Академический Документы
Профессиональный Документы
Культура Документы
ROSENTHAL ROAD
SMITHERS, BC
Submitted to:
Town of Smithers
Attention: Mark F. Allen, P.Eng.
1027 Aldous Street PO Box 879
Smithers, British Columbia, V0J 2N0
Submitted by:
Amec Foster Wheeler Environment & Infrastructure,
a Division of Amec Foster Wheeler Americas Limited
#3 3167 Tatlow Road
Smithers, British Columbia V0J 2N0
October 2017
KS00423
Town of Smithers Amec Foster Wheeler
Geotechnical Site Assessment Environment & Infrastructure
Rosenthal Road
Smithers, British Columbia
13 October 2017
TABLE OF CONTENTS
PAGE #
LIST OF FIGURES
LIST OF APPENDICES
LIST OF TABLES
Selected soil samples collected during the field investigation were tested by Amec Foster
Wheelers Smithers laboratory for:
Water (Moisture) Content, ASTM D2216;
Atterberg Limits, ASTM D4318; and
Grain Size Distribution Analysis, ASTM C136/C117.
Borehole logs describing the soils encountered, sampling depths, and laboratory results are
presented in Appendix B. An explanation of terms and symbols used on the logs is also included.
Detailed laboratory testing results are presented in Appendix C.
3.2 Test Pitting Program
Three additional test pits were completed on 29 September 2017 along the perimeter trail in order
to identify a suitable subgrade near the toe of the existing embankment. These test pits were
completed after the Town of Smithers indicated that they preferred to proceed with the soil
buttress remediation option which will extend beyond the toe of the existing embankment.
The three test pits were excavated to depths of 2 m to 2.5 m using a small backhoe that was
operated by the Town of Smithers and observed by an Amec Foster Wheeler representative. The
soils were classified in general accordance with the Modified Unified Soil Classification System
and samples were taken for laboratory testing. GPS coordinates of the three test pit locations
were recorded using a handheld GPS device.
Test pit logs including descriptions of the soils encountered and laboratory results are in included
in Appendix B with the borehole logs from the initial site investigation. Detailed laboratory testing
results are included in Appendix C.
4.0 SITE CONDITIONS
4.1 Surficial Geology
The published and available mapped surficial geology of the Smithers area1 indicates that it is
generally dominated by morainal landforms with a constituent till that is typically silt- to clay-rich.
Drift is common on moderate to steep slopes in this area, while glacio-fluvial sediments are also
present in the valley, though these sediments are much less common than in surrounding areas.
There is also widespread fluvial terrain related to historical post glacial flows of the Bulkley River
throughout the valley.
Additional available mapped surficial geology of the area2 indicates that the subject section of
Rosenthal Road has been constructed across a relatively steep erosional river terrace slope that
consists of several different stratigraphic sections with varying lithologies. The Smithers Soils
Map (83-M-03) dated 07 November 1983 indicates that the site area generally consists of a thin
veneer or blanket of colluvium above layers of morainal tills and other glacial deposits.
1
Clague, John J., Quaternary Geology and Geomorphology, Smithers-Terrace-Prince Rupert Area, British Columbia, Geographical
Survey of Canada, 1984
2
Geological Compilation Map of the Smithers, Hazelton and Terrace Areas, British Columbia Department of Mines and Petroleum
Resources, Map69-1, Compiled by NC Carter and RV Kirkham
compositionally similar to the overlying fill material with a grain size distribution of 19%
gravel, 12% sand, 47% silt and 22% clay. Atterberg Limits completed on the same sample
indicate it is medium plastic with a liquid limit of 40 and a plastic limit of 23. This transitional
fill and colluvium material had natural water contents of 19% to 30%, similar to what was
measured in the overlying fill. This material appears to be a transitional fill and possibly
some clayey colluvium that has come down from the slope above. This layer extends to
depths of 8.7 m and 6.1 m in boreholes BH17-01 and BH17-02, respectively.
INTERBEDDED SAND AND SILT (likely glaciofluvial or fluvial origin): A 1.5 m thick layer
of interbedded silt and sand was encountered below the transitional fill and colluvium in
BH17-01. This material primarily consisted of reddish brown silt and sand that was
interbedded with poorly graded silty sand and low plastic, firm to stiff clay laminations.
The clay laminations ranged in thickness from 25 mm to 60 mm. This interbedded sand
and silt layer was primarily firm to stiff with an SPT N-value of 11. One sample taken from
this layer had a natural water content of 30%.
GLACIAL TILL (GREY): Underlying the transitional fill/colluvium material and/or
interbedded sand and silt was a very stiff to hard silt and clay till with trace to some gravel
and trace to some sand. This glacial till material was encountered at depths of 10.2 m
and 6.1 m below the road surface in boreholes BH17-01 and BH17-02 respectively and
where tested consisted of 17% gravel, 22% sand, 33% silt and 28% clay. SPT N-values
were generally higher in this till material than in the overlying soils, with SPT N-values
ranging from 20 to 39 with one low SPT N-value of 10 in BH17-01 just below the
interbedded sand and silt. This material was also medium plastic with a liquid limit of 35
and a plastic limit of 19. Natural water contents of this glacial till generally ranged from
15% to 17%, with one sample near the top of the till having a higher natural water content
of 23%. Both of the boreholes were terminated in this clay and silt.
