Вы находитесь на странице: 1из 15

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/24077265

Contributors to construction delays

Article in Construction Management and Economics January 1998


DOI: 10.1080/014461998372556 Source: RePEc

CITATIONS READS

130 181

2 authors, including:

Dr Daniel W.M. Chan


The Hong Kong Polytechnic University
109 PUBLICATIONS 2,828 CITATIONS

SEE PROFILE

All content following this page was uploaded by Dr Daniel W.M. Chan on 06 April 2016.

The user has requested enhancement of the downloaded file.


This article was downloaded by: [Hong Kong Polytechnic University]
On: 23 December 2014, At: 21:25
Publisher: Routledge
Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office:
Mortimer House, 37-41 Mortimer Street, London W1T 3JH, UK

Construction Management and Economics


Publication details, including instructions for authors and subscription
information:
http://www.tandfonline.com/loi/rcme20

Contributors to construction delays


Mohan M. Kumaraswamy & Daniel W. M. Chan
Published online: 21 Oct 2010.

To cite this article: Mohan M. Kumaraswamy & Daniel W. M. Chan (1998) Contributors to construction
delays, Construction Management and Economics, 16:1, 17-29, DOI: 10.1080/014461998372556

To link to this article: http://dx.doi.org/10.1080/014461998372556

PLEASE SCROLL DOWN FOR ARTICLE

Taylor & Francis makes every effort to ensure the accuracy of all the information (the Content)
contained in the publications on our platform. However, Taylor & Francis, our agents, and our
licensors make no representations or warranties whatsoever as to the accuracy, completeness,
or suitability for any purpose of the Content. Any opinions and views expressed in this
publication are the opinions and views of the authors, and are not the views of or endorsed
by Taylor & Francis. The accuracy of the Content should not be relied upon and should be
independently verified with primary sources of information. Taylor and Francis shall not be liable
for any losses, actions, claims, proceedings, demands, costs, expenses, damages, and other
liabilities whatsoever or howsoever caused arising directly or indirectly in connection with, in
relation to or arising out of the use of the Content.

This article may be used for research, teaching, and private study purposes. Any substantial
or systematic reproduction, redistribution, reselling, loan, sub-licensing, systematic supply, or
distribution in any form to anyone is expressly forbidden. Terms & Conditions of access and use
can be found at http://www.tandfonline.com/page/terms-and-conditions
Construction Management and Economics (1998) 16, 17 29

Contributors to construction delays


MOHAN M. KUMARASWAMY and DANIEL W. M. CHAN
Department of Civil and Structural Engineering, The University of Hong Kong, Pokfulam Road, Hong Kong

Received 26 October 1995; accepted 8 July 1996


Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Projects can be delayed for a large number of reasons. The third phase of an investigation into such factors
focused on the causes of construction delays in Hong Kong. A questionnaire was based on 83 factors iden-
ti ed in previous phases of the investigation. Analysis of the responses reveals differences in perceptions of
the relative signi cance of factors between clients, consultants and contractors. There was general agreement
about the relative importance of delay factors such as unforeseen ground conditions. Improving productivity
is a useful approach to controlling delays. Important factors affecting productivity itself are thus examined
in more depth, with a view to enhancing productivity and reducing delays. The conclusions of this phase of
the investigation include a ranking of factors and factor categories that are perceived by different groups of
project participants to contribute to delays. For example, higher-ranking factors, such as unforeseen ground
conditions, and factor categories such as project-related factors, are found to merit special management atten-
tion in countering construction delays. The high degree of disagreement as discerned between the groups
of clients, consultants and contractors is indicative of their experiences, possible prejudices and lack of effec-
tive communication. It is also con rmed that productivity and other non-scope factors such as effective
communications should supplement the project scope factors incorporated into the construction time predic-
tion models that were proposed in the previous phases of this investigation.

Keywords: productivity, project management, delay, time, Hong Kong

Background and introduction study (Kumaraswamy and Chan, 1995); and (b) site
organization variables also merited further investiga-
The rst two phases of an ongoing investigation into tion, in relation to project durations (Chan and
factors affecting construction durations in Hong Kong Kumaraswamy, 1995). Furthermore, the second phase
(Chan and Kumaraswamy, 1995) focused on project of the Hong Kong investigation also incorporated a
scope variables such as project cost, oor area and case study on construction plant and labour produc-
number of oors in buildings. The results were similar tivity. This indicated the contribution of productivity
to those previously derived by Bromilow et al. (1988) levels to activity times, overall construction project
in Australia and Kaka and Price (1991) in the UK, in durations and construction delays, for example through
respect of the types of relationship and the correlation different utilization/idling patterns.
between project time and cost. The previous investi- This paper highlights the principal ndings of the
gation also indicated the probable impact on construc- third phase of the Hong Kong investigation, in respect
tion durations of non-scope factors such as external and of the main factors causing delays, as perceived by
management variables, in line with the conclusions different industry subsectors: clients, consultants and
from a recent study in Australia (Walker, 1995a). contractors. The degree of agreement/disagreement
Previous reports on the ongoing study into construc- between the subsectors as to the importance of
tion time performance in Hong Kong noted that: these factors is also indicated, to illustrate differences
(a) productivity was a key factor needing further in collective perspectives and any possible popular
0144 6193 1998 E & FN Spon
18 Kumaraswamy and Chan

