu-
tual interaction of the tower and substation ground electrodes.
The mutual interaction existing between these two electrodes
decreases the current leaking into the ground from the tower
ground electrode. Furthermore, the ground surface potentials
generated by the current leaking from the substation ground
electrode, superimposed upon the potentials stemming from the
current discharging from the tower ground electrode, increase
the ground surface potentials. The typical case, analyzed in this
paper, has shown that both of these effects have substantially
Fig. 11. Potential distribution on the ground surface for the complete grounding
system model. Real potential distribution (R), potentials generated by the sub-
reduced the maximum touch-and-step voltages at the tower lo-
station ground electrode (S ), and potentials generated by the tower ground elec- cation. If any of the aforementioned effects were neglected,
trode (T ). much higher and dangerous voltages than actual would be cal-
culated, leading to extra cost and labor for implementing addi-
tional safety measures at the tower.
APPENDIX A
Self and Mutual Impedances of Line Conductors for
Ground Return: The self impedance of a line conductor for
current ground return for 50 Hz is equal to
km
with , , and being the conductor resistance per kilometer,
diameter, and relative permeability, respectively. Parameter
is the equivalent depth of current ground return
km
tentials stemming from the tower and substation ground elec-
trodes are separately determined. Then, the potentials gener- In calculating the equivalent mutual impedance between the
ated by the ground current leaking from the substation electrode line phase conductors and a ground wire, is the mean ge-
are superimposed upon the potentials caused by the current dis- ometrical distance of the phase conductors to the ground wire.
charging from the tower ground electrode. The phase differ- These parameters are determinable from the conductors dispo-
ences existing between these two components of potentials are sition displayed in Fig. 1.
accounted for at each location along the considered route on the Table VI gives the supplemental data on the ground wires of
ground surface to properly determine the associated root mean the line considered in this paper.
square (rms) values of potentials. The maximum touch voltages Indices 1 and 2 refer to the optical ground wire and Aldrey
given in Table V are determined from the potential distributions wire, respectively.
along the critical route calculated in the examined cases.
APPENDIX B
Simple Interaction Model: For illustration, consider a ver-
IV. CONCLUSION
tically driven rod and a horizontal round plate that are parallel
The safety conditions at a tower located in close proximity to connected. The length of the rod is and the diameter is . The
the substation that it is connected to, in the case of the phase-to- top of the rod is on the surface level. The diameter of the plate
1514 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 25, NO. 3, JULY 2010
is . The distance between the rod and the closest edge of the TABLE VII
plate is . The total current emanating from the considered CHARACTERISTIC PARAMETERS FOR VARIOUS
SPACING BETWEEN GROUND ELECTRODES
ground electrodes into the surrounding soil is and the soil re-
sistivity is . The equivalent resistance to ground of two par-
allel-connected electrodes is as follows from the corresponding
scheme analogous to this in Fig. 7
[10] W. Koch, Erdungen in Wechselstrom Anlagen Ueber 1 kV. Berlin, Dragutin D. Salamon was born in Vukovar, Croatia, in 1942. He received the
Germany: Springer, 1961, pp. 5153. Dipl. Eng., M.Sc., and D.Tech. degrees in electric power engineering from the
University of Belgrade, Belgrade, Serbia, in 1973, 1978, and 1992, respectively.
Jovan M. Nahman was born in Belgrade, Serbia. He received the Dipl.Eng. In 1973, he joined the Faculty of Electrical Engineering, University of Bel-
and D.Tech. degrees in electrical power engineering from the Faculty of Elec- grade, where he is Associate Professor in the Power System Department.
trical Engineering, University of Belgrade, Belgrade, Serbia, in 1960 and 1969,
respectively.
From 1960 to 2001, he was a Professor with the Faculty of Electrical Engi-
neering at the University of Belgrade in the Power System Department. Cur-
rently, he is a Freelance Consultant for electric power systems.