4.4 Subsurface Conditions at the Toe of the Embankment Slope
The following sections describe the soil encountered at the toe of the existing embankment slope
during the secondary test pitting program completed on 29 September 2017. This subsurface
information should be read in conjunction with the test pit logs provided in Appendix B.
TOPSOIL: The topsoil generally consisted of either a sandy silt or a fibrous organic layer.
The topsoil ranged in thickness from 0.3 m to 0.5 m and contained a significant amount of
roots and other organics. In test pit TP17-03 the topsoil was highly saturated with ponded
water visible near the ground surface. It appeared that this water was ponding on top of
the relatively impermeable clay colluvium encountered directly below the topsoil at this
location.
SILT AND CLAY: Underlying the topsoil was a grey silt or clay with variable amounts of
clay, sand and gravel. In test pits TP17-01 and TP17-02 this material was generally a
poorly graded dense silt representative of overbank fluvial deposits. In TP17-03 this
material was more of a stiff medium plastic silty clay that was likely deposited as colluvium
as indicated by the lack of any discernible structure in the clay. In TP17-03, the clay and
silt colluvium had a natural water content of 31% and appeared to be saturated with water
ponding at the surface.
FLUVIAL SAND: A dense fine grained sand layer with some silt and trace gravel was
encountered below the colluvium in each of the three test pits. The sand was brown and
uniformly graded and was observed at depths of 0.8 m to 1.5 m below the existing ground
surface. The sand was generally damp to moist and had natural water contents that
ranged from 4% to 12% with the highest value being recorded in the sand underlying the
highly saturated clay colluvium in TP17-03. No groundwater or seepage was observed in
the fluvial sand deposits.
4.5 Groundwater Conditions
One groundwater level reading was taken in the standpipe installed in BH17-02 on 14 August
2017 and indicated a water level of 5.6 m below the ground surface. Groundwater level readings
were not possible during drilling because the boreholes were constantly filled with water during
sonic drilling. Ponded water was identified at the base of the embankment slope during the site
visits and test pitting. It appeared that the water was ponding on top of a layer of clayey colluvium
located just below the ground surface.
emphasized that the potential for larger scale failures through this entire section of road will still
remain unless a robust long term option is chosen.
Amec Foster Wheeler provided the Town of Smithers with three potential remediation options for
fixing the road, in addition to a Do Nothing approach. The Do Nothing approach was
considered in case the Town of Smithers decided that they wanted to further monitor the area to
assess whether or not the road shoulder continues to move. This approach would allow for a
single lane of traffic and would provide the Town of Smithers with more time until a decision is
made on a more permanent solution. While this approach would provide more time to make a
decision and would avoid having to implement an expensive fix, this option also contains the
greatest risk with respect to future movement and the potential for a larger, more sudden failure
to occur through the entire road section, effectively cutting of access for the entire road.
Three other general options were provided to the Town of Smithers in the draft geotechnical report
that would address the failed section of road embankment and provide a road surface wide
enough for two lanes of traffic. For each option it was recommended that the failed soil and
existing retaining structure timbers be completely removed prior to undertaking any other
construction work along the road embankment. Each of the three options provided would allow
for a single lane to remain open to local traffic for the duration of the remediation construction
work.
The three options considered to address the failed road embankment and retaining structure were
as follows:
Option 1: Replace the failed retaining structure with a short retaining wall constructed on
top of a reinforced soil base constructed within the upper portion of the existing
embankment fill (maximum retaining structure height of 2-3 m). Lock-block or gabion
mesh basket gravity retaining walls with or without Mechanically Stabilized Earth (MSE)
reinforcement behind the wall facing were considered to be suitable short wall alternatives.
This remediation option was proposed as a lower cost alternative; however, this option
would only be a temporary fix as it would not fully address the long term global stability of
the road embankment. Deeper failures could develop below the new retaining structure
after construction of a short MSE wall if there is still unsuitable uncontrolled fill left below
the wall. It is also possible that failure surfaces could develop through the underlying fill
during construction of such a short wall which could lead to significant cost over-runs and
delay during construction.
Option 2: Excavate the uncontrolled fill all the way down to suitable native undisturbed
subgrade soil and construct a tall MSE retaining wall with either lock-block, wire mesh, or
gabion basket facing. In order to remove the suspect old fill, the height of such a wall could
be as much as 10 m on its southern end. This option was provided as a long term solution
for overall global stability as it would remove the potential for deep seated failures below
the new retaining structure. With respect to Option 1, this option would involve
considerably more excavation and a much more expensive wall design given the
anticipated required depth of excavation to reach a suitable native subgrade.
