Вы находитесь на странице: 1из 11

Magazine of Concrete Research Magazine of Concrete Research, 2013, 65(14), 855864

Volume 65 Issue 14 http://dx.doi.org/10.1680/macr.12.00192


Paper 1200192
Behaviour of double prestress system in Received 09/10/2012; revised 09/01/2013; accepted 15/04/2013
prestressed concrete girders Published online ahead of print 04/06/2013

Kim, Kim and Kim ICE Publishing: All rights reserved

Behaviour of double prestress


system in prestressed concrete
girders
Choong Eon Kim Jin Kook Kim
PhD candidate, Department of Civil and Environmental Engineering, Seoul Senior Research Engineer, Energy Infrastructure Research Department,
National University, Gwanak-gu, Seoul, Korea Steel Structure Research Division, Research Institute of Industrial Science
Jae Kwan Kim and Technology, Yeonsu-Gu, Incheon, Korea
Professor, Department of Civil and Environmental Engineering, Seoul
National University, Gwanak-gu, Seoul, Korea

Prestress generally refers to the compressive prestress that is introduced by a compressive force beforehand to
prevent tensile stress on the lower fibre of the bending member, and is often used in concrete girders. In girders
with a smaller height compared to span length, compressive stress, which has a harmful impact on structural
behaviour, is applied excessively to the girders upper edge, limiting the reduction in girder height of the prestressed
concrete girder. In this study, a prestress system integrating a tendon and two bars to support the compressive force
in the girders side ends was devised to offset the compressive force generated in the girder as a result of the
introduction of prestress. To manage the jacking force of this system, formulae are proposed by theoretically
clarifying the behaviour manifested during jacking in relation to the friction coefficient of the tendon and bars. A
10-m long rectangle-shaped girder is fabricated to check the friction coefficient of the bar and to verify the moment
prestress method using the proposed double prestress system. Applicability to real structures is validated by
measuring the behaviour manifested during the jacking of 35-m long real bridge girders.

Notation 1940s to control tensile stress in concrete girders (Billington,


AC area of compression member 2004; Dinges, 2009). The prestress load is applied in the
AT area of tension member opposite direction to the stress attributable to the design load of
C(x) distribution of force on compression member the structure. To achieve this, the tendon is arranged in a
EC elastic modulus of compression member downwards convex parabola shape. Using this arrangement, the
ET elastic modulus of tension member tendon generates bending towards the direction in which the
f C (x) distribution of frictional force on compression centre of the concrete girder is lifted, thereby causing bending
member stress in the opposite direction to the external design load.
f T (x) distribution of frictional force on tension member However, the concurrent compressive force causes compressive
L length of girder stress throughout the girder, which has a harmful effect on the
l(x) cumulative length girders upper flange, but not on the lower flange. If the height
T (x) distribution of force applied on tension member of the girder is low, the controllability of the compressive stress
(x) sum of absolute values of angular change of on the upper flange of the girder is limited in the structural
prestressing steel path from jacking end design because the bending attributable to the prestressing is
1 movement of anchorage on jacking side small and the compressive force is relatively strong.
2 movement of anchorage on non-jacking side
s elongation of tendon To resolve these problems, a post-compression technology was
C elastic deformation of compression members developed in 1977 in Austria. This introduces a tensile prestress
T elastic deformation of tensile members in the opposite direction of the normal prestressing by using a
kC wobble friction coefficient of compression member bar (compression member) (Johns, 1979; Parkinson, 1978). The
kT wobble friction coefficient of tension member BiPre method was developed in Japan in the early 1980s; it
T curvature friction coefficient of tension member refined the aforesaid technology and applied post-tension and
post-compression together (Kondo et al., 1986; Suzuki et al.,
Introduction 1991). The BiPre method has so far been applied to over 640
Technology to introduce prestress through the arrangement of bridges (Bi-Prestressing System Institute, 2004). When introdu-
the tendon (tension member) has been widely applied since the cing prestress through the application of tension and compres-

