. SISTEMA DE PRESUPUESTOS DE OBRA Pg.

: 1
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES - ESTRUCT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
01.00. OBRAS PROVISIONALES

01.06. Letrinas Und 1,997.56

MATERIALES:
02010 Perno 1/4"x2 1/2" UND 75.0000 1.02 76.50 0.04
03007 Fierro corrugado de construccion KG 8.6400 2.45 21.17 0.01
04001 Arena gruesa M3 0.1820 152.54 27.76 0.01
05001 Piedra Confitillo de 1/2" M3 0.3325 161.02 53.54 0.03
21002 Cemento Tipo MS BLS 3.5200 21.53 75.79 0.04
43001 Madera tornillo P2 25.3500 4.50 114.08 0.06
51020 Platina de Fierro 1 1/2"x1/4"x6m ML 12.8000 12.00 153.60 0.08
51049 Angulo 1" x 1/8" ml 25.8500 14.80 382.58 0.19
54004 Pintura Esmalte Sintetico GLN 1.4000 36.00 50.40 0.03
54005 Pintura Anticorrosiva zincromato GLN 1.4000 36.00 50.40 0.03
61007 Calamina de 8' x 0.20 importada Und 5.6000 16.47 92.23 0.05
73004 Tubo PVC-SAL campana 4"x3m ML 3.0000 7.70 23.10 0.01
----------------------------------
Sub-Total: 1,121.15 0.56
MANO DE OBRA:
47002 Operario HH 16.0000 20.79 332.64 0.17
47003 Oficial HH 16.0000 17.05 272.80 0.14
47004 Peon HH 16.0000 15.34 245.44 0.12
----------------------------------
Sub-Total: 850.88 0.43
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 850.8800 0.03 25.53 0.01
----------------------------------
Sub-Total: 25.53 0.01

03.00. MOVIMIENTO DE TIERRAS


03.02. EXCAVACIONES

03.02.01 Excavacin de zanjas para zapatas y cimentacin m3 39.50

MANO DE OBRA:
47004 Peon HH 2.5000 15.34 38.35 0.97
----------------------------------
Sub-Total: 38.35 0.97
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 38.3500 0.03 1.15 0.03
----------------------------------
Sub-Total: 1.15 0.03

03.03. CORTES

03.03.02 Corte de terreno explanado M3 4.05

MANO DE OBRA:
47004 Peon HH 0.0320 15.34 0.49 0.12
----------------------------------------------------------------------------------------------------SyS-CU
. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 2
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES - ESTRUCT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
----------------------------------
Sub-Total: 0.49 0.12
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 0.4909 0.03 0.01 0.00
49068 Tractor Oruga CAT 402 HM 0.0320 110.79 3.55 0.88
----------------------------------
Sub-Total: 3.56 0.88

03.04. RELLENOS

03.04.03 Relleno compactado c/hormigon e=10cm M3 21.57

MATERIALES:
10020 Agua M3 0.0375 10.00 0.38 0.02
38001 Hormigon M3 0.1200 135.60 16.27 0.75
----------------------------------
Sub-Total: 16.65 0.77
MANO DE OBRA:
47003 Oficial HH 0.0615 17.05 1.05 0.05
47004 Peon HH 0.1846 15.34 2.83 0.13
----------------------------------
Sub-Total: 3.88 0.18
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 3.8803 0.03 0.12 0.01
49033 Compactadora Vibrat. tipo Plancha 7Hp HM 0.0615 15.00 0.92 0.04
----------------------------------
Sub-Total: 1.04 0.05

03.05. ELIMINACION DE MATERIAL EXCEDENTE

03.05.01 Acarreo interno de material procedente de excavacion M3 21.06

MANO DE OBRA:
47004 Peon HH 1.3333 15.34 20.45 0.97
----------------------------------
Sub-Total: 20.45 0.97
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 20.4528 0.03 0.61 0.03
----------------------------------
Sub-Total: 0.61 0.03

03.05.02 Eliminacin de Material Excedente d=5km M3 11.03

MANO DE OBRA:
47004 Peon HH 0.0267 15.34 0.41 0.04
----------------------------------
Sub-Total: 0.41 0.04
EQUIPO Y HERRAMIENTAS:
48006 Volquete 10 m3 HM 0.0533 180.00 9.59 0.87
----------------------------------------------------------------------------------------------------SyS-CU
. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 3
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES - ESTRUCT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
49003 Cargador sobre llantas 100-115hp HM 0.0067 154.41 1.03 0.09
----------------------------------
Sub-Total: 10.62 0.96

