HOJA DE METRADOS

PROYECTO :
ELABORADO POR :
PROPIETARIO :
FECHA :
AREA COCINA Y COMEDOR
PART DESCRIPCION UND N VECES ANCHO LARGO ALTURA PARCIAL TOTAL
1.00 ESTRUCTURAS
1.01 TRABAJOS PROVISIONALES
01.01.01 SEALIZACION CON CINTA DE SEGURIDAD ml 1.00 43.80 43.80

1.02 TRABAJOS PRELIMINARES


01.02.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 area= 114.41 114.41 114.41
01.02.02 TRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO m2 1.00 area= 114.42 114.41 114.41
01.02.03 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR m2 1.00 area= 114.43 114.41 114.41

1.03 MOVIMIENTO DE TIERRAS


01.03.01 EXCAVACION DE ZANJAS PARA CIMENTACIONES m3 9.42
Eje A-A,C-C:1-4 2.00 0.40 8.61 0.60 4.13
Eje 1-1,4-4: A-C 2.00 0.40 8.52 0.60 4.09
Eje 1'-1 A-C 1.00 0.40 5.01 0.60 1.20
01.03.02 EXCAVACION PARA ZAPATAS 1.00M A 1.90 M DE PROFUNDIDAD m3 13.90
Z-1 4.00 0.85 0.90 1.20 3.67
Z-2 4.00 0.90 0.95 1.20 4.10
Z-3 2.00 1.00 1.05 1.20 2.52
Z-4 2.00 1.25 1.20 1.20 3.60
01.03.03 EXCAVACION PARA CUNETAS H=0.30 7.45
Cuneta perimetral 1.00 Area= 0.17 43.80 7.45

01.03.04 RELLENO CON MATERIAL PROPIO m2 4.40


Z-1 4.00 Area 0.67 0.60 1.61
Z-2 4.00 Area 0.46 0.60 1.10
Z-3 2.00 Area 0.70 0.60 0.84
Z-4 2.00 Area 0.71 0.60 0.85
01.03.05 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 101.36
1.00 Area 101.36 101.36
01.03.06 ACARREO MANUAL DE MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROM. m3 34.27
1.30 26.36 34.27
01.03.07 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO PESADO m3 34.27
1.00 34.27

1.04 OBRAS DE CONCRETO SIMPLE


01.04.01 SOLADO DE CONCRETO C:H-1:12 E=4" PARA ZAPATAS m2 11.58
Z-1 4.00 0.85 0.90 3.06
Z-2 4.00 0.90 0.95 3.42
Z-3 2.00 1.00 1.05 2.10
Z-4 2.00 1.25 1.20 3.00
01.04.02 CONCRETO PARA CIMIENTOS CORRIDOS C:H-1:10+30% P.G m3 8.93
Eje A-A,C-C:1-4 2.00 0.40 10.50 0.60 5.04
Eje 1-1,4-4: A-C 2.00 0.40 5.60 0.60 2.69
Eje 1'-1 A-C 1.00 0.40 5.01 0.60 1.20
01.04.03 CONCRETO PARA SOBRECIMIENTOS CORRIDOS C:H-1:8+25% P.G 1.58
Eje A-A:1-4 1.00 0.15 10.50 0.30 0.47
Eje A-A:1-2,3-4 1.00 0.15 7.00 0.30 0.32
Eje A-A:2-3 1.00 0.15 2.50 0.30 0.11
Eje 4-4: A-C 1.00 0.15 5.60 0.30 0.25
Eje 1-1:A-C 1.00 0.15 4.80 0.30 0.22
Eje 1'-1 A-C 1.00 0.15 4.75 0.30 0.21
01.04.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO H=0.30 CM m2 21.09
Eje A-A:1-4 2.00 10.50 0.30 6.30
Eje A-A:1-2,3-4 2.00 7.00 0.30 4.20
Eje A-A:2-3 2.00 2.50 0.30 1.50
Eje 4-4: A-C 2.00 5.60 0.30 3.36
Eje 1-1:A-C 2.00 4.80 0.30 2.88
Eje 1'-1 A-C 2.00 4.75 0.30 2.85
01.04.05 FALSO PISO DE CONCRETO C:H DE E=4" 74.10
Falso piso de concreto e=4" 1.00 Area 74.10 74.10

