ESTRUCTURAS 6,001,577.69
01.00.00 Obras Provisionales 100%
S/. 125,144.13 125144.13
02.00.00 Trabajos Preliminares 80% 20%
S/. 178,335.07 142668.06 35667
03.00.00 Movimiento de Tierras 60% 40%
S/. 718,113.24 430867.94 287245.30
04.00.00 Obras de Concreto Simple 20% 40% 40%
S/. 286,859.37 57371.87 114743.75 114744
05.00.00 Obras de Concreto Armado 10.00% 15.00% 25.0% 25.0% 15.0% 10.00%
S/. 4,428,430.10 442843.01 664264.52 1107107.53 1107107.53 664265 442843.01
06.00.00 Coberturas 25% 50% 25%
S/. 264,695.78 66173.945 132347.89 66173.945
COSTO DIRECTO (S/.) S/. 10,543,220.61 S/. 756,052.00 S/. 894,824.08 S/. 933,048.77 S/. 1,350,010.91 S/. 1,636,950.06 S/. 1,466,426.83 S/. 1,488,426.71 S/. 928,298.245 S/. 690,519.407 S/. 398,663.61
GASTOS GENERALES (15.00%) (S/.) 1,581,483.09 S/. 113,407.80 0.00 0.00 S/. 134,223.61 0.00 0.00 S/. 139,957.31 0.00 S/. 202,501.64 0.00 S/. 245,542.51 0.00 S/. 219,964.02 0.00 S/. 223,264.01 0.00 S/. 139,244.74 0.00 S/. 103,577.91 0.00 S/. 59,799.54 0.00
SUB TOTAL (S/.) 12,124,703.70 S/. 869,459.80 0.00 0.00 S/. 1,029,047.69 0.00 0.00 S/. 1,073,006.08 0.00 S/. 1,552,512.54 0.00 S/. 1,882,492.56 0.00 S/. 1,686,390.85 0.00 S/. 1,711,690.72 0.00 S/. 1,067,542.98 0.00 S/. 794,097.32 0.00 S/. 458,463.15 0.00
IGV (18%) (S/.) 2,182,446.67 S/. 156,502.76 0.00 0.00 S/. 185,228.58 0.00 0.00 S/. 193,141.09 0.00 S/. 279,452.26 0.00 S/. 338,848.66 0.00 S/. 303,550.35 0.00 S/. 308,104.33 0.00 S/. 192,157.74 0.00 S/. 142,937.52 0.00 S/. 82,523.37 0.00
TOTAL (S/.) S/. 14,307,150.37 S/. 1,025,962.57 0.00 0.00 S/. 1,214,276.28 0.00 0.00 S/. 1,266,147.18 0.00 S/. 1,831,964.80 0.00 S/. 2,221,341.22 0.00 S/. 1,989,941.21 0.00 S/. 2,019,795.05 0.00 S/. 1,259,700.72 0.00 S/. 937,034.84 0.00 S/. 540,986.51 0.00
PORCENTAJE DE AVANCE PARCIAL 7.17 % 8.49 % 8.85 % 12.80 % 15.53 % 13.91 % 14.12 % % 8.80 % 6.55 % 3.78 %
PORCENTAJE ACUMULADO 7.17 % 15.66 % 24.51 % 37.31 % 52.84 % 66.75 % 80.87 % % 89.67 % 96.22 % 100.00 %