METHOD OF STATEMENT FOR ERECTION WORKS

BACKGROUND INFORMATION
COMPANY DETAILS: No. 70, Jalan SC2, Pusat Perindustrian Sungai Chua 43000 Kajang,
Selangor Darul Ehsan, Malaysia.
Tel: 603 - 8733 9163 / 8737 0168 / 8736 5168
Fax: 603 - 8737 3163 / 8734 6641
CLIENT: Tenaga Nasional Berhad
OVERVIEW OF PROJECT/ACTIVITY: On Site Maintenance and Service Battery Charger No.1 and No.2

IMPLEMENTATION AND CONTROL OF RISK

Bil Detail Description Of Activities Hazard & Potential Risk Method Of Control PIC Remarks

1. Unloading DC Charger PCBs, Hand tool


to site.

Check cleanliness of the Unclear boundary Use a proper PPE Competent


equipment and environment. of working. Use proper person at site
Ergonomic equipment and
tools for unloading

2. Isolation existing DC Charger No.1 and


transfer all out going loads to DC
Charger No.2

Simulate both Chargers on Unclear boundary Use a proper PPE Competent Equipment will be
Manual Float condition. of working. Use isolated person at site use:
Switch OFF or Isolate Battery Risk of Electrical equipment and Digital Multi-Meter
Bank No.1 Isolator. shock. tools AC/DC Clamp
Switch OFF DCDB DC Incomer Meter
Breaker No.1.

3. Checking and Service the DC Charger


system No.1

Recalibration the DC Charger Unclear boundary Use a proper PPE Competent Equipment will be
No.1 output voltage, such as V. of working. Use isolated person at site use:
Float and V. Boost. Risk of Electrical equipment and Digital Multi-Meter
All alarms indicator on the LED shock. tools AC/DC Clamp
front panel. Meter
Bil Detail Description Of Activities Hazard & Potential Risk Method Of Control PIC Remarks

4. Replacement new PCB Card on


existing DC Charger No.1 (*If found that
the existing PCBs or Parts faulty)
Unclear boundary Use a proper PPE Competent Equipment will be
Replace and relocate the new of working. Use isolated person at site use:
PCB Card or parts. Risk of Electrical equipment and Digital Multi-Meter
Reconnect all existing cables or shock. tools AC/DC Clamp
additional new cables to new PCB Ergonomic Meter
Cards. Charger Control
Card
Or Multi- Alarm
Card

5. Isolation existing DC Charger No.2 and


transfer all out going loads to DC
Charger No.1

Simulate both Chargers on Unclear boundary Use a proper PPE Competent Equipment will be
Manual Float condition. of working. Use isolated person at site use:
Switch OFF or Isolate Battery Risk of Electrical equipment and Digital Multi-Meter
Bank No.2 Isolator. shock tools AC/DC Clamp
Switch OFF DCDB DC Incomer Meter
Breaker No.2.

6. Replacement new PCB Card on


existing DC Charger No.1 (*If found that
the existing PCBs or Parts faulty)

Replace and relocate the new Unclear boundary Use a proper PPE Competent Equipment will be
PCB Card or parts. of working. Use isolated person at site use:
Reconnect all existing cables or Risk of Electrical equipment and Digital Multi-Meter
additional new cables to new PCB shock. tools AC/DC Clamp
Cards. Ergonomic Meter
Charger Control
Card
Or Multi- Alarm
Card
Bil Detail Description Of Activities Hazard & Potential Risk Method Of Control PIC Remarks
7. Normalize the DC Charger No.1 and
Charger No.2 to DCDB.

Ensure DCDB both Incomer Risk of Electrical Use a proper PPE Competent Equipment will be
supply are same polarity. Shock Use isolated person at site use:
Switch ON both DCDB Incomer equipment and Digital Multi-Meter
breakers. tools AC/DC Clamp
Meter

8. House keeping
Site access 1) All unwanted Competent
blocked materials must be person at site
removed from time
to time
2) Ensure emergency
is clear from
materials and
debris

Prepared by: Approved by:

Derek Fong Wai Yin


..
(Name) (Name)

(Signature)
(Signature)