Вы находитесь на странице: 1из 21

BILL OF QUANTITIES

PROPOSED FACTORY
BUILDING FOR IKON EXIM PVT LTD AT
60B,MAGULPOKUNA
ROAD,WELISARA,RAGAMA
ACTORY
T LTD AT

AMA
BILL OF QUANTITIES

Item DESCRIPTION OF WORK UNIT QTY

1 PRELIMINARIES

Construct, maintain, and removal on completion of the work Item 1.00


, a temporary building for Construction workers accommodation
Allow lump sum

Construct, maintain, temporary buildings to be used as workshops and stores Item 1.00
for perishable materials - Allow lump sum
.
Construct, maintain a Temporary Toilet Block for Construction Workers Item 1.00
- Allow lump sum

Construct & Maintain temporary building for Site Office with Sanitary Item 1.00
Facilities - Allow lump sum

Electricity & Water usage for the work during the period of Construction
Prov
Sum
(To be paid by the Owner)

Demolition of Existing Piles upto Pile Cut off Level item allow

Total

2 EXCAVATOR
NOTE:
Rates for excavation and earth work shall be included
a. Leveling bottom of trenches and pits and keeping all sides plumb.
b Disposal of surplus soil
c. All works under this section are measured net and no working space is allowed

Excavation

Excavate foundation trench/pit in any material met with except rock requiring Cube 16.41
blasting,
Earth Filling
Approved hard core earth filling 9" thk. layers watered well rammed Cube 129.36
and consolidated inside of the foundation using available soil at site

TRADE TOTAL CARRIED TO SUMMARY

3 MASONRY WORK and BRICKWORK


Random Rubble Masonry work at foundations as per the detail Cube 20.51

8" thick Blockwork in cement & sand 1:5 mix in Ground floor. Sqr 44.00
(note -6" blocks cannot construct up to 15' height without slendering)

6" thick Blockwork in cement & sand 1:5 mix in First floor. Sqr 23.57

6" thick Blockwork in ct.& sand 1:5 mix in roof floor including the half wall Sqr 12.48
TRADE TOTAL CARRIED TO SUMMARY

4 CONCRETE WORK
FORMWORK

15mm thk. Plywood formwork in the following including dismantling

71
Item DESCRIPTION OF WORK UNIT QTY

Ground Beams Sqr 16.32

Pile Caps as per the detail drawing Sqr 5.03

Side of Ground supported Slab Sqr 1.64

Water Sump base Sqr 0.75

Water Sump walls and the cover slab Sqr 3.75

5" thick 1st Floor Slab Sqr 32.50

5" thick 2 nd Floor Slab Sqr 37.20

5" thick slab above 2 nd Floor level Sqr 3.11

REINFORCEMENT

Supplying ,Fabricating and fixing of steel reinforcement of various


diameter as per the structural detail drawings

Ground Beams Tons 3.06

Pile Caps as per the detail drawing Tons 0.91

Ground supported Slab Tons 4.74

Water Sump base Tons 0.24


Water Sump walls and the cover slab Tons 0.81

RCC Stair Case Tons 0.20

5" thick 1st Floor Slab Tons 3.83

5" thick 2 nd Floor Slab Tons 4.39

5" thick slab above 2 nd Floor level Tons 0.37

CONCRETE WORK
Gauge 1000 polythene laid below basement floor slab.Rate shall Sqr 37.20
include 6" horizontal laps and 3" vertical ends.

Mass Concrete
50 mm thick lean concrete by using Grade 15 concrete 1:3:6(11/2") mix Sqr 10.26

Supplying and laying concrete in grade 25 (3/4") as per the detail drawings

Ground Beams Cu 9.82

Pile Caps as per the detail drawing Cu 2.93

6" thick Ground supported Slab Cu 18.60

Water Sump base Cu 0.75

Water Sump walls and the cover slab Cu 2.50

RCC Stair Case Cu 0.70

5" thick 1st Floor Slab Cu 13.54

72
Item DESCRIPTION OF WORK UNIT QTY
5" thick 2 nd Floor Slab Cu 15.50

5" thick slab above 2 nd Floor level Cu 1.30

TRADE TOTAL CARRIED TO SUMMARY

5 Structural Steel Work


(Note That -All Structural Steel & Steel Plates to be Supplied by the Owners)
Fabricate & Fixing of Structural Steel members as per the detail drawings

