1. DATE:25.10.2017- Loading of 04 no.s modular toilets concrete blocks in our truck by using 05 labour
including 03 local labour .
2. Date:26.10.2017:-Delivery made to Misrilall mines, Kaliapani 04 no.s toilets by using 06 no.s labour
including 04 no.s local labour .
3. Date: 27.10.2017:- Loading of another 04 no.s modular toilets concrete blocks in our truck by using 06
no.s labour including 04 no.s local labour .
5. On dt: 29/30 .10.2017 :Eight set of soak pit ring with cover will be loaded in truck & deliver to Misrilal
mines and on same day unloading of soak pit ring done at once .
6. Erection of 08 toilets may take approx. three to four days or from 31.10.17 to 03.11.17 .
7. Date : 04.11.2017 :-Loading of two no.s Toilet cum Bathroom will be done.
9.Date: 06.11.2017:-Pre cast block shifting through truck & pick up (small vehicle) will be made from
Bileipada to Balita village (Erection site) .
11. Plastering work of TCB two no.s will start from 09.11.2017 .