Вы находитесь на странице: 1из 93

Medium Voltage Distribution

MCset 1-2-3 17.5 kV


Withdrawable switchgear

Marine application
Civil engineering - Installation - Instruction of use
April 2012
Content

General 3
Glossary 3
Symbols 3
Recommendations 4
Standard tightening torques 4
List of bags and accessories 5

Civil engineering
Content 6

Dimensions and weights 7


AD, CL-GL, TT cubicles (SF6 technology) 7
Cubicle fitted with IPX1/ IPX2 roofs 8
Transition enclosure MTP (Motorpact transition enclosure) 8

Space to be provided around a switchboard 9


Middle of the room mounting 9
Installation against a wall 9
Civil engineering with maintenance space 10
Transition enclosure MTP (Motorpact transition enclosure) 10
Switchboard location in the installation room 11
Position of MV cables 12
MOTORPACT cubicle 13

Floor finishing and support members fastening 14


Floor finishing 14
Summary of different mounting methods 14

Incoming configuration of MV cables 15


General information 15
Civil engineering with maintenance space 15

Installation
Content 16

Cubicle packaging 17
Cubicle unit packing 17

Handling instructions 18
Land packaging 18
Ocean shipment packaging 18
Handling using a sling 18
Handling by rolling 19
Storage 19

Installation and operation recommendation 20

Installation instructions 21
Unpacking cubicles 21
Placing cubicles in a switchboard 21
Surface condition 22
Floor quality 22
Cubicle fastened on rails 22
Linking two cubicles 23
Assembling a MOTORPACT cubicle / MTP transition enclosure 24
Rack-in check 25
Removing the mobile part transport fixations 25
Installing the electric connections of the busbars and MV cables 26
Installing the main earth connection 28

BBV19342.indd version 02 
Content

Installing busbars 29
Installing busbars between MTP and the MOTORPACT cubicle 32
Placing MV cables on AD cubicle 34
MV cable screen earthing 40
LV cable routing and connection 41
Installing the tunnels 43
Installing the end sheets 48

Installation of a FU equipped with electromagnetic


locking options 51
Earthing switch with electromagnetic locking 51
Rack-in prevention with electromagnetic locking 52
Prior to installing the front panels 52

Steps to be taken for tests and inspection 53


Power frequency dielectric test 53

Tests on site 54
Checking and cocking the internal arcing detector 54

Instruction of use
Content 55

General description 56
Warning for readers 56
AD cubicle 56
TT1, TT2 cubicles 57
CL-GL cubicles 57
Withdrawable mobile part 58
Identification 60
Read the inscriptions on the front panel 60

Instructions for access to the inside of a AD cubicle 62


AD cubicle 62
Removing front protection cover plates 63
Removing the MV compartment separation sheet 64
Removing the manhole sheet 65
Removing and inserting fixed or withdrawable VTs 65
Removing the stop arc sheet in the cable compartment 66
Accessing busbars 66
Accessing the main contacts 67

Steps for the tests 68


Voltage presence on MV cables 68
MV cable tests 68

Operating Instructions 70
Extracting or inserting the mobile part 70
Racking-in the mobile part 75
Racking-out the mobile part 76
Closing the earthing switch 77
Opening the earthing switch 79
Racking-in VT fuses 81
Racking-out VT fuses 82
Preventing access using padlocks 83
Locking with key locks (option) 85
Locking with electromagnet (option) 86

Corrective maintenance 87
Replacement of VT box fuses 87

Index 89

 version 02 BBV19342.indd
General

Glossary UF Functionnal Unit (cubicle + mobile part + Sepam)


AD Incoming/feeder cubicle
Note: this document is available for all the MCset CL-GL Withdrawable line coupling cubicle
1-2-3 units ordered from the 1st of October 2008.
TT Measurement and busbar earthing cubicle
MTP Transition enclosure between an MCset cubicle
and a MOTORPACT cubicle

Switchgear and definitions


VT Voltage transformer
CT Current transformer or current sensor
VPIS Voltage Presence Indicating System
LV Low voltage
MV Voltage class, including levels 7.2 - 12 and 17.5 kV
SMALT Earthing switch

Mobile part
LF SF6 withdrawable circuit breaker which is used in AD
and CL cubicles
ERT Tool to remove/insert the mobile part from the switchgear.
The tool allows to place the mobile part on the floor.

Symbols

SMALT operation Rack-in prevention position.


Locking possible.

Rack-in or racked-out position.

Operation position.

Open earthing switch mechanical


indicator.

Closed earthing switch mechanical


indicator.

Position can be locked using padlocks.

BBV19342.indd version 02 
General

Mobile part operation Operation position.

Racked-in position.

Racked-out position.

Insertion/extraction position.

Recommendations

Height (H) of ceiling for installation The ceiling must be 2.6 m high for a small tunnel and 2.8 m high for a tall tunnel.
of an anti-arc IPX1 or IPX2 tunnel According to switchboard configuration, external extraction may be
recommended (consult us). The following constraints have to be considered:
- Exhaust duct as big as possible,
- Exhaust duct directed towards the top.

Installation above the switchboard All installation of equipment, such as lights is forbidden to avoid walking on
the switchgears roof to replace them.

Marking

It is compulsory forbidden to walk It is compulsory forbidden to remove


on the parts with this label. the parts with this label when
the equipment is energised.

Standard tightening torques

(Non greased screws and bolts) Screw Torque in Nm


Application methods:

6 13 The elastic washers placed on


the external sides of the connections
8 28 and busbars ensure better distribution
10 50 of stress induced by the screw torque.
12 75
14 120

 version 02 BBV19342.indd
General

List of bags and accessories

Cubicle unit packing or switchboard Package Content


assembled without tunnels Switchboard end and fixing - Switchboard end sheets
- Fixing columns
- Bag of screws and bolts
- Wiring collector external closure
Mobile part tools - 3 cubicle operation cranks
- 10 mm2 wire
- 1 earth fishplate and seal
Tunnels for the whole - Tunnels
switchboard - Bag of screws and bolts

Package (Optional) Content


Tests and inspection - Manual earthing kit
Spare parts - Fuses
Optional accessories - 1 busbar earthing truck
- 1 phase balance testing device
- 1 I and U test bar
- 1 tunnel closure kit
- 1 mobile part extraction tool
(ERT or extraction table)

Packing of assembled switchboard Package Content


with tunnels Switchboard end and fixing - Switchboard end sheets
- Fixing columns
- Bag of screws and bolts
- Wiring collector external closure
Mobile part tools - 3 cubicle operation cranks
- 10 mm2 wire
- 1 earth fishplate and seal

Package (Optional) Content


Tests and inspection - Manual earthing kit
Spare parts - Fuses
Optional accessories - 1 busbar earthing truck
- 1 phase balance testing device
- 1 I and U test bar
- 1 tunnel closure kit
- 1 mobile part extraction tool
(ERT or extraction table)

BBV19342.indd version 02 
Civil engineering
Content

Dimensions and weights 7


AD, CL-GL, TT cubicles (SF6 technology) 7
Cubicle fitted with IPX1/ IPX2 roofs 8
Transition enclosure MTP (Motorpact transition enclosure) 8

Space to be provided around a switchboard 9


Middle of the room mounting 9
Installation against a wall 9
Civil engineering with maintenance space 10
Transition enclosure MTP (Motorpact transition enclosure) 10
Switchboard location in the installation room 11
Position of MV cables 12
MOTORPACT cubicle 13

Floor finishing and support members fastening 14


Floor finishing 14
Summary of different mounting methods 14

Incoming configuration of MV cables 15


General information 15
Civil engineering with maintenance space 15

 version 02 BBV19342.indd
Civil engineering Dimensions and weights

AD, CL-GL, TT cubicles (SF6 technology)


Cubicles with 1 or 2 CT per phase, internal arcing withstand on 4 sides

Dimensions AD1 AD2 AD3 CL1 CL2 CL3 TT1 TT2


(2500A) (3150A) (2500A) (3150A)
Width (mm) L 570 700 900 900 570 x 2 700 x 2 900 x 2 900 x 2 570 570
Cubicle height* (mm) H1 2300 2300 2300 2300 2300 2300 2300 2300 2300 2300
Total height* (mm) H2 Small tunnel 2530 2530 2530 2530 2530 2530 2530 2530 2530 2530
Total height* (mm) H2 Tall tunnel 2732 2732 2732 2732 2732 2732 2732 2732 2732 2732
Depth (mm) P 1725 1725 1725 1725 1725 1725 1725 1725 1725 1725
Weight** (kg) 900 1050 1350 1750 700 x 2 800 x 2 900 x 2 1300 x 2 550 600
Weight (kg) of VT compartment 120 130 130 130 120 130 130 130 120 130

* This dimension excludes cable flanges.


** Maximum weight fully equipped excluding tunnel.

BBV19342.indd version 02 
Civil engineering Dimensions and weights

Cubicle fitted with IPX1/ IPX2


roofs
(e.g.: AD1 with internal arcing withstand
on 4 sides)

Dimensions AD1 IPX1 AD1 IPX2

Width (mm) L 570 570


Cubicle height* (mm) H1 2300 2300
Total height* (mm) H2 Small tunnel 2530 2530
Total height* (mm) H2 Tall tunnel 2732 2732
Depth (mm) P 1815 2485

* This dimension excludes cable flanges.