misconceptions or prejudices. The resulting sectoral 1. project-related;


and combined rankings of the main causes of construc- 2. client-related;
tion delays suggest suitable priorities in devising and 3. design team-related;
focusing strategies to counteract such critical contrib- 4. contractor-related;
utors to delays in future projects. 5. materials-related;
In developing such counter-delay strategies, a focus 6. labour-related;
on productivity is justi ed by the main ndings of the 7. plant/equipment-related;
questionnaire and literature surveys, both of which 8. external factors.
indicate a general perception of the signi cance of
Although a certain degree of overlap may be antici-
`non-scope factors that either directly or indirectly
pated between these categories, this was minimized
affect productivity levels and project durations. Lower
during the speci c allocations of the 83 factors. It was
productivity than planned is thus identi ed as a key
noted that: (a) there may be interactions between
contributor to (or a root cause of) delays, which there-
the factor categories, for example in one affecting the
fore merits special attention.
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

other either positively or negatively; and (b) achieved


The ndings of this phase of the investigation are
(vs planned) productivity levels can affect many of the
framed within the context of relevant results of recent
categories (as a common root cause), for example in
research into construction productivity and other
design team productivity, contractors organizational
factors affecting construction durations and construc-
productivity, labour productivity and plant produc-
tion delays in other countries, in order to consider the
tivity.
general applicability of the conclusions.
Projects can be delayed by the impact of such factor
categories; it was also noted that these may interact to
produce `multiplier effects, where problems in one
Productivity, project durations and delays
category may trigger further problems in another. For
example, weak contractor management may lower
Because productivity levels were found to be a principal
labour morale, and decrease plant productivity as well.
determinant of project durations (Chan and
Kumaraswamy, 1995), lowered productivity could
feasibly contribute signi cantly to project delays. The
potential for improvement is re ected in the nding that Survey methodology
`productivity rates in the United Kingdom varied
between one site and another by as much as three to The survey questionnaire was designed on the basis of
one (NEDO, 1989). Enhanced productivity is evidently 83 previously identi ed delay-causing factors divided
a necessary but not suf cient condition for reducing into the foregoing eight factor categories. Respondents
project durations. While the productivity of each type of were requested to rate the signi cance of each factor
resource (factor), such as labour, may be increased, by as either extremely signi cant, very signi cant, moder-
motivation for example, the overall (total factor) pro- ately signi cant, slightly signi cant or not signi cant.
ductivity will not be correspondingly enhanced unless a The rst page of the ve-page questionnaire is repro-
proper balance and appropriate synergy is achieved. duced in Appendix 1.
This requires effective management of the resources and This questionnaire was sent to 400 clients, con-
their interactions within the project, as well as their sultants and contractors in Hong Kong in Decem-
interactions with the external environment. ber 1994, requesting responses based on projects
Conversely, project durations have been reduced in completed between 1990 and 1994. Follow-up
practice, despite lower productivity levels, for example communications led to the return of 147 completed
by mobilizing more resources. Seemingly impossible questionnaires. The distribution of the respondents, as
target dates have been achieved by such deployment classi ed according to their industry grouping (clients,
of additional resources and/or a sudden surge of consultants or contractors) and their main works
synergistic `partnering type teamwork by all project type (buildings or civil engineering) is indicated in
participants who needed to meet a critical deadline. Appendix 2.
Similarly, project delays have also been caused by The pro le of the respondents in terms of their
factors other than lowered productivity levels. average work experience in each such group, as indi-
For the purposes of the third phase of this investi- cated in Appendix 3, con rms the considerable expe-
gation, potential delay factors were identi ed from a rience on which the responses are based. It is noted
literature review and the observations from the rst that the subjective and general nature of the responses
two phases of the investigation. These were classi ed required would be less reliable than more quanti able
into eight factor categories as follows: information, or that obtained from speci c projects.
Construction delays 19

