Index

The Project Management Workbook (PMW) is the governing document, from the initial authorization for work, through
the implementation phase. This workbook, in conjunction with the detailed Microsoft Project Schedule, constitute the
Software Development Plan for this project. Refer to the index below for a summary of its content.

Instructions Provides instruction on when to update this workbook during the life of the project
Project Initiation
ROM Estimate Record ROM estimates (effort hrs, budget, schedule, and assumptions)

Project Planning
Project Log Track project risks, lessons learned, new requirements, CM and QA Findings
Project Estimate Record detailed estimates (effort hrs, budget, schedule, and assumptions)
Status Record and track project status (budget, schedule, etc.)
Resources Project team, staffing, materials and environment needs
Standards Record project standards, CM Plan-config items/units, QA Plan, team responsibilities
Estimate Backup Backup/assumption detail of estimates that feeds the Project Estimate tab
Budget Tracking Record and track project budget and customer billing requirements
Rates Rate lookup table for labor categories - feeds estimate backup & budget tracking tabs

Project Control
Status Current budget/schedule & current planned tasks
Budget Tracking Record and track project budget and customer billing requirements

Test Log OPTIONAL: log used to record and track test plan and results

Approvals Approvals required and received by work product

11/13/2017
PMW Instructions

PROJECT INITIATION Tab


Required
1) Enter ROM estimate with assumptions ROM
2) Enter preliminary project schedule with assumptions ROM
3) Record approvals for Work Package Approvals
Enter if applicable
4) Enter any known staffing and/or facilities/tools requirements ROM
5) Enter known resources Resources
6) Enter customer imposed standards Standards
7) Enter any budget tracking/invoice requirements Budget Tracking
CM Requirements
Prior to Work Package Approval - Store PMW in LAN Project Directory until project is approved.
After Work Package Approval - Create a project directory in VSS and store the current PMW.

PROJECT PLANNING Tab


Required
Software Development Plan (authored by the PM or designee)
1) Enter detailed estimate with assumptions (size, effort and cost) Estimate
2) Enter detailed project schedule with assumptions Estimate
3) Enter budget information and customer billing requirements Budget Tracking
4) Review/Update billing rates for the contract - match to Contract Order Rate
5) Enter risks along with mitigation plan Project Log
6) Enter Project Team including customer contacts and other affected groups Resources
7) Enter/Update facilities and tools requirements Estimate
8) Enter/Update customer imposed standards Standards
9) Enter standard procedures and tools to be followed - indicated any deviations to Standards
JMCS standards
CM Plan (authored by the CM Manager)
10) Enter CM and CCB resources and responsibilities Resources
11) Identify configuration items/units, file names and project directory Standards
12) Enter CM estimate, facilities and tools requirements Estimate
QA Plan (authored by the QA Manager)
13) Enter QA resources Resources
14) Enter estimate, facilities and tools Estimate
15) Enter QA activities, procedures, tools and standards to be followed Standards

16) Record approvals for Requirements Doc, SDP, CM and QA Plans Approvals
CM Requirements
Draft Copies - Store PMW in LAN Project Directory until project plan is approved.
After PMW Approval - Save the current version of PMW in VSS.

PROJECT CONTROL Tab


17) Update status on risks Project Log
18) Record actual effort expended and actual schedule Status
Record approvals for Technical Requirements Document, Revised Requirements
19) Document and Project Plan, and Test Plan (as required) Approvals
20) Record updated estimate and reason for replan (if applicable) Estimate
21) Record updated schedule and reason for replan Status
Record reason for missed budget or schedule milestone after each phase
22) completion Project Log

Instructions Tab 11/13/2017 Page 2


PMW Instructions

23) Record lessons learned throughout the project Project Log


24) Create and distribute Status report for customer/sr management Status
25) Enter and track to closure CM and QA audit findings Project Log
CM Requirements
Draft Copies - Store PMW in LAN Project Directory until project plans are re-approved.
After PMW Re-Approval - Save the new version of PMW in VSS.

