Cierres Pisos Puertas Facilidades Plafon

Nivel Nombre
1 Cara 2 caras liberado Colocado Lista Colocada CL Ennova Isemsa Data Liberado Estructura
N2 Lab Medicina Anatomia P P P P P P P
N2 Sala Anatomia P P P P P P P
N2 Lab Bioquimica P P P P P P P
N2 Lab Microbiologia e Inm. P P P P P P P
N2 Lab Fisiologia P P P P P P P
N2 Aula 1 P P P P P P
N2 Hall P P P P P P
N2 Cuarto Servicios Oeste P P P P P P
N2 Cuarto Servicios Este P P P P P P P
N2 Bao Caballeros Oeste P P OK P P P P
N2 Bao Caballeros Este P P OK P P P P
N2 Baos Damas Oeste P P OK P P P P
N2 Baos Damas Este P P OK P P P P
N2 Cuarto Electrico Oeste P P P P P P
N2 Cuarto Electrico Este P P P P P P
N2 Cuarto Redes P P P P P P P
N2 Cordinador Unidad Investigacion P P OK P P P P
N2 Cordinador Unidad Educacion P P OK P P P P
N2 Cordinador Unidad Servicio P P OK P P P P
N2 Cordinador Unidad Proceso P P OK P P P P
N2 Cordinador Unidad Medidas Basicas P P OK P P P P
N2 Cordinador Unidad Medidas Clinicas P P OK P P P P
N2 Cubiculos (3) P P OK P P P P
N2 Bedel P P OK P P P P
N2 Pasillo P P P P P P
N3 Sala de Microscopia 1 P P OK P P P P
N3 Sala de Microscopia 2 P P P OK P P P P
N3 Aula 1 P P P OK P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N3 Aula 2 P P P P P P P
N3 Lab. Biologia P P P P P P P
N3 Almacen P P P P P P P
N3 Kitchennette P P P P P P P
N3 Lab. Quimica P P P P P P P
N3 Cuarto Servicios Oeste P P P P P P P
N3 Cuarto Servicios Este P P P P P P P
N3 Bao Caballeros Oeste P P OK P P P P
N3 Bao Caballeros Este P P OK P P P P
N3 Baos Damas Oeste P P OK P P P P
N3 Baos Damas Este P P OK P P P P
N3 Cuarto Electrico Oeste P P P P P P
N3 Cuarto Electrico Este P P P P P P
N3 Cuarto Redes P P P P P P P
N3 Enfermeria P P P P P P
N3 Director Enfermeria P P P P P P P
N3 Nutricion P P P P P P P
N3 Director Nutricion P P P P P P P
N3 Sala de Reunion P P P P P P P
N3 Cubiculos (4) P P P P P P P
N3 Terapia Fisica P P P P P P P
N3 Director Terapia Fisica P P P P P P P
N3 Pasillo P P P P P
N4 Aula 1 P P P P P P P
N4 Sala de Reuniones P P P P P P P
N4 Lab. Informatica P P P P P P P
N4 Sala Simulacion P P P P P P
N4 Sala Observacion/Sala simulacion P P P P P P P
N4 Sala de Situacion Monitores P P P P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N4 Aula 2 P P P P P P P
N4 Aula 3 P P P P P P P
N4 Cuarto Servicios Oeste P P P P P P P
N4 Cuarto Servicios Este P P P P P P P
N4 Bao Caballeros Oeste P P OK P P P P
N4 Bao Caballeros Este P P P P P P P
N4 Baos Damas Oeste P P OK P P P P
N4 Baos Damas Este P P P P P P P
N4 Cuarto Electrico Oeste P P P P P P
N4 Cuarto Electrico Este P P P P P P
N4 Cuarto Redes P P P P P P P
N4 Medicina P P P P P P P
N4 Premedica P P P P P P P
N4 Estomatologia P P P P P P P
N4 Director Estomatologia P P P P P P P
N4 Cubiculos (7) P P P P P P P
N4 Monitor P P P P P P P
N4 Secretaria Decano P P P P P P P
N4 Director Medicina P P P P P P P
N4 Pasillo P P P P P
N5 Aula 1 P P P P P P P
