ESTIMATE FOR THE SPETIC TANK WORKS AT RAHMATH NAGAR

The following is the estimate for construction of two additional septic tank

and digging an already existing reach pit. The following works are done inside

the compound and hence the digging can only be done manually.

Construction of two septic tanks :- (5 X 18) & (5 X 18)

S.NO DESCRIPTION CU.FT RATE AMOUNT


PER
CFT

1. Demolishing the floor using L.S 2000


Demolishing machine (chipping)

2. Digging manually to depth 7ft 1291 10 12,910

3. Demolishing the ground level rock L.S 4000


Inside the septic tank

4. P.C.C concrete 83 90 7470

5. Brick work 419 140 58,660

6. Plastering 640sft 25 16,000

7. Concrete cover using steel 92 cft 450 41,400


reinforcement
8. Manual cover (2 nos) L.S 4500

9. Plumbing charges L.S 3500

TOTAL Rs 1,50,440

Construction of already existing reach pit (56 x 16)

S.NO DESCRIPTION CU.FT RATE AMOUNT


PER CFT

1. Demolishing the floor L.S 4000


chipping

2. Digging the reach pit manually 616 10 6160

3. Laying the concrete cover 44 450 19,800

4. Plumbing works L.S 4000

TOTAL Rs 33,960

AMOUNT FOR REMOVAL OF WASTE WATER (3 TIMES x 2000 ) - Rs 6000/-

GRAND TOTAL FOR THE ENTIRE WORKS IS Rs Rs 1,90,400 /-

VISWA CONSTRUCTION