Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 25/10/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report S S S S R S S S S S S
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Mechanical Activity
1 Remove skin casing and seal box at inlet header (Front side) 70% 1 Remove skin casing and seal box at inlet header (Front side) 100% Complete 1 RH tube mark-cutting Left side = 145 joint

2 Remove pin stopper (Right side) 85% 2 Continues remove pin stopper (Right side) 100% Complete 2 Stub tube skin casing remove
3 Remove pin stopper (Left side) 100% Complete 3 Continues remove pin stopper (Front side) 100% Complete 3 Preparation spare part tube laydown area
4 Start remove pin stopper (Front side) 70% 4 Installation additional temporary support and welding (Right side) = 6 pcs 100% Complete
5 Installation additional temporary support and welding (Left side) = 6 pcs 100% Complete
6 RH tube mark-cutting Right side = 145 joint 100 % Complete
7 RH tube mark-cutting Left side = 145 joint
Piping Activity

Item Position Up to Last day Today Accumulated Mechanical Activity Photo


MANPOWER Front side Pin stopper (Front side)
1 Site Engineer
2 QA Engineer 1 1 1
3 Safety 2 2 1
4 QA,QC Superviser 1 1 1
5 Superviser 4 4 4
6 Admin Staff 1 1 1
7 Foreman 3 3 3
8 Welder 2 2 2
9 Fitter A,B 13 13 13
10 Electricain 1 1 1
11 Store 1 1 1
Piping Activity Photo
Total (Man-Day) 29 29 29