However, it must be also noted that this survey supple- from 1 to 20 are also indicated in Tables 2 and 3.
ments (and is supplemented by) a previous survey, These were assigned on the basis of the factor RIIs.
which derived such quanti able data from speci c Where the RIIs were the same for two or more factors,
projects (Chan and Kumaraswamy, 1995), but which rank differentiation was achieved by examining the
also indicated the need for wider experience-based distribution of the ratings against such factors. For
assessments of factors causing delays. The question- example, if more respondents had ranked one of the
naire survey was supplemented by follow-up interviews factors as either `extremely signi cant or `very signif-
to clarify some of the responses. icant (i.e. more ranks of 4 or 5, than assigned to
another factor), then the former was assigned the
higher rank.
The next step distinguished between building works
Survey ndings
and civil engineering works, thereby dividing each of the
three participant groups into two such work types, with
Observations and analysis
each work type containing the three groups of clients,
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Table 1 presents a pro le of the magnitudes of time consultants and contractors. The weighted average of
overruns, as observed on different types of projects the RIIs for each of the previously selected 20 factors
during the rst survey in 1993/94. This pro le from each group was next computed within each work
indicates that project delays are fairly common in Hong type, by combining it with the RIIs from the other two
Kong. groups. This combination of three RIIs to nd the
Tables 2 and 3 summarize the responses in respect weighted average for each factor within each work type
of the 20 most important factors causing delays as was achieved by adding the products of (a) the RII for
perceived by two of the six groups surveyed: contrac- each group and (b) the proportion of respondents from
tors on building projects and consultants on civil the corresponding group (as a proportion of the total
engineering projects, respectively. Four more of such respondents, as can be derived from Appendix 2).
summarized response sheets were obtained for the For example, the weighted average of the factor `poor
other groups surveyed, but are not reproduced here, site management and supervision in the `building
to save space. However, the consolidated summaries works type, as in Table 4, was computed as 0.800
that are presented later (in Tables 4, 5 and 8) re ect (27/78) + 0.858 (24/78) + 0.822 (27/78) = 0.825,
the comparative results from the other groups as well. as appears in Table 4.
The relative importance index (RII) derived to summa- The ten factors with the highest weighted averages
rize the importance of each `factor was computed as in the `buildings works and `civil engineering works
types are shown in Tables 4 and 5 respectively.
o w Figures 1 and 2 facilitate a visual comparison of the
RIIs, (as derived from the perceptions of the different
RII 5
A3 N groups) of the ten most signi cant factors in respect
where: w = weighting as assigned by each respondent of the `building works and `civil engineering works
in a range from 1 to 5, where 1 implies `not signi - types respectively.
cant and 5 implies `extremely signi cant ; A = the The overall RIIs for each of the eight factor cate-
highest weight (5); N = the total number in the sample. gories were next determined for each group in turn,
The relative rankings of the factors within each group by taking the mean of all factor RIIs in that category.

Table 1 Percentage of time overruns in the three project samples in the previous survey in Hong Kong

Actual percentage of Government Private Civil engineering


time overrun building projects (%) building projects (%) projects (%)
0 40 25 34
1 10 27 28 21
11 20 11 17 21
21 30 14 11 13
31 40 5 11 5
41 50 3 0 3
> 50 0 8 3
Mean percentage of
time overrun 9 17 14
Sample size 37 36 38
20 Kumaraswamy and Chan

Table 2 Contractors responses and ranking of the signi cance of factors causing delays in building projects
(sample size = 27)

Hypothesized factors Percentage of Relative Rank


respondents scoring importance
> 4 3 < 2 index
(1) (2) (3) (4) (5) (6)
Delays in design information 88.89 7.41 3.70 0.889 1
Long waiting time for approval of drawings 85.19 11.11 3.70 0.822 2
Poor site management and supervision 81.48 14.82 3.70 0.822 3
Unrealistic contract durations imposed
by client 75.00 25.00 0.00 0.817 4
Mistakes and discrepancies in
design documents 81.48 14.82 3.70 0.815 5
Long waiting time for approval of
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

test samples of materials 77.78 18.52 3.70 0.815 6


Inappropriate overall organizational structure
linking all project teams 66.67 29.63 3.70 0.807 7
Inadequate design team experience 81.48 11.11 7.41 0.8 8
Lack of communication between
consultant and contractor 74.07 22.23 3.70 0.8 9
Low speed of decision making involving
all project teams 74.07 14.82 11.11 0.8 10
Delays in subcontractors work 69.23 26.92 3.85 0.792 11
Inadequate contractor experience 62.96 33.34 3.70 0.785 12
Necessary variations 74.07 22.23 3.70 0.778 13
Disputes/con icts 77.78 14.81 7.41 0.770 14
Low speed of decision making within
each project team 70.37 22.22 7.41 0.770 15
Lack of communication between
client and consultant 66.67 22.22 11.11 0.770 16
Shortage of materials in markets 62.96 25.93 11.11 0.770 17
Client-initiated variations 74.07 22.23 3.70 0.763 18
Unforeseen ground conditions 66.67 25.92 7.41 0.756 19
Slow information ow between
project team members 62.96 37.04 0.00 0.756 20