Ground Floor steel Columns & 1 st Floor Steel Beams Tons 22.80

1 st Floor Steel Columns and Roof Slab Steel beams Tons 17.81

Above Roof level Structural Steel Tons 1.57


TRADE TOTAL CARRIED TO SUMMARY

6 DOORS & WINDOWS

D2 type Timber door -size 3'-0"x7'-0" (3Nos) Sq.ft 63.00


Rate to be inclusive of door frame and fixed complete

D3 type Marine PVC Framed PVC Door Sq.ft 154.00


Rate to be inclusive of door frame and fixed complete

SW type Timber Glazed Window 5'-0"x 8'-0" Sq.ft 120.00

FL type Timber Glazed Fanlight . Sq.ft 72.00

Aluminium Roller Door


Approved quality natural colour anodized aluminium framed roller door Nos 2.00
size 14' 0"x 10' 0" high overall with 1"x2" frame, colour bond
zinc al. panel, U channels, aluminium framed colour bond box, etc.,
fixed complete as shown in drawings .

TRADE TOTAL CARRIED TO SUMMARY

7 PLUMBING WORK & SANITARY FITTINGS

Sanitary fixtures and Fittings

Supply and fix close couple water closet including cistern accessories nr. 6.00
such as WC connector, flush pipe, seat cover approved angle valves
and flexible connector installed. Complete to working order.
(at the Toilets)

Supply and fix Wash Basins nr. 2

M - WATER SUPPLY, SEWERAGE AND DRAINAGE

WATER SUPPLY
Internal water supply

40 mm dia uPVC pipe Lft 68.00

32 mm dia uPVC pipe Lft 160.00

20mm dia uPVC pipe Lft 310.00


Stop valves

73
Item DESCRIPTION OF WORK UNIT QTY
Supply and installation of 32mm Pegler gate valve Nos 4.00

Internal Drainage

110mm dia uPVC pipes Lft 128.00

-Ditto- to pipe connecting to water closet Lft 80.00

90mm dia uPVC pipes Lft 140.00

Waste Water & Storm Water Drainage

Waste water disposal system


Main disposal line (vertical stacks)
50mm (11/2") dia uPVC pipes Lft 90.00

63mm (2") dia uPVC pipes Lft 90.00

Trapped floor gully


150x150mm uPVC trap moulded floor gully Nr 6.00
Pipes
Type 600 uPVC pipes for external waste & sewerage
110mm dia in soil pipe lines Lft 185.00

Manholes & water seal catch pit


Construct manhole average size 600x600x600mm
internally Nos 5.00

Construct manhole average size 750x750x750mm


internally No 2.00

Construct manhole average size 900x900x900mm


internally No 1.00

Construct water sealed catch pit average size


750x750x750mm internally No 4.00

TRADE TOTAL CARRIED TO SUMMARY

8 FLOOR WALL AND CEILING FINISHES

Floor Tiles (Toilets Only)

24" x 12" Non skid ceramic colour tiles laid on and including 1/2" thick cement Sqr 2.50
screed in cement sand 1:3 mix in Toilet floor.

Wall Tiles(Toilets Only)


12" x 12" glazed ceramic wall tiles up to 7' 0" level to toilets Sqr 10.20
laid on and including 1/2" thick cement and sand screed in 1:3 mix
in ground floor toilet.

WALL FINISHES

EXTERNAL /INTERNALWALLS

1/2" thick cement and sand plaster semi rough finished(for walls) Sqr 160.08

TRADE TOTAL CARRIED TO SUMMARY

74
Item DESCRIPTION OF WORK UNIT QTY

9 PAINTING
EXTERNAL /INTERNAL WALL PAINTING
Primer and paint shall be of one brand and skim coat shall also be
compatiblewith the selected brand of paint as approved by the
manufacturer.

Prepare surface to smooth finish with approved skim coat putty or equivalent, and apply 1

coat of primer and 2 coats of approved emulsion paint


For the Ground ,1 st Floor & above roof slab walls Sqr 160.08

Painting Structural Steel Columns & Beams as per the instructions Sqr 49.00

TRADE TOTAL CARRIED TO SUMMARY

10 ELECTRICAL INSTALLATION
Provide and install electrical installation strictly in accordance with
the specifications and as indicated on drawings for the Building and all
builder's work.
.MCBs & other accessories to be approved Quality.
All switches and socket outlets shall be plated type make"Clipsal", " Orange ", "Krypton" or
any other approved equivalent complying to SLS1000:1993 for switches & SLS 1998 : 1991
for soket outlets
Rate to include switch boxes, Rowl plugs, round/square pin plug base, Chromium plated
M.S. chains, brass hooks, ceiling roses, holders and any other item necessary.

