Вы находитесь на странице: 1из 3

Part 3: Section 8 Special Conditions of Contract

Section 8. Special Conditions of Contract


The following Special Conditions of Contract (SCC) shall supplement the General Conditions of
Contract (GCC). Whenever there is a conflict, the provisions herein shall prevail over those in the
GCC.

GCC Clause Special Conditions


Reference
GCC 1.1 The Employer is ____________________
The Engineer is ____________________
The name and procurement reference number of the Contract is
______________________________________________________.
The Works consist of _____________________________________.
The Site is located at __________ and is defined in Drawings Nos.:
_______________.
The Start Date shall be __________.
The Intended Completion Date for the whole of the Works shall be
__________.
GCC 2.3 The following documents also form part of the Contract:
____________________________________________________________

GCC 4.1 The Employers specific approval is required for:


GCC 8.1 The Schedule of Other Contractors __________ part of the Contract
GCC 9.1 The Schedule of Key Personnel __________ part of the Contract
GCC 11.1 The Employers risks are as specified in the GCC.
GCC 13.1 The minimum insurance cover and deductibles shall be:
(a) The minimum cover for insurance of the Works, Plant and
Materials is __________.
(b) The maximum deductible for insurance of the Works, Plant and
Materials is __________.
(c) The minimum cover for insurance of Equipment is __________.
(d) The maximum deductible for insurance of Equipment is
__________.
(e) The minimum cover for insurance of property is __________
(f) The maximum deductible for insurance of property is _________
(g) The minimum cover for personal injury or death insurance is

Standard Bidding Document for the Procurement of Works issued by the PPA (Version 1, January 2006)
Document: Section 8. Page 1 of 3 File Ref: 370181914.doc
Part 3: Section 8 Special Conditions of Contract

GCC Clause Special Conditions


Reference
__________ with no deductible.
GCC 14.1 Site Investigation Report(s) __________ part of the contract.
GCC 25.2 Fees and types of reimbursable expenses to be paid to the Adjudicator are:
__________.
GCC 25.3 The institution whose arbitration procedures shall be used is: __________.
Arbitration shall take place at: _______________
GCC 26.1 The Appointing Authority for the Adjudicator is: _______________.
GCC 27.1 The Contractor shall submit a revised Program for the Works within
__________ days of delivery of the Notice of Acceptance.
GCC 27.3 The period between Program updates is __________ days.
The amount to be withheld for late submission of an updated Program is
__________.
GCC 35.1 The Defects Liability Period is __________ days.
GCC 37.1 This Contract is a _______________ Contract.
GCC 44.1(l) The following events shall also be Compensation Events:
GCC 45.1 The Engineer shall not adjust the Contract Price if taxes, duties and other
levies are changed that subsequently affect the Contract Price.
GCC 47.1 The Contract __________ subject to price adjustment in accordance with
Clause 47 of the Conditions of Contract.
GCC 48.1 The proportion of payments retained is __________ percent.
GCC 49.1 The liquidated damages for the whole of the Works are __________ of the
final Contract Price per day.
The maximum amount of liquidated damages for the whole of the Works is
__________ percent of the final Contract Price.
GCC 50.1 The Bonus for the whole of the Works is __________ percent of final
Contract Price per day. The maximum amount of Bonus for the whole of the
Works is __________ percent of the final Contract Price.
GCC 51.1 The Advance Payment will be equivalent to __________ percent of the
Contract Price and will be paid in Ethiopian Birr. It will be paid to the
Contractor no later than __________.
GCC 51.3 The Advance Payment will be repaid by deducting proportionate amounts
from each payment certificate during the period starting __________ months
after the Start Date and ending __________ months after the Start Date.

Standard Bidding Document for the Procurement of Works issued by the PPA (Version 1, January 2006)
Document: Section 8. Page 2 of 3 File Ref: 370181914.doc
Part 3: Section 8 Special Conditions of Contract

GCC Clause Special Conditions


Reference
GCC 52.1 The Contract Security shall be for __________ of the Contract Price:
GCC 58.1 The date by which operating and maintenance manuals are required is
__________.
The date by which as built drawings are required is __________.
GCC 58.2 The amount to be withheld for failing to produce as built drawings and/or
operating and maintenance manuals by the date required is __________
Ethiopian Birr.
GCC 60.1 The percentage to apply to the value of the work not completed,
representing the Employers additional cost for completing the Works, is
__________.