The weighted averages of these overall RIIs from the the different groups. A further overall comparison
factor categories were obtained for three building works between the building works and civil engineering works
groups as in Table 6; and for the three civil engineering as a whole yields a RAF of 0.50 and a PA of 87.5%,
works groups as in Table 7. indicating a high overall correlation. Figure 3 illustrates
The rank agreement factors (RAFs) were next com- the proportions of agreement between the different
puted using the formula and methodology described groups based on the PAs in Tables 8 and 9.
by Okpala and Aniekwu (1988) to measure the agree-
ment in ranking between groups of project participants.
Speci c conclusions from the survey
The RAF can range from 0, indicating perfect agree-
ment, to higher values indicating increasing disagree- While the detailed results as indicated in Tables 2 9
ment. The percentage disagreement and the percentage and Figures 1 3 contain a wealth of information, the
agreement (PA) were computed from the RAF, also following speci c conclusions are relevant to the focus
using the prescribed formulae. of this paper.
Table 8 records the RAFs and PAs as computed for There is a fair degree of agreement between the
the ten most signi cant factors causing delays, as groups in their ranking of the factor categories, partic-
perceived by the different groups. Table 9 records the ularly between clients and consultants. However, there
RAFs and PAs in respect of the relative importance of is an apparent divergence in perceptions between
the eight factor categories themselves, as perceived by clients and contractors, or even between consultants
Construction delays 21

Table 3 Consultants responses and ranking of the signi cance of factors causing delays in civil engineering projects
(sample size = 25)

Hypothesized factors Percentage of Relative Rank


respondents scoring importance
> 4 3 < 2 index
(1) (2) (3) (4) (5) (6)
Unforeseen ground conditions 80.00 12.00 8.00 0.816 1
Inadequate contractor experience 80.00 16.00 4.00 0.8 2
Poor site management and supervision 68.00 28.00 4.00 0.792 3
Inappropriate type of foundations 78.26 13.04 8.70 0.791 4
Low speed of decision making involving
all project teams 75.00 12.50 12.50 0.783 5
Necessary variations 72.00 24.00 4.00 0.776 6
Client-initiated variations 76.00 16.00 8.00 0.768 7
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

De ciencies in planning and scheduling


at preconstruction stage 72.00 12.00 16.00 0.76 8
Unsuitable leadership style of
contractor s construction manager 68.00 20.00 12.00 0.76 9
Improper control over site resource allocation 56.00 36.00 8.00 0.76 10
Slow information ow between
project team members 70.83 16.67 12.50 0.758 11
Shortage of plant/equipment 68.00 20.00 12.00 0.752 12
Unsuitable management structure and style 68.00 20.00 12.00 0.752 13
Low speed of decision making within
each project team 62.50 33.33 4.17 0.75 14
Inadequate managerial skills 64.00 28.00 8.00 0.736 15
Shortage of skilled labour 60.00 32.00 8.00 0.736 16
Inappropriate type of main construction 70.83 20.83 8.34 0.733 17
Small extent of design information
available at construction start 66.66 16.67 16.67 0.733 18
Shortage of managerial and supervisory
personnel 72.00 12.00 16.00 0.728 19
Delays in subcontractors work 60.00 32.00 8.00 0.728 20

and contractors, on many speci c factors themselves: ti ed in Tables 4 and 5 respectively, yield six common
this is re ected in the percentage agreements (PAs) in factors, as listed in Table 10.
Tables 8 and 9 and Figure 3. Of the remaining four signi cant factors from
For example, the clients and consultants appear to building works, two are contractor related, one is
agree on the signi cance of the contractor-related project related, and the other is design-team related.
factor category in contributing to delays in both On the other hand, three of the four remaining factors
building works and civil engineering works, as per from civil engineering works are contractor related,
Tables 6 and 7. However, an examination of the signif- with the other classi ed as labour related also
icant `factors so identi ed does not appear to re ect usually being within the purview of the contractor.
this general perception to a corresponding extent in It is evident that there are differences in the percep-
the case of the speci c factors in Tables 4 and 5. This tions of different groups as to the causes of construc-
apparent anomaly could perhaps be explained, for tion delays. Such perceptions may be attributed to a
example, as a general `conditioning of one group (such certain degree of group bias, arising either from some
as consultants) vis- -vis another (such as contractors), speci c experiences, from limited exposure, and/or
which may manifest itself in a random distribution of from conditioning by colleagues. Even though the
adverse responses relating to the latter group in recorded experience levels of the survey respondents
general, i.e. within the relevant factor category, despite seem suf ciently high, and not dissimilar between
a lack of agreement on speci c factors. groups as in Appendix 3, some bias is evident in the
The top ten signi cant factors as isolated separately group perceptions. Perhaps the wording of the factors
for building works and civil engineering works, as iden- and the classi cation of the factor categories in the
22 Kumaraswamy and Chan

Table 4 Relative importance indices (RII) of the ten most signi cant factors causing delays in building works (in descend-
ing order of signi cance)