The whole installation shall be carried out according to CEB/IEE wiring regulations.

Main Switch board

Free standing cubicle multitier type Fully Automated low voltage Main switchboard( MDB's)
fitted with the indicator lamps, bus bars & accessories interconnections wiring etc.,and with
required nos of MCCB ' s & MCB 's including Neutral link Busbars & necessary back of
board wiring for general lighting,Power and provisions for AC system

(Fixing Only - Main Switch Board to be Supplied by the Owner) Nos 1.00

Supply and install suitable power cables enclosed in PVC conduit Lft 120.00
pipes/cable trays from the main DB to sub distribution boards

Supply and install suitable PVC/PVC/CU cable earth wire, enclosed Lft 145.00
in PVC conduit pipes/cable trays from the main DB to sub distribution
boards

Point wiring

Wall bracket lamp point No.s 40.00

Garden Lamp Point Nos 6.00

Ceiling lamp / Pendent lamp point No.s 70.00

13 Amp socket Outlet No.s 14.00

15A socket outlet No.s 6.00

Telephone Outlet No.s 2.00

30 amp 3 Phase wiring system for Air Conditioner points No.s 3.00

75
Item DESCRIPTION OF WORK UNIT QTY

Electrical Fittings

Supply and install 13 AMP switch socket outlet Nr 14.00

Supply and install 15 AMP switch socket outlet Nr 6.00

Supply & install approved type wall brackt lamp complete fittings with necessary
Nr 40.00
accessories

Nr 6.00
Supply & install approved type Garden light complete fittings with necessary accessories

Supply & install approved type Ceiling light(LED) complete fittings with necessary
Nr 70.00
accessories

Earthing system
Provide a complete earthing system including main earth electrode pits, Item 1.00
tinned copper electrodes ,earth continuity conductors etc as specified

TRADE TOTAL CARRIED TO SUMMARY

Miscellaneous Work items

Termite treatment for the building as per the instructions and as Sq. ft 3,720
per the specifications

Construction of Entrance gate with steel frame and Zn/Al sheet cladding as per the detail
Nos 1.00
drawings

Supply and install centrifugal electric water pump fixing close Item 1.00
to the sump to the approval with Peglar or approved quality
Gate valves, Non - Return valves, including float switch, control
panel with the tank and suction. All complete to woking order.