Transition enclosure MTP


(Motorpact transition enclosure)

This gutter is factory-mounted to the right or left


of an MCset cubicle (depends on switchboard
configuration).

Dimensions MTP
1250A 2500A 3150A
Width (mm) L 375 375 375
Cubicle height (mm) H1 2300 2300 2300
Total height (mm) H2 Small tunnel 2530 2530 2530
Total height (mm) H2 Tall tunnel 2732 2732 2732
Depth (mm) P1 1665 1665 1665
Depth (mm) P2 2335 2335 2335
Weight (kg) 240 275 310

 version 02 BBV19342.indd
Civil engineering Space to be provided
around a switchboard

Middle of the room mounting

A: at least 70 mm space under ceiling


B: cubicle height with tunnel: 2530 mm (small tunnel)
or 2732 mm (tall tunnel)
C: the maximum height of the switchboard support
(skids or rails)must be 340 mm to allow
the insertion/extraction of the mobile part with
the ERT.

Installation against a wall

A: at least 70 mm space under ceiling


B: cubicle height with tunnel: 2530 mm (small tunnel)
or 2732 mm (tall tunnel)
C: the maximum height of the switchboard support
(skids or beams) must be 340 mm to allow
the insertion/extraction of the mobile part with
the ERT.
D: rear space of at least 200 mm.

BBV19342.indd version 02 
Civil engineering Space to be provided
around a switchboard

Civil engineering with


maintenance space
AD1, AD2, AD3

A: access to room
B: main earth bus
C: reserved floor space, if necessary,
for routing of LV cables
D: reserved floor space for routing
of MV cables
E: MV cable clamps.

(*) Minimum dimension (in mm):


This passageway is necessary to remove a cubicle.
The depth of the maintenance space must respect
the bending radius of the cables used.

Transition enclosure MTP


(Motorpact transition enclosure)

A: access to room
B: main earth bus
C: reserved floor space for routing
of MOTORPACT(1) MV cables
D: reserved floor space for routing
of MCset 1-2-3 MV cables

(1) For more details see the MOTORPACT civil


engineering guide: 46032-700-07A.

(*) Minimum dimension (in mm):


This passageway is necessary to remove a cubicle.
The depth of the maintenance space must respect the
bending radius of the cables used.

10 version 02 BBV19342.indd
Civil engineering Space to be provided
around a switchboard

Switchboard location
in the installation room
(*): minimum dimension (in mm)
(1): AD1, CL1, TT1
(2): AD2, TT2, CL2, DI2
(3): AD3, CL3.

The L dimension is a function of the functional units


making up the switchboard.

A: this dimension must be equal to:


- 1600 mm* for operation (extraction
and positioning of moving parts)

B: this dimension must be equal to:


- 800 mm* for a 900 mm long FU at the end
of the switchboard
- 500 mm* for all other FUs.

C: this dimension must be equal minimum to 200 mm

D: access to room

E: main earth bus of switchboard

F: closing plates.

BBV19342.indd version 02 11
Civil engineering Space to be provided
around a switchboard

Position of MV cables

AD1

Maximum external cables:


Single-pole 70 mm
Three-pole 90 mm.

AD2

Maximum external cables:


Single-pole 70 mm
Three-pole 90 mm.

AD3 (1250 A)

Maximum external cables:


Single-pole 70 mm
Three-pole 90 mm.

AD3 (2500 A)

Maximum external cables:


Single-pole 70 mm
Three-pole 90 mm.

12 version 02 BBV19342.indd
Civil engineering Space to be provided
around a switchboard

AD3 (3150 A)

Maximum external cables:


Single-pole 70 mm
Three-pole 90 mm.

MOTORPACT cubicle See MOTORPACT civil engineering guide: 46032-700-07A.

BBV19342.indd version 02 13
Civil engineering Floor finishing and support
members fastening

Floor finishing

Surface condition Floor flatness is such that a 2 meter rule moved over all surfaces and
in all directions, does not display a difference of more than 5 mm.

Floor Strength The floor must have a compression withstand u 33 MPa to roll the extraction
tool on it without any damage.

Summary of different fixation types

Rails fastened on the floor

By screws. By bolts. By welding.

Skid fastened on the floor

By screws. By bolts. By welding.

14 version 02 BBV19342.indd
Civil engineering Incoming configuration
of MV cables

General information The civil engineering execution and Some recommendations are given
the installation of MV cables must take below.
several inputs into account:
Other incoming configurations are
- The bending radius of the cables possible, particularly if there is greater
- Cable slack to push and pull them clearance under the FUs.
- Cable handling, according to incoming
configurations and free cable length from Note: if the cable box is used, adapt
its point of insertion in the maintenance the depth of the maintenance space.
space.
Should you have questions concerning
a configuration, contact your nearest
Schneider Electric representative.

Civil engineering with


maintenance space
MV cables incoming

Intended for cables up to 240 mm.

Not recommended for 630 mm cables.

Indicative dimensions of unshielded medium-voltage (MV) dry cables:

Conductor cross section Conductor diameter Minimum bend


radius after assembly
1 x 240 mm 45 mm 600 mm
3 x 240 mm 90 mm 1500 mm
1 x 630 mm 65 mm 1000 mm

Note: the dimensions indicated can be greater in the case of shielded medium
voltage (MV) dry cables.

BBV19342.indd version 02 15
Installation
Content

Cubicle packaging 17
Cubicle unit packing 17

Handling instructions 18
Land packaging 18
Ocean shipment packaging 18
Handling using a sling 18
Handling by rolling 19
Storage 19

Installation and operation recommendation 20

Installation instructions 21
Unpacking cubicles 21
Placing cubicles in a switchboard 21
Surface condition 22
Floor quality 22
Cubicle fastened on rails 22
Linking two cubicles 23
Assembling a MOTORPACT cubicle / MTP transition enclosure 24
Rack-in check 25
Removing the mobile part transport fixations 25
Installing the electric connections of the busbars and MV cables 26
Installing the main earth connection 28
Installing busbars 29
Installing busbars between MTP and the MOTORPACT cubicle 32
Placing MV cables on AD cubicle 34
MV cable screen earthing 40
LV cable routing and connection 41
Installing the tunnels 43
Installing the end sheets 48

Installation of a FU equipped with electromagnetic


locking options 51
Earthing switch with electromagnetic locking 51
Rack-in prevention with electromagnetic locking 52
Prior to installing the front panels 52

Steps to be taken for tests and inspection 53


Power frequency dielectric test 53

Tests on site 54
Checking and cocking the internal arcing detector 54

16 version 02 BBV19342.indd
Installation Cubicle packaging

Cubicle unit packing

Package Content

1 Screws and bolts for:


- Cubicle fastening on civil engineering works
- Busbar fastening
- Intercubicle fastening
- Coupling gaskets

Package (may be supplied)


- Busbar shims
- Lock associated with the cubicle
- Lock unit

2 Cable fastening (AD cubicle)


- Flange supports
- Flanges

Cable floor
- Bottom plates
- Bottom closure
- Cable support sleeves
- Bag of screws and bolts

Package (may be supplied)


- Zero frequence toroids
- Locking unit (if it exists)
- 3 surge arrester links

3 - Busbars
- Cable connection brackets

4 - Busbar covers

BBV19342.indd version 02 17
Installation Handling instructions

Land packaging

Functional Unit

Ocean shipment packaging

Functional unit

Cubicles packed by threes

Handling using a sling

FU with circuit-breaker

Assembled switchboard

18 version 02 BBV19342.indd
Installation Handling instructions

Handling by rolling

Storage

Store the devices in their original


packaging, placed on dry ground or on
a material insulating it from humidity.

Long storage After long storage, clean insulating parts before operation.

BBV19342.indd version 02 19
Installation Installation and operation
recommendation

The switchgears resistance Need for good implementation Ensure that draughts and/or thermal
of cable-end restoration: shocks are avoided in all cubicle
to ageing in an MV substation compartments in order to avoid the
New cold retractable or slip-on creation of dew points (sources of
depends on 3 main factors: technology offers ease of installation partial discharges).
that favours resistance over time. The equipment must be installed
in conformity with the relevant IEC
Their design allows them to used in standard. Outside of these normal
polluted environments with harsh usage conditions, we recommend
climatic conditions. contacting Schneider Electric to
determine the operations to be carried
out as well as their frequency according
Impact of the relative humidity to the actual service conditions.
factor:
Ventilation control:
Installing a heating device is essential
in climates with high relative humidity Grid size must be suited to the power
levels and major temperature dissipated in the substation. These
differences. grids must be placed exclusively
in the vicinity of the transformer, in
order to avoid air circulation on the LV
switchboard.

Operation and maintenance It is strongly advised to periodically Our service center is at your
carry out, a few operation cycles on disposal at any time:
operating devices.
- To diagnose the installation,
Outside normal conditions of use,
(between -5C and 40C , absence - To offer suitable maintenance
of dust, corrosive gas, etc.), it is operations,
recommended to
examine, with our Schneider Electric - To offer maintenance contracts,
services center, the steps to be
taken, in order to ensure correct - To offer adaptations.
operation of the installation.
See the Maintenance guide (DEAI03).