Hypothesized Factor Clients Consultants Contractors Weighted


factor category (RII) (RII) (RII) average
Poor site management Contractor 0.800 0.858 0.822 0.825
and supervision related
Unforeseen ground Project 0.763 0.842 0.756 0.814
conditions related
Delays in design Design 0.689 0.742 0.889 0.775
information team related
Lack of communication Project 0.741 0.783 0.8 0.774
between consultant related
and contractor
Inadequate contractor Contractor 0.763 0.765 0.785 0.771
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

experience related
Low speed of Project 0.733 0.808 0.800 0.761
decision making related
involving all project
teams
Client-initiated Client 0.741 0.808 0.763 0.757
variations related
Necessary variations Project 0.756 0.783 0.778 0.756
of works related
Delays in subcontractors s Contractor 0.708 0.767 0.792 0.755
work related
Improper control over Contractor 0.769 0.775 0.719 0.754
site resource allocation related

Table 5 Relative importance indices (RII) of the ten most signi cant factors causing delays in civil engineering works (in
descending order of signi cance)

Hypothesized Factor Clients Consultants Contractors Weighted


factor category (RII) (RII) (RII) average
Unforeseen ground Project 0.826 0.816 0.8 0.814
conditions related
Poor site management Contractor 0.878 0.792 0.710 0.796
and supervision related
Low speed of decision Project 0.755 0.783 0.743 0.761
making involving all related
project teams
Client-initiated Client 0.757 0.768 0.743 0.757
variations related
Necessary variations Project 0.678 0.776 0.733 0.756
of works related
Inadequate contractor Contractor 0.817 0.8 0.632 0.755
experience related
Unsuitable management Contractor 0.773 0.752 0.7 0.743
structure and style of related
contractor
Contractor s de ciencies in Contractor 0.8 0.76 0.648 0.739
planning and scheduling related
at preconstruction stage
Shortage of managerial Contractor 0.765 0.728 0.695 0.730
and supervisory personnel related
Unsuitable leadership Contractor 0.752 0.76 0.67 0.730
style of contractor s related
construction manager
Construction delays 23
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Figure 1 Comparison of the relative importance indices (RIIs) of the factors considered most signi cant by clients, consul-
tants and contractors of building works (as in Table 4): 1. poor site management and supervision; 2. unforeseen ground
conditions; 3. delays in design information; 4. lack of communication between consultant and contractor; 5. inadequate
contractor experience; 6. Low speed of decision making involving all project teams; 7. client-initiated variations; 8. neces-
sary variations of works; 9. delays in subcontractors work; 10. improper control over site resource allocation

Figure 2 Comparison of the relative importance indices (RIIs) of the factors considered most signi cant by clients, consul-
tants and contractors of civil engineering works (as in Table 5): 1. unforeseen ground conditions; 2. poor site management
and supervision; 3. low speed of decision making involving all project teams; 4. client-initiated variations; 5. necessary
variations of works; 6. inadequate contractor experience; 7. unsuitable management structure and style of contractor;
8. contractor s de ciencies in planning and scheduling at preconstruction stage; 9. shortage of managerial and supervisory
personnel; 10. unsuitable leadership style of contractor s construction manager
24 Kumaraswamy and Chan

Table 6 Relative importance indices (RII) and ranks (R) for different factor categories, and by different survey respondents
in the building works grouping

Factor category Client Consultant Contractor Weighted


average
RII R RII R RII R RII R
Project related 0.588 6 0.645 4 0.672 5 0.635 5
Client related 0.572 8 0.609 7 0.649 7 0.610 8
Design team related 0.641 3 0.677 3 0.778 1 0.700 2
Contractor related 0.708 2 0.711 1 0.699 3 0.706 1
Materials 0.606 4 0.600 8 0.681 4 0.630 6
Labour 0.717 1 0.682 2 0.662 6 0.687 3
Plant/equipment 0.577 7 0.636 5 0.634 8 0.615 7
External 0.598 5 0.632 6 0.746 2 0.660 4
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Table 7 Relative importance indices (RII) and ranks (R) for different factor categories, and by different survey respondents
in the civil engineering grouping

Factor category Client Consultant Contractor Weighted


average
RII R RII R RII R RII R
Project related 0.619 4 0.646 4 0.615 5 0.628 5
Client related 0.526 7 0.610 7 0.571 7 0.570 7
Design team related 0.639 3 0.681 2 0.677 1 0.666 2
Contractor related 0.701 1 0.701 1 0.632 4 0.680 1
Materials 0.520 8 0.591 8 0.555 8 0.556 8
Labour 0.665 2 0.680 3 0.643 3 0.665 3
Plant/equipment 0.604 6 0.645 5 0.574 6 0.610 6
External 0.605 5 0.618 6 0.672 2 0.630 4