Supply & Install Plastishel Water Tanks (4Nos of 1000 Litre Capacity) Item

Construction of a Septic Tank as per the given detail Item


TRADE TOTAL CARRIED TO SUMMARY

76
RATE AMOUNT (Rs:
Cts:)

175,000.00 175,000.00

160,000.00 160,000.00

90,000.00 90,000.00

125,000.00 125,000.00

allow 285,000.00

835,000.00

2,100.00 34,461.00

2,900.00 375,144.00

409,605.00

31,200.00 639,990.00

33,376.00 1,468,377.12

29,300.00 690,454.50

29,900.00 373,152.00
3,171,973.62

77
RATE AMOUNT (Rs:
Cts:)

13,900.00 226,848.00

13,900.00 69,955.92

13,900.00 22,768.20

13,900.00 10,425.00

13,900.00 52,125.00

13,900.00 451,750.00

13,900.00 517,080.00

13,900.00 43,290.16

215,000.00 656,979.97

215,000.00 196,210.92

215,000.00 1,018,545.30

215,000.00 52,478.81
215,000.00 174,929.38

215,000.00 42,591.50

215,000.00 823,942.71

215,000.00 943,097.50

215,000.00 78,844.98

560.00 20,832.00

12,100.00 124,131.48

54,100.00 531,045.60

54,100.00 158,599.88

54,100.00 1,006,260.00

54,100.00 40,575.00

54,100.00 135,250.00

54,100.00 37,870.00

54,500.00 738,020.83

78
RATE AMOUNT (Rs:
Cts:)
54,900.00 850,950.00

54,900.00 71,141.25

9,096,539.40

65,000.00 1,481,829.35

65,000.00 1,157,768.71

65,000.00 102,013.54
2,741,611.60

1,600.00 100,800.00

600.00 92,400.00

1,900.00 228,000.00

1,850.00 133,200.00

215,000.00 430,000.00

984,400.00

25,000.00 150,000.00

19,500.00 39,000.00

78.33 5,326.67

56.67 9,066.67

21.67 6,716.67

79
RATE AMOUNT (Rs:
Cts:)
1,750.00 7,000.00

450.00 57,600.00

450.00 36,000.00

308.33 43,166.67

115.00 10,350.00

185.00 16,650.00

3,500.00 21,000.00

800.00 148,000.00

10,000.00 50,000.00

12,000.00 24,000.00

15,000.00 15,000.00

12,000.00 48,000.00

686,876.67

58,300.00 145,750.00

59,000.00 601,800.00

5,900.00 944,472.00

1,692,022.00

80
RATE AMOUNT (Rs:
Cts:)

5,050.00 808,404.00

9,100.00 445,900.00

1,254,304.00

35,000.00 35,000.00

1,400.00 168,000.00

900.00 130,500.00

3,100.00 124,000.00

3,400.00 20,400.00

3,200.00 224,000.00

3,700.00 51,800.00

3,900.00 23,400.00

2,800.00 5,600.00

4,800.00 14,400.00

81
RATE AMOUNT (Rs:
Cts:)

625.00 8,750.00

775.00 4,650.00

3,300.00 132,000.00

3,700.00 22,200.00

3,300.00 231,000.00

135,000.00 135,000.00

1,330,700.00

21.50 79,980.00

275,000.00 275,000.00

125,000.00 125,000.00

96,000.00

290,000.00
865,980.00

82
ITEM DESCRIPTION OF WORK

GRAND SUMMARY

1 PRELIMINARIES

2 EXCAVATOR

3 MASONRY WORK and BRICKWORK

4 CONCRETE WORK

5 Structural Steel Work

6 DOORS & WINDOWS

7 PLUMBING WORK & SANITARY FITTINGS

8 FLOOR WALL AND CEILING FINISHES

9 PAINTING

10 ELECTRICAL INSTALLATION

11 Miscellaneous Work items


TOTAL AMOUNT

Prepared By

D.H.Jayawardena (C.Eng.,MIE(S.L.),CCE)
(Chartered Civil Engineer & Certified Cost Engineer)

180,Henamulla Road,Wattalpola,Panadura
Tel: 0779872188

71
AMOUNT
(Rs: Cts:)

835,000.00

409,605.00

3,171,973.62

9,096,539.40

2,741,611.60

984,400.00

686,876.67

1,692,022.00

1,254,304.00

1,330,700.00

865,980.00
23,069,012.29

72
1 st Floor
STEEL Beams
nos Kg/m L (m) Weight (Total) Kg
6 106 6.00 3816.00
3 26 3.00 234.00
1 137 6.00 822.00
2 106 4.00 848.00
1 76 4.00 304.00
8 106 7.62 6463.41
3 90 6.30 1701.00
3 26 6.00 468.00
3 66 5.70 1128.60
1 76 6.40 486.40
16271.41

2 nd Floor
STEEL Beams
nos Kg/m L (m) Weight (Total) Kg
3 76 6.00 1368.00
3 90 6.00 1620.00
3 66 6.00 1188.00
3 76 4.00 912.00
3 26 3.00 234.00
8 76 7.62 4634.15
3 56 6.30 1058.40
4 50 6.00 1200.00
1 26 5.70 148.20
1 76 6.30 478.80
1 50 6.30 315.00
13156.55

Roof Top

nos Kg/m L (m) Weight (Total) Kg


2 36 9.50 684.00
3 18 2.00 108.00
792.00

Columns
G. Floor- 1 st Floor
STEEL Columns
nos Kg/m L (m) Weight (Total) Kg
9 94 4.57 3866.22
6 72 4.57 1974.24
3 50 4.57 685.50
6525.96

1 st Floor -2 Floor
STEEL Columns
nos Kg/m L (m) Weight (Total) Kg
9 94 3.26 2757.96
6 72 3.26 1408.32
3 50 3.26 489.00
4655.28

above 2 Floor
nos Kg/m L (m) Weight (Total) Kg
6 50 2.59 777.44

Total Struct Steel 42178.64

Add 4% for MS Steel Plates etc 1265.36


43444.00 KG

=43.44 Tons

Total Area of Concrete Slab 7392.00 ft2


Total Concrete Volume 3080.00 ft3
87.16 m3
Total R/f to provide 9588.04 KG

7392 150
43.44 225000 9,774,000.00 1/3 as a Labour Cost 2,932,200.00

75000

1,108,800.00

Вам также может понравиться