01.04.06 VEREDAS
01.04.06.01 VEREDA DE CONCRETO f'c= 140 kg/cm2-4" 2.69
1.00 Area 26.90 0.10 2.69
1.05.06.02 ENCOFRADO Y DESENCOFRADO DE VEREDAS 7.91
longitudinal 1.00 41.41 0.15 6.21
transversal 5.00 0.95 0.15 0.71
5.00 0.60 0.15 0.45

1.04.07 CUNETAS 6.00 0.60 0.15 0.54


1.05.07.01 CONCRETO EN CUNETAS f'c= 140 kg/cm 7.45
1.00 area 0.17 43.80 7.45
1.05.07.02 ENCOFRADO Y DESENCOFRADO DE CUNETAS 15.52
longitudinal 1.00 43.80 0.30 13.14
transversal 14.00 area 0.17 2.38

1.05 OBRAS DE CONCRETO ARMADO


1.06.01 ZAPATAS
1.06.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 m3 6.95
Z-1 4.00 0.85 0.90 0.60 1.84
Z-2 4.00 0.90 0.95 0.60 2.05
Z-3 2.00 1.00 1.05 0.60 1.26
Z-4 2.00 1.25 1.20 0.60 1.80
1.06.01.02 ACERO Fy=4200kg/cm2 GRADO 60 168.34
ver hoja de metrado 1.07 157.33 168.34

1.06.02 COLUMNAS
1.06.02.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 3.81
C-1 8.00 0.25 0.30 3.75 2.25
C-2 4.00 0.25 0.30 5.20 1.56

1.06.02.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS M2 55.88


C-1 8.00 1.10 3.75 33.00
HOJA DE METRADOS

PROYECTO :
ELABORADO POR :
PROPIETARIO :
FECHA :
AREA COCINA Y COMEDOR
PART DESCRIPCION UND N VECES ANCHO LARGO ALTURA PARCIAL TOTAL
C-2 4.00 1.10 5.20 22.88

1.06.02.03 ACERO Fy=4200kg/cm2 GRADO 60 Kg 616.31


ver hoja de metrado 1.07 575.99 616.31

1.06.03 COLUMNETAS
1.06.03.01 CONCRETO EN COLUMNETAS f'c=175 kg/cm2 m3 0.22
Columnetas pluviales 4.00 0.20 0.15 1.85 0.22

1.06.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETAS m2 3.70


4.00 0.50 1.85 3.70
1.06.03.03 ACERO Fy=4200kg/cm2 GRADO 60 kg 35.67
ver hoja de metrado 1.07 33.34 35.67

1.06.04 VIGAS
1.06.04.01 CONCRETO EN VIGAS f'c=210 kg/cm2 m3 4.92
VP-101(0.25*0.30) 9.00 3.50 0.25 0.30 2.36
VP-101(0.25*0.25 3.00 3.50 0.25 0.30 0.79
VP-102 ( 0.25*0.30) 4.00 2.85 0.25 0.30 0.86
VP-102 ( 0.25*0.30) 4.00 3.05 0.25 0.30 0.92
1.06.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 23.48
VP-101(0.25*0.30) 9.00 3.50 0.35 11.03
VP-101(0.25*0.30) 3.00 3.50 0.40 4.20
VP102(0.25*0.30) 4.00 2.85 0.35 3.99
VP102(0.25*0.30) 4.00 3.05 0.35 4.27
1.06.04.03 ACERO Fy=4200kg/cm2 GRADO 60 Kg 851.28
ver hoja de metrado 1.07 795.59

1.06.05 DOBLE VIGUETA


1.06.05.01 CONCRETO EN DOBLE VIGUETA m3 0.43

CORTE K-K 2.00 0.10 8.10 0.20 0.32


6.00 0.30 0.30 0.20 0.11
1.06.05.02 ENCOFRADO Y DESENCOFRADO DE VIGUETAS m2 6.12
Encofrado y desencofrado de viguetas 6.00 0.30 0.70 1.26
2.00 0.30 8.10 4.86
1.06.05.03 ACERO Fy=4200kg/cm2 GRADO 60 52.48
ver hoja de metrado 1.07 34.42 36.83