04.00. OBRAS DE CONCRETO SIMPLE

04.08.01 Falso piso e=3" mezcla 1:8 M2 28.83

MATERIALES:
10020 Agua M3 0.0300 10.00 0.30 0.01
21002 Cemento Tipo MS BLS 0.3355 21.53 7.22 0.25
38001 Hormigon M3 0.0938 135.60 12.72 0.44
43001 Madera tornillo P2 0.0500 4.50 0.23 0.01
----------------------------------
Sub-Total: 20.47 0.71
MANO DE OBRA:
47002 Operario HH 0.1070 20.79 2.22 0.08
47003 Oficial HH 0.0270 17.05 0.46 0.02
47004 Peon HH 0.3200 15.34 4.91 0.17
----------------------------------
Sub-Total: 7.59 0.26
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 7.5937 0.03 0.23 0.01
48009 Mezcladora de concreto de 9-11 p3 HM 0.0270 20.00 0.54 0.02
----------------------------------
Sub-Total: 0.77 0.03

08.00. ESTRUCTURAS DE MADERA Y COBERTURAS

08.01. Columnas de madera tornillo P2 8.12

MATERIALES:
43001 Madera tornillo P2 1.0200 4.50 4.59 0.57
----------------------------------
Sub-Total: 4.59 0.57
MANO DE OBRA:
47002 Operario HH 0.0670 20.79 1.39 0.17
47004 Peon HH 0.1330 15.34 2.04 0.25
----------------------------------
Sub-Total: 3.43 0.42
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 3.4332 0.03 0.10 0.01
----------------------------------
Sub-Total: 0.10 0.01

08.02. Vigas de Tornillo 1.18 Kg/p P2 9.89

MATERIALES:
43001 Madera tornillo P2 1.0200 4.50 4.59 0.46
----------------------------------------------------------------------------------------------------SyS-CU
. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 4
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES - ESTRUCT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
----------------------------------
Sub-Total: 4.59 0.46
MANO DE OBRA:
47002 Operario HH 0.1000 20.79 2.08 0.21
47004 Peon HH 0.2000 15.34 3.07 0.31
----------------------------------
Sub-Total: 5.15 0.52
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 5.1470 0.03 0.15 0.02
----------------------------------
Sub-Total: 0.15 0.02

08.03. Correas de madera tornillo P2 7.24

MATERIALES:
43001 Madera tornillo P2 1.0200 4.50 4.59 0.63
----------------------------------
Sub-Total: 4.59 0.63
MANO DE OBRA:
47002 Operario HH 0.0500 20.79 1.04 0.14
47004 Peon HH 0.1000 15.34 1.53 0.21
----------------------------------
Sub-Total: 2.57 0.35
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 2.5735 0.03 0.08 0.01
----------------------------------
Sub-Total: 0.08 0.01

08.04. Paneles de triplay con madera torniloo M2 61.78

MATERIALES:
02007 Clavos P/madera C/C 2" KG 0.5000 2.82 1.41 0.02
39003 Cola sintetica GLN 0.0800 16.02 1.28 0.02
43001 Madera tornillo P2 3.0500 4.50 13.73 0.22
44001 Triplay lupuna 4'x8'x 4mm. PCH 0.3600 25.34 9.12 0.15
----------------------------------
Sub-Total: 25.54 0.41
MANO DE OBRA:
47002 Operario HH 1.2000 20.79 24.95 0.40
47003 Oficial HH 0.6000 17.05 10.23 0.17
----------------------------------
Sub-Total: 35.18 0.57
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 35.1780 0.03 1.06 0.02
----------------------------------
Sub-Total: 1.06 0.02

. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 1
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES-ARQUITECT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
12.00.00 PISOS Y PAVIMENTOS

12.04.02 Piso de cemento frotachado y bru e=2.5cm S/colorear M2 26.16

MATERIALES:
04001 Arena gruesa M3 0.0210 152.54 3.20 0.12
10020 Agua M3 0.0110 10.00 0.11 0.00
21001 Cemento portland tipo I mejorado BLS 0.3200 20.51 6.56 0.25
43001 Madera tornillo P2 0.1000 4.50 0.45 0.02
----------------------------------
Sub-Total: 10.32 0.39
MANO DE OBRA:
47002 Operario HH 0.3200 20.79 6.65 0.25
47003 Oficial HH 0.1600 17.05 2.73 0.10
47004 Peon HH 0.3200 15.34 4.91 0.19
----------------------------------
Sub-Total: 14.29 0.55
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 14.2896 0.03 0.43 0.02
48009 Mezcladora de concreto de 9-11 p3 HM 0.0560 20.00 1.12 0.04
----------------------------------
Sub-Total: 1.55 0.06

17.00.00 COBERTURAS

17.02.00 Cobertura c/plch.corug.asb-cement.8P A.U 1.05*2.3=2.415m2 M2 34.04

MATERIALES:
30006 Gancho J galvanizado 10 cm UND 1.5000 3.47 5.21 0.15
59002 Plancha fibrocemento 10P PCH 0.4265 50.42 21.50 0.63
----------------------------------
Sub-Total: 26.71 0.78
MANO DE OBRA:
47002 Operario HH 0.2500 20.79 5.20 0.15
47004 Peon HH 0.1250 15.34 1.92 0.06
----------------------------------
Sub-Total: 7.12 0.21
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 7.1150 0.03 0.21 0.01
----------------------------------
Sub-Total: 0.21 0.01