Considerable soil reinforcement would also be required for a tall MSE wall (typically
extending back some 70% to 100% of the wall height), further increasing the costs
associated with this option. Other high wall options that involve less excavation such as
soldier pile and lagging or sheet pile walls were also considered; however given the
anticipated height of the retaining structure, tie-back anchors or excessive pile wall facing
stiffness would be required to provide internal stability.
Option 3: Replace all or a portion of the existing weak embankment fill soils with well
drained gravel fill down to a competent foundation level on the adjacent lower river terrace.
This option would effectively buttress the existing slope by adding weight at the toe of the
slope, while also removing weakened soils that failure surfaces could develop through.
There are various ways in which this option could be implemented based on the overall
dimensions of the existing slope and the amount of space available for construction. This
option could also be optimized using geogrid reinforced soil slopes or a benched slope
configuration to minimize the amount of material, space and costs associated with a slope
buttress.
Option 1 has the greatest amount of risk associated with it since there would still be a high
possibility for further slope instability issues to occur in any uncontrolled fill or colluvium that
remains in place below the new retaining structure. Potential failure surfaces below a short wall
are shown in Figure 5 of the draft geotechnical report. This option also comes with the risk of
cost over-runs and schedule delays occurring if the slope started to fail during or just after
construction. Given the amount of information available for the road and embankment slope, fully
addressing the long term global stability of the road embankment could only be achieved by
implementing either Option 2 or Option 3.
For Option 2, a considerable amount of excavation would be required in order to remove all
uncontrolled fill and colluvium down to a suitable native subgrade material. The costs associated
with building a taller MSE wall would be significantly greater than Option 1, given the extent of
excavation and construction required for a taller wall. The excavation of such a large amount of
the lower embankment slope could also lead to slope instability issues in the remaining portion of
roadway fill (required to keep the road open during construction) and potentially the cut slope
above the road. Construction would need to be staged in such a manner as to minimize the
amount of excavation that is left open at any point in time, resulting in more difficult access,
construction efficiency and schedule. An alternative to deep excavation would be to construct a
pile supported retaining wall (with or without tie-backs); however, this option would likely be more
expensive than a tall MSE wall given the costs associated with the extra piling materials and/or
specialty contractors required for such systems.
Option 3 would address the global stability of the road embankment without the costs associated
with constructing a large retaining structure for this entire section of the road. This option would
still require the removal of failed soil and embankment material down to a suitable subgrade,
though it would not require the same amount of excavation as for Option 2. The uncontrolled fill
and colluvium along the lower portion of the embankment slope would only need to be excavated
to a depth sufficient to provide adequate space for constructing a suitably thick fill buttress against
the existing slope. One concern related to the soil buttress option was crossing the perimeter trail
with the toe of the buttress; however, the Town of Smithers indicated that the perimeter trail could
be re-located as part of the slope remediation construction work (re-established adjacent to the
toe of the buttress slope). Amec Foster Wheeler indicated that there were several potential
variations to this option which could be considered to optimize the costs and amount of space
required to buttress the slope; however, in order to optimize the slope design, a detailed survey
of the existing slope would have to be completed.
Other design considerations such as the desired service life of this section of Rosenthal Road
and the overall stability of the entire slope above and below the road were also mentioned in the
draft report as factors that should to be taken into consideration when deciding how to address
the current road failure.
Following receipt of the draft report recommendations, the Town of Smithers indicated that they
would like to proceed with Option 3 to remediate the failed road embankment. The chosen
remediation option will consist of a 2.5H:1V buttress slope from the shoulder of Rosenthal Road
down to a suitable bearing layer on the lower river terrace. The buttress slope will be constructed
using locally sourced granular backfill material that is properly tied into the existing embankment
slope. Guidelines for the construction of the chosen remediation are provided in Sections 7 and
8 of this report, below.
that underlies the lower river terrace level. The toe of the new soil buttress is expected to be at
least 30 m or more from the western bank of the Bulkley River and is not expected to have any
negative impact on the current stability of the river bank itself. Continual erosion of the river bank
towards the soil buttress and perimeter trail is not addressed in this soil buttress design, but may
have to be considered and mitigated in the future.
The soil buttress should extend a minimum of 2 m north and south of the ends of the tension
cracks where the cracks intersect the outer edge of the road. The soil buttress is anticipated to
be approximately 80 m long at the top of the slope based on the extent of cracking observed
during the site visits. The maximum height of the soil buttress is expected to be approximately
12-15 m on the southern end of the road failure where the elevation difference between the road
and the perimeter trail is the greatest. The soil buttress should also tie into the existing slope
using 2.5H:1V backfilled side slopes on either end of the soil buttress. A sketch plan view of the
approximate extents of construction and dimensions for the soil buttress are illustrated in Figure
5, including the estimated locations of the buttress side slopes. A cross-section showing
approximate extents of the soil buttress excavation and final surface are shown in Figure 6.