20 version 02 BBV19342.indd
Installation Installation instructions

Unpacking cubicles

The preparation of cubicles must be carried out


on the premises where they will be installed.

Remove the 4 handling lugs (1 and 2).

The circuit-breakers are delivered in cubicles


in a racked-out position.

Unpack the functional unit by removing the wooden


frame (8 screws), then the plastic cover.

Remove the cubicle packaging.

To avoid damaging the FU front panel


components, leave the protection foam
in place until the switchboard is in the
operation phase.

Placing cubicles in a switchboard Note: place switchboard cubicles


according to front panel drawings
and the single-line diagram.
Assembling, adjusting and fastening
Start by placing the cubicle located in
the middle of the switchboard (except in
the case of an extension of the existing
switchboard) then place the cubicles on
either side of it, according to the Civil
Engineering Guide indications.

Placing above the maintenance space

Do not remove any part of the cubicle.

Note: placing can be carried out by rolling or lifting.

BBV19342.indd version 02 21
Installation Installation instructions

Surface condition Floor flatness is such that a 2 meters rule moved over all surfaces and in all
directions, does not display a difference of more than 5 mm.

Floor strength The floor must have a compression withstand u 33 MPa to roll the extraction tool
on it without any damage.

Cubicle fastened on rails Note: remove the front panel if the cubicle is fitted with VT, it is first necessary
to remove them, see the chapter Instructions for access to
the interior of a cubicle.

Fixation at the front of the cubicle

Pick from the two hardware bags B Place the screws and tighten them.
and C.

Fixation at the rear of the cubicle

Pick from the two hardware bags A Place the screws and tighten them.
and B.

22 version 02 BBV19342.indd
Installation Installation instructions

Linking two cubicles

Installing the inter cubicle gasket Place the self-adhesive inter cubicle
gasket along the full height of the right
side of the cubicle, except on the top
Access to the fastening points: wireway of the cubicle.
See chapter Instructions for access to the interior
of a cubicle and the chapter Removing the mobile This operation is not necessary for
part transportation devices. the cubicle at the right extremity
of the switchboard.

Install the second cubicle on the floor


as described before.

Assemble the 2 cubicles together


(11 fastening points).

Assembling cubicles

The lifting rings and its associated


cage nuts must be removed.

A: assembly of HM8 x 30 screws + M8 washers


and HM8 nut.

B: assembly of HM8 x 16 screws + M8 washers


and M8 cage nuts.

C: assembly of HM6 x 16 screws + M6 washers


and HM6 nut + M6 washers.

AFLR Internal Arc option:

D: assembly of 6 screws H M8 + M8 washers


+ HM8 nuts + M8 washers.

BBV19342.indd version 02 23
Installation Installation instructions

Assembling a MOTORPACT
cubicle/ MTP transition enclosure
Left-hand assembly

Right-hand assembly

Implementation:

1: disassemble the transition enclosure


front E and rear panel
2: open the top and bottom front doors
of the Motorpact
3: remove the central front cover D
of Motorpact by removing
the 4 screws
4: remove the rear panels of
the Motorpact compartments:
see manual (46032-700-08),
Installation guide
5: install screws A, nuts B and washers C
as shown opposite.

24 version 02 BBV19342.indd
Installation Installation instructions

Rack-in check Each time a cubicle is linked to another For the insertion and rack-in
one, check that the mobile can be of the mobile part as well as closing
racked-in and locked in position the door, refer to the operating manual
properly. (07897302) in the chapter on
Operating instructions.

Removing the mobile part To extract the mobile part and to open the door, refer to operating manual
in the chapter on Operating instructions.
transport fixations The operations described here after, must only be carried out once the cubicle
has been placed and secured on the floor.

Do not operate the mobile parts before removing the transport


fixations.

On LF circuit breaker

1: remove the 2 transport fixations


(3 screws per fixation)

2: place the 4 screws and washers to fix the CB


front cover. Tightening torque: 8.5 Nm.

3: remove the warning label:

On a ROLLARC contactor

1: remove the 2 transport fixations


(3 screws per fixation)

2: place the 4 screws and washers to fix the CB


front cover. Tightening torque: 8.5 Nm.

3: remove the warning label:

On an EVOLIS circuit-breaker

1: remove the front panel screws


2: extract the circuit breaker (out of the cubicle)
3: remove the top fixation with access
via the LV compartment
4: remove the fixation circuit breaker.
Tightening torque: 8.5 Nm.
5: remove the warning label:

BBV19342.indd version 02 25
Installation Installation instructions

Installing the electric connections


of the busbars and MV cables
General information Assemblies with bolts for MV and LV Connection maintenance:
internal equipment.
During downtime, check the connection
Screws and bolts to be used: torque with a torque wrench.

Class 8.8 according to standard In the case of disassembly, change


NF E 27 005, i.e. an elastic limit, the elastic washers.
Re 630 Mpa.
Note: to carry out the following
preliminary switchboard operations see
chapter Instructions for access to
the interior of a cubicle.

Cubicle AD and CL without VT Preliminary operations Placing Placing MV


to be carried out busbars cables
Extraction of the mobile part
(Optional)
Close the earthing switch

Remove the front panel


protective cover plates

Remove the separation sheet from


the MV compartment
(Optional)
Remove the busbar access sheet

Remove the manhole sheet

Cubicle AD and CL with fixed VT Preliminary operations Placing Placing MV


to be carried out busbars cables
Extraction of the mobile part
(Optional)
Close the earthing switch

Remove the front panel protective


cover plates

Remove the fixed VTs

Remove the separation sheet from


the MV compartment
(Optional)
Remove the busbar access sheet

Remove the manhole sheet

26 version 02 BBV19342.indd
Installation Installation instructions

Cubicle AD and CL with withdrawable VT Preliminary operations Placing Placing MV


to be carried out busbars cables
Extraction of the mobile par
(Optional)
Withdraw the VT fuses

Close the earthing switch

Remove the front panel protective


cover plates

Remove the withdrawable VTs

Remove the separation sheet from


the MV compartment
(Optional)
Remove the busbar access sheet

Remove the manhole sheet

TT cubicle with fixed VTs Preliminary operations Placing Placing MV


 to be carried out busbars cables
Remove the front panel
protective cover plates

Remove the fixed VTs

Remove the separation sheet from


the MV compartment
(Optional)
Remove the busbar access sheet

Remove the manhole sheet

TT cubicle with withdrawable VT Preliminary operations Placing Placing MV


to be carried out busbars cables
Withdraw VT fuses

Close the earthing switch

Remove the front panel


protective cover plates

Remove withdrawable VTs

Remove the separation sheet from


the MV compartment
(Optional)
Remove the busbar access sheet

Remove the manhole sheet

BBV19342.indd version 02 27
Installation Installation instructions

Installing the main earth


connection
Inter-cubicles

Note: this connection can be done during the


installation of each cubicle or at the end of
switchboard assembly.

For a switchboard with a MOTORPACT cubicle at the


end, refer to MOTORPACT installation manual ref.
46032-700-08.

A: located at the base of the cubicle Pick the self adhesive gasket from
B: located in the middle of the cubicle. the hardware bag.

Place this gasket around the link.

Install the link by sliding it from cubicle Place the bolt and tighten it.
2 to cubicle 1. Use only screws HM8x30.
28 Nm tightening torque.

Stick the gasket onto the cubicle sheet


as shown in A.

From the switchboard to the buildings


earth

Note: during the installation of the end sheets


punch the knock-outs from the sheets.

For a switchboard with a MOTORPACT cubicle at the


end, refer to MOTORPACT installation manual ref.
46032-700-08.

Connect the earth bar to the buildings earth at the end of the switchboard, on the
right and on the left, place the specific link with the oblong hole inside the cubicle.

Tighten with a torque of 28 Nm.

28 version 02 BBV19342.indd
Installation Installation instructions

Installing busbars This connection is done during Place the busbar between the 2
the installation of each cubicle. previously assembled cubicles
(refer to chapter on Principle
Access the busbars through the cubicle of assembling busbars).
side. If this is not possible, access
through the interior of the cubicle Tighten the fixation screws from
(refer to chapter on Instructions for the head side.
access to the interior of a cubicle). 50 Nm tightening torque.

Retrieve; Repeat these operations each time


- The main busbar in the cubicle a switchboard cubicle is placed.
packaging
- The busbar shims and hardware
bag in the cubicle packaging.

Principle of assembling busbars

1250 A busbars

A: top view of busbars


B: 1 x (100 x 8) bar per phase
C: nut
D: conical contact washer
E: flat washer
F: M10 x 40 screws.

BBV19342.indd version 02 29
Installation Installation instructions

2500 A busbars

A: top view of busbarss E: flat washer


B: 2 x (100 x 8) per phase F: M10 x 55 screws
C: nut G: 3 hole shim
D: conical contact washer H: 6 hole shim.

3150 A busbars

A: top view of busbarss E: flat washer


B: 3 x (100 x 8) per phase F: M10 x 70 screws
C: nut G: 3 hole shim
D: conical contact washer H: 6 hole shim.

30 version 02 BBV19342.indd
Installation Installation instructions

3600 A / 4000 A busbars

A: top view of busbars


B: 4 x (100 x 8) per phase
C: nut
D: conical contact washer
E: flat washer
F: M10 x 85 screws (special)
G: 3 hole shim
H: 6 hole shim.

