Turnaround Management Workflow Process

TURNAROUND

Asset Management
Next
Page

Corporate Philosophy

Maintenance Execution Management Process

XXXX

Reliability Management Process

Turnaround Management Plan Methodologies


Asset Work Management System

DEFINE ASSIGN CONTROL

eAM
Turnaround Management Workflow Process
TURNAROUND

Previous TAR-01
Page Create & Define TAR
Project
Preliminary Worklist Plus Items
Scope Of Work
Identified From Previous
Turnaround

TAR-02
NO Does The Client
Approves ?

YES

TAR-03

Establish & Monitor


Develop TAR risk / Preliminary TAR Develop TAR Phylosophy Client approved
Plan of the Plan
mitigation plans execution plan and Objectives milestone Planning
schedule

Establish core team/ Develop TAR Phylosophy Develop Project audit Develop TAR Phylosophy Establish phased Staffing
Distribution matrix and Objectives checklists and Objectives plan

Next
Page

eAM
Turnaround Management Workflow Process
TURNAROUND

FROM
TAR-30 FROM :
NO TAR-022

TAR-05 TAR-012
TAR-04 TAR-05 TAR-011:
Define scope for large/ Establish frozen scope,
Establish master work list Implement change Approve scope/ YES
small/maint packages for worklist & track/control
Previous (all work) management process estimate?
review & estimates change
Page

TAR-06 TAR-07
Design walkdown FEL estimate

TAR-013
TAR-9: Next
Maintain frozen master Page
TAR-08
work list
Review For Long
Lead Items

TAR-09
Bill Of Material

TO :
TAR-19
TAR-010
Requisition Long Lead
Material

eAM
Turnaround Management Workflow Process
TURNAROUND

TO: TAR-022 :
TAR-12 Reduce scope/
worklist
TAR- 021:
Modify window or NO
TAR-023 : TAR scope? TAR-020:
Shut down and start Acceptable YES TO :
up logic schedule? TAR-33
TAR- 024 TAR- 025
Execute pre TAR Reconcile TO :
Construction Work incomplete pre-TAR TAR-30
with TAR scope

TAR-014: TAR-015:
Develop, complete & issue Develop preliminary Next Page
approved documents TAR work package
Previous
Page

TAR-016
Preliminary job card

TAR-017:
Preliminary TAR
schedule

FROM : TAR-019: TAR-018: TO :


TAR-07
TAR work item TAR work item TAR-35
estimate template estimate

TAR-027
TAR-028 Bag & Tag TAR
Requisition Bill Of
Procure All Materials Materials
Material

TAR-026
TAR EXECUTION PLAN :
- Organization Chart
- Safety Plan
- Quality Plan
- Logistics Plan
Preliminary - Facilities Plan
TAR - Engineering Plan Final TAR
execution - Materials Plan Execution Plan
Plan - Communications Plan
- Progress Reporting Plan
- Turnover Plan
- TAR Change Management Plan

eAM
Turnaround Management Workflow Process
TURNAROUND

TAR-37 :
TAR-20 Work package walk
down validation

TAR-32:
Work package
distribution

TAR-31: TO:
YES Update work NO TAR-43
FROM : packages?
TAR-25 TAR-30 TO:
Add Pre-TAR NO TAR-47
With TAR
TO:
TAR-12 YES

TAR-33:
Previous
Issue final TAR work
Page
package

TAR-34:
Final job card

TAR-36:
TAR CPM schedule
FROM: TAR-35:
TAR-19 Final TAR estimate

FROM :
TAR-018 TAR-40 TAR-041
Award Contracts Mobilize Contractors TAR-042
Bag and Tag TAR
Material

eAM
Turnaround Management Workflow Process
TURNAROUND

TAR-039 TAR-044
Execute Shutdown Operation support

FROM: TAR-43: Next Page


TAR-31 Execute turnaround

TAR-044
TAR-045 Daily TAR Progress
Provide technical Reviews
Support to TAR

TAR-046
Daily Reporting
Daily Progressing
TAR Change Mgt
Work Pkg Execution
Issue Job Cards

eAM
Turnaround Management Workflow Process
TURNAROUND

FROM: TAR-047
TAR-30 Defer incomplete
pre-TAR Work

TAR-048
Execute Start-Up

FROM:
TAR-43

TAR-049
Project CLOSEOUT