The toe of the soil buttress should be constructed on top of a suitable undisturbed native subgrade
surface. Test pitting at the toe of the slope indicated that a suitable subgrade consisting of fluvial
sand was encountered approximately 0.8 m to 1.5 m below the existing ground surface. Sub-
excavation at the toe of the slope to remove topsoil and fine grained soils down to the sand
subgrade should be a minimum of 15 m wide and should extend all the way from the outer toe of
the soil buttress into the existing slope. An example of the required amount of subgrade
excavation into the existing slope at the base of the soil buttress is shown in Figure 6. The existing
embankment slope should be stripped of all vegetation, topsoil and any other unsuitable wet or
soft material until a suitable subgrade surface is identified. All failed road soils and remnants of
the failed retaining structure should be completely removed down to a suitable subgrade as well.
All subgrade surfaces should be inspected and approved by the geotechnical engineer.
Excavation to remove and replace the upper failed portion of the road surface and embankment
should extend a minimum of 0.5 m beyond the tension cracks (towards the centerline of the road)
to make sure that all failed soil is completely removed from below the road surface. First, the
roadway should be excavated and unloaded down to the base of the failed retaining structure. All
failed soil and retaining wall remnants should be completely removed to stop any movement that
may still be occurring. The roadway fills behind the failed retaining structure can be excavated
with a maximum overall slope of 1H:1V under the supervision of a representative of the
geotechnical engineer who should constantly monitor the slope for signs of instability. Shallower
excavation slopes than 1H:1V could be required if there are any signs of instability during
construction. Following unloading and removal of all of the failed retaining structure remnants and
roadway soils, construction of the buttress should begin at the toe of the slope. Construction of
the soil buttress should begin by excavating down to a suitable subgrade at the toe of the buttress.
Once a suitable subgrade is identified, excavation of unsuitable surficial material along the slope
and backfilling of the buttress can proceed up towards the road. Excavation of unsuitable material
from the existing slope can be completed in a series of benches starting from the base of the
slope and progressing to the top of the road surface. The excavated benches should extend a
sufficient distance into the existing slope to remove all vegetation, top soil, loose and wet surficial
soils. Note that width of the excavation into the existing slope will likely be the greatest above the
base of the failed retaining in order to make sure that all failed material is removed from the slope.
The excavated benches can be completed using a minimum bench width of 1.5 m and a maximum
bench height of 1.5 m as long as the overall angle of the excavated slope does not exceed 1H:1V.
In addition to being a minimum width of 1.5 m, the excavation benches should be of sufficient
width to allow the construction equipment to safely access the site. It is recommended that the
slope be excavated one bench at a time, with each bench being completely backfilled prior to
excavating the next bench. Excavating and backfilling the slope from the bottom up will provide
added stability at the toe of the slope during construction, as well as a wider more stable working
base for the construction equipment. This sequence of excavation and backfilling should be
adopted all the way from the toe of the buttress up to the final grade.
A layer of non-woven geotextile should be placed on top of all stripped subgrade surfaces once
the subgrade has been inspected and approved by the geotechnical engineer. The purpose of
the geotextile is to prevent the migration of fines from the subgrade into the granular backfill in
order to preserve its strength and drainage properties. Guidelines for the placement and
compaction of suitable granular backfill including the use of vibratory compaction equipment are
provided in Section 8. The use of vibratory equipment to compact the backfill material is not
expected to have an impact on the stability of the Bulkley River bank to the east of the
embankment slope given the distance between the toe of the soil buttress and the river.
Vibrations from compaction are also expected to have minimal impact on the stability of the overall
valley slope during construction, though the slope should still be monitored closely during
compaction activities to check for any signs of instability developing as a result of the compaction
vibrations. It is recommended that the Town of Smithers consider implementing a vibration
monitoring program both before and after construction to assess the impact of construction
vibrations on the slope. Such a program could be carried out by Amec Foster Wheeler using
specialized vibration monitoring equipment set-up at different locations along the slope to
measure vibrations induced during construction. As part of the vibration monitoring program an
initial set of readings should be taken prior to construction to develop a baseline for the vibration
monitoring readings. These pre-construction baseline readings should be taken along the road
and at the crest of the slope near the private properties that border the slope. Without the pre-
construction baseline readings the Town of Smithers will not have any way to assess whether or
not the compaction vibrations are having an impact on the slope or the nearby properties. If the
compaction vibrations appear to be having an adverse impact on the slope, alternative methods
of compaction such as static compaction will need to be considered.
In addition to constructing the soil buttress, sufficient space should be left open at the toe of the
buttress to re-establish the perimeter trail. The proposed location for the re-established perimeter
trail is also shown in brown on Figure 6. It is expected that a minimum width of 3 m to 4 m will be
required for the new perimeter trail. The perimeter trail can be constructed using the same backfill
material used to construct the buttress.