1.06.06 VIGA CANAL


1.06.06.01 CONCRETO EN VIGA CANAL f'c=210 kg/cm2 m3 5.11
Frontal 1.00 Area 0.25 12.10 3.06
Posterior 1.00 Area 0.17 12.10 2.06

1.06.06.02 ENCOFRADO Y DESENCOFRADO DE VIGA CANAL m2 20.75


Frontal 1.00 12.10 1.55 18.76
tapas 2.00 Area 0.25 0.51
seccion J-J 1.00 12.10 1.15 1.15
tapas 2.00 Area 0.17 0.34
1.06.06.03 ACERO Fy=4200kg/cm2 GRADO 60 KG 279.90
ver hoja de metrado 1.07 261.59

1.06.08 LOSA ALIGERADA


1.06.08.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 7.05
Frontal 1.00 Area 39.90 0.05 2.00
viguetas pao a-a 9.00 0.10 0.15 11.00 1.49
Posterior 1.00 Area 38.40 0.05 1.92
viguetas (b-b) 10.00 0.10 0.15 11.00 1.65
1.06.08.02 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA 78.30
Frontal 1.00 Area 39.90 39.90
Posterior 1.00 Area 38.40 38.40
1.06.08.03 ACERO Fy=4200kg/cm2 GRADO 60 Kg 649.55
1.07 607.06
1.06.08.04 LADRILLO HUECO DE ARCILLA 15X30X30 PARA LOSA LIGERADA m2 657.72
Ladrillo hueco de arcilla 0.15x0.30x0.30 para losa aligerada 1.05 78.30 8.00 657.72

1.07 COBERTURA
1.07.01 COBERTURA CON TEJA ANDINA TIPO ETERNIT 103.46
Area m2 1.00 12.10 8.55 103.46
1.07.02 CUMBRERA ARTICULADA DE TEJA ANDINA ml 12.10
1.00 12.10 12.10

2.00 ARQUITECTURA
2.01 MUROS Y TABIQUES DE ALBAILERIA
2.01.01 MURO DE LADRILLO DE ARCILLA CORRIENTE CABEZA MEZC. C:A-1:4X1.50 CM 60.34
Eje C-C:1-4 2.00 3.50 1.05 7.35
Eje C-C:1-2 1.00 2.74 1.05 2.88
Eje C-C:1-2 1.00 0.76 2.45 2.45
Eje A-A:1-2,3-4 2.00 3.75 1.35 7.50
Eje A-A:2-3 2.00 1.25 2.45 6.13
Eje 1-1,4-4: A-B 2.00 Area 7.90 15.80
Eje 1-1,4-4: C-D 2.00 Area 9.12 18.24
2.01.02 MURO DE LADRILLO DE ARCILLA CORRIENTE SOGA MEZC. C:A-1:4X1.50 CM m2 37.54
Cocina 1.00 2.86 3.85 11.01
1.00 Area 4.20 4.20

2.02 REVOQUES ENLUCIDOS Y MOLDURAS


2.02.01 TARRAJEO PRIMARIO Y/O RAYADO C:A-1:5 E=1.5CM 15.53
Tarrajeo Cocina 2.00 6.47 1.20 15.53
2.02.02 TARRAJEO EN MUROS INTERIORES FROTACHADO MEZC. C:A-1:5 E=1.5CM 77.96
Eje C-C:1-4 2.00 3.50 1.05 7.35
Eje C-C:1-2 1.00 2.74 1.05 2.88
Eje C-C:1-2 1.00 0.76 2.45 1.86
HOJA DE METRADOS