Cover assembly principle Retrieve: from package 4 of the cubicle packaging, the covers.
(depending on needs)

Assembling the covers with clips

Place the half-covers on Close the covers on the bars.


the main busbar connections.

Mounting the covers with wire ties

Close the covers on the bars by Place the half-covers on the busbar
tightening the wire ties through connection.
the notches.

BBV19342.indd version 02 31
Installation Installation instructions

Installing busbars between MTP MOTORPACT MOTORPACT


to the right to the left
and the MOTORPACT cubicle
1250 A busbars

A: nut
B: contact washer
C: flat washer
D: M10 x 40 screws
E: 1 x (76 x 9,5) per phase
F: 2 holes shim
G: M10 x 60 screws
H: 1 hole shim.

Note: for phase 3, the connection bar on the transition


enclosure side is fastened to an insulator support.

2500 A busbars MOTORPACT MOTORPACT


to the right to the left
A: nut
B: contact washer
C: flat washer
D: M10 x 55 screws
E: 2 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 70 screws.

Note: for phase 3, the connection bar on the transition


enclosure side is fastened to an insulator support.

32 version 02 BBV19342.indd
Installation Installation instructions

3150 A busbars MOTORPACT MOTORPACT


to the right to the left

A: nut
B: contact washer
C: flat washer
D: M10 x 70 screws
E: 3 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 80 screws.

Note: for phase 3, the connection bar on the transition


enclosure side is fastened to an insulator support.

Optional insulated busbars MTP - Top views

Assembling the covers:

A: install a wire tie around the busbar,


inside the cover (used to block the cover
in position)

B: close the cover with wire ties

C: close the cover with the clips

D: fit the entire cover assembly with clips.

For cover assembly, refer to the chapter


Cover mounting principle.

BBV19342.indd version 02 33
Installation Installation instructions

Placing MV cables on AD cubicle

General information

An explanation is given for all types of cables.

Retrieve: from package 2 of the cubicle packaging,


floor plates, cable support and hardware bag.

A: 3 single-pole cables
B: 1 tri-pole cable.

To access the interior of a cubicle


(see chapter Instructions for access to the interior
of a cubicle ) Cut cable glands according to Install them around the cables.
the number and diameter of cables.
Refer to manufacturer instructions
for cable termination.

MV cable maintenance

Successively assemble, after having installed a row


of cables:

- Cable support

- Flanges

- Floor plates.

Fix the flange support under the floor,


after placing the cables vertical to
their attachment bracket.
Fix the flange support under the cubicle Reassemble bottom plates.
floor and block the cables with half-
flanges. Fill in the openings that have not been
Only qualified personnel are to used with uncut cable glands.
perform cable terminations and cable Make sure that the cable dielectric
installation. Workers must be aware insulation does not contact any
and understand the hazards involved grounded metal parts or other
in working with medium voltage phases.
circuits. Neglecting fundamental
installation requirements may lead The grounded metallic support
to personal injury, as well as damage must be in contact with the external
to electrical equipment or other protective cable sheath.
property.

Cable termination height Type of cubicle Configuration H (mm)

AD1 - AD2 630 A LV toroids 621


1 set of 3 CTs 540
2 sets of 3 CTs 507
1250 A LV toroids 621
1 set of 3 CTs 525
2 sets of 3 CTs 507
AD3 1250 A 1 set of 3 CTs 525
2 sets of 3 CTs 507
2500 A 1 set of 3 CTs 405
2 sets of 3 CTs 405
3150 A 1 set of 3 CTs 383

34 version 02 BBV19342.indd
Installation Installation instructions

Surge arrester
This operation must only be carried out after dielectric tests,
and before the connection of medium voltage cables to the FU.

See chapter Placing MV cables on AD cubicle.

Removing

In the case of an AD1 or AD2 cubicle


fitted with a surge arrester, access
to the cable compartment through
the front requires removal of the
surge arrester assembly.

1: remove the busbar surge arrester connection


2: remove the insulator support.

Installing
Carry out the operations in the reverse order
of removal.

Tightening torque
B: 50 Nm
E: 20 Nm.

BBV19342.indd version 02 35
Installation Installation instructions

Single-pole or three-pole cable without Drill a hole in bracket A according


to the cable head to be connected.
toroid TC
Place and fix bracket A.
AD1 and AD2, 1, 2 or 3 cables per phase

An explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in the cubicle packaging,


the bracket and the hardware.

Connect the cables. B: 50 Nm tightening torque.


Apply standard tightening torque depending
on the diameter of the bolt. Note: assembly sequence of the bolts
for the bracket:
The cable support is installed after the row of cable
is installed (see chapter on MV cable maintenance 1: M10 x 30 screws
on AD cubicle). 2: M10 washer
3: M10 nuts.
Dielectric tests must be carried out before
connecting the surge arresters.

For the connection of surge arresters, refer to chapter


on Surge arresters.

Place and fix brackets A, C and D.

B: 50 Nm tightening torque.

Connect the cables.


Apply standard tightening torque depending
on the diameter of the bolt.

The cable support is installed after the row of cable


is installed (see chapter on MV cable maintenance
on AD cubicle).

Dielectric tests must be carried out before


connecting the surge arresters.

For the connection of surge arresters, refer to chapter


on Surge arresters.

AD3, 1 to 4 cables per phase

Remove the bars. Drill a hole in the bars according to the


cable heads to be connected.

36 version 02 BBV19342.indd
Installation Installation instructions

Put back the bars with new washers. Dielectric tests must be carried
Install the cable lugs inside the bars out before connecting the surge
and place the screw head outside arresters.
the bars.
Apply standard tightening torque For the connection of surge arresters,
depending on the diameter of refer to chapter on Surge arresters.
the bolt. Tightening torque:
B: 50 Nm
A: screw E: 20 Nm.
B: washer
C: nut
D: lug.

AD3 3150 A/ 4000 A up to 8 cables


per phase

Remove the bars. Drill a hole in the bars according to the


cable heads to be connected.

Put back the bars with new washers. Dielectric tests must be carried
Install the cable lugs inside the bars out before connecting the surge
and place the screw head outside arresters.
the bars.
Apply standard tightening torque For the connection of surge arresters,
depending on the diameter of refer to chapter on Surge arresters.
the bolt.
Tightening torque:
A: screw B: 50 Nm
B: washer E: 20 Nm.
C: nut
D: lug.

BBV19342.indd version 02 37
Installation Installation instructions

Single-pole cable with toroid CT


on cubicle AD1 and AD2

AD1 and AD2, 1 or 2 cables per phase

The explanation is given for one phase.

Do the same for the two other phases.

Retrieve: in package of the cubicle packaging,


links A and hardware.

Drill a hole in link A according to Place and fix link A.


the cable head to be connected. 50 Nm tightening torque.

Note: assembly sequence of the bolts


for the link:
1: M10 x 30 screws
2: M10 washers
3: M10 nuts.

AD1 1 cable per phase Place phase 2 cable in the toroid.

The explanation is given for one phase.

Do the same for the two other phases.

Note: assembly sequence of the bolts for the cable Connect the cables on the link.
heads:
Apply standard tightening torque
1: M10 x 30 screws depending on the diameter of
2: M10 washers the bolt.
3: M10 nuts.
The cable support is installed after
the row of cable is installed
(see chapter on MV cable
maintenance on AD cubicle).

38 version 02 BBV19342.indd
Installation instructions

AD2 1 cable per phase Place the cables through the toroids.

Note: assembly sequence of the bolts for the cable Connect the cables.
heads:
1: M10 x 30 screws Apply standard tightening torque
2: M10 washer depending on the diameter
3: M10 nuts. of the bolt.

After having installed a row of cables,


then assemble the support flange
(see chapter on MV cable
maintenance on AD cubicle).

AD2 2 cables per phase Place the cables through the toroids.
AD3 2 cables per phase

Note: assembly sequence of the bolts for the cable Connect the cables.
heads:
1: M10 x 30 screws Apply standard tightening torque
2: M10 washer depending on the diameter of
3: M10 nuts. the bolt.

Dielectric tests must be carried


out before connecting the surge
arresters.

After having installed a row of cables,


then assemble the support flange
(see chapter on MV cable
maintenance on AD cubicle).

BBV19342.indd version 02 39
Installation Installation instructions

MV cable screen earthing

For single-pole or two-pole toroid CT The braid connection is done inside In all cases, the insulated MV cable
the cubicle. screen braids must go through
the toroids before connection to
the switchboard main earth bar.

For zero frequence toroid

Example of cable installation:


A: 1 three-pole cable
1 cable per phase
3 earthing braids

B: 2 three-pole cables
2 cables per phase
6 earthing braids

C: 3 single-pole cables
1 cable per phase
3 earthing braids

D: 6 single-pole cables
2 cables per phase
6 earthing braids.

In all cases, the MV cable screen braids The braid earth connection is done
must be insulated and go through the on the switchboard earth bars inside
zero frequence toroid before connection the maintenance space.
to the switchboards earth. Example: one cable per phase, 3 braids
to be connected. Two cables per phase,
6 braids to be connected.