18.00.00 CARPINTERIA DE MADERA

18.02.00 Puerta contraplacada c/madera tornillo triplay 4mm M2 248.71

MATERIALES:
02008 Clavos P/madera S/C 3/4 KG 0.1223 6.61 0.81 0.00
39003 Cola sintetica GLN 0.0661 16.02 1.06 0.00
39004 Lija para Madera UND 0.0500 0.69 0.03 0.00
----------------------------------------------------------------------------------------------------SyS-CU
. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 2
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES-ARQUITECT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
43001 Madera tornillo P2 1.3500 4.50 6.08 0.02
44001 Triplay lupuna 4'x8'x 4mm. PCH 0.6292 25.34 15.94 0.06
54006 Barniz Marino GLN 0.1000 48.31 4.83 0.02
----------------------------------
Sub-Total: 28.75 0.12
MANO DE OBRA:
47002 Operario HH 6.1123 20.79 127.07 0.51
47003 Oficial HH 5.0723 17.05 86.48 0.35
----------------------------------
Sub-Total: 213.55 0.86
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 213.5574 0.03 6.41 0.03
----------------------------------
Sub-Total: 6.41 0.03

18.03.02 Ventana madera tornillo barnizado M2 105.04

MATERIALES:
02005 Clavos P/madera 4" KG 0.0300 2.82 0.08 0.00
39003 Cola sintetica GLN 0.0500 16.02 0.80 0.01
43001 Madera tornillo P2 9.9000 4.50 44.55 0.42
43016 Lija para madera UND 0.5600 0.76 0.43 0.00
54006 Barniz Marino GLN 0.1000 48.31 4.83 0.05
----------------------------------
Sub-Total: 50.69 0.48
MANO DE OBRA:
47002 Operario HH 1.8000 20.79 37.42 0.36
47003 Oficial HH 0.9000 17.05 15.35 0.15
----------------------------------
Sub-Total: 52.77 0.50
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 52.7670 0.03 1.58 0.02
----------------------------------
Sub-Total: 1.58 0.02

20.00.00 CERRAJERIA

20.03.00 Bisagra Aluminizada de 2 1/2"x 2 1/2" pesada en ventana PZA 5.76

MATERIALES:
26029 Bisagra 2" pesada fierro aluminizada UND 1.0000 2.29 2.29 0.40
----------------------------------
Sub-Total: 2.29 0.40
MANO DE OBRA:
47002 Operario HH 0.1667 20.79 3.47 0.60
----------------------------------
Sub-Total: 3.47 0.60

20.04.00 Bisagra Aluminizada de 3" pesada en puerta PZA 8.78

----------------------------------------------------------------------------------------------------SyS-CU
. SISTEMA DE PRESUPUESTOS DE OBRA Pg. : 3
Centro de Cmputo ANALISIS DE PRECIOS UNITARIOS A MARZO - 2017 Fecha : 31/03/2017
PLAN DE CONTINGENCIA AULAS PROVISIONALES-ARQUITECT
------------------------------------------------------------------------------------------------------
Cd. Descripcin UND Particip. Precio S/. Parcial S/. Incid.
------------------------------------------------------------------------------------------------------
MATERIALES:
26017 Bisagra 3" pesada fierro Aluminizada c/t UND 1.0000 4.82 4.82 0.55
----------------------------------
Sub-Total: 4.82 0.55
MANO DE OBRA:
47002 Operario HH 0.1905 20.79 3.96 0.45
----------------------------------
Sub-Total: 3.96 0.45

20.04.01 Cerradura dos golpes en puerta c/tirador UND 61.04

MATERIALES:
26033 Cerradura para puerta pricipal dos golpe Und 1.0000 40.25 40.25 0.66
----------------------------------
Sub-Total: 40.25 0.66
MANO DE OBRA:
47002 Operario HH 1.0000 20.79 20.79 0.34
----------------------------------
Sub-Total: 20.79 0.34

21.00.00 VIDRIOS, CRISTALES Y SIMILARES

21.01.00 Vidrio Semidoble importado incoloro P2 5.47

MATERIALES:
30158 Silicona (tub. 305 ml) Tub 0.0800 9.24 0.74 0.14
79002 Vidrio semidoble e=3mm P2 1.1000 1.60 1.76 0.32
----------------------------------
Sub-Total: 2.50 0.46
MANO DE OBRA:
47002 Operario HH 0.1333 20.79 2.77 0.51
47003 Oficial HH 0.0067 17.05 0.11 0.02
----------------------------------
Sub-Total: 2.88 0.53
EQUIPO Y HERRAMIENTAS:
37001 Herramientas % 2.8855 0.03 0.09 0.02
----------------------------------
Sub-Total: 0.09 0.02