150 100
50 55 to 100
25 38 to 100
16 32 to 85
5 20 to 65
0.315 6 to 30
0.075 0 to 5
All materials used for structural fill should be free of ice, snow and frozen particles. Organic soils
and soils that cannot be properly moisture-conditioned are not suitable for use as structural fill.
Structural fill required to construct the buttress slope up to base of the road structure should be
placed in horizontal lifts not exceeding 300 mm in loose thickness, moisture conditioned and
uniformly compacted to not less than 95% of the maximum dry density as determined by ASTM
D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard
Effort. Lifts placed directly over geotextiles should not be less than 150 mm in uncompacted
thickness or as recommended by the manufacturer. This thickness is required to protect the
geotextile from damage during compaction.
Compaction of all lifts should be completed with a vibratory roller or other suitable vibratory
equipment. Compaction using vibratory equipment is not expected to have an adverse impact on
the stability of the slope during construction; however, if sensitive subgrade soils are encountered
along the existing embankment slope static compaction shall be used to compact the first lift or
until there are no visible signs of rutting or settlement during compaction. Structural fill placement
and compaction should be monitored by a qualified field representative or geotechnical engineer
on a full-time basis during construction. If issues arise during compaction, alternative methods of
compaction such as static compaction might need to be considered. Smaller equipment such as
vibratory plate compactors should be used for compaction of lifts placed directly on top of
geotextiles.
Compaction should be monitored by field density testing at regular frequencies. The
recommended minimum density test frequency should be two to three representative field density
tests per lift of fill material.
8.3 Excavating, Trenching and Backfilling
Temporary excavations greater than 1.2 m deep where worker entry is required should be
constructed in accordance with Part 20 of the Occupational Health and Safety Regulation, BC
Regulation 296/97 as currently amended for the Workers Compensation Board (WCB) of British
Columbia. For temporary excavations more than three meters deep the excavation sidewalls
should be no steeper than 1H:1V. The excavation can be benched using a minimum bench width
of 1.5 m as long as the overall slope of the excavation does not exceed 1H:1V and the individual
benches do not exceed a vertical height of 1.5 m. The ultimate width of the benches will depend
on the size of the construction equipment, as the benches need to be sufficiently wide for the
equipment to safely access the site. The excavation should be monitored on a full-time basis to
watch for any signs of instability. If seepage or sloughing conditions are observed in the
excavation side walls, flatter slopes than those originally allowed will be required. Excavation
sidewalls must be stable or suitably supported by bracing or shoring prior to worker entry as
required by the regulation. The construction contractor is ultimately responsible for making all
excavations in a safe and legal manner.
Equipment shall, in general, not be allowed within a distance equal to the depth of the excavation,
as measured from the crest of the excavation. Where construction equipment is required to
operate at closer distances from the upper edge of the excavation, the influence of this
construction equipment on excavation stability shall be reviewed by the geotechnical engineer
with appropriate measures being taken to ensure excavation stability. Vibratory compaction
equipment should stay a minimum of 0.5 m away from excavation side slopes. If sloughing occurs
along the backfilled slopes during compaction, smaller equipment or static compaction techniques
could be required to prevent further sloughing of the slope.
8.4 Groundwater and Surface Water Control
In general, site drainage works should be implemented during the early stages of the site grading
earthworks. To promote surface runoff and to minimize potential saturation and degradation of
the subgrade, the subgrade surface should be graded with a minimum slope of two percent,
directed towards drainage ditches or low areas leading away from the excavation. Drainage
ditches required to direct surface water away from the base of the excavations should be designed
in accordance with the British Columbia Water Sustainability Act. Water should not be allowed to
enter excavations or pond on subgrades. Any soils softened by standing water in the bottom of
excavations and trenches or by water ponded on subgrades should be removed and replaced as
specified for the overlying materials or as approved by the geotechnical engineer.
Perched groundwater could be encountered in the excavation depending on the subsurface
conditions encountered during excavation. The contractor should be prepared to initiate
dewatering in the event that perched groundwater is encountered in the excavation. A
groundwater management plan should be in place prior to the start of construction. The
groundwater management plan is best prepared by the construction contractor so that the plan is
specific to the contractors planned construction methods and provides drainage away from the
excavated areas and potential retained soil zones. Any discharge from dewatering systems
should follow the guidelines provided in the British Columbia Water Sustainability Act.
8.5 Pavements and Road Drainage
Once the slope remediation construction work has been completed the roadway should be re-
established following the recommendations provided in the Town of Smithers By-law Number
1800. Recommended structural sections for pavement are provided in Section 2 of the by-law.
The base and sub-base courses should be compacted to minimum 100% SPMDD and have less
than five percent passing the 0.075 mm sieve. Suitable gradations of the base and sub-base
courses are also provided in the Section 2 of the by-law. Sub-base is not required in those areas
where structural fill has been placed if the structural fill materials meets the gradation requirement
for sub-base and the thickness of the structural fill is equal to or greater than the minimum
thickness provided in Section 2 of the By-law. The Town of Smithers By-law also provides
guidelines for asphalt pavements if this section of road is going to be paved upon completed. If
the Town chooses to retain this section as a gravel surfaced road, high fines surfacing aggregate
(HFSA) can be used in place of asphalt. Gradations for HFSA material can be found either in
Section 200 of the 2016 BC Standard Specification for Highway Construction or in the provincial
Master Municipal Construction Documents (MMCD). If the Town of Smithers later decides to
upgrade from a gravel surfaced road to an asphalt surfaced road in this area, all high fines
surfacing aggregate placed previously should be removed and replaced with an appropriate base
course layer prior to placing asphalt.