40 version 02 BBV19342.indd
Installation Installation instructions

LV cable routing and connection

2 versions of top wireway:


Standard height LV box

Remove the roof on each cubicle Remove the cubicle cable troughs.
(6 screws).

Place the power supply lead cable Connect the wiring to the terminal
inside the trough. Connect the wiring blocks.
from the power supply lead cable for
each cubicle through the cable glands. Reassemble the roofing sheets
Place back the trough. (6 screws per sheet).

High LV box

Place the power supply lead cable Connect the wires to the terminal blocks.
at the top of the LV boxes of the
switchboard.

BBV19342.indd version 02 41
Installation Installation instructions

Incoming cables from below,


cubicle by cubicle

Remove the cable trough. (maximum 5 diameters 20 mm)


Cut according to the number at the base of the cable trough.
and the diameter of the cables.

Thread the wiring as well as feeder


cables up to the LV compartment.

Place the wires on the terminal blocks.

42 version 02 BBV19342.indd
Installation Installation instructions

Installing the tunnels

4 side anti arc tunnel IPX1


High LV box

A: front of the cubicle


B: HM6 screws + M6 washers
C: HM6 screws + M6 washers and HM6 nuts.
D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the supports (1) (with bottom holes),


(2 and 3) (without bottom holes) onto the cubicle
using the screws (B).

2/ Fix the roof (4) to the support (1, 2 and 3)


with the bolts (D) (the sealing washers are placed
outside to avoid leakage).

3/ Fix the tunnels of each cubicle together with


the bolts (C).

4 side anti arc tunnel IPX2


High LV box

A: front of the cubicle


B: HM6 screws + M6 washers
C: HM6 screws + M6 washers and HM6 nuts.
D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the supports (1) (with bottom holes),


(2 and 3) (without bottom holes) onto the cubicle
using the screws (B).

2/ Fix the roof (4) to the support (1, 2 and 3)


with the bolts (D) (the sealing washers are placed
outside to avoid leakage).

3/ Fix the tunnels of each cubicle together with


the bolts (C).

BBV19342.indd version 02 43
Installation Installation instructions

4 sides anti arc tunnel IPX1


Standard Height LV box

A: front of the cubicle


B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts.
D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheets (1) without bottom hole


at the back and the sheets (3) with bottom hole
at the front onto the cubicle using four screws (B)
for MCset 1 and six screws (B) for MCset 2
and MCset 3 for each sheet.

2/ Fix the roof (2) onto the sheet (1 and 3) using


two screws (D) for MCset 1 and three screws (D)
for MCset 2 and MCset 3.

3/ Fix the tunnels of each cubicle together using


5 screws according to the vue (C).

4 sides anti arc tunnel IPX2


Standard Height LV box

A: front of the cubicle


B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts.
D: HM6 screws + M6 sealing washers and HM6 nuts.

1/ First fix the sheet (1) without bottom hole


at the back and the sheet (3) with bottom hole
at the front onto the cubicle using four screws
(B) for MCset 1 and six screws (B) for MCset 2
and MCset 3 for each sheet.

2/ Fix the feet (4) onto the cubicle using two screws
(B).

3/ Fix the roof (2) onto the sheet (1) and (3) using
two screws (D) for MCset 1 and three screws (D)
for MCset 2 and MCset 3.

4/ Fix the roof (2) on the feet (4) using two screws (D).

5/ Fix the tunnel of each cubicle together


using 5 screws according to the vue (C).

44 version 02 BBV19342.indd
Installation Installation instructions

4 sides anti arc tunnel end IPX1/ IPX2


High LV box

A: rear of the cubicle


B: front of the cubicle
C: HM6 screws
D: HM6 screws + M6 washers and HM6 nuts.

1/ Fix the sheets (1 and 2) onto the cubicle


using the screws (C).

2/ Fixing the sheet (1) onto the tunnel


and on the sheet (2) with the screws (D).

3/ Fixing the sheet (2) onto the tunnel


with the screws (D).

4 sides anti arc tunnel end IPX1/ IPX2


Standard Height LV box

A: front of the cubicle


B: rear of the cubicle

The sheets are fixed with HM6 screws + M6 washers


and HM6 nuts.

1/ Fix the sheet (1) onto the cubicle and onto


the tunnel.

2/ Fix the sheet (2) onto the tunnel feet at the front.

3/ Fix the sheet (3) onto the cubicle, the tunnel


and the sheet (1).

4/ Fix the sheet (4) onto the sheet (1).

BBV19342.indd version 02 45
Installation Installation instructions

Installing a tunnel on a MTP transition


enclosure

Next to a MCset with the High LV Box for IPX1/IPX2

A: HM6 screws + M6 washers and HM6 nuts.


B: HM6 screws + M6 sealing washers and HM6 nuts.

1/ Mount the support sheets (1) first.

2/ Mount the side panel (2).

3/ Fasten together the support sheets of each cubicle.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets in the front


and rear (4).

6/ Fasten together the tunnel roofs of each cubicle

Next to a MCset with the standard height LV Box


for IPx1

The sheets are fixed with HM6 screws + M6 sealing


washers and HM6 nuts (A):

1/ Mount the support sheets (1) first.

2/ Mount the side panel (2).

3/ Fasten the support sheets of each cubicle together.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets to the front


and rear (4).

6/ Fasten the tunnel roof of each cubicle together.

46 version 02 BBV19342.indd
Installation Installation instructions

Next to a MCset with the standard height LV Box


for IPx2

The sheets are fixed by HM6 screws + M6 sealing


washers and HM6 nuts (A):

1/ Mount the support sheets (1) first and the feet (5).

2/ Mount the side panel (2).

3/ Fasten the support sheet of each cubicle together.

4/ Mount the roof (3).

5/ Mount the tunnel closing sheets at the front


and rear (4).

6/ Fasten the tunnel roof of each cubicle together.

BBV19342.indd version 02 47
Installation Installation instructions

Installing the end sheets

On the left end cubicle, place the cage nuts


on the sides.

For internal arc switchboards, stick the self adhesive


gasket (A) along the front of the switchgear for both
end sheets

Note: operations are identical for the right or left ends


of the switchboard.

Make sure that the busbar end cover


is assembled before mounting
the switchboards end covers.

On the left and right end cubicles, place and screw


(M8 screw) the end sheet support beams.

Assembling cover panels of cubicle ends

Punch the knock-out at the panel bottom to let


the earth bus to go through it (1 per panel).

48 version 02 BBV19342.indd
Installation Installation instructions

Note: operations are identical for the right or left ends


of the switchboard.

On the right end panel, place the cage nuts at


the front line.

Assemble the end cover panels 1 and 2


(right and left end of the switchboard).

A: HM8 screws+ M8 washers


B: HM6 screws+ M6 washers
D: assembly of HM8 x 30 screws + M8 washers
and HM8 nut + M8 washers.

BBV19342.indd version 02 49
Installation Installation instructions

D: assembly of HM8 x 30 screws + M8 washers


+ HM8 nut + M8 washers.

E: assembly of HM8 x 6 screws + M8 washers


+ HM8 nuts + M8 washers.

Standard height LV Box


(Top wireway closing sheet)

Place the top wireway closing sheet 4.

Place the two screws to fix the top wireway


closing sheet.

Pop the 2 rivets to fix the operating handle support


at the front of the end sheets.

Store the operating handle in the front end panel.

50 version 02 BBV19342.indd
Installation Installation of a FU equipped with
electromagnetic locking options

Earthing switch with To rack-in and rack-out the circuit


breaker, the earthing switch must be
electromagnetic locking operated.

At the installation of the FU,


FU delivered with the earthing switch the electromagnetic locking is not yet
closed enegised, it must be manually released
in order to operate the earthing switch.

Initial status:
- The earthing switch is closed,
- Selector 4 is in the locked closed
position.

Opening the earthing switch


without auxiliary supply

Disassemble the VPIS without Insert a screwdriver via the box hole.
disconnecting the wiring.

Push back and hold in place Open the earthing switch, inserting
the electromagnet (A) using the the crank in reference 5 until the
screwdriver, then pull towards you mechanical indicator light changes
and turn the selector to the right in the status.
operation position.

Position selector 4 in the locked open Put back the VPIS.


position.

BBV19342.indd version 02 51
Installation Installation of a FU equipped with
electromagnetic locking options

Rack-in prevention with


electromagnetic locking
Initial status: The locking system is accessible
- The circuit-breaker is in the racked-out position. as per the arrow in the drawing
- The earthing switch is closed. opposite.
- The front panel is disassembled to access cable
connections. To access the cable connection
compartment, circuit-breaker rack-in
must be prevented.

At the installation of the FU, the


electromagnetic lock is not energised,
it must be manually released in order
to place the front panel when the
operations are complete.

Prior to installing the front panels

If lever (A) is positioned as per figure 1, locking is


active and prevents installation of the front panel.

To desactivate the locking, insert a tool (screwdriver)


into the hole placed under the box support and push
the electromagnet rod (B).
Push the lever (A) to position it as per figure 2.
The system is released and the front panel can be
placed back.

Figure 1

Figure 2

52 version 02 BBV19342.indd
Installation Steps to be taken
for tests and inspection

Power frequency dielectric test This test can be carried out in one This procedure requires to defeat
single operation. the interlocks.

