General requirements 2.01 The works and materials specified in Clauses 2.02 and 2.03 shall comply
with the sections stated, unless otherwise stated in this Section.
Pipes and manholes to 2.02 The abandonment of pipes and manholes shall comply with Section 5.
be abandoned
SITE CLEARANCE
Demolition 2.04 (1) Areas adjacent to demolition works shall be protected from
damage resulting from the demolition.
Pipes and cables 2.05 The Contractor shall make all arrangements with and obtain the necessary
approvals from the relevant authorities for disconnecting utilities inside
and outside the Site. The ends of disconnected utilities shall be made
good and sealed; the positions of the ends shall be marked with marker
posts or by other methods agreed by the Engineer.
Trees 2.06 The Contractor shall comply with the requirements of preservation and
protection of existing trees stipulated in Section 26 before commencing
site clearance.
Reinstatement 2.07 (1) Unless otherwise permitted by the Engineer, areas affected by site
clearance shall be reinstated as stated in Clause 2.07(2) to (5).
(2) Fine fill material shall be deposited and compacted in voids that
are left in the ground.
(3) Holes that are left in structures and pavements shall be made good
using material similar to that in the adjoining area.
2.3
2006 Edition
(4) The ends of fences, walls, structures, utilities and other items shall
be made good in such a manner that the affected parts will not corrode or
deteriorate, and will remain stable.
(5) Straining posts shall be fixed at the end of strained fences that have
been cut, and the fences shall be restrained.
Materials and 2.08 (1) Items that are to be re-used or taken to store shall be dismantled
equipment for re-use and removed by a suitable method so as to avoid damage or minimise the
and storage damage if this is unavoidable. The items shall be cleaned before re-use
or taking to store.
(2) Items that are to be re-used in the Works shall be kept in storage
areas provided by the Contractor. Storage areas shall be on levelled,
well drained and maintained hard-standing ground to facilitate cleansing
and minimize dust generation.
2.4