855
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

sion members, the axial force becomes offset and a moment methods that require separate jacking for post-tension and post-
prestress attributable to the eccentric arrangement of the tension compression. A tendon consisting of high-strength strands is
member is introduced (see Figure 1); this enables control of the used for post-tension to introduce the compressive prestress,
tensile stress on the girders lower flange and the compressive whereas high-strength bars (PS bars) are used for post-compres-
stress on its upper flange (Fu et al., 2001; Mou et al., 2003, sion to introduce the tensile prestress. The DPS consists of the
2004; Zhao et al., 2007). The depth of beam can be reduced by tension member, compression member and DPS anchorage, to
using bi-prestress (Mou et al., 2003, 2004). However, post- which the tension and compression member were jacked and
tension and post-compression are performed separately under the anchored at the same time (Figure 2). The compression member
existing methods; therefore, the anchorage zone needs to be is arranged linearly on the girders upper area, and the tension
reinforced separately from the process of introducing the jacking member is arranged parabolically at the lower side of the girder
force, in two stages (Zheng et al., 2002). from its centre and integrated with the compression member on
both ends to enable simultaneous jacking (Figure 2). Then, the
In the present study, a double prestress system (DPS) was devised jacking force applied on the tendon is supported by the bars
that simplified the jacking force introduction process by integrat- through DPS anchorage. Thus the moment is introduced into the
ing the tendon and bars on both ends of the girder to ensure that girder without compressive force by lifting up the girder by the
the tension to the tendon and the compression of the bars are tendon with parabolic profile. A high level of stress is imposed
applied simultaneously. However, the method for analysing the on the slender PS bar and may cause excessive transverse
behaviour characteristics associated with the friction coefficient behaviour by buckling. In order to avoid such unexpected
of the tendon and bars needs to be clearly established, along with deformation, a 50-mm dia. duct is used to carry the 40-mm dia.
the design application method, because interaction between the PS bar, of which the outer diameter of the thread is 45 mm.
corrugated and galvanised metal sheath and the prestress (PS)
thread bar under compression is not clear, even though the same Formulation of DPS
corrugated sheath is used for the PS bar as for the tendon. For Double prestress system anchorages should be able to move in a
this purpose, a formula is developed in the current study by longitudinal direction along the bars to ensure that elastic short-
theoretically clarifying the behaviour manifested during jacking ening of the bars is allowed. DPS anchorages are divided into the
for the double prestress system. The friction coefficient of the anchorage (active side) on the side of jacking, where the jacking
bars from measurement during jacking of a 10-m long, rectangle- force is directly applied, and the anchorage (passive side) on the
shaped girder is verified, and the moment prestress method using non-jacking side (Figure 3).
the proposed double prestress system is validated. Moreover, the
present study validates applicability to real structures by measur- When the jacking force is introduced, the anchorage on the
ing the behaviour during jacking of 35-m long real bridge girders. jacking side moves towards the internal direction of the girder
(A2) because elastic shortening occurs in the compression
Double prestress system member (Figure 3). The direction of movement of the ancho-
Double prestress system refers to a system that introduces rage on the non-jacking side is determined by the magnitude of
moment prestress through one-time jacking, unlike conventional axial force of the tension and compression member at the
Post-tension Axial Flexural Combined


Tendon

Post-compression Axial Flexural Combined



PS bar

Post- Post-
BiPre (bi-prestressing) Combined
tension compression

PS bar
Tendon

Figure 1. Stress distribution in PS concrete girders at the middle


section according to prestressing methods

856
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

DPS anchorage PS bar

Duct PS bar

Tendon
Tendon DPS anchorage

Linear Parabolic Linear

Figure 2. Double prestress system (DPS) and anchorage

DPS anchorage DPS anchorage


(active side) (passive side)