All circuit-breakers must be racked-in, It is essential to follow the sequences


closed, with FU doors open. here after.

All the VTs and surge arresters must The insulation level of the switchgear
This test must be performed be disconnected during this test. can be tested on site. The test voltage
by trained & authorized people. shall be 80 % of the rated short-
More over, one of the FU feeder must duration power-frequency withstand
have its lower panel open to connect voltage of the switchgear as specified
the test cable. in clause 7.105 of IEC 62271-200.

Defeating Interlocks Rack-in the circuit breaker


(refer to the operating manual).

On FUs not connected to the generator Remove the shim.

Place the circuit-breaker in the test position,


with the door open.

Raise and block the door lock rod using Press the pushbutton I to close the
a 55 mm U shim. circuit-breaker

Surge arrester connection


This operation must only be carried out after dielectric tests,
and before the connection of medium voltage cables to the FU.

Place and fix the connection of each surge arrester.


Refer to the chapter on MV cable connection.

BBV19342.indd version 02 53
Installation Tests on site

Checking and setting up


the internal arcing detector(1)
This operation has to be made during assembly of the The internal arcing detector is located
tunnels (option) or during operation on the roof of the on the roof of the cubicle.
cubicle. To be operational, it must be in spring
loaded position.

(1) The internal arcing detector is mounted according


to the internal arcing withstand characteristics of the
cubicle.

Setting up the internal arcing detector:

- Push the metal rod (1) toward


the back of the cubicle,

- Hook the rod (1) on the support (2).

1: metal rod,
2: support.

54 version 02 BBV19342.indd
Instruction of use
Content

General description 56
Warning for readers 56
AD cubicle 56
TT1, TT2 cubicles 57
CL-GL cubicles 57
Withdrawable mobile part 58
Identification 60
Read the inscriptions on the front panel 60

Instructions for access to the inside of a AD cubicle 62


AD cubicle 62
Removing front protection cover plates 63
Removing the MV compartment separation sheet 64
Removing the manhole sheet 65
Removing and inserting fixed or withdrawable VTs 65
Removing the stop arc sheet in the cable compartment 66
Accessing busbars 66
Accessing the main contacts 67

Steps for the tests 68


Voltage presence on MV cables 68
MV cable tests 68

Operating Instructions 70
Extracting or inserting the mobile part 70
Racking-in the mobile part 75
Racking-out the mobile part 76
Closing the earthing switch 77
Opening the earthing switch 79
Racking-in VT fuses 81
Racking-out VT fuses 82
Preventing access using padlocks 83
Locking with key locks (option) 85
Locking with electromagnet (option) 86

Corrective maintenance 87
Replacement of VT box fuses 87

BBV19342.indd version 02 55
Instruction of use General description

Warning for readers As the MCset range is very extensive and presents a vast number of front panel
options, we have decided to present a Functional Unit presentation equipped with
the maximum switchgear.

AD cubicle

AD1 630/1250 A
AD2 630/1250/1600 A Incomer/Feeder Incomer/Feeder
AD3 2500/3150 A without VT or with fixed VT with withdrawable VT fuses

A: access to inter-cubicle wiring for High LV box


switchgears
B: LV compartment door
C: protection, monitoring, control by Sepam
D: compartment door mobile part
E: position inspection windows of the mobile part
F: handrail
G: operation plate and padlocking of the mobile part
H: voltage indicators
I: earthing switch operation and locking plate
and padlocking of the mobile part
J: access panel to connection compartment of MV
cables or withdrawable VT fuses
K: operation and padlocking plate of withdrawable
VT fuses.
L: visualisation windows of cables or of VT fuse
position.

56 version 02 BBV19342.indd
Instruction of use General description

TT1, TT2 cubicles Voltage transformers Voltage transformers


with withdrawable fuses without VT or with fixed VT

A: access to inter-cubicle wiring for High LV box


switchgears
B: LV compartment door
C: fixed busbar bridge compartment door
D: visualisation windows
E: handrail
F: voltage indicators
G: earthing switch operation and locking plate
and padlocking of the mobile part
H: operation and padlocking plate of withdrawable
VT fuses
I: visualisation windows of cables or of VT fuse
position
J: access panel to connection compartment of MV
cables or withdrawable VT fuses.

CL-GL cubicles Circuit-breaker Bus riser cubicle


coupling cubicle

With upstream or downstream VT


with withdrawable fuses

A: access to inter-cubicle wiring for High LV box


switchgears
B: LV compartment door
C: protection, monitoring, control by Sepam
D: compartment door mobile part
E: position inspection windows of the mobile part
F: handrail
G: operation plate and padlocking of the mobile part
H: voltage indicators
I: earthing switch operation and locking plate
and padlocking of the mobile part
J: operation and padlocking plate of withdrawable
VT fuses
K: visualisation windows of cables or of VT fuse
position
L: access panel to withdrawable VT fuses
and to the lower busbar compartments
M: fixed busbar bridge compartment door.

BBV19342.indd version 02 57
Instruction of use General description

Withdrawable mobile part

LF1

LF2

LF3

Disconnector truck LF

Note: available in 3 widths.

58 version 02 BBV19342.indd
Instruction of use General description

Busbar earthing truck LF

Note: option available in 3 widths.

ROLLARC 400

Evolis

Note: available in 3 widths.

BBV19342.indd version 02 59
Instruction of use General description

Identification

Ex : AD functional unit

A: name of the cubicle


B: manufacturers label
C: characteristics, designations and serial number.

LF withdrawable mobile part

D: characteristics, designations and serial number.

Rollarc withdrawable mobile part

E: characteristics, designations and serial number.

Evolis withdrawable mobile part

F: characteristics, designations and serial number


G: location of operating instructions (behind the cover).

Read the inscriptions on the front


panel
A: procedure pictogram
B: withdrawable mobile part
C: earthing switch plate
D: withdrawable fuse voltage transformer plate.

60 version 02 BBV19342.indd
Instruction of use General description

Procedure pictogram

1: mobile part operation


2: earthing switch operation.

Mobile part

1: mechanical opening push-button


2: mobile part position selector
3: opening for inserting mobile part operating handle
E: mechanical indicator for indication of the mobile
part position
F: location for disconnector truck lock (optional).

Cubicle

Earthing switch, voltage presence and rack-in


prevention

4 : earthing switch position selector


5 : opening for the insertion of the earthing switch
operating handle
G : voltage presence
H : rack-in prevention selector switch
L : mechanical indicator of earthing switch status
M : location for rack-in prevention lock
N : location for earthing switch locks.

Withdrawable voltage transformer

6 : position selector for voltage transformer


withdrawable fuses
7 : opening for the insertion of the voltage transformer
withdrawable fuse operating handle.

BBV19342.indd version 02 61
Instruction of use Instructions for access
to the inside of a AD cubicle

AD cubicle

Markings Access
above
1 To the lower compartment via the maintenance space or gutter
(access to CTs also).

2 Rear (removal is optional and is not secured by interlocks).

3 Facilitates access to cables (AD cubicle ), through the front


(access to Cts also).
4 To the busbars (not possible for TT cubicle).

4 and 5 To the rear inter cubicle fastening screws.


This sheet must be reassembled before installation of busbars.
6 To the lower compartment through the front
(access to CTs and VTs also).
7 To the mobile part.

8 To low voltage box.

All operations described hereafter must be carried out in compliance


with the safety standards in force, under the responsibility
of a competent person.

62 version 02 BBV19342.indd
Instruction of use Instructions for access
to the inside of a AD cubicle

Removing front protection cover


panels
Cubicle with or without fixed voltage
transformer (VT)

In case upstream VT, presence


of voltage in the cables compartment
even if the circuit-breaker of
the switchgear is racked-out.

Close earthing switch (see chapter In the case of a cubicle equipped


Closing the earthing switch). with a fixed VT.

It is recommended to padlock it in this Open the protection switch of the VT


position (see chapter Padlocking and secondaries which is located in
preventing access using padlocks). the troughs or in the LV box.

Closure

To put back into operation, carry out


operations in the reverse order of
removal (closed earthing switch).

Remove the panel (10 screws).

Cubicle equipped with voltage Withdraw VT fuses (see chapter


Racked-out VT fuses).
transformer with withdrawable fuses

In case upstream VT, presence


of voltage in the cables compartment
even if the circuit-breaker of
the switchgear is racked-out.

Close earthing switch (see chapter


Closing the earthing switch).

It is recommended to padlock it in this


position (see chapter Padlocking and
preventing access with padlocks).

BBV19342.indd version 02 63
Instruction of use Instructions for access
to the inside of a AD cubicle

Open the protection switch of the VT Remove the access panel to the Vts
secondaries which is located in fuses (6 screws).
the troughs or in the LV compartment.

Remove the L bracket at the front Remove the access panel to


of the cubicle (4 screws and 2 nuts). the connection compartment of MV
cables (4 screws).

Closure
To put back into operation, carry out
operations in the reverse order of
removal (closed earthing switch).

Removing the MV compartment


separation sheet
Remove the circuit-breaker (see chapter Removing
and inserting the mobile part).

Remove screws A and remove


the separation sheet from the MV
compartment.

Closure To put back into operation, carry out operations in the reverse order of the removal.