PROYECTO :
ELABORADO POR :
PROPIETARIO :
FECHA :
AREA COCINA Y COMEDOR
PART DESCRIPCION UND N VECES ANCHO LARGO ALTURA PARCIAL TOTAL
Eje A-A:1-2,3-4 2.00 3.75 1.35 10.13
Eje A-A:2-3 2.00 1.25 2.45 6.13
Eje 1-1,4-4: A-B 2.00 Area 7.90 15.80
Eje 1-1,4-4: C-D 2.00 Area 9.12 18.24
Cocina 2.00 2.86 2.65 7.58
2.00 Area 4.00 8.00
2.02.03 TARRAJEO EN MUROS EXTERIORES FROTACHADO MEZC. C:A-1:5 E=1.5CM 62.38
Eje C-C:1-4 2.00 3.50 1.05 7.35
Eje C-C:1-2 1.00 2.74 1.05 2.88
Eje C-C:1-2 1.00 0.76 2.45 1.86
Eje A-A:1-2,3-4 2.00 3.75 1.35 10.13
Eje A-A:2-3 2.00 1.25 2.45 6.13
Eje 1-1,4-4: A-B 2.00 Area 7.90 15.80
Eje 1-1,4-4: C-D 2.00 Area 9.12 18.24
2.02.04 TARRAJEO EN COLUMNAS CON C:A-1:5 E=1.5CM 21.66
C-1 2.00 0.55 2.55 2.81
2.00 0.55 2.70 2.97
2.00 0.25 2.70 1.35
2.00 0.25 2.55 1.28
C-2 2.00 1.10 3.90 8.58
2.00 0.60 3.90 4.68
2.02.05 TARRAJEO DE COLUMNETAS m2 4.07
Columnetas Pluviales 4.00 0.55 1.85 4.07

2.02.06 TARRAJEO EN VIGAS C:A-1:5 E=1.5CM m2 40.13


VP-101(0.25*0.30) 9.00 3.50 0.50 15.75
VP-102(0.25*0.30) 2.00 7.20 0.45 6.48
VP-102(0.25*0.30) 2.00 7.20 0.25 3.60
VIGA CANAL 2.00 11.00 0.65 14.30

2.02.07 TARRAJEO CON IMPERMEABIZANTES m2 37.93 37.93 37.93

2.02.08 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS CON C:A-1:5 E=1.5CM ml 93.50
Vestidura de derrame de ventanas 1.00 74.70 74.70
Vestidura de derrames en puertas 1.00 18.80 18.80

2.02.09 BRUAS DE 1.50 CM ml 236.20


1.00 236.20 236.20
2.03 CIELORRASOS
2.03.01 TARRAJEO EN CIELORRASOS CON C:A-1:4 E=1.5CM 78.30
Primer piso 1.00 Area 78.30 78.30

2.04 PISOS Y PAVIMENTOS


2.04.01 CONTRAPISO DE 40 MM 65.70
primer piso 1.00 Area 65.70 65.70

2.04.02 PISO CERAMICO ANTIDESLIZANTE ALTO TRANSITOS 30X30 CM m2 65.70


Primer piso 1.00 Area 65.70 65.70

2.05 CONTRAZOCALOS
2.05.01 CONTRAZOCALO DE CERAMICO 10X30CM H=10CM 27.40
1.00 27.40 27.40
2.05.02 CONTRAZOCALO DE CEMENTO PULIDO H=30CM MEZCLA 1:5 E=2CM 34.20
Cocina y Comedor ml 1.00 34.20 34.20

2.06 ZOCALOS
02.06.01 ZOCALO DE CERAMICOS 0.20X0.30CM 15.53
Cocina y Comedor 2.00 6.47 1.20 15.53

2.07 CARPINTERIA DE MADERA Y MELAMINA


2.07.01 PUERTA P-1 MDF TIPO CEDRO (0.80MX2.10M) ACABADO AL DUCO E=2" und 3.00 3.00 3.00
2.07.02 PUERTA P-2 MDF TIPO CEDRO (1.00MX2.10M) ACABADO AL DUCO E=2" und 1.00 1.00 1.00

2.08 CARPINTERIA METALICA Y HERRERIA


2.08.01 VENTANA METALICA INC/ INSTALACION
2.08.01.01 V1(METALICA INCLUYE INSTALACION) Und 4.00 4.00 4.00
2.08.01.02 V2(METALICA INCLUYE INSTALACION) Und 1.00 1.00 1.00
2.08.01.03 V3(METALICA INCLUYE INSTALACION) Und 1.00 1.00 1.00
2.08.01.04 V4(METALICA INCLUYE INSTALACION) Und 3.00 3.00 3.00

2.90 CERRAJERIA
2.09.01 BISAGRA ALUMINIZADA CAPUCHINA DE 4"X4" Und 9.00
Puertas 3.00 3.00 9.00
2.09.02 CERRADURA PARA PUERTA PRINCIPAL DE SOBREPONER 3 GOLPES LLAVE EXTERIOR Und 3.00
Puertas 3.00 3.00