N5 Aula 2 P P P P P P P
N5 Aula 3 P P P P P P P
N5 Aula 4 P P P P P P P
N5 Aula 5 P P P P P P P
N5 Aula 6 P P P P P P P
N5 Aula 7 P P P P P P P
N5 Cuarto Servicios Oeste P P P P P P P
N5 Cuarto Servicios Este P P P P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N5 Bao Caballeros Oeste P P OK P P P P
N5 Bao Caballeros Este P P OK P P P P
N5 Baos Damas Oeste P P OK P P P P
N5 Baos Damas Este P P P OK P P P P
N5 Cuarto Electrico Oeste P P P P P P
N5 Cuarto Electrico Este P P P P P P
N5 Cuarto Redes P P P P P P P
N5 Aula 8 P P P P P P P
N5 Aula 9 P P P OK P P P P
N5 Deposito Audiovisual P P P P P P P
N5 Sala Estudiantes P P P P P P P
N5 Pasillo P P P P P
N6 Aula 1 P P P P P P P
N6 Aula 2 P P P P P P P
N6 Aula 3 P P P P P P P
N6 Aula Virtual P P P P P
N6 Aula 4 P P P P P P P
N6 Aula 5 P P P P P P P
N6 Aula 6 P P P P P P P
N6 Aula 7 P P P P P P P
N6 Aula 8 P P P P P P P
N6 Aula 9 P P P P P P P
N6 Cuarto Servicios Oeste P P P P P P P
N6 Cuarto Servicios Este P P P P P P P
N6 Bao Caballeros Oeste P P P P P P P
N6 Bao Caballeros Este P P P P P P P
N6 Baos Damas Oeste P P P P P P P
N6 Baos Damas Este P P P P P P P
N6 Cuarto Electrico Oeste P P P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N6 Cuarto Electrico Este P P P P P P
N6 Cuarto Redes P P P P P P P
N6 Tep P P P P P P P
N6 Director Tep P P P P P P P
N6 Enc. Servicios Adm. P P P P P P P
N6 Cubiculo (1) P P P P P P P
N6 Sala de Reunion P P P P P P P
N6 Sala Profesores P P P P P P P
N6 Eventos P P P P P P P
N6 Monitor P P P P P P P
N6 Bedel P P P P P P P
N6 Reproduccion P P P P P P P
N6 Pasillo P P P P P
N7 Lab. Telecomunicaciones P P P P P P P
N7 Lab. Redes Convergentes P P P P P P P
N7 Lab. Ciber Seguridad P P P P P P P
N7 Lab. Cableado Estructurado P P P P P P P
N7 Lab. Investigacion Computacionales P P P P P P
N7 Data Center P P P P P P P
N7 Lab Inteligencia Artificial P P P P P P P
N7 Lab. Computacion General 1 P P P P P P P
N7 Lab. Computacion General 2 P P P P P P P
N7 Lab. Ing. De Software P P P P P P P
N7 Cuarto Servicios Oeste P P P P P P P
N7 Cuarto Servicios Este P P P P P P P
N7 Bao Caballeros Oeste P P P P P P P
N7 Bao Caballeros Este P P P P P P P
N7 Baos Damas Oeste P P P P P P P
N7 Baos Damas Este P P P P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N7 Cuarto Electrico Oeste P P P P P P
N7 Cuarto Electrico Este P P P P P P
N7 Cuarto Redes P P P P P P
N7 Telematica P P P P P P P
N7 Director Telematica P P P P P P P
N7 Cubiculos (5) P P P P P P P
N7 Sala de Tutorias P P P P P P
N7 Cubiculos (4) P P P P P P
N7 Ciencias Computacionales P P P P P P P
N7 Director Ciencias Computacionales P P P P P P P
N7 Monitor P P P P P P P
N7 Pasillo P P P P P
N8 Lab. Metrologia y Control Calidad P P P P P P
N8 Lab. Diseo Industrial P P P P P P
N8 Lab. Ergonomia Estudio del Trabajo P P P P P P
N8 Lab. Robotica P P P P P P
N8 Lab. CAD/CAM/CAE P P P P P P
N8 Lab. Medidas Electricas P P P P P P