PROJECT CLOSING Tab


26) Record approvals for release of baseline to production Approvals
27) Record final lessons learned Project Log
28) Record final project actuals Status
CM Requirements
After project completion - Save the final version of PMW in VSS.

Instructions Tab 11/13/2017 Page 3


Initial Project Commitments
(ROM Estimate)

ROM Estimate and Schedule

Effort Planned Planned


Phase Hours Start Date End Date
Planning/Analysis
Design Phase
Code & Unit Test
System Test
Acceptance Test
Implementation
Documentation
Project Management
Quality Assurance
<Other>
<Other>

Comments: <insert any general comments or assumptions about this ROM estimate. Include references to backup material
used to develop this estimate. This might include an MS Project Plan. NOTE: All backup material must be
stored in the Project Directory and listed as a Configuration Item in this PMW.>

ROM Budget

Labor $0.00
Travel $0.00
Other Costs $0.00
Total $0.00 See detailed assumptions and calculations below

Comments: <insert any general comments or assumptions about this ROM estimate. Include references to backup material
used to develop this estimate. This might include an MS Project Plan. NOTE: All backup material must be
stored in the Project Directory and listed as a Configuration Item in this PMW.>

Labor
Position Rate Effort Hrs Cost
Project Manager $0.00
Senior Management $0.00
Lead Analyst $0.00
Support Analyst $0.00
Lead Developer $0.00
Developer $0.00
Testing Specialist $0.00
DBA/Application Architect $0.00
Total $0.00
Travel
Trip Description Rate per Trip # of Trips Cost
<insert trip description> $0.00
<insert trip description> $0.00
Total $0.00

Other Costs
Other Cost Description Cost # of items Cost
<insert description of hardware> $0.00
<Insert description of software> $0.00
<insert description of other cost> $0.00
Total $0.00

ROM Tab 11/13/2017 Page 4


Initial Project Commitments
(ROM Estimate)

STAFFING REQUIREMENTS

<Identify any specific resources needed to satisfy the project requirements. Resources include, but are not limited to: Special skills (may or may not
be able to satisfy with the Training Plan) or Additional staffing requirements (e.g., hiring needs, outsource needs)

Document any specific requirements, when they are needed, and who is responsible to ensure these requirements are satisfied on time. Place a
milestone on the project schedule to track this critical dependency or track in the Project Management Workbook - Project Log tab as a risk.> Replace
this text

FACILITIES AND TOOLS

<Indicate any special needs to facilities or tools to successful complete the project. Summarize the costs associated with this facilities and tools in the
Other budget section above.> Replace this text

ROM Tab 11/13/2017 Page 5


Initial Project Commitments
(ROM Estimate)

Assumptions

sumptions about this ROM estimate. Include references to backup material


might include an MS Project Plan. NOTE: All backup material must be
ted as a Configuration Item in this PMW.>

ssumptions and calculations below

sumptions about this ROM estimate. Include references to backup material


might include an MS Project Plan. NOTE: All backup material must be
ted as a Configuration Item in this PMW.>

Assumptions

Assumptions

Assumptions

ROM Tab 11/13/2017 Page 6


Initial Project Commitments
(ROM Estimate)

. Resources include, but are not limited to: Special skills (may or may not
(e.g., hiring needs, outsource needs)

esponsible to ensure these requirements are satisfied on time. Place a


in the Project Management Workbook - Project Log tab as a risk.> Replace

project. Summarize the costs associated with this facilities and tools in the

ROM Tab 11/13/2017 Page 7


Project Estimate

<template to be developed - enter estimate including size, effort, budget>

Estimate Tab 11/13/2017 Page 8


ABC Reporting Project Status
Status for period of 12/1/2001 to 12/31/2001
Life Cycle Phase: Code and Unit Test Johnston McLamb
BACK TO INDEX TAB
Project Description Project Status Project Team
Phase I -- Develop 15 Business Objects reports for the Activity Based Project Lead Bill Knecht
Costing (ABC) system. This will provide ABC users with ready access to Schedule Customer USPS
G
data about the cost of processing mail at processing centers nationwide.
G Resource
Requirements for these reports are described in detail in the ABC For a complete list of members see Resources
Requirements document and ABC Report Layouts. Budget
G
Resources