The finished road should be graded in such a manner as to provide positive drainage into the
drainage ditch on the upslope (west) side of the road. This will help prevent runoff from
oversaturating the embankment slope material. The drainage ditch along the upslope side of the
road should be regularly maintained to provide a path for water flow during heavy rainfall events,
but also protected from erosion which could destabilize the slope above.
Prince George
Kamloops
0m 500 1000 1500 2000
465
485
475
5
51
510
505
500
Bulkey River
49
5 490
480
4 85
5
48
0
48
0
49
Smithers
NOTES: Site image provided by the town of Smithers, and topographic contours
acquired from the Government of Canada CDEM data base March 30, 2016. 1 : 10000
CLIENT: DWN BY: PROJECT: DATE:
N.Whelan
CHK'D BY: SITE PLAN OCTOBER 2017
PROJECT NO:
C.Banks
amec DATUM:
TITLE: KS00423
foster Amec Foster Wheeler NAD 83 REV. NO:
PROJECTION:
wheeler Environment & Infrastructure GEOTECHNICAL SITE ASSESSMENT
Box 3966, #3-3167 Tatlow Road 0
UTM Zone 9
Environment & Smithers, BC, CANADA V0J 2N0 SCALE: ROSENTHAL ROAD FIGURE NO:
RECOVERY (%)
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL
SPT (N)
SPT "N" (BLOWS/300 mm) ADDITIONAL
20
PLASTIC
40
M.C.
60 80
LIQUID
DESCRIPTION INFORMATION
20 40 60 80
0 SAND (fine to coarse grained), gravelly, (fine to coarse
grained), trace to some silt, well graded, brown, loose, damp
[Gravel Road Fill] 0.3m
SAND (fine to coarse grained), some gravel, some silt to G01
silty, trace to some clay, dark brown, poorly graded, loose to
compact, moist, organics [FILL]
0.8m
SILT, some sand to sandy (fine to coarse grained), trace to
some clay, trace gravel (fine to coarse grained), medium
1 plastic, soft to firm, dark brown, moist, wood and organics 1
SPT01 79 9
[FILL] G02
SPT02 25 7
2 2
SPT03 58 7
PP = 50 to 100kPa
BOREHOLE LOG ROSENTHAL ROAD UPDATED.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 20/9/17
G04
PP = 75 to 195kPa
4 4
SPT04 79 10
PP = 50 to 145kPa
5 5
5.2m
SILT, clayey to some clay, trace to some gravel (fine to PP = 195 to 270kPa
coarse grained), trace to some sand, medium plastic, stiff, Atterberg (GRAB
G05
brown, moist [TRANSITIONAL FILL/COLLUVIUM] G05):
Plastic Limit:23%
Liquid Limit:40%
Sieve (GRAB G05):
Gravel:19% Sand:12%
6 Fines:69% 6
... some clay to clayey, reddish brown and brown
SPT05 92 15
PP = 195 to 245kPa
RECOVERY (%)
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL
SPT (N)
SPT "N" (BLOWS/300 mm) ADDITIONAL
20
PLASTIC
40
M.C.
60 80
LIQUID
DESCRIPTION INFORMATION
20 40 60 80
7 SILT, clayey to some clay, trace to some gravel (fine to
coarse grained), trace to some sand, medium plastic, stiff,
brown, moist [TRANSITIONAL FILL/COLLUVIUM]
(continued)
G07
PP = 295 to 390kPa
8.7m
SILT and SAND, trace clay, trace gravel (fine to coarse
grained), poorly graded, compact, light reddish brown, wet,
interbedded silt and sand layers [GLACIOFLUVIAL or G08
9 PP = 25 to 100kPa 9
FLUVIAL]
... 25 to 60mm interbedding of poorly graded silty sand and
low plastic, firm to stiff clay with trace laminations
SPT07 71 11
10 10
10.2m
SILT, and clay to clayey, trace to some gravel (fine to
coarse grained), trace to some sand (fine to coarse grained),
medium plastic, firm to stiff, grey, moist, disturbed laminations G09
[TILL]
BOREHOLE LOG ROSENTHAL ROAD UPDATED.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 20/9/17
11 SPT08 100 10 11
... trace clay to clayey, some sand (fine grained), very stiff,
damp
G11
PP = 195 to 390kPa
13 13
RECOVERY (%)
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL
SPT (N)
SPT "N" (BLOWS/300 mm) ADDITIONAL
20
PLASTIC
40
M.C.