Table 8 Cross-comparison of the relative importance of Table 9 Cross-comparison of the relative importance of
the ten most signi cant factors causing delays as perceived factor categories causing delays as perceived by the different
by the different groups of respondents groups of respondents
Project participant Rank agreement Percentage Project participant Rank agreement Percentage
factor agreement factor agreement
Building Civil Building Civil Building Civil Building Civil
Clients and Clients and
consultants 2.0 2.6 60 48 consultants 1.50 0.50 62.5 87.5
Consultants and Consultants and
contractors 3.4 2.4 32 52 contractors 2.50 1.25 37.5 68.75
Clients and Clients and
contractors 4.2 3.6 16 28 contractors 1.75 1.25 56.25 68.75

questionnaire itself may also be re-examined to mini- differences of perception and their consequences
mize any defensive posturing or `buck passing by can also lead to claims for extension of time that
different groups; but a residual bias is apparent even generate further pressures to direct or de ect blame,
if allowances are made for this possible distortion. rather than seek root causes and solutions.
Unfortunately, such biases may be counter- A re-examination of Tables 6 and 7 relating to signif-
productive: for example, when blaming other groups, icant factor categories indicates that project-related
rather than examining the real causes of delays. Such factor categories rank only fth in signi cance, whereas
Construction delays 25

Table 10 The six common signi cant factors from both


building works and civil engineering works

Factor Factor category


Unforeseen ground conditions Project related
Poor site management and
supervision Contractor related
Low speed of decision making
involving all project teams Project related
Client-initiated variations Client related
Necessary variations of works Project related
Inadequate contractor experience Contractor related
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

also suggests a re-examination of methods of measuring


and improving productivity levels in construction
projects, as one important approach to avoiding or
minimizing delays.

A re-examination of aspects of construction


productivity that contribute to project
delays

Concept and classi cations


Commencing with the basic conceptualization of
productivity as output/input, Prokopenko (1987) iden-
ti ed three main productivity factor groups as:
1. job related;
Figure 3 Percentage agreement (PA) between different 2. resource related;
groups as to (a) factors and (b) factor categories contributing 3. environment related.
to project delays; based on Tables 8 and 9 respectively
He also distinguished between (a) external (non-con-
trollable) and (b) internal (controllable) factors, further
contractor-related, design-team-related and labour- subdividing the latter into hard factors (those related to
related factor categories rank rst, second and third product, plant and equipment, technology, materials
respectively. This suggests that project- (or scope-) and energy) and soft factors (people, organization and
related factors are not that signi cant in the context systems, work methods and management styles).
of delays (although they are important in establishing The importance of total factor productivity as against
the project durations at the outset), in comparison with single factor productivity to construction organizations
the aforementioned rst three factor categories, and and to the industry itself has been reported previ-
even the fourth (external conditions). Furthermore, ously (Ganesan, 1984). The former takes into account
case studies and interviews during this investigation all input resources (factors), whereas the latter is
indicated the importance of productivity levels of the usually useful only in the case of a critical or scarce
contractor, of the design team, and of the labour itself, resource, such as skilled labour.
in contributing to the signi cance of the rst three
(as ranked) aforementioned factor categories. It was
Improving productivity levels
also noted that the wide variations possible in such
productivity levels could well contribute to project The observations from the Hong Kong survey in the
delays (Chan and Kumaraswamy, 1995). current investigation indicated the perceived impor-
The foregoing conclusion re-con rms previous nd- tance of contractor-related, design-team-related and
ings, from this investigation and from the literature, as labour-related factor categories. This appears to: (a)
to the signi cance of productivity in determining align with the concept of increasing total factor produc-
project durations and in contributing to delays. This tivity and of synergizing the inputs to optimize the
26 Kumaraswamy and Chan

outputs; and (b) provide a reminder of the importance The apparent complexity is magni ed when consid-
of organizational variables in both contractors and ering: (a) the possibilities of interactions between such
design organizations. For example, the rapid response factors affecting labour productivity, and (b) the fact
and constructive inputs of design teams to site prob- that similarly complex networks of factors may simul-
lems enhance productivity and reduce delays. taneously affect other factor productivities, such as that
Special work study techniques such as multiple- of equipment. The consequential impacts on project
activity charts and activity sampling have been adapted activities could well lead to project delays.
and developed for measuring and improving construc- It is thus necessary to focus on critical factors
tion productivity (Heap, 1987; McCaffer and Harris, affecting overall (or total factor) productivity. Maloney
1995), but there is little evidence as yet of their popular (1983) con rmed that labour has a signi cant in uence
usage in the industry, for example in structured and on construction productivity, and that management in
scienti c approaches to developing improved work turn has a major impact on labour productivity. He
methods and in establishing and improving work identi ed sets of speci c driving, induced and restraining
norms. Such techniques and tools can be useful to forces acting positively and negatively on productivity
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

