Precondition for Turbine Box-Up

No. Contents Result


1
MPH (turbine house) shall be a enclosure space;
2 ;
Cleanness of all the turbine components shall meet requirements.
3
Shafting alignment shall be qualified in trial box-up when turbine proper is fully assembled.
4
Alignment and adjustment of Front bearing housing and MOP shall be completed.
5
H&IP steam pipe for HIP outer lower half casing shall be installed; big diameter pipes connecting (incl. the cross pipe) with the casing
shall be installed to the place beyond the first support & hanger.
6
Condenser and LP casing connection shall be completed.
7 ;
Tightness test, i.e. water filling/ hydro test for condenser shall be completed
8
Installation of Extraction pipe of the LP casing shall be completed.
9
Connection of TDBFP turbine exhaust pipe and the condenser shall be completed.
10
All pipes connected with the condenser shell shall be connected to the root valve.
11
Prior to turbine final box-up, all site registers and formal protocols, as well as stipulated protocols, shall be completed.

1
No. Contents Result
12
Mortar pad and soleplate matching records, soleplate and casing or bearing housing clearance records shall be in accordance with
manufacturer requirements.
13
Sliding pin system clearance inspection:
13.1
Final clearance of soleplate vertical and horizontal sliding pin, casing vertical pin and casing lug horizontal pin shall be measured to be
in accordance with design requirements.
13.2
Clearance Measurement of inner casing lug, vertical and horizontal sliding pin and axial locating pin shall be in accordance with design
requirements.
14
Clearance records of Casing horizontal parting surface shall meet manufacturer requirements.
15
Records of leveling and uplift of casing as well as rotor uplift shall meet manufacturer requirements (including records after connection
with condenser).
16
Rotor locating records shall meet manufacturer requirements.
17
Records of rotor alignment at oil retainer bore area shall meet manufacturer technical requirements.
18
Coupling centering records shall meet manufacturer technical requirements.
19
Diaphragm alignment records shall meet manufacturer technical requirements.
20
Clearance of steam seals and flow passage shall meet manufacturer technical requirements.

2
No. Contents Result
21
All internal measurement, inspection and adjustment of HIP inner & outer casings shall be completed.
22
Drain pipes of inner casing and other parts shall be installed and completed.
23
Thrust bearing clearance record shall meet requirements.
24
PMI for alloy parts, bolt hardness test, ultrasonic and metallographic examination reports shall meet requirements.
25
Defect elimination involved with components and parts in the casing shall be completed and records shall be made.
26
Casing inside cleaning inspection shall be verified and recorded (including interior of casing, pipe section, steam chamber, instrument
socket and dummy sealing)
27
Casing exposing openings shall be temporarily sealed.
28
Installation of Each bearing shall meet manufacturer technical requirements and records shall be made.
29
For all nuts, there shall be no touching between the screw and the nut inner ceiling and no clearance fouling. And they shall meet
expansion requirements.
30
All internal components and parts shall be counted without shortage and put neatly.
31
C&I temperature measuring elements involved in turbine proper box-up shall be calibrated and trial-installed without error.
32
Part of inner casing drain pipe and LP casing spray pipe that are located in the casing shall be installed.