Schedule and Budget Summary -- Phase I, first 5 reports


Planned Actual Planned Actual Planned Actual Remaining
Unit Description Start Date Start Date End Date End Date Hours Hrs Hrs Phase Status
Project Management 11/7/2001 11/7/2001 12/28/2001
Planning/Analysis 11/13/2001 11/13/2001 11/26/2001 11/30/2001 52 ### 0 0 Closed
Design Phase 11/19/2001 11/19/2001 12/7/2001 12/7/2001 236 ### 0 0 Closed
Code & Unit Test 11/27/2001 11/29/2001 12/28/2001 160 ### 0 0 Open
Acceptance Test 12/20/2001 12/28/2001 40 ### 0 0 Open
Implementation 12/28/2001 12/28/2001 15 ### 0 0 Open
Quality Assurance 0 ### 0 0 Open

Total Hours 503 ### 0 0

Actions or Comments:
Customer is planning to modify the work order to allow more time for review and QA of first 5 reports, to allow an
additional month for the 2nd 5 reports, and to postpone the 3rd 5 reports until Phase II. They felt the schedule was too
aggressive and did not allow them enough time to incorporate feed back into the first set of reports.

*Contains labor costs and other material costs detailed in estimate.

Last Period's Accomplishments Current Period's Plan


Completed the design of the cross reference tables and data mart tables. Publish first five reports in the staging environment so that customers can
Populated these tables in the development environment. Worked with the review the reports and get feedback. Incorporate feedback into the reports.
customer to finalize requirements for the first five reports. Developed, Finalize requirements for the second five reports. Begin development of the
tested, and gained customer acceptance of the aggregation routines. second five reports.
Developed the first five reports.

Project Risks/Issues See Project Log <insert any additional comments or concerns>

NOTE: Project changes identified after approval of this agreement, which affect the estimated hours, costs or schedule will be re-negotiated as to the project impacted and incorporated into this
tracking document for re-distribution and sign-off.

11/13/2017
Project Log

Project Name: ABC Reporting BACK TO INDEX TAB


Phase Number 1
Activity Identification

Act. Phase Resource


ID Stat Prty Description Originator Date Disc.
Type Disc Assigned

1 O N 1 New requirement to be able to download data for any report into USPS ABC C
Excel team
2 O N 1 Requirement to change the date for moving the first five reports Jim Grahn 12/17/2001 C
into production from 12/28/2001 to 2/25/2002.

3 O N 1 Requirement to change the date for moving the second five Jim Grahn 12/17/2001 C
reports into production from 1/15/2002 to 2/25/2002.

4 O
5 O
6 O
7 O
8 O
9 O
10 O
11 O
12 O
13 O
14 O
15 O
16 O
17 O
18 O
19 O
20 O
21 O

Project Log Tab 11/13/2017 Page 10


Project Log

Project Name:
Phase Number
on Activity
Activity Identification
Resolution

Estimated
Act. Date Effort
ID Stat Complete Resolution
Type Closed Hours
Date (ECD)

1 O N Estimate provided to USPS for developing


this capability.
2 O N 0 On 12/28, Jim Grahn sent an email to Peter
Tuttle, the COR, asking him to modify the
SOW.
3 O N 0 On 12/28, Jim Grahn sent an email to Peter
Tuttle, the COR, asking him to modify the
SOW.
4 O
5 O
6 O
7 O
8 O
9 O
10 O
11 O
12 O
13 O
14 O
15 O
16 O
17 O
18 O
19 O
20 O
21 O

Project Log Tab 11/13/2017 Page 11


Project Standards and Procedures

This worksheet contains a plan for how the project will be managed. It covers the standards and procedures that the project will follow, the
method/mode/frequency of the different types of statusing to be done, the environment assumptions about the project, the configuration items that will be used
to control the project throughout the SDLC and the plan for ensure requirements are met and procedures are followed.