64 version 02 BBV19342.indd
Instruction of use Instructions for access
to the inside of a AD cubicle

Removing the manhole sheet On a cubicle equipped with VTs,


remove them.

Remove the screws and remove


manhole sheet.

Access to the connection compartment


of MV cables is possible via the
maintenance space at the cubicle
manhole level.

Likewise, it is possible to access the


maintenance space or gutter through
the inside of the cubicle.

See chapter Instructions for access


to the inside of a cubicle.

Closure To put back into operation, carry out operations in the reverse order of removal.

Removing and inserting fixed Fixed VTs

or withdrawable VTs On each VT, disconnect the connection


bar, by unscrewing the screw and lift
the connection bar.

Similar operation whatever type of VT

Disconnect the VT low voltage Remove the VTs using the handle.
connector.

Closing the MV connection To put back into operation, For fixed VTs:
carry out operations in the reverse tightening torque on VT: 30 Nm.
compartment order of removal.

BBV19342.indd version 02 65
Instruction of use Instructions for access
to the inside of a AD cubicle

During the first VT Connect the VT low voltage connector.


insertion, cut and
remove the wire ties
on the connector.

Removing the stop arc sheet


in the cable compartment

This sheet MUST be reassembled


before the cubicle is re-energized.

Remove the 6 fixation screws (A)


in order to take off the sheet.

Accessing busbars

Safety rules
All operations described hereafter must be carried out
in compliance with the safety standards in force, under
the responsibility of a competent person.

Upper For access to busbars, see chapter Instructions for access to the inside of the
cubicle.

Lower Access to lower busbars is possible through the maintenance space by removing
the cubicle manhole sheet.

See chapter Instructions for access to the inside of the cubicle.

66 version 02 BBV19342.indd
Instruction of use Instructions for access
to the inside of a AD cubicle

Accessing the main contacts

Safety rules
All operations described hereafter must be carried out
in compliance with the safety standards in force, under
the responsibility of a competent person.

Opening and closing lower shutters

Using a screwdriver, raise the flat The shutters will fall and will lock
spring to release the lock. in the down position.
Push the ball into the link axis. To close, pull the the shutters up until
they lock.

Opening and closing upper shutters

Using a screwdriver, raise the flat The shutters will fall and will lock
spring to release the lock. in the down position.
Push the ball into the link axis. To close, pull the the shutters up until
they lock.

Before racking-in the mobile part, ensure that the shutters


mechanisms have been put back into their initial position
(locked closed). Failure to comply with this instruction may
result in damage to the equipment.

BBV19342.indd version 02 67
Instruction of use Steps for the tests

Voltage presence on MV cables

Cubicle equipped with VPIS voltage VPIS : Voltage Presence Indicator


System, a box with 3 integrated lamps.
indicator
Characteristics:
The voltage presence indication is
only ensured on the voltage range
stipulated by IEC 61958.

Instruction for use

VPIS must not be used as a VDS


(Voltage Detecting Systems).

When the ambient light is bright, it may


be necessary to improve visibility by
protecting the indication lights.

The indication of a VPIS alone is not A: voltage presence indicator light


enough to ensure that the system is (1 for each phase)
de-energised: B: connection outlets for the phase
concordance unit.
if the operation rules require this,
then suitable voltage detectors in Once the cables are energised, the
compliance with IEC 61243 must be voltage indicator lights should light up.
used.

MV cable tests

Test condition Open earthing switch.


Cables connected to injection tools.

Voltage injections on MV cable heads

On feeder cables (without VT)

It is mandatory to rack-out the circuit-


breaker of the switchgear or/and open
the circuit-breaker of the upstream
feeder.

Check voltage absence. Close the earthing switch.

Voltage indicator lights are not lit. See chapter Closing the earthing
switch.

68 version 02 BBV19342.indd
Instruction of use Steps for the tests

Remove the front panels.

See chapter Instructions for access


to the inside of a cubicle.

Connect the voltage injection circuit to


cable lugs.

Open the earthing switch. See chapter


Opening the earthing switch, then
carry out the tests.

At the end of the tests:

- Close the earthing switch


- Remove the accessories of the cable
injection.
- Install the front panels.

BBV19342.indd version 02 69
Instruction of use Operating Instructions

Extracting or inserting
the mobile part
Start Note: the following operations are
described using the ERT (tool to
remove/insert the mobile part from
Cubicle + mobile part in a disconnected /test position.
the switchgear that also allows
to place the mobile part on the floor).

Extraction Open the access door to the mobile


part by pulling then turning the handle
towards the right.

Operate the door sufficiently to ensure


that it is completely locked.

Disconnect the LV auxiliary plug


by pressing on the red button
and by pulling the plug lock
(circuit-breaker or contactor).

Bring the ERT into position (the pins


should be inserted inside the cubicle
holes).

70 version 02 BBV19342.indd
Instruction of use Operating Instructions

Lock the ERT by pushing in


and then turning towards the right
the two latches.
Check that the ERT is locked.

Secure the 2 ERT castors.

Change the position of the selector

2 to pull out the mobile part using

the handles A until it bottoms the ERT.


Change the position of selector switch 2
back to .

Note: the travel of the CB on the ERT


must be done with the CB close to
the ground.

Unlock the ERT by turning toward


the left and pulling out the latches.

Unblock the ERT castors.


Back up a little and slowly the ERT
from the switchgear.
Take down the mobile part by turning
the ERT operating handle.

BBV19342.indd version 02 71
Instruction of use Operating Instructions

Remove the ERT.

Before closing the cubicle door,


pull down the black cover.

To release the blocking system door


by moving the stop rod.

Close the access door to the mobile


part by turning the handle towards the
left, then pushing it.

72 version 02 BBV19342.indd
Instruction of use Operating Instructions

Insertion Open the access door to the mobile


part by pulling then turning the handle
towards the right.

Operate the door sufficiently to ensure


that it is completely locked.

Bring the ERT in position (the pins


should be inserted inside the cubicle
holes).
Secure the 2 ERT castors.

Lock the ERT by pushing in


and then turning towards the right
the two latches.
Check that the ERT is locked.

Change the position of the selector

2 to .

Push the mobile part into the cubicle


until it bottoms it and change
the position of the selector 2 back
to .

BBV19342.indd version 02 73
Instruction of use Operating Instructions

Unlock the ERT by turning toward


the left and pulling out the latches.

Unblock the 2 ERT castors


and remove it.

To connect the LV plug, push the red


button and hold in position.
Connect the LV plug and secure it
by latching it.

Before closing the cubicle door, lift


the black cover and latch it up.
Ensure that it well latched up.

To release the blocking system door


by moving the stop rod.

Close the access door to the mobile


part by turning the handle to the left
then pushing it.

74 version 02 BBV19342.indd
Instruction of use Operating Instructions

Racking-in the mobile part

Start Door closed

Selector 4 to
(open earthing switch)

Selector H in racked-in or racked-out

position to

Operation Lower the protective flap of push-button


1. Press push-button 1, and while
keeping it pushed down.
Change the position of selector 2

to .

Insert the operating handle into opening 3.

Rack-in the mobile part by turning


the operating handle (45 turns) clockwise
until the position indicator changes its
status.

Change the position of selector 2

to .

The circuit-breaker or contactors


are electrically operationnal to energise
the downstream circuit.

The pictogram with a black background


at the front is a reminder
of the operations.

BBV19342.indd version 02 75
Instruction of use Operating Instructions

Racking-out the mobile part

Start The mobile part in the racked-in.

Operation Press push-button 1 (which sends


an order for the mechanical opening
of the circuit-breaker). While keeping
it pushed down, change the position

of selector 2 to .

Insert the operating handle into


opening 3.
Rack-out the mobile part by turning
the crank (45 turns) anti-clockwise until
the position indicator changes its status.

Change the position of selector 2

to .

The mobile part is racked-out,


disconnected or in test position.

The pictogram with a black


background at the front is a reminder
of the operations.

76 version 02 BBV19342.indd
Instruction of use Operating Instructions

Closing the earthing switch

Start The mobile part is racked-out or ready


to be extracted or out of the switchgear.

Check that the voltage presence


lights are not lit.

The safety key locks are in a state


that allows the following operations.

Operation Change the position of selector 4

to , by pulling it and turning

it towards the right.

Insert the operating handle into the hole


5, and turn it clockwise until the position
indicator changes status.

The closing is quick and makes a noise.

BBV19342.indd version 02 77
Instruction of use Operating Instructions

Change the position of selector switch 4

to , by pulling it and turning it towards


the right.

The earthing switch closed.

The MV cable heads are short-circuited


and earthed.

The pictogram with a yellow


background at the front, is a reminder
of the operations.

78 version 02 BBV19342.indd
Instruction of use Operating Instructions

Opening the earthing switch

Start Closed earthing switch

The safety key locks are in a state


that allows the following operations.

Operation Change the position of selector 4

to , by pulling it and turning

it towards the left.

Insert the operating handle into


the hole 5, and turn it anti-clockwise
until position indicator changes status.

The opening makes a noise.

Change the position of selector

4 to by pulling it and turning

it towards the left.

BBV19342.indd version 02 79
Instruction of use Operating Instructions

The earthing switch is open.

The pictogram with a yellow


background at the front,
is a reminder of the operations.