N8 Lab. Instrumentacion y Control Proc. P P P P P P
N8 La. Ing. Fluidos P P P P P P
N8 La. Electronica Analoga P P P P P P
N8 Lab. Electronica Digital P P P P P P
N8 Cuarto Servicios Oeste P P P P P P
N8 Cuarto Servicios Este P P P P P P
N8 Bao Caballeros Oeste P P P P P P
N8 Bao Caballeros Este P P P P P P
N8 Baos Damas Oeste P P P P P P
N8 Baos Damas Este P P P P P P
N8 Cuarto Electrico Oeste P P P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N8 Cuarto Electrico Este P P P P P
N8 Cuarto Redes P P P P P
N8 Ingenieria de Procesos e Indust. P P P P P P
N8 Director Ing. Procecos e Indust. P P P P P
N8 Cubiculos (12) P P P P P P
N8 Ing. Mecanica Control y Automatiz. P P P P P P
N8 Director Ing. Mecanica Control y Aut. P P P P P P
N8 Monitor P P P P P P
N8 Pasillo P P
N9 Aula 1 P P P
N9 Sala Grupo Invest. Control/Energia P P
N9 Lab. Termofluidos P P P
N9 Lab. Sistemas Energeticos de Potencias P P P
N9 Lab. Maquinas Elec. Y Turbo Maquinas P P P
N9 Lab. Eficiencia Energetica y EERR P P P P
N9 Salon de Ingenieria de Software P P P
N9 Lab. Desarrollo de Proyectos P P P P
N9 Aula 2 P P P
N9 Cuarto Servicios Oeste P P P P P
N9 Cuarto Servicios Este P P P P P
N9 Bao Caballeros Oeste P P P P P
N9 Bao Caballeros Este P P P P P
N9 Baos Damas Oeste P P P P P
N9 Baos Damas Este P P P P P
N9 Cuarto Electrico Oeste P P P P
N9 Cuarto Electrico Este P P P P
N9 Cuarto Redes P P P P
N9 FCI P P P
N9 Decano FCI P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N9 Cubiculos (5) P P P
N9 Sala de Tutorias P P
N9 Ingenieria Renovable P P
N9 Director Ingenieria Renovable P P
N9 Ingenieria Civil P P P
N9 Director Ingenieria Civil P P P
N9 Monitor P P P
N9 Pasillo
N10 Preclinico. Lab de Simulacion
N10 Cuarto Servicios Oeste P P P
N10 Cuarto Servicios Este P P P
N10 Bao Caballeros Oeste P P P
N10 Bao Caballeros Este P P P
N10 Baos Damas Oeste P P P
N10 Baos Damas Este P P P
N10 Cuarto Electrico Oeste P P P
N10 Cuarto Electrico Este P P P
N10 Cuarto Redes P P P
N10 Pasillo
N11 Cuarto Servicios Oeste P P P
N11 Cuarto Servicios Este P P P
N11 Bao Caballeros Oeste P P P
N11 Bao Caballeros Este P P P
N11 Baos Damas Oeste P P P
N11 Baos Damas Este P P P
N11 Cuarto Electrico Oeste P P P
N11 Cuarto Electrico Este P P P
N11 Cuarto Redes P P P
Cierres Pisos Puertas Facilidades Plafon
Nivel Nombre
N11 Pasillo
N12 Sala Eventos P
N12 Kitchennette Catering P
N12 Almacen P
N12 Cuarto Servicios Oeste P P P
N12 Cuarto Servicios Este P P P
N12 Bao Caballeros Oeste P P P
N12 Bao Caballeros Este P P P
N12 Baos Damas Oeste P P P
N12 Baos Damas Este P P P
N12 Cuarto Electrico Oeste P P P
N12 Cuarto Electrico Este P P P
N12 Cuarto Redes P P P
N12 Salon de Reuniones P
N12 Salon de Eventos 1 P
N12 Deposito P
N12 Salon de Eventos 2 P
N12 Pasillo P
Observaciones
Observaciones
Observaciones
Observaciones
Observaciones
Observaciones
Observaciones
Observaciones
Observaciones
Cierres Pisos Puertas Electricidad Plafon Mis