A1 A2 P2 P1
1 2

C(x)
x0 T(x) xL

Figure 3. Behaviour of DPS anchorage

anchorage. The anchorage moves towards the external direction compression member, the frictional force and so on were
(P1) of the girder if the force of the compression member is formulated as follows.
larger than that of the tension member. The resultant elastic
deformation leads to a gradual increase in the force of the The relation arising from the equilibrium of force can be
tension member and, as a result, the two forces become equal estimated by Equations 13
in magnitude, causing movement to stop. The movement
continues until the two forces reach equilibrium towards the 1: T 0 C(0) T L C(L)
internal direction (P2) of the girder if the tensile force of the
tension member is larger than that of the compression member
(Figure 3). Table 1 shows the related characteristics of this
behaviour. x x
T x T 0  f T ydy, C x C 0  f C ydy
To analyse behaviour during jacking, relations among the force 2: 0 0
applied on the tension member, the force transmitted to the

Type Direction Cause Results

Anchorage on the jacking side A1 external side Elastic restoration of bar Decrease (compressive force of the bars)
A2 internal side Jacking/bar shortening Increase (compressive force of the bars)
Anchorage on the non-jacking side P1 external side C.T Increase (tensile force of the tendon)
C: compressive force of bars
T: tensile force of tendon
P2 internal side C,T Increase (compressive force of the bars)
C: compressive force of bars
T: tensile force of tendon

Table 1. Cause of behaviour of DPS anchorage and changes


resulting from the movement

857
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

L L equilibrium of each member force. Thus, the anchorage on the


\ f T xdx f C xdx non-jacking side moves towards the external direction of the
3: 0 0 girder, causing the direction of the frictional force to change in
the tension member when the absolute value of frictional force in
the tension member is greater (Figure 4(a), case 1). The
The frictional force on the prestressed steel is divided into wobble anchorage on the non-jacking side moves towards the internal
friction and curvature friction, which are expressed through an direction of the girder when the absolute value of frictional force
exponential function, but can be expressed as a linear function if in the compression member is greater (Figure 4(b), case 2). For
the exponential number is small (Spiegel and Liu, 1999). Because
the compression member of the DPS is arranged linearly, the
Force
frictional force can be expressed as
T(0) C(0) PS bars
f T T (x)kT lT (x)g 
f T x T 0 3 1  e  T 0 T(L) C(L)
Tend
o n
4: 3 T T (x) kT lT (x)

f C x C 0 3 1  ef C C (x)kC lC (x)g   C 0

5: 3 kC lC (x) x
0 a L
(a)
Force

In this paper, three values measured from test specimens, namely


T(0) C(0) Tendon
tendon elongation (s ), movement of the anchorage on the
jacking side (1 ) and movement of the anchorage on the non- PS ba T(L) C(L)
rs
jacking side (2 ) are compared with their estimates to find the
wobble friction coefficient between corrugated sheath and PS bar,
as shown later in Figure 6. Once the coefficients related to
friction have been determined, then the behaviour of the DPS,
every value in Table 2, can be easily estimated and the stresses
on the concrete can be calculated.
x
Different arrangements and friction coefficients of tension and 0 b L
(b)
compression members induce differences in force profiles of each
member along the girder, even though they started at the same Figure 4. Distribution of force in a DPS: (a) case 1; (b) case 2
point. However, the profiles meet at the other end to form

Type Case 1 Case 2

L
T (x)
Elastic deformation of the compression member T dx
ET AT
0
L
C(x)
Elastic deformation of the tensile member C dx
E C AC
0
L L
T (x) C(x)
Movement of the DPS anchorage on the non-jacking side 2 dx 2 dx
E T AT E C AC
a b
Movement of the DPS anchorage on the jacking side 1 C 2 1 C  2
Elongation of tendon s T C s T C