organizations with a longer-term perspective: i.e. those levels, and formulated approaches based on such forces
prepared to invest in improved productivity despite to facilitate productivity improvements.
short-term pressures or priorities. Their usefulness is Motivation of both management and labour can be
underlined by the signi cantly variable construction hypothesized as a key contributor to productivity.
productivity levels indicated by the literature (NEDO, Methods of motivating personnel to increase produc-
1989); and by the previous (second) phase of this tivity have been demonstrated by Khan (1993),
investigation (Chan and Kumaraswamy, 1995), which through applications of different human relations theo-
indicated potential improvements through better plant ries of motivation. Such enhancement of productivity
and labour utilization and appropriate methodologies, could help to counteract delays induced by other
for example in concreting. causes. Conversely, a lack of proper management can,
even `by default , mobilize factors that adversely affect
productivity and lead to project delays.
Factors affecting productivity and project
durations
Lim and Price (1995) cited (a) the following seven Other factors affecting construction time
factors identi ed as affecting overall construction
performance
productivity in Singapore:
1. buildability; The literature review of recent research also revealed
2. structure of the industry; many factors that were found to affect construction
3. training; time performance, apart from those factors that
4. mechanization and automation; achieved such effects through their initial impact on
5. foreign labour; productivity levels.
6. standardization; For example, Nkado (1995) demonstrated the prior-
7. building controls. itization of construction-time-in uencing factors that
can be incorporated in an information system, which
and (b) the following ten factors identi ed as affecting
could then help in planning project durations. He used
labour productivity:
12 scope-related variables, such as gross oor area, to
1. quality, number and balance of labour force; develop this particular model, but had also previously
2. motivation of labour force; examined a total of 33 time-in uencing factors that
3. degree of mechanization; had been identi ed from the literature. From the latter,
4. continuity of work as affected by supply of he identi ed the ten most important factors, including
materials, performance of other contractors for example client and designers priority on construction
or subcontractors, availability and adequacy of time. He also identi ed the ten least important factors
technical information, and variations; from this set of 33, including for example the form of
5. complexity of project; contract and its suitability for the project.
6. required quality of nished work; In a similar context, an investigation of the rela-
7. method of construction; tionship between the building team, procurement
8. type of contract; method and project performance by Naoum and
9. quality and number of managers; Mustapha (1995) did not yield enough evidence to
10. weather. con rm the claim that alternative procurement
Construction delays 27

methods shorten construction times. Parallels can thus productivity levels, although not explored in this paper,
be drawn with the work of Walker (1995b) in Australia, is the possibility of reductions in the planned project
which `revealed that contract type does not affect the durations themselves, in the rst instance. An integra-
speed of construction , and that several client-related tion of these ndings with those from the previous
factors proved more signi cant, particularly as to `how phases of the ongoing study (Chan and Kumaraswamy,
well the clients or their representatives relate to the 1995) con rms that productivity is one of the key
project team . Walker (1995a) also found that the `four factors in determining both planned and achieved
factors affect(ing) construction time performances and project durations, and that while project scope factors
best practice worldwide were: must be used to model the planned project durations,
other non-scope factors need to be incorporated in the
1. construction management effectiveness;
model, in setting the baselines and in adjusting for
2. the sophistication of the client and the client s
particular priorities, capabilities and motivations of the
representative in terms of creating and main-
interacting project participants.
taining positive project team relationships with
The questionnaire survey in this investigation also
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

the construction management and design team;


revealed differences in perceptions as to causes of
3. design team effectiveness in communicating
delays by different groups of project participants:
with construction management and client s
clients, consultants and contractors in building works
representative teams;
as well as in civil engineering works. It is suggested
4. a small number of factors describing project
that these apparent collective biases of different
scope and complexity.
industry groups may often direct blame for delays to
Such ndings collaborate the results of the question- other groups, and discourage a search for the root
naire survey in Hong Kong, as to the relative signi - causes of delays and solutions to same. The origin of
cance of non-scope factor categories, such as such biases may be traced to group conditioning, as
`contractor related , `design team related and `labour well as to the present adversarial nature of the contrac-
related in contributing the construction delays. tual systems, including the clashes, blame allocation
Speci c factors also highlighted as signi cant in this and defensive postures induced by the not uncommon
study included poor site management and supervision, `extension of time claims and associated costs in
low speed of decision making involving all project construction contracts.
teams, delays in design information, and lack of Studies on causes of project delays must thus
communication between consultant and contractor. make allowances for such biases when verifying the
real reasons, whether through interviews or through
selected project documents. Furthermore, special
efforts must be made to overcome such biases, as well
Concluding observations as to analyse and address the factors and factor cate-
gories identi ed in this study and the literature, as
The third phase of this investigation into factors signi cant contributors to project delays. Particular
affecting construction durations led to the identi ca- strategies may be designed to address the signi cant
tion of some major causes of construction project factors, such as unforeseen ground conditions, poor
delays. Both the questionnaire survey results in Hong site management and supervision, and delays in design
Kong and the review of recent relevant research information. As a general principle, for example, more
revealed the signi cance of non-scope contributors intensive site investigations and stronger management
such as project participant priorities and relationships. are probably warranted in projects where delays can
Such contributors affect project durations both be crucial. Of course, such principles need to be trans-
directly, and indirectly through their effects on produc- lated into practice through appropriate guidelines and
tivity levels. project-speci c procedures.
For example, the questionnaire survey indicated the This study thus provides pointers to appropriate
perceived importance of the impact on construction strategies and particular measures that may be adopted
delays of the contractor-related, design-team-related to avoid and/or mitigate project delays by focusing on
and labour-related factor categories. The particular the direct and indirect common contributors to same,
contribution of variable productivity levels to these such as delays in design information and productivity
signi cant factor categories was noted, leading to an levels. While the present survey was based in Hong
examination of factors affecting productivity itself and Kong, the international literature revealed general simi-
of how productivity could be considerably enhanced larities that may merit detailed comparative investiga-
and delays minimized, through techniques such as tions elsewhere.
work study. Another aspect of consistently increased
28 Kumaraswamy and Chan