Cierre Completo

Control Acceso
Nivel Nombre

Luminarias

Accesorios
Terminado

Terminado
Estructura
Entregada
Finalizado
Ventanas

Colocada
Liberado

Liberado

Breakers
Llaves
N2 Lab Medicina Anatomia P P P P P P P P P P
N2 Sala Anatomia P P P P P P P P P
N2 Lab Bioquimica P P P P P P P P P P P
N2 Lab Microbiologia e Inm. P P P P P P P P P P
N2 Lab Fisiologia P P P P P P P P P P
N2 Aula 1 P P P P P P P P P P
N2 Hall P P N/A N/A N/A N/A
N2 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
N2 Cuarto Servicios Este P N/A P P P P P N/A N/A
N2 Bao Caballeros Oeste P P P P P P P
N2 Bao Caballeros Este P P P P P P P P P
N2 Baos Damas Oeste P P P P P P P
N2 Baos Damas Este P P P P P P P P P
N2 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N2 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N2 Cuarto Redes P N/A P P P P P P N/A N/A
N2 Cordinador Unidad Investigacion P N/A P P P P P P
N2 Cordinador Unidad Educacion P N/A P P P P P P P P P
N2 Cordinador Unidad Servicio P N/A P P P P P P P P P
N2 Cordinador Unidad Proceso P N/A P P P P P P P P P
N2 Cordinador Unidad Medidas Basicas P N/A P P P P P P P P P
N2 Cordinador Unidad Medidas Clinicas P N/A P P P P P P P P P
N2 Cubiculos (3) P N/A P P P P P P P P P
Cierres Pisos Puertas Electricidad Plafon Mis
N2 Bedel P N/A P P P P P P P P P
N2 Pasillo P N/A P
Nivel Nombre
N3 Sala de Microscopia 1 P P P P P P P P R P
N3 Sala de Microscopia 2 P P P P P P P P R P
N3 Aula 1 P X P P P P P P R P
N3 Aula 2 P X P P P P P P R P
N3 Lab. Biologia P X P P P P P P R P
N3 Almacen P P P P P P P P
N3 Kitchennette P N/A P P P P P P
N3 Lab. Quimica P P P P P P
N3 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
N3 Cuarto Servicios Este P N/A P P P P P N/A N/A
N3 Bao Caballeros Oeste P P P P P P P P
N3 Bao Caballeros Este P P P P P P P P P P
N3 Baos Damas Oeste P P P P P P P P
N3 Baos Damas Este P P P P P P P P P P
N3 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N3 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N3 Cuarto Redes P N/A P P P P P P N/A N/A
N3 Enfermeria P N/A P P
N3 Director Enfermeria P N/A P P P
N3 Nutricion P N/A P P P P
N3 Director Nutricion P N/A P P P
N3 Sala de Reunion P N/A P P P P P
N3 Cubiculos (4) P N/A 3 de 4 P 3 de 4 3 de 4 R P
N3 Terapia Fisica P N/A P P
N3 Director Terapia Fisica P N/A P P P P
N3 Pasillo P N/A P
Cierres Pisos Puertas Electricidad Plafon Mis
N4 Aula 1 P P P P P
N4 Sala de Reuniones P P P P P P P P P P
Nivel
N4 Lab. Informatica Nombre P P P P P P P P R P
N4 Sala Simulacion P P P P P P P P R P
N4 Sala Observacion/Sala simulacion P P P P P P P P R P
N4 Sala de Situacion Monitores P P P P P P P P R P
N4 Aula 2 P P P P P P P P R P P
N4 Aula 3 P P P P P P P P P
N4 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
N4 Cuarto Servicios Este P N/A P P P P P N/A N/A
N4 Bao Caballeros Oeste P P P P P P P
N4 Bao Caballeros Este P P P P P P P P P
N4 Baos Damas Oeste P P P P P P P
N4 Baos Damas Este P P P P P P P P P
N4 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N4 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N4 Cuarto Redes P N/A P P P P P P N/A N/A
N4 Medicina P N/A P P
N4 Premedica P N/A P P P
N4 Estomatologia P N/A P R P
N4 Director Estomatologia P N/A P R P
N4 Cubiculos (7) P N/A P P P P R P
N4 Monitor P N/A P P P P P
N4 Secretaria Decano P N/A P P