2.09.03 REJILLA METALICA EN CUNETAS INC/INSTALACION ml 47.21 47.21 47.21

2.10 VIDRIOS,CRISTALES Y SIMILARES


2.10.01 VIDRIO SEMIDOBLE TRANSPARENTE P2 Conversion 328.27
V1(METALICA INCLUYE INSTALACION) 4.00 3.50 1.50 10.80 226.80
V2(METALICA INCLUYE INSTALACION) 1.00 2.74 1.50 10.80 44.39
V3(METALICA INCLUYE INSTALACION) 1.00 0.50 0.70 10.80 3.78
V4(METALICA INCLUYE INSTALACION) 3.00 3.50 0.47 10.80 53.30

2.11 PINTURA 77.96


2.11.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE m2 1.00 Area 77.96 77.96
62.38
2.11.02 PINTURA EN MUROS EXTERIORES C/LATEX LAVABLE m2 1.00 Area 62.38 62.38

2.11.03 PINTURA EN COLUMNAS C/LATEX LAVABLE m2 21.66


1.00 Area 21.66 21.66
2.11.04 PINTURA EN VIGAS C/LATEX LAVABLE m2 40.13
HOJA DE METRADOS

PROYECTO :
ELABORADO POR :
PROPIETARIO :
FECHA :
AREA COCINA Y COMEDOR
PART DESCRIPCION UND N VECES ANCHO LARGO ALTURA PARCIAL TOTAL
1.00 Area 40.13 40.13
2.11.05 PINTURA EN COLUMNETAS C/LATEX LAVABLE m2 4.07
1.00 Area 4.07 4.07
2.11.07 PINTURA EN DERRAMES C/LATEX LAVABLE ml 93.50
1.00 total 93.50 93.50
2.11.08 PINTURA EN BRUAS CON ESMALTE SINTETICO ml 236.20
1.00 total 236.20 236.20
2.11.09 PINTURA EN CIELORRASO C/LATEX m2 78.30
1.00 Area 78.30 78.30
2.11.10 PINTURA ESMALTE EN CONTRA ZOCALO DE CEMENTO H=0.30 CM ml 34.20
1.00 total 34.20 34.20
2.12 VARIOS
2.12.01 JUNTAS ASFALTICAS ml 9.80
Frontal 4.00 0.95 3.80
Posterior 4.00 0.60 2.40
Laterales 6.00 0.60 3.60

3.00 INSTALACIONES ELECTRICAS


3.01 SALIDA A TECHOS
3.01.01 SALIDA DE TECHO CENTRO DE LUZ 6.00
pto 1.00 6.00 6.00
3.01.02 SALIDA DE PARED PARA INTERRUPTOR SIMPLE 3.00

3.02 SALIDA PARA TOMACORRIENTES pto 1.00 3.00 3.00


03.02.01 SALIDA DE TOMACORRIENTES BIPOLARES DOBLES 5.00
pto 1.00 5.00 5.00

3.03 CANALIZACION Y/O TUBERIAS


3.03.01 TUBERIA PVC SAP 3/4" P/INST.ELECTRICAS ml 1.00 25.30 25.30 25.30
3.03.02 TUBERIA PVC SAP 1/2" P/INST.ELECTRICAS ml 1.00 33.90 33.90 33.90

3.04 CONDUCTORES Y/O CABLES


3.04.01 CONDUCTOR ELECTRICO 2.5 MM2 TW ml 1.00 67.80 67.80 67.80
3.04.02 CONDUCTOR ELECTRICO 4 MM2 TW ml 1.00 75.30 75.30 75.30

3.05 TABLEROS DE DISTRIBUCION


3.05.01 CAJA METALICA PARA TABLEROS DE DISTRIBUCION CON CHAPA pza 1.00 1.00 1.00 1.00
3.05.02 TABLERO DE DISTRIBUCION DE 5 CIRCUITOS pza 1.00 1.00 1.00 1.00

3.06 LLAVES DE INTERRUPCION


3.06.01 INTERRUPTOR THERMOMAGNETICO AUTOMATICO DE 2X15 AMP Und 1.00 1.00 1.00 1.00
3.06.02 INTERRUPTOR THERMOMAGNETICO AUTOMATICO DE 2X20 AMP Und 1.00 1.00 1.00 1.00
3.06.03 INTERRUPTOR THERMOMAGNETICO AUTOMATICO DE 2X30 AMP Und 1.00 1.00 1.00 1.00