References ence of labour. ASCE Journal of Construction Engineering


and Management, 109(3), 321 34.
Bromilow, F.J., Hinds, M.F. and Moody N.F. (1988) The McCaffer, R. and Harris, F.C. (1995) Modern Construction
time and cost performance of building contracts Management. Blackwell Science, Oxford.
1976 1986. The Building Economist, 27, September 4. Naoum, S.G. and Mustapha, F.H. (1995) Relationship
Chan, D.W.M. and Kumaraswamy M.M. (1995) A study between the building team, procurement methods and
of the factors affecting construction durations in Hong project performance. Journal of Construction Procurement,
Kong. Construction Management and Economics, 13(4), 1(1), 38 49.
319 33. NEDO (1989) Promoting Productivity in the Construction
Ganesan, S. (1984) Construction productivity. Habitat Industry. National Economic Development Of ce,
International, 8(34), 29 42. U.K.
Heap, A. (1987) Improving Site productivity. ILO, Geneva. Nkado, R.N. (1995) A model for predicting and planning
Kaka, A. and Price, A.D.F. (1991) Relationship between construction times at early design stages, Proceedings of
value and duration of construction projects. Construction Eleventh Annual ARCOM Conference, ARCOM, Septem-
Management and Economics, 9(4), 383 400. ber, pp. 298 307.
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Khan, M.S. (1993) Methods of motivating for increased Okpala, D.C. and Aniekwu, A.N. (1988) Causes of high
productivity. ASCE Journal of Management in Engineering, costs of construction in Nigeria. ASCE Journal of Construc-
9(2), 148 56. tion Engineering and Management, 114(2), 233 44.
Kumaraswamy, M.M. and Chan, D.W.M. (1995) Deter- Prokopenko, J. (1987) Productivity Management. ILO,
minants of construction duration. Construction Management Geneva.
and Economics, 13(3), 209 17. Walker, D.H.T. (1995a) An investigation into construction
Lim, E.C. and Price, A.D.F. (1995) Construction produc- time performance. Construction Management and Economics,
tivity measurements for residential buildings in Singapore, 13(3), 263 74.
Proceedings of First International Conference on Construction Walker, D.H.T. (1995b) The in uence of client and project
Project Management, Singapore, January, pp. 605 12. team relationships upon construction time performance.
Maloney, W.F. (1983) Productivity improvement: the in u- Journal of Construction Procurement, 1(1), 4 20.

Appendix 1: First page of ve-page questionnaire for research project

SECTION A: GENERAL ORGANIZATION INFORMATION

Date information collected


Name of organization
Major type of work involved
(e.g. buildings, roads or others)
Contact person and designation
Relevant working experience year(s)
Contact address
Contact phone No. Contact Fax. No.
SECTION B: FACTORS INCREASING CONSTRUCTION DURATIONS OF PROJECTS
COMPLETED DURING 1990 1994 IN HONG KONG

Please indicate the signi cance of each factor by ticking the appropriate boxes. Add any remarks relating to each
factor on the last column e.g. as to the reasons, the critical factors or the solutions.

E.S. = extremely signi cant (100) V.S. = very signi cant (75)
M.S. = moderately signi cant (50) S.S. = slightly signi cant (25)
N.S. = not signi cant (0)

Hypothesized factors E.S. V.S. M.S. S.S. N.S. Remarks


(100) (75) (50) (25) (0)
1. Project-related factors
Downloaded by [Hong Kong Polytechnic University] at 21:25 23 December 2014

Necessary variations
Inappropriate type of contract
used (e.g. traditional, design-
and-build, etc.)
Type of project
(e.g. building or civil)
End use of product
(e.g. housing, of ce or bridge)
Work type (e.g. new,
refurbished, mixed, etc.)
Large gross oor area
of building

Appendix 2: Distribution pro le of respondents to the survey questionnaire

Project category Clients Consultants Contractors Total


Building works 27 24 27 78
Civil works 23 25 21 69
Total 50 49 48 147

Appendix 3: Work experience pro le (in years) of respondents to the survey questionnaire

Project category Clients Consultants Contractors Mean


Building works 15.2 15.0 13.2 14.4
Civil works 13.9 17.4 18.8 16.7

View publication stats

Вам также может понравиться