TABLE OF CONTENTS
Project Standard Procedures List of the standards and tools to be employed by this project.
Project Status
Status Meetings Describes the type, purpose, attendees, frequency and location of project team meetings.
Status Reports Describes the type, purpose, recipients, frequency and location of status reports.
Project Environment Assumptions about the environment to be employed by this project.
Project Configuration Items
Documentation Documentation work products that will be used to document and control this project
Source List of source units that is used for managing the project and organizing the CM Lib
Development Tools List of development tools to be used in the project and the version numbers/dates
Project Quality Assurance
Testing Plan for testing product to ensure customer requirements are met
QA Audits/Reviews Plan for audits and reviews to be performed

Standards Tab 11/13/2017 Page 12


Project Standards and Procedures

PROJECT STANDARD PROCEDURES/TOOLS

This standards and procedures can be located <insert location>

Functional Area Process Asset Description Version


Date
Software Development Lifecycle SDLC Process Document - Waterfall Defines the standard lifecycle phases and
activities for two lifecycles.
Project Management Project Management Workbook Main tool used on all projects to record and 12/18/2001
manage estimate, schedule, risks,
facilities/tools plan
- Risks PMP - Risk Mgmt Procedures Instructions for identifying/managing risks
- Schedule PMP - Scheduling Procedures Instructions for identifying/managing
schedules
- Estimate PMP - Estimating Procedures Instructions for identifying/managing
estimates
- Project Plan PMP - Project Planning Procedures Instructions for identifying/managing SDP

Requirements Management Requirements Document Record requirements baseline during


Planning Phase
Requirements Management Procedures Instructions for identifying/managing
requirements
PMW - Project Log tab Used to manage change in requirements after 12/18/2001
the Planning Phase

Configuration Management Project Management Workbook - CM Plan


JMCS Standard SCM Plan
CM Procedures
SNAFU Procedures Used to manage baseline releases and issues
with the baseline.

Software Quality Assurance SQA Plan


SQA Procedures
Project Management Workbook - QA Plan

Standards Tab 11/13/2017 Page 13


Project Standards and Procedures

PROJECT STATUS

Status Purpose Required Attendees Frequency


Team Status Review project status - schedule, estimate, risks, Project Leader and all JMCS project team Bi-Weekly
issues members (miniminum)
Team Leads Meeting Inform Sr Mgmt of project status and Sr Mgmt, Team Leads Bi-Weekly
escalation project barriers (miniminum)
QA Status Review Give QA status and escalation QA Manager, Sr Mgmt Monthly (or ad
noncompliance issues hoc as
needed)
Project Status Report Inform Sr Mgmt of project status and Sr Mgmt Bi-Weekly
escalation project barriers (miniminum)

SQA Status Report Summarized status of QA audits and findings Sr Mgmt Monthly
including summary of open noncompliance
issues

<insert other status report or meeting, as <indicate purpose of additional status report <indicate required attendees or recipients of <input
required> or meeting> the status> frequency of
status>

Comments: <insert any other special notes about project statusing and/or communication>

Standards Tab 11/13/2017 Page 14


Project Standards and Procedures

PROJECT CONFIGURATION ITEMS/UNITS

Documentation Version Control Location/File Name Assignee


Work Package Store Work Package on LAN until project is VSS/wp_usps_<project name>.doc Consulting
approved. Then store in VSS. Mgr
Project Management Workbook
Project Initiation baseline PMW is kept in the Project Directory in the VSS/pmw_usps_<project name>.doc PM
Requirements baseline LAN. A copy must be saved in VSS after <NOTE: keep working copy on LAN>
Design baseline Project Initiation, Project Planning, Design,
Change Control baselines and any other times the project commitments
change (SDP, CM, or QA items)

Software Development Plan


Project Planning/Analysis end SDP is a subsection of the Project See Project Management Workbook PM
Revisions to SDP Management Workbook and will be archived
per the PMW requirements listed above.