Table 2. Calculation of behaviour of the DPS

858
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

this distribution of frictional force, a non-sliding point exists in force as indicated in Figure 4(a), case 1, and the equilibrium of
the tension member in case 1 and the direction of the frictional force reached while the anchorage on the non-jacking side moved
force is reversed based on that point. Another non-sliding point towards the girders external direction.
exists in the compression member in case 2 and the direction of
the frictional force is reversed based on that point. Friction coefficient of high-strength bars
Rigid body behaviour appears in the DPS anchorage as the forces
The formulation above is based on the assumption that there is a between bars and tendon come into equilibrium. In other words,
non-sliding point during jacking of the DPS and the position of the behaviour of the anchorage needs to be taken into considera-
the point remains unchanged. In a real structure, the position of tion in addition to the friction behaviour of the tendon and bars.
the non-sliding point may change slightly because the friction However, the behaviour was not considered separately in this
coefficient of the tension and compression members change study, because it appears in association with the behaviour of the
slightly in the process of jacking, although the coefficient is tendon and bars. At the present time, the friction coefficient of
constant on average. A behaviour different from the calculated the tendon, assumed in the calculation above, is used.
behaviour may appear when friction exists between the DPS
anchorage and concrete girder. However, the forces applied to the Based on the measurement of the behaviour of the DPS
compression and tension members become equal to the design anchorage and the elongation of the tendon during jacking, it was
values if the relative behaviour of the DPS anchorage and tension found that the movement (m 1 ) of the anchorage on the jacking
member remain unchanged. side was 36 mm and the movement (m 2 ) of the anchorage on the
non-jacking side was 18 mm towards the external direction of the
girder (case 1). The elongation of the tendon (m s ) was 64 mm.
Experimental verification of DPS
Figure 6 shows comparisons between the results of calculations
Test specimen based on the wobble friction coefficient of the bar. The elongation
Two rectangular girders, 10 m long, 450 mm wide and 800 mm of the tendon (s ) was scarcely affected by the wobble friction
high, were prepared using 40 MPa concrete to determine whether coefficient of the bar, as shown in Figure 6. Meanwhile, the
their behaviour would be consistent with calculated behaviour behaviours of the anchorages on the jacking side and the non-
during jacking of the DPS and how much moment prestress jacking side show similar slopes; this suggests that the behaviours
would be introduced. The DPS was applied to one rectangular were affected at a similar level in respect of the changes in
girder (DPS girder), and conventional post-tensioning was applied wobble friction coefficient of the bar.
to the other rectangular girder (conventionally post-tensioned
girder) for comparison. To ensure that equal stresses were gener- Thus, the results of the experiment and calculation were com-
ated on the bottom fibres of the two specimens, a tendon pared only for the anchorages on the jacking side and the non-
consisting of 19 strands was arranged linearly at the centre of the jacking side, and the wobble friction coefficient of the bar was
girder for the conventionally post-tensioned girder and a tendon estimated to range between 0.005 and 0.007/m. This is a similar
consisting of nine strands was arranged parabolically. For value to that of the friction coefficient (Igarashi et al., 1986;
purposes of comparison, the same height was chosen for the two Kuranari et al., 1987) of the compression member used in
girders. In the DPS girder, the 19-strand tendon was arranged existing post-compression. Since contact which might have
linearly at the centre of the girder in the same way as the caused friction between the DPS anchorage and specimen is
conventionally post-tensioned girder, and the DPS consisting of negligible, the friction behaviour of the anchorage in the DPS
two 40-mm bars and seven 15.2-mm strands was applied. anchorage could be excluded from consideration in the calcula-
tion. The wobble friction coefficient of the bar in DPS may be
Figure 5 shows a drawing of the specimen; 2750 kN was intro- proper to apply 0.007/m in the calculation.
duced into the 19 strands, whereas 1350 kN was introduced into
the nine strands; 1000 kN was introduced into the DPS. The Stress comparison of conventional prestressing and
calculated stresses on the specimens are presented in Table 3. At moment prestressing
this time, the coefficients of elasticity of concrete and steel were Jacking of the specimen began with the girders lower side being
assumed to be 28 600 MPa and 200 000 MPa, respectively. The supported entirely. Stress was generated by the prestress as the
wobble friction coefficient (kT ) and curvature friction coefficient jacking force was introduced, and the stress by the self-weight is
(T ) of the tendon were assumed to be 0.005/m and 0.25/rad, added as the girder bends upward. The coefficient of elasticity of
respectively (AASHTO, 2010; Eurocode 2 (CEN, 2003); Korea concrete was assumed to be 28 600 MPa to convert the strain into
highway bridge design code (Korea Road and Transportation the stress of concrete at the reinforcement bar position, which
Association, 2010)). The wobble friction coefficient (kC ) of the bar was the measured value, and the calculated stress was compared
was assumed to be 0.007/m (Igarashi et al., 1986; Kuranari et al., at the same position (Figure 7). In Figure 7, mea represents
1987). measured value and cal represents calculated value.