N4 Director Medicina P N/A P P P P
N4 Pasillo P N/A P
N5 Aula 1 P P P P P P P P
N5 Aula 2 P P P P P P P R P P
N5 Aula 3 P P P P P P P R P P
Cierres Pisos Puertas Electricidad Plafon Mis
N5 Aula 4 P P P P P P P P R P P
N5 Aula 5 P P P P P P P R P
Nivel
N5 Aula 6 Nombre P P P P P P P P R P
N5 Aula 7 P P P P P P P
N5 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
N5 Cuarto Servicios Este P N/A P P P P P N/A N/A
N5 Bao Caballeros Oeste P P P P P P P
N5 Bao Caballeros Este P P P P P P P P P
N5 Baos Damas Oeste P P P P P P P
N5 Baos Damas Este P P P P P P P P P
N5 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N5 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N5 Cuarto Redes P N/A P P P P P P N/A N/A
N5 Aula 8 P N/A X P P P P P
N5 Aula 9 P N/A X P P P R P P
N5 Deposito Audiovisual P N/A P P P
N5 Sala Estudiantes P N/A P P P P P P
N5 Pasillo P N/A P
N6 Aula 1 P P P P P P P
N6 Aula 2 P P P P P P P P
N6 Aula 3 P P P P P P P P
N6 Aula Virtual P P
N6 Aula 4 P P P P P P P R P
N6 Aula 5 P X P P P P P R P
N6 Aula 6 P X P P P P P R P
N6 Aula 7 P X P P P P
N6 Aula 8 P P P P P P P R P
N6 Aula 9 P P P P P P P
N6 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
Cierres Pisos Puertas Electricidad Plafon Mis
N6 Cuarto Servicios Este P N/A P P P P P N/A N/A
N6 Bao Caballeros Oeste P P P P P P P
Nivel
N6 Bao Caballeros EsteNombre P P P P P P P P P
N6 Baos Damas Oeste P P P P P P P
N6 Baos Damas Este P P P P P P P P P
N6 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N6 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N6 Cuarto Redes P N/A P P P P P P N/A N/A
N6 Tep P N/A P P
N6 Director Tep P N/A X P P
N6 Enc. Servicios Adm. P N/A P P P
N6 Cubiculo (1) P N/A P
N6 Sala de Reunion P N/A P P P
N6 Sala Profesores P N/A P P P
N6 Eventos P N/A X P P P
N6 Monitor P N/A P P P P
N6 Bedel P N/A P P P P
N6 Reproduccion P N/A X P P P
N6 Pasillo P N/A
N7 Lab. Telecomunicaciones P P P P P
N7 Lab. Redes Convergentes P P P P P P
N7 Lab. Ciber Seguridad P P P P P P
N7 Lab. Cableado Estructurado P P P P
N7 Lab. Investigacion Computacionales P P P P P P P P
N7 Lab Inteligencia Artificial P P P P P
N7 Lab. Computacion General 1 P P P P P P
N7 Lab. Computacion General 2 P P P P P P P
N7 Lab. Ing. De Software P P P P P P
N7 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
Cierres Pisos Puertas Electricidad Plafon Mis
N7 Cuarto Servicios Este P N/A P P P P P N/A N/A
N7 Bao Caballeros Oeste P P P P P P P
Nivel
N7 Bao Caballeros EsteNombre P P P P P P P P P
N7 Baos Damas Oeste P P P P P P P
N7 Baos Damas Este P P P P P P P P P
N7 Cuarto Electrico Oeste P N/A P P P P P P N/A N/A
N7 Cuarto Electrico Este P N/A P P P P P P N/A N/A
N7 Cuarto Redes P N/A P P P P P P N/A N/A
N7 Telematica P N/A P P
N7 Director Telematica P N/A X P P
N7 Cubiculos (5) P N/A 3 de 5 P 3 de 5 P
N7 Sala de Tutorias P N/A X P P
N7 Cubiculos (4) P N/A P
N7 Ciencias Computacionales P N/A P P
N7 Director Ciencias Computacionales P N/A X P P P
N7 Monitor P N/A P P P P
N7 Pasillo P N/A
N8 Lab. Metrologia y Control Calidad P P P P P P
N8 Lab. Diseo Industrial P P P P P P
N8 Lab. Ergonomia Estudio del Trabajo P P P P P P P
N8 Lab. Robotica P X X P P P P
N8 Lab. CAD/CAM/CAE P X X P P P P
N8 Lab. Medidas Electricas P X X P P P P
N8 Lab. Instrumentacion y Control Proc. P P P P P P P