60 80
LIQUID
DESCRIPTION INFORMATION
20 40 60 80
14 SILT, and clay to clayey, trace to some gravel (fine to SPT10 54 28
PP = 270 to 295kPa
coarse grained), trace to some sand (fine to coarse grained),
medium plastic, firm to stiff, grey, moist, disturbed laminations
[TILL] (continued)
G12
PP = 100 to 220kPa
15 15
SPT11 63 21
PP = 100 to 245kPa
15.8m
End of Borehole
16 Completion Depth of 15.8 m. 16
No bedrock encountered.
Hole backfilled with drill cuttings and bentonite chips.
17 17
BOREHOLE LOG ROSENTHAL ROAD UPDATED.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 20/9/17
18 18
19 19
20 20
21
LOGGED BY: DG COMPLETION DEPTH: 15.8 m
ENTERED BY: DG COMPLETION DATE: 18/7/17
REVIEWED BY: CB Page 3 of 3
CLIENT: Town of Smithers PROJECT: Rosenthal Road Geotechnical Assessment BOREHOLE NO: BH17-02
DRILLER: Blue Max Drilling Inc. Smithers, BC PROJECT NO: KS00423
DRILL TYPE/METHOD: Sonic NORTHING: EASTING: ELEVATION:
SAMPLE TYPE TUBE NO RECOVERY SPLIT SPOON GRAB MUD RETURN CORE RETURN
BACKFILL TYPE BENTONITE PEA GRAVEL SLOUGH GROUT DRILL CUTTINGS SAND
RECOVERY (%)
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL
SPT (N)
SLOTTED
SPT "N" (BLOWS/300 mm) ADDITIONAL PIEZOMETER
20
PLASTIC
40
M.C.
60 80
LIQUID
DESCRIPTION INFORMATION
20 40 60 80
0 SAND fine to coarse grained, and gravel fine to coarse 0m Very little granular
grained, trace silt, well graded, compact [GRAVEL ROAD] material overlying silty
G01
SILT, sandy (fine to coarse grained), trace gravel (fine to fill material at this
coarse grained), trace clay, low plastic, stiff to very stiff, location
brown and reddish brown, wood and organics [ROAD FILL] PP = 220 to 390kPa
G02
... dark brown to black, stiff
SPT02 33 11
2 2
2.3m
SILT, clayey to some clay, some sand (fine to coarse
grained), trace to some gravel (fine to coarse grained),
medium plastic, very stiff, light brown to greyish brown, moist
[TRANSITIONAL FILL/COLLUVIUM] G03
3 3
... trace to some clay, very stiff, light brown, damp to moist,
trace organics
SPT03 0 22
BOREHOLE LOG ROSENTHAL ROAD UPDATED.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 20/9/17
G04 PP = >440kPa
4 4
SPT04 50 26
5 5
PP = 245 to 345kPa
G05
6 6.1m 6
CLAY, and silt to silty, trace to some sand (fine to coarse
grained), trace to some gravel
(fine to coarse grained), trace cobbles, low to medium plastic, SPT05 83 39
very stiff to hard, light grey to grey, moist [TILL]
7
LOGGED BY: DG COMPLETION DEPTH: 9.8 m
ENTERED BY: DG COMPLETION DATE: 19/7/17
REVIEWED BY: CB Page 1 of 2
CLIENT: Town of Smithers PROJECT: Rosenthal Road Geotechnical Assessment BOREHOLE NO: BH17-02
DRILLER: Blue Max Drilling Inc. Smithers, BC PROJECT NO: KS00423
DRILL TYPE/METHOD: Sonic NORTHING: EASTING: ELEVATION:
SAMPLE TYPE TUBE NO RECOVERY SPLIT SPOON GRAB MUD RETURN CORE RETURN
BACKFILL TYPE BENTONITE PEA GRAVEL SLOUGH GROUT DRILL CUTTINGS SAND
RECOVERY (%)
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL
SPT (N)
SLOTTED
SPT "N" (BLOWS/300 mm) ADDITIONAL PIEZOMETER
20
PLASTIC
40
M.C.
60 80
LIQUID
DESCRIPTION INFORMATION
20 40 60 80
7 CLAY, and silt to silty, trace to some sand (fine to coarse
grained), trace to some gravel
(fine to coarse grained), trace cobbles, low to medium plastic,
very stiff to hard, light grey to grey, moist [TILL] (continued)
8 8
G06
9 9
SPT06 83 22
9.8m
End of Borehole
Completion Depth of 9.8 m.
10 Installation of a 25 mm Standpipe Piezometer to 8.8 m depth. 10
Screened between 5.8 m to 8.8 m, sandpacked from 4.9 m to
8.8 m and backfilled with bentonite chips from 0 m to 4.9 m.
No bedrock encountered.