The results of calculation showed the distribution of prestress Calculated stresses in the conventionally post-tensioned girder

859
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

450 450
150

150
235
5
350

350
800

800
300

300
450 450

DPS girder
10 000
PS bar (2EA)
800

Tendon (19 strands) Tendon (seven strands)

Conventionally post-tensioned girder


10 000
800

Tendon (19 strands) Tendon (nine strands)

Figure 5. Geometry of test girders (unit: mm)

were 6.64 MPa at the girders top fibre and 16.81 MPa at the were similar. Variations in strain at the top fibre of the girder were
girders bottom fibre, which are equivalent to 252 3 106 m=m negligible and only the compressive strain at the girders bottom
and 568 3 106 m=m: The DPS girders calculated stresses were fibre varied, as shown in Figure 7(a), during jacking of the nine-
0.29 MPa (22 3 106 m=m) at the girders top fibre and strand tendon in the conventionally post-tensioned girder. As a
16.27 MPa (536 3 106 m=m) at the girders bottom fibre. result, the typical stress distribution of conventionally post-
Stress arising from the self-weight was calculated while the tensioned girders appeared, which is attributable to the paraboli-
19-strand tendon underwent jacking. Regarding the sequence of cally arranged tendon. In the DPS, the variations in strain implied
introducing the prestress, the 19-strand tendon underwent jacking the introduction of moment prestress that led to an increase in the
initially for the two specimens, which was followed by jacking of compressive stress at the girders bottom fibre and a decrease in
the nine-strand tendon, then the seven-strand DPS. the compressive stress at the girders top fibre, as shown in Figure
7(b). The final strain after post-tensioning was 287 3 106 m=m
Figure 7 presents the strains of the reinforced bar at the top and at the girders top fibre and 577 3 106 m=m at the girders
bottom fibres based on the jacking sequence. Although the two bottom fibre in the conventionally post-tensioned girder. In the
specimens exhibited some differences in stiffness during the DPS girder, the final strain after post-tensioning was
jacking of the 19-strand tendon, the variation in strain based on 66 3 106 m=m at the girders top fibre and 517 3 106 m=m
the jacking phase and the final strain were similar because the at the girders bottom fibre, which reveals that the final prestress
magnitude of the introduced force and the effect of self-weight value measured was consistent with the calculated value.

860
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

70 m 0
s 64 mm
Calculated displacement: mm

60 100

50 200

Micro strain
40 c 00068 m
1 36 mm 300

30 400
c 00051 m
20 2 18 mm 500

10 600
Tendon 1 (19 strands) Tendon 2 (nine strands)
0
0 0005 0010 0015 0020
mea_upper mea_lower cal_upper cal_lower
c: per m
1_cal 2_cal s_cal (a)

