Project Proposal Zoonotic Diseases Training

Last Revised: 08/27/17

Zoonotic Diseases Training


Project Proposal
Project Manager: Brianne Fitzgerald
Sponsor: Dr. Mike Murray, DVM
Prepared by: Brianne Fitzgerald

Revision History
Revision date Revised by Approved by Description of change
8/27/17 BFitzgerald First draft

Project Goal

Revise current in-person training to an asynchronous online module within Adobe


Captivate and deliver in MBALearns (LMS).

Problem/Opportunity Definition

Current training delivered by Dr. Mike is a challenge to schedule with all the various
work groups in the aquarium. Learning transfer has not occurred within the Husbandry
Dept. as workers have been observed not practicing the preventative measures
recommended in the current training. There are no systems of accountability as there
exists a lack of clear expectations and requirements. There exists certain cavalier
attitudes toward adopting preventative practices(wearing gloves and washing hands) by
some workers.

Proposed Solution

1. In-person session facilitated for Husbandry Dept. workers to identify attitudinal


barriers, address, and mitigate them through constructive group discussions and
problem-solving activities. The session will also introduce new requirements for
using prescribed safety measures (wearing gloves).

2. Work with managers to develop accountability/recognition systems in support of


training.

3. Develop a 1-hour, online training course to increase knowledge and awareness


of zoonotic disease risks and exposure. Deliver the course within MBALearns.

Fast Foundation for Project Management Project Proposal


Reference The Fast Forward MBA in Project Management
Filename: 370145341.doc 1 of 3
Project Proposal Zoonotic Diseases Training
Last Revised: 08/27/17

Project Selection & Ranking Criteria


Project benefit category:
X Compliance/Regulatory X Efficiency/Cost reduction Revenue increase
Portfolio fit and interdependencies
TBD

Project urgency current course has been developed in MBALearns which satisfies
compliance but which is ineffective for learning transfer and is not supported by an instructional
design process. Revised course to be implemented in First Quarter of 2018.

Cost/Benefit Analysis
Tangible Benefits
Benefit- reduction in costs related to Workers Compensation claims.
Value & Probability- TBD
Assumptions Driving Value- increase in practicing preventative measures will decrease
injuries.
Intangible Benefits
Benefit- greater acceptance of departmental requirements supported by managerial support
systems will mitigate social issues amongst team and change attitudes toward a safety
culture.
Value & Probability
Assumptions Driving Value
Cost Categories Amount TBD
Internal Labor hours- 300 hrs. for course
development, X hours of SME(Veterinarian) time
External costs
Labor (consultants, contract labor) N/A
Equipment, hardware or software-
potential software upgrade to Adobe
Captivate 9 ($349)
Server space for course
List other costs such as travel & training
Financial Return TBD

Business Requirements
1. TBD
2.

Fast Foundation for Project Management Project Proposal


Reference The Fast Forward MBA in Project Management
Filename: 370145341.doc 2 of 3
Project Proposal Zoonotic Diseases Training
Last Revised: 08/27/17

Scope
Major project activities
1. Working with SME on content and support media
2. Storyboard
3. Develop course evaluation
4. Project development templates in Captivate
5. Development of course
6. Development of managerial support systems
7. Instructor-led session for online course roll-out and new requirements introduction
Out of scope activities that are critical to the success of the project

Major Obstacles
1. Scheduling with SME
2. Captivate learning curve

Risks
1. TBD
2.

Schedule Overview
Estimated Project Completion Date: [11/14/17]
Major Milestones
Storyboard completion 9/26/17
Master Templates 10/10/17
Development halfway 10/24
External Milestones Affecting the Project
[Milestone] mm/dd/yy
[Milestone] mm/dd/yy
Impact of Late Delivery- late delivery delays my graduation

Fast Foundation for Project Management Project Proposal