N8 La. Ing. Fluidos P P P P P P P
N8 La. Electronica Analoga P P P P P P P
N8 Lab. Electronica Digital P P P P P P P
N8 Cuarto Servicios Oeste P N/A P P P P P N/A N/A
N8 Cuarto Servicios Este P N/A P P P P P N/A N/A
Cierres Pisos Puertas Electricidad Plafon Mis
N8 Bao Caballeros Oeste P P P P P P P
N8 Bao Caballeros Este P P P P P P P P
Nivel
N8 Baos Damas Oeste Nombre P P P P P P
N8 Baos Damas Este P P P P P P P P
N8 Cuarto Electrico Oeste P N/A P P P P P N/A N/A
N8 Cuarto Electrico Este P N/A P P P P P N/A N/A
N8 Cuarto Redes P N/A P P P P P P N/A N/A
N8 Ingenieria de Procesos e Indust. P N/A P P
N8 Director Ing. Procecos e Indust. P N/A X P P
N8 Cubiculos (12) P N/A 6 de 12 P 6 de 12
N8 Ing. Mecanica Control y Automatiz. P N/A P P
N8 Director Ing. Mecanica Control y Aut. P N/A X P P
N8 Monitor P N/A P P
N8 Pasillo P N/A P
N9 Aula 1 P P P P
N9 Sala Grupo Invest. Control/Energia P P P P
N9 Lab. Termofluidos P X P P P
N9 Lab. Sistemas Energeticos de Potencias P P P P P
N9 Lab. Maquinas Elec. Y Turbo Maquinas P P P P P
N9 Lab. Eficiencia Energetica y EERR P P P P P
N9 Salon de Ingenieria de Software P P P P P
N9 Lab. Desarrollo de Proyectos P P P P
N9 Aula 2 P P P P
N9 Cuarto Servicios Oeste P N/A P P P P N/A N/A
N9 Cuarto Servicios Este P N/A P P P P N/A N/A
N9 Bao Caballeros Oeste P P P P P P
N9 Bao Caballeros Este P P P P P P P
N9 Baos Damas Oeste P P P P P
N9 Baos Damas Este P P P P P P P P
Cierres Pisos Puertas Electricidad Plafon Mis
N9 Cuarto Electrico Oeste P N/A P P P P N/A N/A
N9 Cuarto Electrico Este P N/A P P P P N/A N/A
Nivel
N9 Cuarto Redes Nombre P N/A P P P P N/A N/A
N9 FCI P N/A P P
N9 Decano FCI P N/A P P
N9 Cubiculos (5) P N/A P
N9 Sala de Tutorias P N/A P
N9 Ingenieria Renovable P N/A P P
N9 Director Ingenieria Renovable P N/A P P
N9 Ingenieria Civil P N/A P
N9 Director Ingenieria Civil P N/A P
N9 Monitor P N/A P P
N9 Pasillo P N/A
N10 Preclinico. Lab de Simulacion
N10 Cuarto Servicios Oeste P N/A P P P P N/A N/A
N10 Cuarto Servicios Este P N/A P P P P N/A N/A
N10 Bao Caballeros Oeste P P P
N10 Bao Caballeros Este P P P P P
N10 Baos Damas Oeste P P P
N10 Baos Damas Este P P P P P P
N10 Cuarto Electrico Oeste P N/A P N/A N/A
N10 Cuarto Electrico Este P N/A P P P P N/A N/A
N10 Cuarto Redes P N/A P P P P P N/A N/A
N10 Pasillo N/A
N11 Cuarto Servicios Oeste P N/A P P P P N/A N/A
N11 Cuarto Servicios Este P N/A P P P P N/A N/A
N11 Bao Caballeros Oeste P P P
N11 Bao Caballeros Este P P P P P P
Cierres Pisos Puertas Electricidad Plafon Mis
N11 Baos Damas Oeste P P P
N11 Baos Damas Este P P P P P P
Nivel
N11 Nombre
Cuarto Electrico Oeste P N/A P P P P N/A N/A
N11 Cuarto Electrico Este P N/A P P P P N/A N/A
N11 Cuarto Redes P N/A P P P P P N/A N/A
N11 Pasillo N/A
N12 Sala Eventos P
N12 Kitchennette Catering P
N12 Almacen P
N12 Cuarto Servicios Oeste P N/A P P P P N/A N/A
N12 Cuarto Servicios Este P N/A P P P P N/A N/A
N12 Bao Caballeros Oeste P P P
N12 Bao Caballeros Este P P P P P P
N12 Baos Damas Oeste P P P
N12 Baos Damas Este P P P P P P
N12 Cuarto Electrico Oeste P N/A P P P P N/A N/A
N12 Cuarto Electrico Este P N/A P P P P N/A N/A
N12 Cuarto Redes P N/A P P P P P N/A N/A
N12 Salon de Reuniones P N/A
N12 Salon de Eventos 1 P N/A
N12 Deposito P N/A
N12 Salon de Eventos 2 P N/A
N12 Pasillo P N/A
Miscelaneos Pintura Detalles Observaciones