0
Figure 6. Prediction of DPS behaviour according to wobble
friction coefficient of bar 100

200
Micro strain

Ultimate load test 300


The three-point load test was performed under the simple support
400
condition for the two girders. As a similar stress in the lower fibre
was introduced in each test girder, cracking occurred at approxi- 500
mately 430 kN in both specimens and there were changes in
stiffness (Figure 8). The ultimate load was slightly higher in the 600
conventionally post-tensioned girder, which was attributable to Tendon 1 (19 strands) DPS
the arrangement of the nine-strand tendon in the conventionally
mea_upper mea_lower cal_upper cal_lower
post-tensioned girder, two strands more than the seven-strand
tendon in the DPS girder. Meanwhile, larger maximum displace- (b)
ment at ultimate load was found in the DPS girder.
Figure 7. Strains during jacking
In the three-point loading of the reinforced concrete girder,
vertical cracks occurred at the girders centre under loading,
along with diagonal cracks propagating towards the loading point In relation to the crack patterns observed in this study, diagonal
between the support and loading points (Nawy, 1996). Such cracks scarcely occurred in the conventionally post-tensioned
cracks occur because the girders fracture behaviour is affected by girder into which the compressive stress by post-tensioning had
the shear, as well as the bending moment. Diagonal cracks been intensively introduced in the upper fibre (Figure 9(a)). In
appeared after vertical cracks propagated to some degree when other words, the effect of shear in fracture behaviour was very
the post-tension force was introduced (Nawy, 1996). In other small. This is attributable to the fact that high compression stress
words, the compressive force applied on the girder by prestress in the upper fibre was introduced and the height of the girder used
controls the direction of crack propagation and induces vertical in the experiment was relatively low, so crushing of the concrete
propagation of cracks at the initial stage of crack appearance. was induced before diagonal cracks propagated. Meanwhile,

DPS girder Conventionally post-tensioned girder

Stage Upper fibre Lower fibre Stage Upper fibre Lower fibre

Self-weight 2.41 2.41 Self-weight 2.36 2.41


19 strands 7.99 7.98 19 strands 7.71 8.13
DPS (seven strands) 10.69 10.69 Nine strands 3.43 11.08
Final stress 0.29 16.27 Final stress 6.64 16.81

Table 3. Calculated stresses (MPa) of DPS girder and


conventionally post-tensioned girder

861
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

1200

1000

800
Load: kN

600 400 mm

400
(a)
200

0
0 20 40 60 80 100
Displacement: mm

1200
400 mm
1000

800
Load: kN

(b)
600
Figure 9. Distribution of cracks resulting from the fracture of
400 girders

200

ally post-tensioned girder specimen. This is also considered to


0
0 20 40 60 80 100 have induced the ductile behaviour of the DPS girder.
Displacement: mm
Application to an actual bridge with DPS
Figure 8. Loaddisplacement curve of specimens
In order to verify the applicability of DPS to the site, stress
distributions and variations in a real bridge were measured during
jacking of girders and compared with calculated elongations and
vertical cracks appeared approximately 200 mm high and were strains. The bridge was Ugeum I Bridge (2@35 m), which was
followed by diagonal cracks in the DPS girder into which the installed in Pocheon City, Gyeonggi Province, South Korea
moment prestress had been introduced (Figure 9(b)). This may be (Figure 10). The height of the bridge girder with DPS is 1.5 m,
attributed to the fact that the compressive stress arising from the which is much shorter than a conventionally post-tensioned girder
prestress at the girders top fibre was less than in the convention- with a height of 2.2 m (Jeon et al., 2012). To measure the

800
13 000

500 1750 250 250 500


4000 4000 1750
T1
550

CL of road T2
S 2000% S 2000%
350
1500

T3
350

T4
250

1200 4@2650 10 600 1200 1200

Figure 10. DPS applied to real bridge (unit: mm)

862
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

150
variations in strain, gauges were installed on to the longitudinal
reinforcement bars on the upper and lower sides of the girder 0
centre during jacking for the external girder (girder 1 (G1)) and 150

Micro strain
the central girder (girder 3 (G3)) among the 10 girders. The 300
friction coefficient, as previously used in the design of the
450
specimen, was used as the friction coefficient of the tendon and
bars when the bridge was designed. 600
750
The bridge girder had an I-shaped cross-section. One DPS system 900
(T1) was arranged on the girders top, and a guide for DPS Moment
prestress T3 T4 (T2)
anchorage was installed for the behaviour that could be mani- (T1)
fested during jacking. Three anchorages (T2,T4) were arranged
Upper_L Upper_R Lower_L Lower_R
using ordinary post-tension. In G1, the DPS system (T1) under-
(a)
went jacking first and ordinary post-tension systems (T2,T4) 150
were jacked sequentially. Meanwhile, T2,T4 were jacked before
0
T1 underwent jacking in G3.
150
Micro strain