3.07 CAJAS DE PASE


3.07.01 CAJA DE PASE DE FG DE 4"X4"X2" Und 1.00 1.00 1.00 1.00

3.08 ARTEFACTOS ELECTRICOS


3.08.01 FLUORESCENTE RECTANGULAR T/PERSIANA 2X40 WATT INCLUYENDO EQUIPO Und 1.00 6.00 6.00 6.00

4.00 INSTALACIONES SANITARIAS


4.01 APARATOS SANITARIOS 1.00
4.01.01 LAVADERO DE CONCRETO FC=175 KG7CM2 pZA 1.00 1.00

4.02 INSTALACIONES SANITARIAS


4.02.01 DESAGUE
4.01.01.01 SALIDA PARA DESAGUE 2"PVC pto 1.00 1.00 1.00 1.00

04.02.02 REDES DE DISTRIBUCION


04.02.02.01 RED DE DISTRIBUCION 2" PVC SAP ,ml 1.00 5.00 5.00 5.00

04.02.03 REDES COLECTORAS


04.02.03.02 EXCAVACION DE ZANJAS 0.50X0.90 M m3 1.00 0.40 20.50 0.90 7.38 7.38
04.02.03.03 RELLENO DE ZANJA m3 1.30 0.40 20.50 0.90 9.59 9.59

4.03 ACCESORIOS
4.03.01 CODOS Pza 1.00
4.03.01.01 CODO 2"X90 PVC SAP 1.00 1.00
4.03.02 YEES Pza 1.00
4.03.02.01 YEES DE 2" PVC SAP 1.00 1.00

4.04 ADITAMENTOS VARIOS


04.04.01 SUMIDERO DE BRONCE CROMADO DE 2" Pza 1.00 1.00 1.00
04.04.02 CAJA DE REGISTRO DE DESAGUE 12"X24" INCLUYE REJILLA METALICA Und 1.00 1.00 1.00

4.05 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO


04.05.01 REDES DE DISTRIBUCION
04.05.01.01 RED DE DISTRIBUCION 1/2" PVC SAP ml 1.00 3.50 3.50
04.05.01.02 RED DE DISTRIBUCION 6" PVC SAP ml 1.00 20.50 20.50

04.05.02 REDES DE ALIMENTACION


04.05.02.01 EXCAVACION DE ZANJAS 0.30X0.40 M m3 1.00 0.40 3.50 0.30 0.42 0.42
04.05.02.02 RELLENO DE ZANJA m3 1.30 0.40 29.50 0.30 4.60 4.60

4.06 ACCESORIOS
04.06.01 CODOS
04.06.01.01 CODO 1/2" PVC C-10 PARA AGUA Pza 3.00 3.00 3.00

04.06.02 LLAVES Y VALVULAS


04.06.02.01 VALVULA DE COMPUERTA DE BRONCE DE 1/2" Pza 1.00 1.00 1.00
04.06.02.02 GRIFO CROMADO DE 1/2" Pza 1.00 1.00 1.00

04.06.03 PIEZAS VARIAS


04.06.03.01 CAJA DE CONCRETO PARA VALVULAS Und 1.00 1.00 1.00
HOJA DE METRADOS

PROYECTO :
ELABORADO POR :
PROPIETARIO :
FECHA :
AREA COCINA Y COMEDOR
PART DESCRIPCION UND N VECES ANCHO LARGO ALTURA PARCIAL TOTAL

4.07 SISTEMA DE AGUAS DE LLUVIA


04.07.01 TUBERIA DE BAJADA Y DISTRIBUCION 15.90
04.07.01.01 TUBERIAS PVC SAP 3" ml 2.00 3.65 7.30
2.00 4.30 8.60
04.07.02 ACCESORIOS DE TUBERIAS
04.07.02.01 CODO 3" A 90 PVC SAP Pza 12.00 12.00 12.00

4.08 VARIOS
04.08.01 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA ml 1.00 20.50 20.50 20.50
04.08.02 SEALIZACION und 1.00 15.00 15.00
04.08.03 EXTINTOR und 1.00 2.00 2.00