Rociadores, Bocinas, etc


Termostato

Rejillas A/C

Termiada
1ra
P P P P
P P P P
P P P P Ver reporte 04/09 Listo para terminacion
P P P P Ver reporte 04/09 Arboleda
P P P P Cruz Lora
P P P P Ingenieria Estrella
N/A P X Plywood
N/A N/A N/A P P R Incompleto
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P P P Ver reporte 04/09
P P P P
P P P P Ver reporte 04/09
P P P P
P P P P
P P P P
P P P P Ver reporte 04/09
Miscelaneos Pintura Detalles Observaciones
P P P

P P P P Completar pisos
P P P P Almacen Pisos
P P P P
P P P P
P P P P Ver reporte 04/09
P P P Oficina
P P P P
P P Colocar Puerta Ver reporte 04/09
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P P P Vidrio Puerta
P P P P
P P P P Ver reporte 04/09
P P P P Terminar muro cortina y recoger materiales
P P P P Llaves
P P P P Llaves Ver reporte 04/09
P P P P Ver reporte 04/09 y 18/9
P P P P Completar Piso
Miscelaneos Pintura Detalles Observaciones
P P P Puerta (vidrio) Ver reporte 04/09 y 18/9
P P P Ver reporte 18/9
P P P Ver reporte 04/09
P P P
P P P Ver reporte 04/09
P P P
P P P
P P P Problema con Llaves, sacar materiales y limpieza Ver reporte 18/9
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P P P
P P P P Completar pisos, masilla y puertas
P P P P Completar pisos, puertas y recoger materiales
P P P P
P P P P Terminar colocar puertas y entregar llaves Ver reporte 18/9
P P P Terminar pintura
P P P P Terminar puerta
P P P P Terminar Ceramica

P P P P Problema llaves Ver reporte 04/09


P P P P Problema llaves y completar pisos Ver reporte 18/9
P P P P
Miscelaneos Pintura Detalles Observaciones
P P P P
P P P P Completar Vidrio muro cortina
P P P P Terminar Piso, sacar materiales Ver reporte 04/09 y 18/9
P P P P Colocar vidrio puerta Ver reporte 04/09
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P P P Completar vidrio muro cortina (guinche)
P P P P Sacar materiales
P P P P Colocar puerta(vidrio)
P P P P Terminar pao fijo (pasillo)

P P P P Oficina
P P P P Oficina
P P P P Oficina
P P P
P P P P Ver reporte 18/9
P P P P Completar estructura plafon
P P P P
P P P P Sacar materiales, entregar llaves
P P P P Limpieza, completar piso
P P P P Sacar materiales Ver reporte 18/9
N/A N/A N/A P P
Miscelaneos Pintura Detalles Observaciones
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P Completar puerta
P P Completar puerta
P P Completar puerta
P P Completar puerta Ver reporte 04/09
P P Completar puerta y sacar materiales
P P
P P
P P Completar puerta, pisos, sheetrock
P P
P P

P P Completar pao fijo, estructura plafon, limpieza


P P Limpieza
P P Limpieza Ver reporte 04/09
P P Limpieza, terminar muro cortina
P P Sacar materiales
P P Terminar plafon, limpieza
P P Limpieza Ver reporte 18/9
P P Limpieza, sacar materiales Ver reporte 18/9
P P Ver reporte 18/9
N/A N/A N/A P P
Miscelaneos Pintura Detalles Observaciones
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P
P P Terminar muro cortina, puerta
P
P P Muro Cortina
P Terminar piso, puerta, muro cortina
P P Terminar Muro cortina, puertas Ver reporte 18/9
P P
P P
Ver reporte 18/9
P P Terminar plafon, pintura
P Terminar plafon, pintura
P P Limpieza
P P Sacar materiales
P P
P P
P P
P P
P P
P P
N/A N/A N/A P P
N/A N/A N/A P P
Miscelaneos Pintura Detalles Observaciones
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
P P Terminar puertas
P P Terminar muro cortina, puerta
P P Terminar muro cortina
P P
P P Terminar muro cortina
P P Colocar puerta

P
P
P

P
P
P
P
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
Miscelaneos Pintura Detalles Observaciones
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P

N/A N/A N/A P P


N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P

N/A N/A N/A P P


N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
Miscelaneos Pintura Detalles Observaciones
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P

N/A N/A N/A P P


N/A N/A N/A P P
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A N/A N/A
N/A N/A N/A P P
N/A N/A N/A P P
N/A N/A N/A P P
Listo para terminacion