Вы находитесь на странице: 1из 2

PRESUPUESTO DE OBRA

Precio Unit.
Item Recurso Unid Cantidad Parcial sin IGV Parcial con IGV
S/.

01 OBRAS PROVISIONALES
43,292.93 51,085.65
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00
1,325.00 1,325.00 1,563.50
01.02 INSTALACIONES PROVISIONALES glb 1.00
1,075.00 1,075.00 1,268.50
01.03 TRAZO Y REPLANTEO EN OBRA m2
42,217.50 0.91 38,417.93 45,333.15
01.04 GASTOS DE OPERACIN est 1.00
1,215.00 1,215.00 1,433.70
01.05 CARTEL DE IDENTIFICACION DE LA OBRA 3.60x2.40 M est 1.00 135.00
135.00 159.30
01.06 MANTENIMIENTO DE TRANSITO est 1.00
1,125.00 1,125.00 1,327.50
MOVIMIENTO DE TIERRAS
2.00 154,710.67 182,558.59
EXCAVACION A NIVEL DE SUBRASANTE m3
2.01 8,443.50 8.75 73,880.63 87,179.14
EXCAVACION MANUAL PARA SARDINELES m
2.02 2,500.00 1.62 4,050.00 4,779.00
RELLENO CON MATERIAL PROPIO m3
2.03 312.50 22.45 7,015.63 8,278.44
ELIMINACION DE MATERIAL EXCEDENTE m3
2.04 2,110.88 33.05 69,764.42 82,322.01
PAVIMENTO FLEXIBLE
3.00 2,725,503.73 3,216,094.40
MEJORAMIENTO, CONFORMACION Y COMPACTACION DE SUBRASANTE C/ EQUIPO m2
3.01 42,217.50 4.62 195,044.85 230,152.92
SUB BASE GRANULAR COMPACTADA, E = 0.20 M, C/ EQUIPO m2
3.02 42,217.50 13.05 550,938.38 650,107.28
BASE GRANULAR COMPACTADA E= 0,20 M C/ EQUIPO m2
3.03 42,217.50 14.65 618,486.38 729,813.92
IMPRIMACION ASFALTICA (DOSIFICACION 0,40 gl/m2 - TANQUE 1800 gl) m2
3.04 42,217.50 3.43 144,594.94 170,622.03
CARPETA ASFALTICA EN CALIENTE DE 2" m2
3.05 42,217.50 28.72 1,212,275.51 1,430,485.10
GIBAS ASFALTICAS m2
3.06 145.00 28.72 4,163.68 4,913.14
SARDINELES SUMERGIDOS
4.00 49,362.50 58,247.75
CONCRETO FC =175 kg/cm2 PARA SARDINEL SUMERGIDO (0,15 X 0,30 M) m
4.01 2,500.00 19.15 47,875.00 56,492.50
JUNTAS DE DILATACION PARA SARDINELES DE CONCRETO m
4.02 250.00 5.95 1,487.50 1,755.25
OBRAS DE ARTE
5.00 17,317.62 20,434.79
MURO DE CONTENCION m3
5.01 585.00 26.72 15,631.20 18,444.82
CRUCE DE CANAL m3
5.02 97.20 17.35 1,686.42 1,989.98
SEALIZACION Y SEGURIDAD VIAL
6.00 346,521.53 408,895.41
PINTADO DE PAVIMENTO (LINEA CONTINUA) m
6.01 12,990.00 10.38 134,771.25 159,030.08
PINTADO DE PAVIMENTO (LINEA DISCONTINUA) m
6.02 6,495.00 31.05 201,669.75 237,970.31
SEGURIDAD DE OBRA EN ZONA DE TRABAJO est 1.00 3.83 4.51
6.03 3.83
RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD
est 1.00
6.04 DURANTE EL TRABAJO 2,625.50 2,625.50 3,098.09
PINTADO DE PAVIMENTO (SIMBOLOS Y LETRAS) m2
6.05 360.83 20.65 7,451.21 8,792.43
COSTO DIRECTO
3,336,708.97 3,937,316.59
GASTOS GENERALES 8.00%
266,936.72 314,985.33
SUB TOTAL SIN IGV
3,603,645.69
18.00
IGV
% 648,656.22
COSTO DE OBRA CON IGV
4,252,301.91
SUPERVISIN 2.50%
114,182.18 114,182.18
COSTO DE INVERSIN
4,366,484.09 4,366,484.09