Requirements Document
Requirements baseline The Reqs Doc must be saved in VSS upon VSS/req_usps_<project name>.doc Business
Revisions to baseline approval at the end of the Project Planning Analyst
stage and when project changes require
updates to the requirements

Project Schedule
ROM Project Schedule is kept in the Project VSS/ps_usps_<project name>.mpp PM
Detailed Schedule Directory in the LAN. A copy must be saved NOTE: If project is small enough an MS
Changes to Planned Schedule in VSS after Project Initiation, Project Project Schedule is not required. In which
Planning, Design, and any other times the case the schedule is recorded in the PMW
planned schedule changes. and adheres to the CM standards for PMW.
Meeting Minutes
Customer/CCB Mtg Minutes All meeting minutes are stored in the Project LAN/ccbmm_usps_<project name>_date.doc CM Mgr
SQA Review Meeting Minutes Directory on the LAN. LAN/sqamm_usps_<project name>_date.doc SQA Mgr
Team Lead Status Mtg Minutes LAN/tlmm_usps_<project name>_date.doc TBD
Project Team Status Meeting Minutes LAN/ptmm_usps_<project name>_date.doc PM

Status Report
Sr Mgmt Status Report All status reports are stored in the Project LAN/msr_usps_<project name>_date.doc PM
Directory on the LAN.
Standards Tab 11/13/2017 Page 15
Project Standards and Procedures

All status reports are stored in the Project


Customer Status Report Directory on the LAN. LAN/csr_usps_<project name>_date.doc PM

SCM Plan
Project Planning/Analysis end The CM Plan must be saved in VSS upon VSS/scmp_usps_<project name>.doc SCM Mgr
Revisions to CM Plan approval at the end of the Project Planning
stage and when project changes require
updates to the plan.

SQA Plan
Project Planning/Analysis end QA Plan is a subsection of the Project See Project Management Workbook SQA Mgr
Revisions to QA Plan Management Workbook and will be archived
per the PMW requirements listed above.

Test Plan Should be created and saved in Project LAN/tp_usps_<project name>.doc Tester
Directory on LAN prior to starting System
Test

Release Notes Should be created and saved in Project LAN/rn_usps_<project name>.doc CM Mgr
Directory on LAN prior to going to Production

Optional Documents
Design Document <insert CM versioning requirements> <location>/dd_usps_<project name>.doc TBD
Users Guide <insert CM versioning requirements> <location>/ug_usps_<project name>.doc TBD
Users Manual <insert CM versioning requirements> <location>/um_usps_<project name>.doc TBD
<insert any Customer Deliverables> <insert CM versioning requirements> <location>/<naming std>_usps_<proj name>.d TBD

Source File Name Location


<insert source configuration items and units> <refer to CM Procedures> <location>

Development Tools Version # Location/File Name


<insert development tool> <insert version #> <location>

Standards Tab 11/13/2017 Page 16


Project Standards and Procedures

PROJECT QUALITY ASSURANCE

Testing
<insert the plan for testing the product to ensure along the SDLC that the customer requirements are met by the final production baseline.>

Quality Assurance Audits/Reviews

Work Product Audits All configuration items Audit will be performed upon completion of
work product
Work Process Audits Requirements Management Process Random audits will be conducted throughout
Project Management Process the life of the project
Configuation Management Process
Reports SQA Status Report Reports will be provided to Sr management
on a monthly basis

Noncompliance Process Give a summary as to how the noncompliance issues will be escalated on the project. Specify individuals to
escalate to.