The measured elongation in the wake of jacking and the 300


calculated elongation are presented in Table 4. The anchorage on 450
the non-jacking side moved towards the girders external side, as
600
shown in case 1. The measured elastic elongation of the tendon
was 220 mm (G1) and 225 mm (G3) when the calculated value 750
was 216.41 mm, with errors below 5%. For the amount of 900
shortening of the bar, the calculated value was 83.21 mm and the T3 T4 T2
Moment prestress
measured values were 81 mm (G1) and 82 mm (G3), with errors (T1)
also below 5%. Although differences in the absolute values of the Upper_L Upper_R Lower_L Lower_R
movements of anchorages (1 , 2 ) were measured, the relative (b)
deformations (c ) were similar.
Figure 11. Variation in strains of girders during jacking: (a) G1; (b)
Distributions of the strains differed between G1 and G3, depend- G3
ing on the stage of jacking force introduction, because of the
difference in time when the stress was applied by the girders
self-weight during the jacking of G1, which underwent jacking of anchorage due to its rigid body behaviour or friction between the
the DPS first, and jacking of G3, which initially underwent DPS anchorage and guide, a prestress identical to the calculated
jacking of the ordinary post-tension (T2,T4). However, the final value was introduced when the relative movement of each part of
strains at the girders upper and lower flanges were found to be the DPS in each girder (which can directly express the magnitude
consistent in the two girders based on a comparison of the of force introduced into the compression member) was identical
measured results (Figure 11). In Figure 11, upper_L represents to the calculated value.
strain in the upper flange at the left side, and upper_R
represents strain in the upper flange at the right side. The measurement results show that the relationship for the
moment prestress presented in Table 2 can accurately estimate
Despite the difference in absolute value in movement of the DPS the distribution of stress that is generated inside the girder,
regardless of its size. The proposed moment prestress system is
expected to perform well in the same way as projected in the
Type 1 2 C T s calculation.

Calculated 90.09 6.88 83.21 216.41 299.62


Girder 1 83 2 81 220 301 Conclusions
Girder 3 94 12 82 225 307 In this study, a prestress system, which integrated the tendon in
the girders side end and the bars supporting the compressive
Note: 1 , 2 , s are measured values; C and T are calculated values
based on measurements. force, was devised to offset the compressive force generated in
the girder as a result of the introduction of prestress. The DPS
Table 4. Comparison of calculated and measured elongation enables easy introduction of moment prestress by simulta-
(mm) of DPS neously jacking the tensile and compression members through
one-time jacking, unlike conventional methods that require

863
Magazine of Concrete Research Behaviour of double prestress system in
Volume 65 Issue 14 prestressed concrete girders
Kim, Kim and Kim