80 version 02 BBV19342.indd
Instruction of use Operating Instructions

Racking-in VT fuses

Start The lower front panels are installed


on the cubicle

Selector 6 to

Operation Change the position of selector 6

to , by pulling it and turning

it towards the right.

Insert the operating handle into


the hole 7, and turn it clockwise until
it is racked-in.
Rack-in is completed when resistance
can be felt (stop).

Change the position of selector 6

to , by pulling it and turning it

towards the right.

The pictogram with a blue


background at the front, is a reminder
of the operations.

BBV19342.indd version 02 81
Instruction of use Operating Instructions

Racking-out VT fuses

Start The lower front panels are installed


on the cubicle

Selector 6 to

Operation Change the position of selector 6

to , by pulling it and turning it

towards the left.

Insert the operating handle into


the hole 7 and turn it anti-clockwise until
racked-out.

Change the position of selector 6

to , by pulling it and turning

it towards the left (the front panel to


access the fuses can now be removed).

The pictogram at the front,


is a reminder of the operations.

82 version 02 BBV19342.indd
Instruction of use Operating Instructions

Preventing access using


padlocks
Number of possible padlocks 3 padlocks on the rack-in prevention 3 padlocks on the earthing selector
selector. in open or closed position.
per cubicle type
1 padlock on the operating mechanism 3 padlocks on the selector the VTs
Nota : used padlocks 6 to 8 mm to be used. of either the top or bottom shutters. box with withdrawable fuses for either
rack-in or rack-out position.
1 padlock on the protective flap of
the mechanical opening push-button
of the mobile part.

Preventing the rack-in of a mobile part Place 1 to 3 padlocks on the rack-in


prevention selector H.

Rack-in forbidden if in

Preventing the opening of the shutters


(option)

Forbid the opening with padlock

On the operating mechanism of the shutters,


when they are closed.

1: top shutters lock


2: bottom shutters lock.
The shutter operating mechanism Press on the shutter guide, place
is located inside the cubicle, the slides (1 and 2, 1 or 2) and insert
on the right side. the padlocks in the holes.

For u 31 kA/1s internal arc switchgears:


the shutter operating mechanism is accessible after
removing the right side sheetmetal (2 screws A).

The metal sheet must be re-installed


before inserting the mobile part
inside the switchgear.

BBV19342.indd version 02 83
Instruction of use Operating Instructions

Preventing the mechanical opening


of the mobile part during operation

It can also be used as an additional lock to prevent Place 1 padlock on the push-button
rack-in and rack-out. protective flap 1.

Preventing the operation of the earthing


switch

Open earthing switch: Closed earthing switch:


place 1 to 3 padlocks on selector 4 place 1 to 3 padlocks on selector 4
to prevent the closure. to prevent the opening.
This also prevents the rack-in of
the mobile part.

Preventing the operation of VT fuses

Racked-in fuses: place 1 to 3 padlocks Racked-out fuses: place 1 to 3 padlocks


on selector 6 to prevent rack-out. on selector 6 to prevent rack-in.
This also prevents removalof the front
panel.

84 version 02 BBV19342.indd
Instruction of use Operating Instructions

Locking with key locks (option)

Number of possible locks Mobile part in a racked-out position: Disconnector truck


1 lock on the cubicle (2 O) or (2 C) (withdrawable busbar bridge):
or (1 O and 1 C) or (1 O) or (1 C): 1 lock in the racked-in position
on earthing switch. (on the disconnector).

Locking to forbid the rack-in The key is only released when


the rack-in prevention is locked.
of the mobile part.

The mobile part is racked-out.


The selector is pulled out.

Locking the disconnector truck The key is only released when


the disconnector is racked-in and
in the racked-in position locked in this position with the selector.

Closed disconnector

Racked-in disconnector truck

Locking the earthing switch


with one key lock

1 lock in closed position 1 lock in open position

Locking the earthing switch (2 O) or (2 F) or (1 O et 1 F) or (1 O)


or (1 F).
with two locks

BBV19342.indd version 02 85
Instruction of use Operating Instructions

Locking with electromagnet


(option)
Locking the earthing switch The electromagnet automatically
locks the earthing switch in the
open and closed position.

A push-button located on the low


voltage compartment will allow
the operation of selector switch 4,
if the switchgear is in the proper
state.

Locking to forbid the rack-in The electromagnet automatically locks


the selector when it is pulled out.
of the mobile part.
A push-button located on the low
Electromagnetic lock prevents the rack-in voltage compartment will allow
of the mobile part. to unlock if the switchgear is
in the proper state.

Preventive and corrective An MCset 17.5 kV Maintenance and Services guide is available.
It gives practical information on:
maintenance
b maintaining the equipment in good operation,
b ensuring that the equipment is safe during all installation, repair and service
operations.

DEAI03EN/ART833121
DEAI03FR/ART833120.

86 version 02 BBV19342.indd
Instruction of use Corrective maintenance

Replacement of VT box fuses

Start Racked-out fuses and VTs LV plug Remove the front panel (see chapter
unplugged (see chapter Operating Instructions for access to the inside
instructions). of a cubicle).

Removing

Lift holder A. Disconnect the small vertical rod B.

Pivot the striker pads C into Carefully remove the pin from
a horizontal position. the striker pads D.

Push the plug E and turn towards Remove the plug and the fuse.
the left and release.
The fuse is unlocked.

BBV19342.indd version 02 87
Instruction of use Corrective maintenance

Installing

Place the spring on the plug Insert the fuses, with the strikers facing
and check that it is flush against the front.
the bottom of the plug and placed Place the plugs on the fuses (spring
between the two clips indicated by towards the bottom).
the arrows.

Push the plug E. Turn it towards the right and release.


The fuse is locked, check that the plug
is well locked.

Carefully insert the pin on the striker Snap the link A et lift it to place
pin C. the striker pads C in a vertical position.

Connect the small vertical rod B and ensure free


operation of the link A.

88 version 02 BBV19342.indd
Index

A
Accessing busbars 66
Accessing the main contacts 67
AD, CL-GL, TT cubicles (SF6 technology) 7-56-57-62
Assembling a MOTORPACT cubicle / MTP transition enclosure 24

C
Checking and cocking the internal arcing detector 54
Civil engineering with maintenance space 10-15
Closing the earthing switch 77
Cubicle fastened on rails 22
Cubicle fitted with IPX1/ IPX2 roofs 8
Cubicle unit packing 17

E
Earthing switch with electromagnetic locking 51
Extracting or inserting the mobile part 70

F
Floor finishing 14
Floor quality 22

G
General information 15
Glossary 3

H
Handling by rolling 19
Handling using a sling 18

I
Identification 9-60
Installation against a wall 9
Installing busbars 29
Installing busbars between MTP and the MOTORPACT cubicle 32
Installing the electric connections of the busbars and MV cables 26
Installing the end sheets 48
Installing the main earth connection 28
Installing the tunnels 43

L
Land packaging 18
Linking two cubicles 23
List of bags and accessories 5
Locking with electromagnet (option) 86
Locking with key locks (option) 85
LV cable routing and connection 41

M
Middle of the room mounting 9
MOTORPACT cubicle 13
MV cable screen earthing 40
MV cable tests 68

O
Ocean shipment packaging 18
Opening the earthing switch 79

BBV19342.indd version 02 89
Index

P
Placing cubicles in a switchboard 21
Placing MV cables on AD cubicle 34
Position of MV cables 12
Power frequency dielectric test 53
Preventing access using padlocks 83
Prior to installing the front panels 52

R
Rack-in check 25
Rack-in prevention with electromagnetic locking 52
Racking-in the mobile part 75
Racking-out the mobile part 76
Read the inscriptions on the front panel 60
Recommendations 4
Removing and inserting fixed or withdrawable VTs 65
Removing front protection cover plates 63
Removing the manhole sheet 65
Removing the mobile part transport fixations 25
Removing the MV compartment separation sheet 64
Removing the stop arc sheet in the cable compartment 66
Replacement of VT box fuses 87

S
Standard tightening torques 4
Storage 19
Summary of different mounting methods 14
Surface condition 22
Switchboard location in the installation room 11
Symbols 3

T
Transition enclosure MTP (Motorpact transition enclosure) 8-10

U
Unpacking cubicles 21

V
Voltage presence on MV cables 68

W
Warning for readers 56
Withdrawable mobile part 58

90 version 02 BBV19342.indd
Schneider Electric group service centers are there to provide:
- engineering and technical assistance,
- commissioning,
- training,
- preventive and corrective maintenance,
- adaptation work,
- spare parts.

Call your sales representative who will put you in touch with your nearest
Schneider Electric group service center or directly call the following telephone
number: +33 (0)4 76 57 60 60 Grenoble France.

BBV19342 - REV. 02 a Schneider Electric Industries SAS All rights reserved.

Schneider Electric Industries S.A.S As standards, specifications and designs change from time to time, please ask for confirmation
35 rue Joseph Monier of the information given in this publication.
CS 30323
92506 Rueil Malmaison Cedex This document has been printed
www.schneider-electric.com on ecological paper.

954 503 439 RCS Nanterre Publishing: Schneider Electric Industries SAS.
Capital social : 896 313 776 Design: Profil.
Printing:

BBV19342 - REV. 02 04/2012

Вам также может понравиться