PROJECT TEAM RESPONSIBILITIES

ROLE ASSIGNED RESOURCE RESPONSIBILITIES

SQA <insert assignee> <List SQA responsibilities>


PM <insert assignee> <List PM responsibilities>

Configuration Management
CM Manager <insert assignee> Manage Configuration Control Board -
organize meeting, facilitate meeting,
document meeting minutes
Develop/maintain/distribute CM plan, stds,
procedures
Identify work products and configuation items
under CM
DBA Create CM Library
Manage access to CM Library
Create/update software baselines

Standards Tab 11/13/2017 Page 17


Project Standards and Procedures

Conduct production software baseline audits

Standards Tab 11/13/2017 Page 18


Project Team

Project Team INDEX

Team Role Name Responsibilities for customer obligations CCB Develop Production
Member Security Security
Customer Team COR - Contracting Officer Peter Tuttle Signs contract, travel authorization, 1357s
Members Representative <Y or N> N/A N/A
COTR - Contracting Officer Jim Grahn Approves technical scope
Technical Representative Y R R
Customer Sponsor Jean Parris Lead within user organization responsible
for approving deliverables - Approves
detailed requirements Y R R
Business Analyst Bill Green Supplies detailed requirements and report
layouts <Y or N> R R
Business Analyst John Kelley Supplies detailed requirements for
aggregation algorithms; tests aggregations
and calculations <Y or N> R R
Business Analyst Cathy Ruth Approves report layouts; responsible for
training <Y or N> R R
Business Analyst, Technical John South Supports Metify interface; general Oracle
Support support; tests reports <Y or N> R R
Business Analyst Joe Hurley <Y or N> R R
General support Linda Threatt <Y or N> R R
Technical Support Doug Watson Supports Metify interface; general Oracle
support <Y or N> R, W, A, D R
Johnston McLamb BAD Wendy Henry Authorize all project commitments and
Team Members changes (budget, schedule, resources).
Remove project barriers <Y or N> R, W, A, D R
Project Manager Bill Knecht Provides customer status, and escalate
project issues/barriers - Manages CCB -
organize/run meeting
Develop Project Plan
Create Requirements Document Y R, W, A, D R
DBA Tom Abrials DBA support for all ABC databases <Y or N> R, W, A, D R, W, A, D
Analyst/Developer Anna Karneh Lead for designing and developing ABC
reports <Y or N> R, W, A, D R
Bus. Objects Programmer Joe Schultz Programs ABC reports N R, W, A, D R
Database Design Review Gavin Martin Assists with DBA support and schema
design review N R, W, A, D R
Database Design Review Lakshmi Purushothaman Schema design review N R, W, A, D R
Other Impacted Business Analyst Eric Rodgers (PWC)
Group Team Members
N R R

[Tab] 11/13/2017 Page 19


Project Team

Metify Analyst/Developer Tim Gatts (Armstrong Laing) Developer and technical support for Metify
data extract utility N N/A N/A

<Critical Dependencies will be listed in the MS Project Plan version date ???>
RESOURCE REQUIREMENTS

Staffing
Need someone who can define a Business Objects universe.
Need two Business Objects report developers.

Materials

We need a software interface that extracts data from the ABC Metify database and loads that data into the ABC Reporting Oracle databse. Armstrong Laing is responsible
for developing that interface and delivering it by the end of Novenber.

Environment

This project does not require the use of any non-standard software development tools or development environments.

Communication Plan

Status Purpose Meeting Frequency Required Attendees Location


Weekly Project Status Entire team reviews status of all Every Monday Jim Grahn, Jean Parris, Bill Green, John Telecon
Telecon project activities Kelley, Cathy Ruth, John South, Joe Hurley,
Linda Threatt, Doug Watson, Eric Rodgers,
Bill Knecht, Anna Karneh
Monthly JMCS Status Report status of all JMCS activities Last day of every month Supplied to Peter Tuttle and Jim Grahn <indicate where
Report to the COR and COTR master copies are
kept>

Comments: <insert any other special notes explaining how the groups will interface. A good example would be to explain the escalation path for
unresolved issues between impacted groups and Johnston McLamb>

[Tab] 11/13/2017 Page 20


Project Approvals

This worksheet is used to track the approvals of the various different work products. Fill in the name of the individual filling each role across the top row. Approval
requirements of each work product is provided in the matrix by project team role . (A = Approval Required, R = Review Only) Enter the date the approval was received from
that individual over top of the approval requirement code. Enter approvals received (via e-mail, verbal, etc.) in the Approval Detail at the bottom of this page.
BACK TO INDEX TAB