separate jacking of the tensile and compression members for bridge. Journal of Southeast University (Natural Science
anchorage. Edition) 31: 128134.
Igarashi K, Matsuno HY and Yokota H (1986) New Technology
To validate the effectiveness of the DPS, the behaviour, which Using Bipre Construction Method for PSC Bridge Girder.
varied depending on the force introduced into the tensile and Development and Construction Department, Hakodate, Japan.
compression members and the frictional force during jacking, Jeon SJ, Choi MS and Kim YJ (2012) Graphical assessment for
was theoretically formulated. Furthermore, the friction coefficient span ranges of PSC girder bridges. Journal of Bridge
of the bar in the DPS was estimated in comparison with Engineering 17(2): 343352.
experimental results for a 10-m specimen. The experimental Johns MR (1979) Post-compression prestressing technique.
results revealed that frictional behaviour of the DPS anchorage Concrete International 1(3): 2931.
was too negligible to be considered in the calculation and it was Kondo O, Nakamura A and Kaizu AM (1986) Test of PSC bridge
deemed proper to use 0.007/m, the friction coefficient of general girder using compression steel rod. Proceedings of the 8th
bars including the DPS anchorage, without any change. Conference of the Concrete Institute, Japan, pp. 925928.
Korea Road and Transportation Association (2010) Korea
Based on the results of the ultimate load test, it was found that Highway Bridge Design Code. Korea Road and
the vertical and diagonal cracks appeared together in the double Transportation Association, Seoul, Korea.
prestress girder, in the same way as for a reinforced concrete Kuranari H, Teshima K and Nakamura T (1987) Design and
girder with general crack patterns under ultimate load, because construction of Shinmachibashi bridge using Bipre
the compressive stress attributable to the prestress at the top fibre construction method. Journal of Prestressed Concrete, Japan
of the girder was scarcely introduced and, consequently, ductile 29(4): 4551.
behaviour was seen. The suitability of the formula for the DPS in Mou X, Wang Q and Xie W (2003) Test and study of the jacking
a real bridge structure, derived by using the 10-m specimen, was pressing method of bi-prestressed concrete beams.
evaluated through comparison with the results of measurements Construction Technology 2003-11.
during construction of a real bridge with a span length of 35 m. Mou X, Wang Q and Xie W (2004) Technical and experimental
From this comparison, it was found that the formula for the study of prestressed concrete beams with additional
proposed moment prestress system could accurately evaluate the compression and tension. In Proceedings of the IABSE
distribution of stress generated inside the girder, regardless of its Symposium. Metropolitan Habitats and Infrastructure,
size, and the proposed moment prestress system was expected to Shanghai, pp. 118123.
perform well in the same way as it was projected in calculations. Nawy EG (1996) Reinforced Concrete: a Fundamental Approach,
3rd edn. Prentice-Hall, Englewood Cliffs, NJ, USA.
Parkinson J (1978) Post-Compression for Super-slim Span.
REFERENCES Institution of Civil Engineers, London, UK.
AASHTO (American Association of State Highway and Spiegel MR and Liu J (1999) Mathematical Handbook of
Transportation Officials) (2010) AASHTO LRFD Bridge Formulas and Tables, 2nd edn. McGraw-Hill, New York,
Design Specifications. AASHTO, Washington, USA. USA, Schaums Outline Series.
Billington DP (2004) Historical perspective on prestressed Suzuki M, Tajima T and Yokota T (1991) Development of
concrete. PCI Journal 49(1): 1430. bi-prestressing system in Japan. Bridges: Interaction between
Bi-Prestressing System Institute (2004) Design/Construction construction technology and design. Proceedings of IABSE
Manual for Bi-Pre. Bi-Prestressing System Institute, Japan. Symposium, Leningrad, pp. 2901.
CEN (European Committee for Standardisation) (2003) Zhao S, Wang T, Guo R and Liu M (2007) Test and theory study
Eurocode 2: Design of concrete structures. CEN, Brussels, on bi-prestressed concrete beam. Journal of Agricultural
Belgium. University of Hebei 30: 110113.
Dinges T (2009) The History of Prestressed Concrete 1888 to Zheng WZ, An JB and Wang Y (2002) Research on design theory
1963. MSc thesis, Kansas State University, Kansas, USA. of tension and compression double action prestressed
Fu G, Yang Y, Geng X and Zhu X (2001) Research on bi- concrete structure. China Journal of Highway and Transport
prestressing system of simply supported concrete girder 15(4): 3542.

WHAT DO YOU THINK?


To discuss this paper, please submit up to 500 words to
the editor at www.editorialmanager.com/macr by 1
January 2014. Your contribution will be forwarded to the
author(s) for a reply and, if considered appropriate by
the editorial panel, will be published as a discussion in a
future issue of the journal.

864
Copyright of Magazine of Concrete Research is the property of Thomas Telford Ltd and its
content may not be copied or emailed to multiple sites or posted to a listserv without the
copyright holder's express written permission. However, users may print, download, or email
articles for individual use.

Вам также может понравиться