BOREHOLE LOG ROSENTHAL ROAD UPDATED.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 20/9/17
11 11
12 12
13 13
14
LOGGED BY: DG COMPLETION DEPTH: 9.8 m
ENTERED BY: DG COMPLETION DATE: 19/7/17
REVIEWED BY: CB Page 2 of 2
CLIENT: Town of Smithers PROJECT: Rosenthal Road Geotechnical Assessment TEST PIT NO: TP17-01
CONTRACTOR: Town of Smithers Smithers, BC PROJECT NO: KS00423
EXCAVATION METHOD: Backhoe NORTHING: 6072897 EASTING: 618169 ELEVATION:
SAMPLE TYPE BULK GRAB
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL ADDITIONAL
20 40 60 80
0 TOPSOIL, sandy, silty, trace gravel, trace clay, loose, dark
brown, moist, rootlets and organics
0.3m
SILT, some sand, some clay, trace gravel, compact to
dense, poorly graded, grey to brown, damp to moist, some
clumps of clay, no discernible structure [FLUVIAL]
0.9m
SAND (fine-grained), trace to some silt, brown, damp to
1 moist, relatively clean, massive [FLUVIAL] 1
G01
1.8m
End of Test Pit
Completion Depth of 2 m.
2 No groundwater encountered upon completion. 2
Backfilled with excavated material.
TEST PIT LOG ROSENTHAL ROAD TEST PITS.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 13/10/17
3 3
4 4
5
LOGGED BY: CB COMPLETION DEPTH: 1.8 m
ENTERED BY: CB COMPLETION DATE: 29/9/17
REVIEWED BY: NP Page 1 of 1
CLIENT: Town of Smithers PROJECT: Rosenthal Road Geotechnical Assessment TEST PIT NO: TP17-02
CONTRACTOR: Town of Smithers Smithers, BC PROJECT NO: KS00423
EXCAVATION METHOD: Backhoe NORTHING: 6072840 EASTING: 618182 ELEVATION:
SAMPLE TYPE BULK GRAB
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL ADDITIONAL
20 40 60 80
0 TOPSOIL, sandy, silty, trace gravel, trace clay, loose, dark
brown, moist, rootlets and organics
0.3m
SILT, some sand, some clay, trace gravel, compact to
dense, poorly graded, grey to brown, damp to moist, some
clumps of clay, no discernible structure [FLUVIAL]
0.8m
SAND (fine-grained), trace to some silt, brown, damp to
moist, relatively clean, massive [FLUVIAL]
1 1
G01
2 2
2.1m
End of Test Pit
Completion Depth of 2.3 m.
No groundwater encountered upon completion.
Backfilled with excavated material.
TEST PIT LOG ROSENTHAL ROAD TEST PITS.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 13/10/17
3 3
4 4
5
LOGGED BY: CB COMPLETION DEPTH: 2.1 m
ENTERED BY: CB COMPLETION DATE: 29/9/17
REVIEWED BY: NP Page 1 of 1
CLIENT: Town of Smithers PROJECT: Rosenthal Road Geotechnical Assessment TEST PIT NO: TP17-03
CONTRACTOR: Town of Smithers Smithers, BC PROJECT NO: KS00423
EXCAVATION METHOD: Backhoe NORTHING: 6072849 EASTING: 618178 ELEVATION:
SAMPLE TYPE BULK GRAB
SAMPLE TYPE
SOIL SYMBOL
SAMPLE NO
DEPTH (m)
DEPTH (m)
SOIL ADDITIONAL
20 40 60 80
0 TOPSOIL, fibrous, some silt, loose, black, wet, rootlets and
organics
0.5m
CLAY, silty, trace to some gravel, trace sand, medium
plastic, firm to stiff, grey with orange mottling, moist to wet,
variable composition clumps of clay [COLLUVIUM] G01
1 1
1.5m
SAND (fine-grained), trace to some silt, trace gravel (less
than 20 mm diameter), brown, damp to moist, relatively clean,
massive [FLUVIAL]
G02
2 2
2.4m
End of Test Pit
Completion Depth of 2.5 m.
TEST PIT LOG ROSENTHAL ROAD TEST PITS.GPJ AMEC-PG-MULTIWELL-DATATEMPLATE.GDT 13/10/17
3 3
4 4
5
LOGGED BY: CB COMPLETION DEPTH: 2.4 m
ENTERED BY: CB COMPLETION DATE: 29/9/17
REVIEWED BY: NP Page 1 of 1
Appendix C
Hole No.
Sample No.
Tare No. 19 20 21 22 23 24
Wt. of Tare
Wt. Sample Wet
Wt. Sample Dry
Wt. Water 0.00 0.00 0.00 0.00 0.00 0.00
Moisture Cont. % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Hole No.
Sample No.
Tare No. 25 26 27 28 29 30
Wt. of Tare
Wt. Sample Wet
Wt. Sample Dry
Wt. Water 0.00 0.00 0.00 0.00 0.00 0.00
Moisture Cont. % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!