<Affected Group 2>

<Affected Group 3>

Configuration Mgr>

<Software Quality
Wendy Henry

Cathy Banks

Assurance>
John Kelley
Bill Knecht

<Software
Bill Green
Version Date
Work Product Date Sent Comments
Work Package 11/27/2001 11/27/2001 ? - 11/19/2001 <A> - - - - -
Requirements Doc <A> <R> <A> <A> <R> <R> <R> - -
First 5 reports
Written requirements 12/6/2001 12/6/2001 12/14/2001 12/7/2001 12/7/2001 12/14/2001
Report layouts 12/6/2001 12/6/2001 12/14/2001 12/7/2001 12/7/2001 12/14/2001
Aggregation formulas 12/5/2001 12/5/2001 12/7/2001 12/7/2001 12/5/2001
Software Dev Plan <A> <R> <R> <R> <R> <R> <R> <R> <R>
Project Schedule <A> <R> <A> <A> <R>* <R>* <R>* - -
SQA Plan <A> <R> - - - - - - <A>
SCM Plan <A> <R> - - - - - <A> <R>
Technical Design <A> <A> - - <R> <R> <R> - -
Code <R> <R> - - - - - - -
Acceptance Test - - <A> <A> - - - - -
Release #1 <R> - <A> <A> <R> <R> <R> - -
Release #2 <R> - <A> <A> <R> <R> <R> - -
Release #3 <R> - <A> <A> <R> <R> <R> - -

Approval Detail

Approval Date Approval Comment/E-mail


<copy and paste approval e-mail or alternate approval received (I.e., verbal approval on phone).>

Approvals 11/13/2017 Page 21


Project Test Plan

Testing for Phase 1 BACK TO INDEX TAB


First 5 Business Objects reports

Status
Test ID Description (Script) of Test Setup Requirements Expected Results Method of Verification Originator (O,I,F,C)
Test procedures that load data into the ABC Data must be loaded into the ABC
1 data mart tables from the ABC data tables and data tables and cross reference
cross reference tables. tables first. Anna Karneh C
Test aggregation routines to ensure that they Data must be loaded into the data All aggregated numbers are calculated correctly Compare our aggregated numbers to ones that
2 are calculating the aggregations correctly. mart tables. based on the aggregation formulas that John Kelley were calculated using John Kelley's own Anna Karneh
provided. aggregation routines. John Kelley (USPS) C
Test calculations that occur within the Business Data must be loaded into the data All calculations are performed correctly. Compare our calculated numbers to ones that Anna Karneh
3 Objects reports mart tables. were calculated by routines from John Kelley and John Kelley (USPS)
John South. John South (USPS) O
Test data selection criteria for each report. Data must be loaded into the data All data selection criteria specified in the report Compare available selection criteria with what is
mart tables. requirements are available for each report. specified in the report requirements.
4 When each report is displayed, it contains only the Run SQL queries with the same selection criteria
data that satisfy the selection criteria. and compare the results to the reports.
O
Test the ability to produce the reports in Data must be loaded into the data Each report will match the report layout in the report Visual comparison with report mockups in the
5
Business Objects. mart tables. requirements. report requirements document. O

371490037.xls/Test Log 11/13/2017 Page 22 of 23


Project Test Plan

Unit Test Acceptance Test


Resource Date Date Status Resource Date Date
Assigned Assigned Completed Actual Results (O,I,F,C) Assigned Assigned Completed Actual Results

Anna Karneh 11/19/2001 11/30/2001 All data verified as correctly loaded. N/A
Testing successful. John accepted the
All aggregation routines verified results of the JMCS aggregation
Anna Karneh 12/7/2001 12/11/2001 working correctly. C John Kelley 12/10/2001 12/14/2001 routines.

John Kelley
Anna Karneh 12/12/2001 I John South 12/17/2001

Anna Karneh
Joe Schultz O
Anna Karneh
Joe Schultz O

371490037.xls/Test Log 11/13/2017 Page 23 of 23